CN106948841A - High ferro tunnel pre-buried channel flow installation mold automatic lifting system and installation method - Google Patents

High ferro tunnel pre-buried channel flow installation mold automatic lifting system and installation method Download PDF

Info

Publication number
CN106948841A
CN106948841A CN201710391068.0A CN201710391068A CN106948841A CN 106948841 A CN106948841 A CN 106948841A CN 201710391068 A CN201710391068 A CN 201710391068A CN 106948841 A CN106948841 A CN 106948841A
Authority
CN
China
Prior art keywords
conduit
top board
high ferro
channel flow
buried channel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710391068.0A
Other languages
Chinese (zh)
Inventor
高江涛
刘继鹏
汤贵海
刘小东
张军
何先虎
庞前凤
郭世荣
徐小燕
朱丽丽
李毅成
王建华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Engineering Co Ltd of China Railway 22nd Bureau Group Co Ltd
China Railway 22nd Bureau Group Co Ltd
Original Assignee
First Engineering Co Ltd of China Railway 22nd Bureau Group Co Ltd
China Railway 22nd Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Engineering Co Ltd of China Railway 22nd Bureau Group Co Ltd, China Railway 22nd Bureau Group Co Ltd filed Critical First Engineering Co Ltd of China Railway 22nd Bureau Group Co Ltd
Priority to CN201710391068.0A priority Critical patent/CN106948841A/en
Publication of CN106948841A publication Critical patent/CN106948841A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/102Removable shuttering; Bearing or supporting devices therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/40Devices or apparatus specially adapted for handling or placing units of linings or supporting units for tunnels or galleries

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention provides a kind of high ferro tunnel pre-buried channel flow installation mold automatic lifting system and installation method.The high ferro tunnel pre-buried channel flow installation mold automatic lifting system includes:Conduit supporting part, the conduit supporting part includes top board and the circumferentially disposed end plate around the top board, and the top board is curved, and the end plate opposed vertical direction is obliquely set;Lowering or hoisting gear, is arranged on the lower section of the conduit supporting part, and the upper end of the lowering or hoisting gear is connected with the conduit supporting part.The present invention can improve the installation accuracy of conduit, and install convenient, rapidly and efficiently, it is simple to operate safely, be not limited by a space, procedure connection is compact etc..

