CN105178968A - Pushing and supporting device of tunneling machine and construction method - Google Patents

Pushing and supporting device of tunneling machine and construction method Download PDF

Info

Publication number
CN105178968A
CN105178968A CN201510313756.6A CN201510313756A CN105178968A CN 105178968 A CN105178968 A CN 105178968A CN 201510313756 A CN201510313756 A CN 201510313756A CN 105178968 A CN105178968 A CN 105178968A
Authority
CN
China
Prior art keywords
anchor hole
supporting
reaction frame
tunnel machine
pushing tow
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510313756.6A
Other languages
Chinese (zh)
Other versions
CN105178968B (en
Inventor
常国阁
周继红
赵志忠
张诗云
余祥忠
雷艳兵
倪四平
崔玉松
柳振杰
尹方辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Gezhouba Group No 1 Engineering Co Ltd
Original Assignee
China Gezhouba Group No 1 Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Gezhouba Group No 1 Engineering Co Ltd filed Critical China Gezhouba Group No 1 Engineering Co Ltd
Priority to CN201510313756.6A priority Critical patent/CN105178968B/en
Publication of CN105178968A publication Critical patent/CN105178968A/en
Application granted granted Critical
Publication of CN105178968B publication Critical patent/CN105178968B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention provides a pushing and supporting device of a tunneling machine and a construction method. The pushing and supporting device of the tunneling machine comprises a plurality of embedded supporting anchor hole beams, at least two inclined slide tracks and a reaction frame; supporting and positioning anchor holes are formed in two ends of each supporting anchor hole beam; reaction frame supporting legs are arranged on the bottom of the reaction frame; and the reaction frame has a frame structure, and is provided with a side surface which is opposite to the end surface of the tail of the tunneling machine and is used for pressing against an auxiliary pushing oil cylinder. The construction method comprises the following steps of (1) welding an embedded bolt on a joint bar; (2) mounting a steel cushion on the embedded bolt through a nut; and (3) mounting the supporting anchor hole beams, the supporting and positioning anchor holes and the slide tracks on the steel cushion, placing the auxiliary hydraulic oil cylinder between the tunneling machine and the reaction frame, and jacking by a stepping stroke. By the steps, the tunneling machine is pushed to walk when beginning to enter a hole. By the pushing and supporting device of the tunneling machine and the construction method, hundreds of tons of stepping thrust can be ensured, and the circumstance that a slide way structure is damaged due to uneven stress can be avoided.

