CN105178968B - Rock tunnel(ling) machine pushing tow support meanss and construction method - Google Patents
Rock tunnel(ling) machine pushing tow support meanss and construction method Download PDFInfo
- Publication number
- CN105178968B CN105178968B CN201510313756.6A CN201510313756A CN105178968B CN 105178968 B CN105178968 B CN 105178968B CN 201510313756 A CN201510313756 A CN 201510313756A CN 105178968 B CN105178968 B CN 105178968B
- Authority
- CN
- China
- Prior art keywords
- ling
- support
- anchor hole
- rock tunnel
- machine
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
Description
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510313756.6A CN105178968B (en) | 2013-11-13 | 2013-11-13 | Rock tunnel(ling) machine pushing tow support meanss and construction method |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510313756.6A CN105178968B (en) | 2013-11-13 | 2013-11-13 | Rock tunnel(ling) machine pushing tow support meanss and construction method |
CN201310561968.7A CN103541735B (en) | 2013-11-13 | 2013-11-13 | Tunneling machine stepping pushing supporting device and construction method |
Related Parent Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310561968.7A Division CN103541735B (en) | 2013-11-13 | 2013-11-13 | Tunneling machine stepping pushing supporting device and construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105178968A CN105178968A (en) | 2015-12-23 |
CN105178968B true CN105178968B (en) | 2017-08-01 |
Family
ID=49965546
Family Applications (2)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310561968.7A Active CN103541735B (en) | 2013-11-13 | 2013-11-13 | Tunneling machine stepping pushing supporting device and construction method |
CN201510313756.6A Active CN105178968B (en) | 2013-11-13 | 2013-11-13 | Rock tunnel(ling) machine pushing tow support meanss and construction method |
Family Applications Before (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310561968.7A Active CN103541735B (en) | 2013-11-13 | 2013-11-13 | Tunneling machine stepping pushing supporting device and construction method |
Country Status (1)
Country | Link |
---|---|
CN (2) | CN103541735B (en) |
Families Citing this family (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103541735B (en) * | 2013-11-13 | 2015-07-08 | 葛洲坝集团第一工程有限公司 | Tunneling machine stepping pushing supporting device and construction method |
CN107575239B (en) * | 2017-10-16 | 2024-04-02 | 粤水电轨道交通建设有限公司 | Movable shield launching device for narrow space |
CN109098206B (en) * | 2018-09-12 | 2020-09-22 | 中交第二航务工程局有限公司 | Prefabricated assembly construction method for urban underpass tunnel and prefabricated assembly heading machine |
CN109296377A (en) * | 2018-09-25 | 2019-02-01 | 中铁工程服务有限公司 | A kind of construction method that rock tunnel(ling) machine stepping is appeared |
CN109441461A (en) * | 2018-12-17 | 2019-03-08 | 中国水利水电第四工程局有限公司 | A kind of Double shield TBM step device and application method |
CN111119911B (en) * | 2019-12-04 | 2024-04-30 | 中铁隧道集团二处有限公司 | Hydraulic shifting device for heading machine |
CN111086573A (en) * | 2020-02-14 | 2020-05-01 | 浙江德马科技股份有限公司 | Modular bear and move year formula AGV automatic handling car |
CN111663902A (en) * | 2020-07-17 | 2020-09-15 | 中国铁建重工集团股份有限公司 | Tension reaction frame for core drilling machine |
CN113818894A (en) * | 2021-10-20 | 2021-12-21 | 中铁十五局集团有限公司 | Working method of sliding plate type TBM stepping device |
CN114263469B (en) * | 2021-11-10 | 2023-11-14 | 中铁二局集团有限公司 | TBM or shield tunneling machine rapid jacking system and construction method |
Family Cites Families (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4405447B2 (en) * | 2005-08-19 | 2010-01-27 | 東和工業株式会社 | Pipe propulsion device |
CN201802408U (en) * | 2010-08-20 | 2011-04-20 | 上海市第一市政工程有限公司 | Self-traveling shield station-crossing movement system |
CN201802406U (en) * | 2010-08-23 | 2011-04-20 | 上海市第一市政工程有限公司 | Shield translation transit counterforce system |
CN102278117B (en) * | 2011-04-29 | 2013-03-20 | 上海交通大学 | Parallel pipe jacking construction simulation device |
CN102418530B (en) * | 2011-12-14 | 2013-07-31 | 中铁十二局集团第二工程有限公司 | Roller guide rail station-passing construction method of whole shield machine |
CN202417508U (en) * | 2011-12-26 | 2012-09-05 | 中铁四局集团有限公司 | Pushing system for pushing and turning construction of shield tunneling machine in subway tunnel |
CN102797471B (en) * | 2012-06-21 | 2016-12-21 | 中铁十三局集团有限公司 | A kind of inclined shaft open cut lining cutting section TBM stepping method |
CN103032071B (en) * | 2012-12-09 | 2015-01-28 | 中铁十二局集团有限公司 | Shield receiving forward-shift construction method of boulder group open excavation and embedment mutation space |