Description

High ferro tunnel pre-buried channel flow installation mold automatic lifting system and installation method
Technical field
The present invention relates to high ferro technical field of tunnel construction, more particularly to a kind of high ferro tunnel pre-buried channel flow installation mold is certainly Dynamic jacking system and installation method.
Background technology
In recent years, the ripe immobilizing foundation applied to Railway Tunnel contact net is filled extensively for the installation of tunnel pre-buried channel flow In putting, reliable guarantee is provided for the installation of Railway Tunnel contact net, is also the important safety of high speed rail train operation Ensure, but be due to current conduit mounting process it is still immature, and there is many drawbacks:1. two conduits are not parallel;2. edge Tunnel lateral direction is buried partially;3. pre-buried depth is undesirable;4. during two lining concreting, conduit is squeezed inclined by concrete lateral pressure, even Conduit " missing ";5. conduit installation accuracy requires high, and common laborer is difficult to accomplish high accuracy install, it is necessary to which professional is carried out; 6. chassis headroom is narrow and small, and workman operates on cambered surface workbench, installs inconvenience, and be unfavorable for safety;7. lining cutting is worked as When concrete has reinforced bar engineering, operating space is even more narrow and small, is forced to change working procedure and influence construction speed;8. conduit is pacified During dress, conduit group, the group inconvenience of lifting conduit are first processed on ground, and lifting process is easily reduced conduit installation accuracy etc..These Drawback often leads to conduit and discarded, and causes the waste of resource.
The content of the invention
It is an object of the invention to provide a kind of high ferro tunnel pre-buried channel flow installation mold automatic lifting system and installation method, It is low with the installation accuracy for solving conduit in the prior art, and install inconvenience, low efficiency, complex operation, it is dangerous, limited by space System, the problem of procedure connection is not compact.
In order to solve the above technical problems, the invention provides a kind of high ferro tunnel pre-buried channel flow installation mold automatic lifting system System, including:Conduit supporting part, the conduit supporting part includes top board and the circumferentially disposed end plate around the top board, institute State top board curved, the end plate opposed vertical direction is obliquely set;Lowering or hoisting gear, is arranged on the conduit supporting part Lower section, and the upper end of the lowering or hoisting gear is connected with the conduit supporting part.
Preferably, the top board surrounds an installing space that Open Side Down, the installing space with the end plate Section from top to bottom gradually increase.
Preferably, it is provided with brace rod in the installing space.
Preferably, the brace rod includes multiple the first brace rods be arrangeding in parallel and multiple the second supports be arrangeding in parallel Muscle, first brace rod and the mutually perpendicularly crossed setting of second brace rod are to form network-like supporting construction.
Preferably, the upper surface of the top board is provided with the spacing mark for positioning conduit to be supported.
Preferably, the connecting bolt for being connected at the opening with trolley formwork is formed with the end plate.
Preferably, the lowering or hoisting gear is four, and lowering or hoisting gear described in two of which is axially arranged along the top board, separately Outer two lowering or hoisting gears are along the circumferentially disposed of the top board.
Preferably, the lowering or hoisting gear is oil cylinder.
Present invention also offers a kind of high ferro tunnel pre-buried channel flow installation method, including:Step 1, measured in arch crown part Go out tunnel center line and lateral reference line, the installation site of Primary Location conduit;Step 2, assembling reinforcement, and make reinforced mesh and groove Road anchor pin is mutually avoided;Step 3, lining trolley is positioned;Step 4, conduit is positioned by T-bolt, and by two conduits with short Reinforcement welding is overall conduit group;Step 5, above-mentioned high ferro tunnel pre-buried channel flow installation mold automatic lifting system is moved to At the opening of lining trolley, and by the upward jacking of its top board, then it will pass through at the edge of opening of its end plate and lining trolley Bolt connection;Step 6, to space the casting concrete more than top board;Step 7, treat that lining concrete intensity meets form removal It is required that when, unclamp and take out T-bolt, and the connection between the bolt of end plate and the edge of opening of lining trolley is kept, then Connection iron pin between lowering or hoisting gear and conduit supporting part, which is taken out, makes it with conduit support section from then withdrawing lining trolley Template is stripped;Step 8, lining trolley moves forward and pours next lining cutting section, then puts on the connection iron pin, takes out end plate Bolt, withdraws lowering or hoisting gear, conduit supporting part is separated with chassis;Step 9, the direct all conduits of circulation step 1-8 are installed Finish.
Preferably, the fixed square hole of a positioning is respectively opened at the two ends and middle part of the conduit, and the length of the fixed square hole of positioning is not Less than 3 times of lining cutting ring bar diameter, width meets the installation of T-bolt, the length direction and circuit of the fixed square hole of positioning It is parallel longitudinal.
The present invention can improve the installation accuracy of conduit, and install convenient, rapidly and efficiently, safety simple to operate, not by sky Between limitation, procedure connection it is compact etc..