Description

Tunnel machine pushing tow bracing or strutting arrangement and construction method
The application is that name is called " tunnel machine stepping pushing tow bracing or strutting arrangement and construction method ", and the applying date is on November 13rd, 2013, and application number is the divisional application of the patent application of " 2013105619687 ".
Technical field
The present invention relates to tunnel machine construction field, particularly a kind ofly to start into the stepping pushing tow bracing or strutting arrangement in hole and construction method for tunnel machine.
Background technology
Railway, highway, large hydraulic engineering etc. need to construct in rock massif usually, and massif is soft by difference, hard, and the rock of different bedding formed.Along with project scale strengthens, speed of application requires to accelerate, and much length is greater than 6Km, and cross section is greater than 80m 2tunnel, inadaptablely adopt extensive drill bursting construction.In order to speed up the work, reduce secondary lining operation, all adopting tunneling boring rock tunnel development machine (tunnel machine: TunnelBoringMachinc is called for short TBM) milling to dig tunnel at present.Tunnel hard rock mole is erecting bed Installation and Debugging before tunnel mouth, start outside the section of hole because main frame originating location is in tunnel, TMB can not utilize support boots and crag to interact, pushing tow body traction rear portion ancillary facility advances, must by the counter-force bracing or strutting arrangement on bottom auxiliary cylinder and ground, by TBM mainframe section and rear portion ancillary facility etc. by erecting bed outside hole, face driving position in pushing tow to hole.TBM body weight about more than 600 ton, tractive force needed for the devices such as rear ancillary facility about 70 tons, sliding friction power about more than 180 ton of TBM body and ground rail, under the compound action of many kinds of force, pre-buried reaction of bearing device on ground concrete slideway according to a conventional method, the embedding precision of embedded part is not high, and its intensity is also held and be can't stand maximum 250 tons of thrust.
Summary of the invention
Technical problem to be solved by this invention is to provide a kind of tunnel machine pushing tow bracing or strutting arrangement, can provide secure support, and be convenient to Adjustment precision for the pushing tow of tunnel machine.
Another technical problem to be solved by this invention is to provide a kind of construction method of tunnel machine pushing tow bracing or strutting arrangement, embedding precision and intensity can meet the bracing or strutting arrangement of tunnel machine auxiliary hydraulic pressure oil cylinder jacking force.
For solving the problems of the technologies described above, the technical solution adopted in the present invention is: a kind of tunnel machine pushing tow bracing or strutting arrangement, comprises many pre-buried support anchor hole crossbeams, is provided with supporting and location anchor hole at the two ends supporting anchor hole crossbeam;
Many described support anchor hole crossbeams are uniform along the direction of advance of tunnel machine, and the position on support anchor hole crossbeam between supporting and location anchor hole is also provided with the slide rail that at least two upper surface perpendicular bisectors point to the inclination in the same center of circle;
Also comprise reaction frame, the bottom of reaction frame is provided with at least two and forms with supporting and location anchor hole the reaction frame supporting leg patching and coordinate, and reaction frame is frame construction, and has a side for withstand auxiliary top push oil cylinder relative with tunnel machine tail end face.
The oblique steel plate of adjustment making each bar slide rail concentric is installed with bottom described slide rail.
The U-shaped reinforcing bar embedded part of many one slide rails is also provided with in the side of slide rail.
Reaction frame is also provided with oil cylinder reaction plate for the side of withstanding auxiliary top push oil cylinder.
Reaction frame is also provided with top ear with the top of supporting and location anchor hole relevant position, and back timber is inserted in the ear of top, between one end and ground of back timber, be provided with jack.
Described support anchor hole crossbeam is installed on billet, and billet is fixedly connected with many pre-embedded bolt adjustable grounds by nut; Pre-embedded bolt and pre-buried joint bar are welded to connect.
Described billet is fixed between two nuts.
Reaction frame supporting leg is at least four.
A construction method for tunnel machine pushing tow bracing or strutting arrangement, comprises the following steps:
One, excavate on ground one with the groove of tunnel machine corresponding size, in groove, water a layer concrete and many joint bars are imbedded in pushing tow direction along tunnel machine, pre-embedded bolt be welded on joint bar;
Two, billet is installed on pre-embedded bolt by nut, utilizes upper and lower double nut to regulate height and the levelness of billet;
Three, support anchor hole crossbeam is installed on billet, the two ends supporting anchor hole crossbeam are installed with supporting and location anchor hole, measuring center line on support anchor hole crossbeam, the oblique steel plate of adjustment between movable support anchor hole crossbeam and slide rail, by the angle of slope of slide rail, elevation, spacing, concentricity precision and parallelism parameter adjustment to meeting designing requirement;
Four, concreting, to the upper surface of supporting and location anchor hole, and slide rail below circular arc that upper surface connects, to form cambered way;