CN203531916U (en) * | 2013-11-13 | 2014-04-09 | 葛洲坝集团第一工程有限公司 | Tunnel boring machine step pushing support device |
CN103541735B (en) * | 2013-11-13 | 2015-07-08 | 葛洲坝集团第一工程有限公司 | Tunneling machine stepping pushing supporting device and construction method |
-
2013
- 2013-11-13 CN CN201310561968.7A patent/CN103541735B/en active Active
- 2013-11-13 CN CN201510313756.6A patent/CN105178968B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN103541735B (en) | 2015-07-08 |
CN105178968A (en) | 2015-12-23 |
CN103541735A (en) | 2014-01-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105178968B (en) | Rock tunnel(ling) machine pushing tow support meanss and construction method | |
CN101614125B (en) | Construction method of V-level surrounding rock tunnel | |
CN101963061B (en) | Construction method for underground box culvert of existing railway line | |
CN105649089B (en) | A kind of excavation of foundation pit closes on existing shallow foundation protection structure construction method | |
CN102251530B (en) | Construction process of double-wall steel cofferdam for construction of pier bearing platform in main river water of Yellow River | |
CN106988750B (en) | Implementation mode of ultra-short-distance underpass of existing station of large-span interval tunnel | |
CN103696784B (en) | Large-diameter long pipe curtain construction method for shallowly-buried large-span under-tunnel-passing architectural structure | |
CN104847380B (en) | A kind of structure and its construction method for reducing tunnel lining structure internal force | |
CN106979021B (en) | Large-section loess tunnel excavates and preliminary bracing quick closure cyclization method | |
CN106437737B (en) | Pipe jacking type coal mine small-section roadway tunneling method | |
CN102121251A (en) | Construction method for pouring main tower pier foundation of bridge on deep-water oblique river bed | |
CN112177630B (en) | Device and method for vertically jacking shield tunnel | |
CN104564091A (en) | Method and device for removing anchor rods from shield crossing area | |
CN106014427A (en) | Construction method of receiving well pipe jacking machine and steel sleeve for construction | |
CN111997043A (en) | Segmented reinforcement cage and diaphragm wall construction method under low-clearance high-voltage line | |
CN110656952A (en) | Shield tunneling machine cutter head access hole and construction method thereof | |
CN212898512U (en) | Reverse-acting tunnel portal entering system for tunnel portal in steep rock mass in complex terrain | |
CN106087996B (en) | Manual digging pile construction method based on self leveling backpressure device | |
CN203531916U (en) | Tunnel boring machine step pushing support device | |
CN210106749U (en) | Counter-force structure of soft soil foundation super large section push pipe jacking operation | |
CN203891047U (en) | Equipment equipped with steel platform for foundation construction of land bridge | |
CN207469303U (en) | A kind of removable assembled template peace tears operating system open | |
CN115584722A (en) | Construction method of secant pile in water-rich rock-filling layer-containing soft soil area | |
CN106948841A (en) | High ferro tunnel pre-buried channel flow installation mold automatic lifting system and installation method | |
CN109706848B (en) | Construction method for jacking bridge and culvert by using through jack |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB02 | Change of applicant information | ||
CB02 | Change of applicant information |
Address after: 443002 Dongshan Avenue, Hubei, Yichang, No. 54 Applicant after: CHINA GEZHOUBA GROUP NO.1 ENGINEERING CO., LTD. Address before: 443002 Dongshan Avenue, Hubei, Yichang, No. 54 Applicant before: Gezhouba Group No.1 Engineering Co., Ltd. |
|
CB03 | Change of inventor or designer information | ||
CB03 | Change of inventor or designer information |
Inventor after: Li Tonglao Inventor after: Chang Guoge Inventor after: Yu Xiangzhong Inventor after: Ni Siping Inventor after: Xiong Jianwu Inventor after: Hu Fanghua Inventor after: Wen Chao Inventor after: Sun Yunhua Inventor after: Zhao Zhizhong Inventor after: Li Xinming Inventor after: Li Xuehao Inventor after: Zhou Jihong Inventor before: Chang Guoge Inventor before: Yin Fanghui Inventor before: Zhou Jihong Inventor before: Zhao Zhizhong Inventor before: Zhang Shiyun Inventor before: Yu Xiangzhong Inventor before: Lei Yanbing Inventor before: Ni Siping Inventor before: Cui Yusong Inventor before: Liu Zhenjie |
|
GR01 | Patent grant | ||
GR01 | Patent grant |