In addition to objects, features and advantages described above, the present invention also has other objects, features and advantages. The present invention is further detailed explanation below.
Brief description of the drawings
The Figure of description for constituting the part of the present invention is used for providing a further understanding of the present invention, and of the invention shows Meaning property embodiment and its illustrate be used for explain the present invention, do not constitute inappropriate limitation of the present invention.In the accompanying drawings:
Fig. 1 is the schematic diagram of the tunnel-liner standard section in the present invention;
Fig. 2 is the schematic diagram of the conduit mould cross-sectional view in the present invention;
Fig. 3 is the top view at the top of the lining trolley in the present invention;
Fig. 4 is Fig. 3 A-A sectional views;
Fig. 5 is Fig. 3 B-B sectional views;
Fig. 6 is the scheme of installation of the conduit in the present invention;
Fig. 7 is that close-up schematic view is installed in conduit mould cross section;
Fig. 8 is the flow chart of conduit installation method.
Reference in figure:
1st, top board;2nd, end plate;3rd, lowering or hoisting gear;4th, the first brace rod;5th, the second brace rod;6th, conduit;7th, chassis mould Plate;8th, connecting bolt;9th, rail level;10th, truss;11st, conduit supporting part;12nd, bolt mounting holes;13rd, steel pipe;14th, backing plate.
Embodiment
It should be noted that in the case where not conflicting, the embodiment in the present invention and the feature in embodiment can phases Mutually combination.The present invention is described in detail with reference to embodiment.
In order that those skilled in the art more fully understand the present invention program, below by the skill in the embodiment of the present invention Art scheme is clearly and completely described, it is clear that described embodiment is only the embodiment of a part of the invention, without It is whole embodiments.Based on the embodiment in the present invention, those of ordinary skill in the art are not before creative work is made The every other embodiment obtained is put, should all belong to the scope of protection of the invention.
Pre-buried channel flow is Railway Tunnel electrified contacting netses immobilizing foundation device, and its installation accuracy directly affects height The safe operation of fast railroad train, therefore, the invention provides a kind of high ferro tunnel pre-buried channel flow installation mold automatic lifting system System, including:Conduit supporting part 11 and lowering or hoisting gear 3.As shown in figure 1, tunnel has rail level 9.
Wherein, the conduit supporting part includes top board 1 and the circumferentially disposed end plate 2 around the top board, the top Plate 1 is curved, and the opposed vertical direction of end plate 2 is obliquely set.Preferably, top board 1 has and lining trolley template arc The consistent radian of radius surface.For example, the thickness of end plate 2 is 16mm.
Lowering or hoisting gear 3, is arranged on the lower section of the conduit supporting part, and the upper end of the lowering or hoisting gear 3 and the conduit Supporting part is connected.Preferably, the lowering or hoisting gear 3 is oil cylinder, naturally it is also possible to be other conventional elevating mechanisms, so as to adjust The predetermined height of conduit supporting part arrival carries out the operation such as demoulding, plays a supporting role simultaneously.
In use, in the top drilling of existing lining trolley, and a set of above-mentioned height is installed immediately below osseotomy site Iron tunnel pre-buried channel flow installation mold automatic lifting system.Then, conduit 6 is placed on top board 1, then utilizes lowering or hoisting gear 3, by the upward jack-up of top board 1, so that conduit 6 is pushed up to predetermined height and position, then pour into a mould concrete again.
Due to conduit is first arranged on top board 1, thus can ensure between conduit it is parallel, prevent along tunnel lateral direction bury partially, Conduit is squeezed inclined even conduit " missing " by concrete lateral pressure during two lining concreting, in addition, can also be controlled by lowering or hoisting gear 3 pre- Buried depth degree reaches pre-provisioning request, therefore does not need the patent personnel can to carry out high accuracy install.
Fig. 6 and Fig. 7 are refer to, during construction, high ferro tunnel pre-buried channel flow installation mold automatic lifting system country fair purlin can be put On frame 10, therefore workman is operated in the underlying space of top board, overcomes (1) chassis headroom in the prior art narrow It is small, and workman operates on cambered surface workbench, installs inconvenience and is unfavorable for safety;(2) when lining concrete has bar bender Cheng Shi, operating space is even more narrow and small, is forced to change working procedure and influence construction speed;(3) conduit group first is processed on ground, risen The inconvenience of conduit group is hung, and lifting process is the problems such as be easily reduced conduit installation accuracy
Thus can hilllock, by above-mentioned technical scheme, the present invention can improve the installation accuracy of conduit 6, and install convenient, Rapidly and efficiently, it is simple to operate safely, be not limited by a space, procedure connection is compact etc..
Preferably, the top board 1 surrounds an installing space that Open Side Down with the end plate 2, and the installation is empty Between section from top to bottom gradually increase.So, one similar truncated rectangular pyramids structure of top board 1 and the end plate 2 formation is upper small Lower big structure.