Five, the reaction frame supporting leg of the bottom of the reaction frame of frame construction is inserted in supporting and location anchor hole, auxiliary hydraulic pressure oil cylinder is placed between tunnel machine tail end face and the side of reaction frame, operation auxiliary hydraulic pressure cylinder jacking, namely promote tunnel machine to walk a stepping stroke, reaction frame is inserted in next group supporting and location anchor hole, the next stepping stroke of jacking;
By above-mentioned steps, realize tunnel machine and start into the pushing tow in hole and walk.
Reaction frame is also provided with top ear with the top of supporting and location anchor hole relevant position, when reaction frame supporting leg is difficult to take out, be inserted into by back timber in the ear of top, between one end and ground of back timber, arrange jack, reaction frame supporting leg top pine can hang out by jack.
A kind of tunnel machine pushing tow bracing or strutting arrangement provided by the invention and construction method, reaction frame is coordinated by pre-buried supporting and location anchor hole, the stepping thrust supporting auxiliary top push oil cylinder hundreds of tons can be guaranteed, structure of the present invention and construction method will make slideway structure be damaged because of unbalance stress, guarantee that TBM starts steadily safe and reliable smoothly into hole stepping pushing tow.In the present invention, pre-embedded bolt coordinates the structure of billet to be convenient to regulate elevation and level, support the structure of anchor hole crossbeam and the oblique steel plate of adjustment, be convenient to the angle of slope adjusting slide rail, elevation, spacing, concentricity precision and parallelism, i.e. structure and method of the present invention, be convenient to very much the precision regulating whole bracing or strutting arrangement, thus avoid unbalance stress.
Physical dimension adjustment of the present invention is simple to operate, and simplify embedded part installation procedure, accelerate mounting and adjusting progress, embedded part installation accuracy is high.The slide rail of cambered way and support anchor hole stress equalization, structural strength is high.
Accompanying drawing explanation
Below in conjunction with drawings and Examples, the invention will be further described:
Fig. 1 is the plan structure schematic diagram of tunnel machine stepping jacking.
Fig. 2 is the structure section schematic diagram of bracing or strutting arrangement of the present invention, have employed omissive representation in figure, is shifted near in the center of circle of slide rail circumscribed circle, so that observe.
Fig. 3 is the structural representation pushing up loose reaction frame supporting leg in the inventive method.
Fig. 4 is the syndeton schematic diagram of joint bar, pre-embedded bolt and billet in the present invention.
Fig. 5 is the structural representation of supporting and location anchor hole and support anchor hole crossbeam in the present invention.
Fig. 6 is slide rail and the structural representation adjusting oblique steel plate in the present invention.
Fig. 7 is the side direction view of Fig. 6.
Fig. 8 is the structural representation of reaction frame in the present invention.
In figure: joint bar 1, pre-embedded bolt 2, billet 3, nut 4, support anchor hole crossbeam 5, supporting and location anchor hole 6, adjusts oblique steel plate 7, sliding rail U-shaped reinforcing bar embedded part 8, slide rail 9, reaction frame supporting leg 10, top ear 11, oil cylinder reaction plate 12, hanger 13, reaction frame 14, auxiliary top push oil cylinder 15, back timber 16, jack 17, cambered way 18, concrete 19, tunnel machine 20.
Detailed description of the invention
Embodiment 1:
As in Fig. 1 ~ 8, a kind of tunnel machine pushing tow bracing or strutting arrangement, comprises many pre-buried support anchor hole crossbeams 5, is provided with supporting and location anchor hole 6 at the two ends supporting anchor hole crossbeam 5; As shown in Fig. 2,3,5, the supporting and location anchor hole 6 in this example preferably adopts rectangular steel tube.
As in Fig. 1,3, many described support anchor hole crossbeams 5 are uniform along the direction of advance of tunnel machine, and the position on support anchor hole crossbeam 5 between supporting and location anchor hole 6 is also provided with the slide rail 9 that at least two upper surface perpendicular bisectors point to the inclination in the same center of circle.As shown in Figure 2, certainly, it will be appreciated by those skilled in the art that error to be there is in actual installation process, as the O in Fig. 2 1and O 2shown in, make O by adjustment as far as possible 1and O 2overlap or in the scope of designing requirement license, Fig. 2 have employed omissive representation, the actual center of circle will in higher position.Slide rail 9 in this example adopts " H " shaped steel slide rail as shown in Figure 6.
As in Fig. 2, below the upper surface of supporting and location anchor hole 6, and slide rail 9 below circular arc that upper surface connects, be filled with concrete 19; Preferably, concrete 19 can meet below circular arc 3 ~ 8mm lower than the upper surface of supporting and location anchor hole 6 and slide rail 9 upper surface.
As in Fig. 1,2,8, also comprise reaction frame 14, the bottom of reaction frame 14 is provided with at least two and forms with supporting and location anchor hole 6 the reaction frame supporting leg 10 patching and coordinate, preferably, adopt four or six to be also feasible according to the weight reaction frame supporting leg 10 of tunnel machine, in this example, then adopt four.
Reaction frame 14 is frame construction, and has a side for withstand auxiliary top push oil cylinder 15 relative with tunnel machine tail end face.Structure thus, as in Fig. 1, is provided the weight support of tunnel machine 20, and provides reliable stepping pushing tow to support by the reaction frame 14 be inserted in supporting and location anchor hole 6 by slide rail 9.
Preferably, as shown in Fig. 2,6,7, bottom described slide rail 9, be installed with the oblique steel plate 7 of adjustment making each bar slide rail concentric.Adjust oblique steel plate 7 higher near one end of this collateral support location anchor hole 6.By adjusting oblique steel plate 7 supporting the position on anchor hole crossbeam 5, the angle of slope of slide rail, elevation, spacing, concentricity precision and parallelism can be regulated easily, thus be convenient to the installation accuracy improving whole bracing or strutting arrangement.
Preferably, as shown in Fig. 6 ~ 7, be also provided with the U-shaped reinforcing bar embedded part 8 of many one slide rails, be also provided with kink in the termination of U-shaped reinforcing bar embedded part 8 in the side of slide rail 9, U-shaped reinforcing bar embedded part 8 is welded to connect with slide rail 9.Structure thus, improves the intensity of slide rail 9 in concrete 19 further.
Preferably, as shown in Fig. 2,8, reaction frame 14 is also provided with oil cylinder reaction plate 12 for the side of withstanding auxiliary top push oil cylinder 15.Structure thus, is convenient to make suffered pressure dissipation to whole reaction frame 14.
Preferably as in Fig. 3, reaction frame 14 is also provided with the top of supporting and location anchor hole 6 relevant position and pushes up ear 11, back timber 16 is inserted in the ear 11 of top, between one end and ground of back timber 16, be provided with jack 17.Structure thus, when reaction frame supporting leg 10 is locked because of slight deformation with supporting and location anchor hole 6, can adopt jack 17 to coordinate back timber 16 that reaction frame supporting leg 10 is pushed up pine, thus be convenient to lift by crane whole reaction frame 14 by the hanger 13 on reaction frame 14.
Described support anchor hole crossbeam 5 is installed on billet 3, and billet 3 is fixedly connected with many pre-embedded bolts 2 adjustable ground by nut 4; Pre-embedded bolt 2 and pre-buried joint bar 1 are welded to connect.
Preferably, as shown in Fig. 2 ~ 4, described billet 3 is fixed between two nuts 4.Structure thus, is convenient to the height-precision and the horizontal accuracy that regulate billet 3.
Embodiment 2:
This example is for adopting the method for embodiment 1 device, the structure do not described in this example, identical with the structure in embodiment 1.
As shown in Fig. 1 ~ 8, a kind of construction method of tunnel machine pushing tow bracing or strutting arrangement, comprises the following steps:
One, excavate on ground one with the groove of tunnel machine 20 corresponding size, in groove, water one deck plain concrete and imbed many joint bars 1 along the pushing tow direction of tunnel machine and stepping pushing tow spacing, pre-embedded bolt 2 being welded on joint bar 1; Plain concrete refers to without muscle or the concrete not configuring steel bar stress.
Two, install billet 3 on pre-embedded bolt 2 by nut 4, in this example, the corner of billet 3 is through pre-embedded bolt 2, and is fixed between upper and lower two nuts 4, utilizes upper and lower double nut to regulate height and the levelness of billet 3;
Three, support anchor hole crossbeam 5 is installed on billet 3, the two ends supporting anchor hole crossbeam 5 are installed with supporting and location anchor hole 6, measuring center line on support anchor hole crossbeam 5, the oblique steel plate 7 of the adjustment between movable support anchor hole crossbeam 5 and slide rail 9, by the angle of slope of slide rail 9 as the α in Fig. 2 1and α 2shown in, elevation, spacing, concentricity precision are as the O in Fig. 2 1and O 2shown in, and parallelism parameter adjustment is to meeting designing requirement;
Four, concreting, to supporting and location anchor hole 6 upper surface, and slide rail 9 below circular arc that upper surface connects, to form cambered way 18; Usually low 3 ~ 8mm.
Five, tunnel machine 20 is placed on slide rail 9, hoist cable is put in the hanger 13 at reaction frame 14 top, with the hoisting mechanism on tunnel machine 20 by reaction frame 14, above handling to cambered way 18, the reaction frame supporting leg 10 of the bottom of the reaction frame 14 of frame construction to be inserted in supporting and location anchor hole 6 and to fall the end, between side auxiliary hydraulic pressure oil cylinder 15 being placed on tunnel machine tail end face and reaction frame 14, operation auxiliary hydraulic pressure oil cylinder 15 cylinder head withstands oil cylinder reaction plate 12, to sinciput stroke, then tunnel machine 20 is at reaction frame 14, under the reaction of reaction frame supporting leg 10 and supporting and location anchor hole 6, promote tunnel machine to walk a stepping stroke, operation auxiliary top push oil cylinder 15 is shunk, reaction frame 14 to be sling reach stepping stroke with the hoisting mechanism of tunnel machine 20, reaction frame 14 is inserted in next group supporting and location anchor hole 6, the next stepping stroke of jacking,
By above-mentioned steps, realize tunnel machine and start into the pushing tow in hole and walk.
Preferably as shown in Figure 3, reaction frame 14 is also provided with the top of supporting and location anchor hole 6 relevant position and pushes up ear 11, when reaction frame supporting leg 10 is difficult to take out, back timber 16 is inserted in the ear 11 of top, between one end and ground of back timber 16, arrange jack 17, reaction frame supporting leg 10 can be pushed up pine and hang out by jack 17.