Because lining trolley osseotomy site is weak link, the steel plate thickness of top board 1 is no less than 16mm.The length of top board 1 Degree is depending on the length of conduit, and width should adapt to two different spacer conditions of conduit, and (two channel lengths are generally 2500mm With two kinds of 3000mm, spacing is two kinds of situations of 400mm and 600mm).
For example, the angle between end plate 2 and horizontal plane is 75 degree, wedge shape is constituted, so as to mold system and chassis top dress Or depart from, and play positioning action.
Preferably, it is provided with brace rod in the installing space.Preferably, the brace rod includes multiple be arranged in parallel First brace rod 4 and multiple the second brace rods 5 be arrangeding in parallel, first brace rod 4 and second brace rod 5 mutually hang down It is directly arranged in a crossed manner to form network-like supporting construction.The thickness of brace rod can be 10mm, the multiple first brace rod 4 and The multiple second brace rod 5 is set as cross-shaped, and lowering or hoisting gear 3 is installed in lower section.
Preferably, the upper surface of the top board 1 is provided with the spacing mark for positioning conduit 6 to be supported.Gag lever post Note can be formed on top board 1 by way of portraying, and it matches with channel lengths and spacing, so as to quick positioning conduit position Put.
Preferably, it is formed with the end plate 2 for the connecting bolt 8 with being connected at the opening of trolley formwork 7.Conduit When supporting part is in top dress state with chassis, bolted by the hole of bolt mounting holes 12 and trolley formwork of surrounding.During disengaging, lay down Bolt connection, makes mould separating chassis, to install conduit again by withdrawing oil cylinder.It should be noted that during oil cylinder withdrawal, tackling mould With certain downward pulling force, pulling force excessive should not be advisable with departing from chassis.Liftable oil cylinder stroke is grasped with meeting staff It is advisable, is located on chassis truss as space.
Preferably, the lowering or hoisting gear 3 is four, and axial direction of the lowering or hoisting gear 3 described in two of which along the top board 1 is set Put, two other described lowering or hoisting gear 3 is along the circumferentially disposed of the top board 1.The stroke of lowering or hoisting gear 3 is at least 500mm.
Preferably, the top of top board 1 is also associated with jacking, and the jacking includes steel pipe 13 and backing plate 14, the upper end of steel pipe 13 It is connected with top board 1, lower end is connected with backing plate 14, the upper end of lowering or hoisting gear 3 and backing plate 14 are detachably connected.
Lining cutting be plain concrete location conduit install and be armored concrete location compared with lining cutting for, it is relatively easy, therefore This only introduces conduit installation method when lining concrete has reinforcing bar.Therefore, present invention also offers a kind of high ferro tunnel is pre-buried Conduit installation method, including:
Step 1, tunnel center line and lateral reference line, the installation site of Primary Location conduit 6 are measured in arch crown part;
Step 2, assembling reinforcement, and reinforced mesh is mutually avoided with conduit anchor pin;
Step 3, lining trolley is positioned;
Step 4, conduit is positioned by T-bolt, and two conduits is welded as overall conduit group with bar dowel;
Step 5, above-mentioned high ferro tunnel pre-buried channel flow installation mold automatic lifting system is moved to opening for lining trolley At mouthful, and by its upward jacking of top board 1, then by its end plate 2 with being bolted at the edge of opening of lining trolley;
Step 6, to the space casting concrete of the top board more than 1;
Step 7, when lining concrete intensity meets form removal requirement, unclamp and take out T-bolt, and keep the spiral shell of end plate Connection between bolt and the edge of opening of lining trolley, then takes the connection iron pin between lowering or hoisting gear 3 and conduit supporting part Send as an envoy to its with conduit support section from then withdrawing the demoulding of lining trolley template;
Step 8, lining trolley moves forward and pours next lining cutting section, then puts on the connection iron pin, takes out end plate 2 Bolt, withdraws lowering or hoisting gear 3, conduit supporting part is separated with chassis;
Step 9, the direct all conduits of circulation step 1-8 are installed.
Preferably, the fixed square hole of a positioning is respectively opened at the two ends and middle part of the conduit, and the length of the fixed square hole of positioning is not Less than 3 times of lining cutting ring bar diameter, width meets the installation of T-bolt, the length direction and circuit of the fixed square hole of positioning It is parallel longitudinal.
In addition, in construction, it should also be noted that following item:
1st, when chassis is walked, jacking cylinder is kept to be in released state with mould, to avoid mold system from deforming;
2nd, it is general to increase 5cm than design lining section when chassis is processed, therefore it is considered as this factor during conduit production The influence of pair radius.
3rd, the position of concrete pumping mouthful and injected hole should avoid conduit mold system.
4th, this conduit mould in concreting stress based on bolt connection stress, supplemented by jack-up system stress.
5th, when mold system declines, there should be the measure for preventing mold tilt or rotation.
The preferred embodiments of the present invention are the foregoing is only, are not intended to limit the invention, for the skill of this area For art personnel, the present invention can have various modifications and variations.Within the spirit and principles of the invention, that is made any repaiies Change, equivalent, improvement etc., should be included within the scope of the present invention.