Claims (10)

1. a tunnel machine pushing tow bracing or strutting arrangement, comprises many pre-buried supports anchor hole crossbeam (5), it is characterized in that: be provided with supporting and location anchor hole (6) at the two ends supporting anchor hole crossbeam (5);
Many described supports anchor hole crossbeam (5) are uniform along the direction of advance of tunnel machine, and in support anchor hole crossbeam (5), the position be positioned between supporting and location anchor hole (6) is also provided with the slide rail (9) that at least two upper surface perpendicular bisectors point to the inclination in the same center of circle;
Also comprise reaction frame (14), the bottom of reaction frame (14) is provided with at least two and forms with supporting and location anchor hole (6) the reaction frame supporting leg (10) patching and coordinate, reaction frame (14) is frame construction, and has a side for withstand auxiliary top push oil cylinder (15) relative with tunnel machine tail end face.
2. a kind of tunnel machine pushing tow bracing or strutting arrangement according to claim 1, is characterized in that: described slide rail (9) bottom is installed with the oblique steel plate of adjustment (7) making each bar slide rail concentric.
3. a kind of tunnel machine pushing tow bracing or strutting arrangement according to claim 1, is characterized in that: be also provided with the U-shaped reinforcing bar embedded part (8) of many one slide rails in the side of slide rail (9).
4. a kind of tunnel machine pushing tow bracing or strutting arrangement according to claim 1, is characterized in that: reaction frame (14) is also provided with oil cylinder reaction plate (12) for the side of withstanding auxiliary top push oil cylinder (15).
5. a kind of tunnel machine pushing tow bracing or strutting arrangement according to claim 1, it is characterized in that: top that is upper at reaction frame (14) and supporting and location anchor hole (6) relevant position is also provided with pushes up ear (11), back timber (16) is inserted in top ear (11), between one end and ground of back timber (16), be provided with jack (17).
6. a kind of tunnel machine pushing tow bracing or strutting arrangement according to claim 1, it is characterized in that: described support anchor hole crossbeam (5) is installed on billet (3), and billet (3) is fixedly connected with many pre-embedded bolts (2) adjustable ground by nut (4); Pre-embedded bolt (2) and pre-buried joint bar (1) are welded to connect.
7. a kind of tunnel machine pushing tow bracing or strutting arrangement according to claim 6, is characterized in that: described billet (3) is fixed between two nuts (4).
8. a kind of tunnel machine pushing tow bracing or strutting arrangement according to claim 1, is characterized in that: reaction frame supporting leg (10) is at least four.
9., as right requires a construction method for the tunnel machine pushing tow bracing or strutting arrangement as described in 1 ~ 8 any one, it is characterized in that comprising the following steps:
One, excavate on ground one with the groove of tunnel machine (20) corresponding size, in groove, water a layer concrete and many joint bars (1) are imbedded in pushing tow direction along tunnel machine, pre-embedded bolt (2) be welded on joint bar (1);
Two, billet (3) is installed on pre-embedded bolt (2) by nut (4), utilizes upper and lower double nut to regulate height and the levelness of billet (3);
Three, anchor hole crossbeam (5) is supported upper installation of billet (3), the two ends supporting anchor hole crossbeam (5) are installed with supporting and location anchor hole (6), at the upper measuring center line of support anchor hole crossbeam (5), the oblique steel plate of adjustment (7) between movable support anchor hole crossbeam (5) and slide rail (9), by the angle of slope of slide rail (9), elevation, spacing, concentricity precision and parallelism parameter adjustment to meeting designing requirement;
Four, concreting, to the upper surface of supporting and location anchor hole (6), and slide rail (9) below circular arc that upper surface connects, to form cambered way (18);
Five, the reaction frame supporting leg (10) of the bottom of the reaction frame (14) of frame construction is inserted in supporting and location anchor hole (6), between side auxiliary hydraulic pressure oil cylinder (15) being placed on tunnel machine tail end face and reaction frame (14), oil cylinder (15) jacking of operation auxiliary hydraulic pressure, namely promote tunnel machine to walk a stepping stroke, reaction frame (14) is inserted in next group supporting and location anchor hole (6), the next stepping stroke of jacking;
By above-mentioned steps, realize tunnel machine and start into the pushing tow in hole and walk.
10. the construction method of a kind of tunnel machine pushing tow bracing or strutting arrangement according to claim 9, it is characterized in that: top that is upper at reaction frame (14) and supporting and location anchor hole (6) relevant position is also provided with pushes up ear (11), when reaction frame supporting leg (10) is difficult to take out, back timber (16) is inserted in top ear (11), between one end and ground of back timber (16), arrange jack (17), reaction frame supporting leg (10) top pine can hang out by jack (17).
CN201510313756.6A 2013-11-13 2013-11-13 Rock tunnel(ling) machine pushing tow support meanss and construction method Active CN105178968B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510313756.6A CN105178968B (en) 2013-11-13 2013-11-13 Rock tunnel(ling) machine pushing tow support meanss and construction method