Claims (10)

1. a kind of high ferro tunnel pre-buried channel flow installation mold automatic lifting system, it is characterised in that including:
Conduit supporting part, the conduit supporting part includes top board (1) and the circumferentially disposed end plate (2) around the top board, The top board (1) is curved, and end plate (2) the opposed vertical direction is obliquely set;
Lowering or hoisting gear (3), is arranged on the lower section of the conduit supporting part, and upper end and the conduit of the lowering or hoisting gear (3) Supporting part is connected.
2. pre-buried channel flow installation mold automatic lifting system in high ferro tunnel according to claim 1, it is characterised in that described Top board (1) surrounds an installing space that Open Side Down with the end plate (2), and the section of the installing space is from top to bottom Gradually increase.
3. pre-buried channel flow installation mold automatic lifting system in high ferro tunnel according to claim 1, it is characterised in that described Brace rod is provided with installing space.
4. pre-buried channel flow installation mold automatic lifting system in high ferro tunnel according to claim 3, it is characterised in that described Brace rod includes multiple the first brace rods (4) be arrangeding in parallel and multiple the second brace rods (5) be arrangeding in parallel, described first Muscle (4) and the mutually perpendicularly crossed setting of second brace rod (5) is supportted to form network-like supporting construction.
5. pre-buried channel flow installation mold automatic lifting system in high ferro tunnel according to claim 3, it is characterised in that described The upper surface of top board (1) is provided with the spacing mark for positioning conduit (6) to be supported.
6. pre-buried channel flow installation mold automatic lifting system in high ferro tunnel according to claim 1, it is characterised in that described It is formed with end plate (2) for the connecting bolt (8) with being connected at the opening of trolley formwork (7).
7. pre-buried channel flow installation mold automatic lifting system in high ferro tunnel according to claim 1, it is characterised in that described Lowering or hoisting gear (3) is four, and lowering or hoisting gear described in two of which (3) is axially arranged along the top board (1), described in two other Lowering or hoisting gear (3) is circumferentially disposed along the top board (1).
8. pre-buried channel flow installation mold automatic lifting system in high ferro tunnel according to claim 1, it is characterised in that described Lowering or hoisting gear (3) is oil cylinder.
9. a kind of high ferro tunnel pre-buried channel flow installation method, it is characterised in that including:
Step 1, tunnel center line and lateral reference line, the installation site of Primary Location conduit (6) are measured in arch crown part;
Step 2, assembling reinforcement, and reinforced mesh is mutually avoided with conduit anchor pin;
Step 3, lining trolley is positioned;
Step 4, conduit is positioned by T-bolt, and two conduits is welded as overall conduit group with bar dowel;
Step 5, the high ferro tunnel pre-buried channel flow installation mold automatic lifting system any one of claim 1 to 8 is moved Move to the opening of lining trolley, and by the jacking upwards of its top board (1), then by the opening of its end plate (2) and lining trolley Edge is bolted;
Step 6, to space the casting concrete more than top board (1);
Step 7, when lining concrete intensity meets form removal requirement, unclamp and take out T-bolt, and keep the bolt of end plate with Connection between the edge of opening of lining trolley, then takes out the connection iron pin between lowering or hoisting gear (3) and conduit supporting part Make it with conduit support section from the then withdrawal lining trolley template demoulding;
Step 8, lining trolley moves forward and pours next lining cutting section, then puts on the connection iron pin, takes out the spiral shell of end plate (2) Bolt, withdraws lowering or hoisting gear (3), conduit supporting part is separated with chassis;
Step 9, the direct all conduits of circulation step 1-8 are installed.
10. high ferro tunnel pre-buried channel flow installation method according to claim 9, it is characterised in that the two ends of the conduit And the fixed square hole of a positioning is respectively opened at middle part, the length of the fixed square hole of positioning is not less than 3 times of lining cutting ring bar diameter, width The installation of T-bolt is met, the length direction and circuit of the fixed square hole of positioning are parallel longitudinal.
CN201710391068.0A 2017-05-27 2017-05-27 High ferro tunnel pre-buried channel flow installation mold automatic lifting system and installation method Pending CN106948841A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710391068.0A CN106948841A (en) 2017-05-27 2017-05-27 High ferro tunnel pre-buried channel flow installation mold automatic lifting system and installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710391068.0A CN106948841A (en) 2017-05-27 2017-05-27 High ferro tunnel pre-buried channel flow installation mold automatic lifting system and installation method