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201510313756.6A CN105178968B (en) 2013-11-13 2013-11-13 Rock tunnel(ling) machine pushing tow support meanss and construction method
CN201310561968.7A CN103541735B (en) 2013-11-13 2013-11-13 Tunnel boring machine stepping push support device and construction method

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201310561968.7A Division CN103541735B (en) 2013-11-13 2013-11-13 Tunnel boring machine stepping push support device and construction method

Publications (2)

Publication Number Publication Date
CN105178968A true CN105178968A (en) 2015-12-23
CN105178968B CN105178968B (en) 2017-08-01

Family

ID=49965546

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201310561968.7A Active CN103541735B (en) 2013-11-13 2013-11-13 Tunnel boring machine stepping push support device and construction method
CN201510313756.6A Active CN105178968B (en) 2013-11-13 2013-11-13 Rock tunnel(ling) machine pushing tow support meanss and construction method

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN201310561968.7A Active CN103541735B (en) 2013-11-13 2013-11-13 Tunnel boring machine stepping push support device and construction method

Country Status (1)

Country Link
CN (2) CN103541735B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107575239A (en) * 2017-10-16 2018-01-12 粤水电轨道交通建设有限公司 A kind of portable shield launching device for small space
CN109098206A (en) * 2018-09-12 2018-12-28 中交第二航务工程局有限公司 City tunnel prefabrication and assembly construction construction method and precast assembly development machine
CN109296377A (en) * 2018-09-25 2019-02-01 中铁工程服务有限公司 A kind of construction method that rock tunnel(ling) machine stepping is appeared
CN111119911A (en) * 2019-12-04 2020-05-08 中铁隧道集团二处有限公司 A hydraulic displacement device for roadheader
CN111663902A (en) * 2020-07-17 2020-09-15 中国铁建重工集团股份有限公司 Tension reaction frame for core drilling machine
CN113818894A (en) * 2021-10-20 2021-12-21 中铁十五局集团有限公司 Working method of sliding plate type TBM stepping device
CN114263469A (en) * 2021-11-10 2022-04-01 中铁二局集团有限公司 TBM or shield tunneling machine rapid jacking system and construction method