Publications (1)

Publication Number Publication Date
CN106948841A true CN106948841A (en) 2017-07-14

Family

ID=59479916

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710391068.0A Pending CN106948841A (en) 2017-05-27 2017-05-27 High ferro tunnel pre-buried channel flow installation mold automatic lifting system and installation method

Country Status (1)

Country Link
CN (1) CN106948841A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108394018A (en) * 2018-04-28 2018-08-14 厦门中建智欣建工科技有限公司 A kind of device and segment die for fixing pre-buried channel flow
CN108643936A (en) * 2018-04-27 2018-10-12 长沙泽和智能科技有限公司 A kind of lining trolley working window having automatic open-close function

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101182774A (en) * 2007-12-20 2008-05-21 中铁十二局集团有限公司 Railway large-bore tunnel overhead contact built-in sliding chute construction method
EP2372035A1 (en) * 2010-03-31 2011-10-05 Ferroberica, S.L. Improvement in the production process of arch segments by the introduction of a new system for securing panels and moulding meshes that comprise it
CN203211121U (en) * 2013-05-03 2013-09-25 中铁十二局集团第七工程有限公司 Assembling device for tunnel contact net groove passages
CN203919350U (en) * 2014-07-01 2014-11-05 山东天盾矿用设备有限公司 The segment die of pre-buried channel flow is installed
CN104790969A (en) * 2015-03-04 2015-07-22 中铁二十四局集团福建铁路建设有限公司 Two-time positioning construction process for pre-buried channels of overhead line system of high-speed railway tunnel
CN205297594U (en) * 2015-11-30 2016-06-08 中交第二航务工程局有限公司 Tunnel construction support device
CN106223975A (en) * 2016-09-23 2016-12-14 中国水利水电第四工程局有限公司 A kind of tunnel overhead contact conduit processing and positioning device
CN106437767A (en) * 2016-11-01 2017-02-22 中昊创业高铁新材料有限公司 Tunnel pre-burying conduit installation structure and tunnel pre-burying conduit installation method
CN206092022U (en) * 2016-10-25 2017-04-12 陕西铁路工程职业技术学院 Be used for lining cutting rectangular -section or radiation gradual change rectangular -section formula operation car of crawling
CN206917668U (en) * 2017-05-27 2018-01-23 中铁二十二局集团第一工程有限公司 High ferro tunnel pre-buried channel flow installation mold automatic lifting system