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103541735B (en) * 2013-11-13 2015-07-08 葛洲坝集团第一工程有限公司 Tunnel boring machine stepping push support device and construction method
CN109441461A (en) * 2018-12-17 2019-03-08 中国水利水电第四工程局有限公司 A kind of Double shield TBM step device and application method
CN111086573B (en) * 2020-02-14 2025-08-01 德马科技集团股份有限公司 Modularized backpack transfer type AGV automatic carrier
CN111502685B (en) * 2020-05-22 2025-05-16 中船(青岛)轨道交通装备有限公司 Auxiliary bracket for self-propelled hard rock tunnel boring machine

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007051513A (en) * 2005-08-19 2007-03-01 Towa Kogyo Kk Pipe propulsion machine
CN201802406U (en) * 2010-08-23 2011-04-20 上海市第一市政工程有限公司 Shield translation transit counterforce system
CN201802408U (en) * 2010-08-20 2011-04-20 上海市第一市政工程有限公司 Self-traveling shield station-crossing movement system
CN202417508U (en) * 2011-12-26 2012-09-05 中铁四局集团有限公司 Pushing system for pushing and turning construction of shield tunneling machine in subway tunnel
CN102797471A (en) * 2012-06-21 2012-11-28 中铁十三局集团有限公司 TBM (tunnel boring machine) stepping method for open cutting of tunnel lining section in inclined shaft
CN103541735B (en) * 2013-11-13 2015-07-08 葛洲坝集团第一工程有限公司 Tunnel boring machine stepping push support device and construction method

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE10040777A1 (en) * 2000-08-21 2002-03-07 Tachus Gmbh Process and machine for tunnel construction, formwork element and formwork system
CN102278117B (en) * 2011-04-29 2013-03-20 上海交通大学 Parallel pipe jacking construction simulation device
CN102418530B (en) * 2011-12-14 2013-07-31 中铁十二局集团第二工程有限公司 Roller guide rail station-passing construction method of whole shield machine
CN103032071B (en) * 2012-12-09 2015-01-28 中铁十二局集团有限公司 Shield receiving forward-shift construction method of boulder group open excavation and embedment mutation space
CN203531916U (en) * 2013-11-13 2014-04-09 葛洲坝集团第一工程有限公司 Tunnel boring machine step pushing support device

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007051513A (en) * 2005-08-19 2007-03-01 Towa Kogyo Kk Pipe propulsion machine
CN201802408U (en) * 2010-08-20 2011-04-20 上海市第一市政工程有限公司 Self-traveling shield station-crossing movement system
CN201802406U (en) * 2010-08-23 2011-04-20 上海市第一市政工程有限公司 Shield translation transit counterforce system
CN202417508U (en) * 2011-12-26 2012-09-05 中铁四局集团有限公司 Pushing system for pushing and turning construction of shield tunneling machine in subway tunnel
CN102797471A (en) * 2012-06-21 2012-11-28 中铁十三局集团有限公司 TBM (tunnel boring machine) stepping method for open cutting of tunnel lining section in inclined shaft
CN103541735B (en) * 2013-11-13 2015-07-08 葛洲坝集团第一工程有限公司 Tunnel boring machine stepping push support device and construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
翟志国: "泥水盾构施工技术", 《水科学与工程技术》 *

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107575239A (en) * 2017-10-16 2018-01-12 粤水电轨道交通建设有限公司 A kind of portable shield launching device for small space
CN107575239B (en) * 2017-10-16 2024-04-02 粤水电轨道交通建设有限公司 Movable shield launching device for narrow space
CN109098206A (en) * 2018-09-12 2018-12-28 中交第二航务工程局有限公司 City tunnel prefabrication and assembly construction construction method and precast assembly development machine
CN109296377A (en) * 2018-09-25 2019-02-01 中铁工程服务有限公司 A kind of construction method that rock tunnel(ling) machine stepping is appeared
CN111119911A (en) * 2019-12-04 2020-05-08 中铁隧道集团二处有限公司 A hydraulic displacement device for roadheader
CN111119911B (en) * 2019-12-04 2024-04-30 中铁隧道集团二处有限公司 Hydraulic shifting device for heading machine
CN111663902A (en) * 2020-07-17 2020-09-15 中国铁建重工集团股份有限公司 Tension reaction frame for core drilling machine
CN113818894A (en) * 2021-10-20 2021-12-21 中铁十五局集团有限公司 Working method of sliding plate type TBM stepping device
CN114263469A (en) * 2021-11-10 2022-04-01 中铁二局集团有限公司 TBM or shield tunneling machine rapid jacking system and construction method
CN114263469B (en) * 2021-11-10 2023-11-14 中铁二局集团有限公司 TBM or shield tunneling machine rapid jacking system and construction method

Also Published As

Publication number Publication date
CN103541735B (en) 2015-07-08
CN105178968B (en) 2017-08-01
CN103541735A (en) 2014-01-29

Similar Documents

Publication Publication Date Title
CN105178968A (en) Pushing and supporting device of tunneling machine and construction method
US9822506B2 (en) Construction system for subway station
CN107191676A (en) Construction method of buried pipeline
CN102200019B (en) Tunnel boring machine middle-plate stepping reinforcing support mechanism and construction method thereof
CN111794783B (en) Trolley is assembled to tunnel open cut tunnel section of jurisdiction
CN109081259B (en) Method for realizing mounting and positioning of large PCC (PCC) equipment of combustion engine in narrow space
CN108396754B (en) Construction method of suspended floating splicing steel cofferdam
KR20190034815A (en) Railroad bridge construction method for keeping preexistence railroad track and rail service
CN203531916U (en) Tunnel boring machine step pushing support device
CN113215991B (en) Rapid steel box girder erection device and construction method thereof
JP5032787B2 (en) Heavy equipment installation equipment
CN111456009A (en) Engineering pile guiding device in piling construction and using method thereof
CN115012950B (en) Water-rich sand layer pipe jacking construction method close to subway
US20100080658A1 (en) System for supporting slab with concrete pier
CN109826173A (en) A kind of pile base construction method using stake top mobile platform
CN214575722U (en) Constructional engineering support
CN119825987A (en) Efficient construction device and construction method for mud-water balance jacking pipe to penetrate through railway roadbed
CN113738156A (en) Temporary support structure in limited space and dismantling method thereof
US6354769B1 (en) Apparatus and method for replacing in-ground elevator cylinder casings
CN109706848B (en) Construction method for jacking bridge and culvert by using through jack
CN215053064U (en) Lattice column verticality correction device
CN107869139B (en) Pile planting machine with monitoring function
CN217419647U (en) Prestress applying structure and foundation pit beam string steel pull rod prestress applying node
JP2005350996A (en) Bridge erection device and method
CN114214919A (en) Counter-force prepressing construction method and system for oversized zero-block bracket of cable-stayed bridge in water area

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: 443002 Dongshan Avenue, Hubei, Yichang, No. 54

Applicant after: CHINA GEZHOUBA GROUP NO.1 ENGINEERING CO., LTD.

Address before: 443002 Dongshan Avenue, Hubei, Yichang, No. 54

Applicant before: Gezhouba Group No.1 Engineering Co., Ltd.

CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Li Tonglao

Inventor after: Chang Guoge

Inventor after: Yu Xiangzhong

Inventor after: Ni Siping

Inventor after: Xiong Jianwu

Inventor after: Hu Fanghua

Inventor after: Wen Chao

Inventor after: Sun Yunhua

Inventor after: Zhao Zhizhong

Inventor after: Li Xinming

Inventor after: Li Xuehao

Inventor after: Zhou Jihong

Inventor before: Chang Guoge

Inventor before: Yin Fanghui

Inventor before: Zhou Jihong

Inventor before: Zhao Zhizhong

Inventor before: Zhang Shiyun

Inventor before: Yu Xiangzhong

Inventor before: Lei Yanbing

Inventor before: Ni Siping

Inventor before: Cui Yusong

Inventor before: Liu Zhenjie

GR01 Patent grant
GR01 Patent grant