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101182774A (en) * 2007-12-20 2008-05-21 中铁十二局集团有限公司 Railway large-bore tunnel overhead contact built-in sliding chute construction method
EP2372035A1 (en) * 2010-03-31 2011-10-05 Ferroberica, S.L. Improvement in the production process of arch segments by the introduction of a new system for securing panels and moulding meshes that comprise it
CN203211121U (en) * 2013-05-03 2013-09-25 中铁十二局集团第七工程有限公司 Assembling device for tunnel contact net groove passages
CN203919350U (en) * 2014-07-01 2014-11-05 山东天盾矿用设备有限公司 The segment die of pre-buried channel flow is installed
CN104790969A (en) * 2015-03-04 2015-07-22 中铁二十四局集团福建铁路建设有限公司 Two-time positioning construction process for pre-buried channels of overhead line system of high-speed railway tunnel
CN205297594U (en) * 2015-11-30 2016-06-08 中交第二航务工程局有限公司 Tunnel construction support device
CN106223975A (en) * 2016-09-23 2016-12-14 中国水利水电第四工程局有限公司 A kind of tunnel overhead contact conduit processing and positioning device
CN206092022U (en) * 2016-10-25 2017-04-12 陕西铁路工程职业技术学院 Be used for lining cutting rectangular -section or radiation gradual change rectangular -section formula operation car of crawling
CN106437767A (en) * 2016-11-01 2017-02-22 中昊创业高铁新材料有限公司 Tunnel pre-burying conduit installation structure and tunnel pre-burying conduit installation method
CN206917668U (en) * 2017-05-27 2018-01-23 中铁二十二局集团第一工程有限公司 High ferro tunnel pre-buried channel flow installation mold automatic lifting system

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108643936A (en) * 2018-04-27 2018-10-12 长沙泽和智能科技有限公司 A kind of lining trolley working window having automatic open-close function
CN108643936B (en) * 2018-04-27 2019-12-20 长沙泽和智能科技有限公司 Lining trolley working window with automatic opening and closing function
CN108394018A (en) * 2018-04-28 2018-08-14 厦门中建智欣建工科技有限公司 A kind of device and segment die for fixing pre-buried channel flow
CN108394018B (en) * 2018-04-28 2023-10-13 厦门智欣建工科技有限公司 Device for fixing embedded channel and duct piece mold

Similar Documents

Publication Publication Date Title
CN104141383B (en) A kind of Bailey beam pendent form support system and construction thereof
CN108019076A (en) Large-size rebar concrete silo construction method and the device for conical shell construction
CN106013776A (en) Hydraulic climbing type elevator shaft finalization operation platform and construction method
CN105178968B (en) Rock tunnel(ling) machine pushing tow support meanss and construction method
CN203794498U (en) Built-in self-elevating tower crane device
CN103046473A (en) Construction method for constructing double-limb hollow high-pier mould side hydraulic jacking creeping formwork and double-limb hollow high-pier
CN114150766B (en) Prefabricated reinforced concrete column connecting node and construction method thereof
CN105401679A (en) Large-gradient cast-in-place concrete inclined roof construction method
CN109537579B (en) Construction method of cast-in-situ bored pile
CN105926672A (en) Mined metro station steel pipe column construction method
CN106948841A (en) High ferro tunnel pre-buried channel flow installation mold automatic lifting system and installation method
CN205976167U (en) Based on cast -in -place floor structures of detachable positioning control spare
KR20070087782A (en) Construction method of top-down concrete slab
CN102733608A (en) Construction method for spray head layer of granulation tower
CN206917668U (en) High ferro tunnel pre-buried channel flow installation mold automatic lifting system
CN109083184A (en) A kind of prefabricated cushion cap of land sectional type and its production and installation method
CN108222006B (en) Construction method of square underground continuous wall
JP5794539B2 (en) How to remove floor slab
CN103938755A (en) Shock insulation structure for under-shaft hanging type transfer girders, and construction method of shock insulation structure
CN105370027B (en) The construction method of steel supporting platform structure is integrally lifted in high-rise hanging structure
CN103924653A (en) Framework type drainage well and construction method thereof
CN207144456U (en) Builder's jack I-steel built-in fitting
CN106049972B (en) Reverse cone-shape water-tower water tank lifts system and method in place
CN109763658A (en) A kind of support device and its construction method for arrangement material distributing machine in elevator
CN211547797U (en) Tower crane foundation structure suitable for basement raft foundation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination