CN105178326B - 上软下硬富水地层基坑工程围护结构止水方法 - Google Patents
上软下硬富水地层基坑工程围护结构止水方法 Download PDFInfo
- Publication number
- CN105178326B CN105178326B CN201510310388.XA CN201510310388A CN105178326B CN 105178326 B CN105178326 B CN 105178326B CN 201510310388 A CN201510310388 A CN 201510310388A CN 105178326 B CN105178326 B CN 105178326B
- Authority
- CN
- China
- Prior art keywords
- grouting
- pile
- floor
- water
- building enclosure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Abstract
本发明公开了一种上软下硬富水地层基坑工程围护结构止水方法,包括步骤1),钻孔灌注桩施工;步骤2),在钻孔灌注桩的外侧,进行高压旋喷桩或三轴搅拌桩的施作;步骤3),在高压旋喷桩或三轴搅拌桩中心位置钻孔,用高压旋喷注浆或用袖阀管注浆;步骤4),施作深孔帷幕注浆;步骤5),开挖首层小导坑;步骤6),对首层小导坑直立开挖面施作初期支护;步骤7),开挖首层基坑中预留核心土;步骤8),设置首层横向钢制围檩,架设钢制横撑;步骤9),待围护结构达到预先设计强度,监控量测的结果正常,进入下一循环,重复步骤4)‑步骤8)至施工完毕。本发明主止水效果好,具有较好的灵活性。工艺简单,施工风险小,对环境影响小,对复杂地层适应性强。
Description
技术领域
本发明涉及一种可以用于基坑工程中,尤其是上软下硬富水地层在上部软弱土层和土-岩分界面等薄弱部位处围护结构的止水方法。
背景技术
随着地下空间的开发利用,复杂基坑工程已成为一些大型建筑、轨道交通、市政、铁路、公路等工程建设的控制性工程。我国相当多地区地质情况复杂,特别是上软下硬富水地层条件下的基坑渗漏问题,给地下工程施工带来很大的困难和风险。
现有的专利中还没有针对上软下硬地层的止水方法,尤其是在上软下硬富水地层软-硬界面处的止水以及上部软弱地层的止水,而这种地质条件在工程实践中很常见。地质条件比较复杂时,实践中大多采用排桩或地下连续墙作为基坑围护结构,但如果施工控制不当极易导致相邻墙段或桩间渗漏水。在上软下硬富水地层中,尤其是土-岩软硬交界处为薄弱环节,渗水漏水问题更加严重,故急需找到一种在上软下硬富水土层中施作界面止水的方法,同时要解决上部软弱地层基坑工程开挖围护结构渗漏水问题,以彻底解决上软下硬富水土层中基坑工程渗水漏水问题。
现有技术一般是采用高压旋喷桩或者三轴搅拌桩的方法来形成软弱富水地层的止水帷幕,但是对于水量水压较大的情况,在软硬界面处常常成为地下水汇流层,该处的介质容易被水冲稀带走而无法形成固化桩,止水效果很不理想。
发明内容
本发明是针对现有技术所存在的不足之处,提供一种上软下硬富水地层基坑工程围护结构的止水方法,以保证上软下硬富水土层基坑工程在安全、快速、高效率开挖的基础上达到有效止水的效果。
本发明提供的技术方案是:
一种上软下硬富水地层基坑工程围护结构止水方法,包括以下步骤:
步骤1),钻孔灌注桩施工,在基坑开挖线外侧地层设计位置,利用钻机钻过土层,钻至岩层内设计位置,下放钢筋笼,灌注混凝土形成钻孔灌注桩;
步骤2),在钻孔灌注桩的外侧,进行高压旋喷桩或者三轴搅拌桩的施作,深度需达到软硬土层交界面。
步骤3),在高压旋喷桩或者三轴搅拌桩的中心位置钻孔,钻孔的深度到达岩层设计位置处,然后用高压旋喷注浆或用袖阀管注浆,形成软硬土层交界面止水帷幕,实现基坑开挖前主动止水;
步骤4),施作首层深孔帷幕注浆,首层深孔帷幕注浆深度至开挖首层基坑深度以下;首层深孔帷幕注浆为使用钻机从基坑内地面斜向操作或者从基坑外地面竖向操作,而以后各层的深孔帷幕注浆需从小基坑内地面斜向操作,帷幕注浆是注浆后形成较大范围的筒状封闭加固区,注浆机理可采用渗透注浆、劈裂注浆、压密注浆或者高压喷灌注浆。
步骤5),开挖首层小导坑,在基坑的外周侧邻近钻孔灌注桩处,开挖小导坑,预留出基坑中部预留核心土;
步骤6),对首层小导坑直立开挖面施作初期支护,初期支护包括铺设钢筋网和喷射混凝土。
步骤7),开挖首层基坑中预留核心土;
步骤8),设置首层横向钢制围檩,架设钢制横撑;
步骤9),待围护结构达到预先设计强度,监控量测的结果正常,进入下一循环,重复步骤4)-步骤8)至施工完毕。
本发明的优点:
本发明的核心在于主动止水和被动止水相结合、坑内止水和坑外止水相结合、事先止水和事中止水相结合、软弱土层止水和界面止水相结合,即基坑开挖前在围护结构外软硬地层交界面上下形成止水帷幕和基坑开挖过程中通过超前导坑对桩间和墙间渗漏部位进一步超前预注浆止水,形成系统的防渗止水方法。
相对于现有技术,本发明具有以下有益效果:
(1)止水效果好。本发明采用了坑外主动止水和坑内被动止水相结合的方法,即在坑外钻孔注浆使旋喷桩或搅拌桩的深度间接达到软硬交界面以下,有效封堵软硬土层的交界缝隙;在坑内施作深孔帷幕注浆有效封堵桩间的缝隙,起到良好的防渗止水的效果。
(2)灵活性好。本发明是根据实际监控量测数据判断是否需要深孔帷幕注浆,具有较好的灵活性。
(3)整体稳定性好。提前施作超前支护,超前支护与初期支护形成整体受力结构;既可以起到很好的挡土作用,又可以达到有效防渗止水的效果,保证基坑稳定性。
(4)适用性强。该方法工艺简单,施工风险小,而且对环境影响小,对复杂地层适应性强,尤其是上软下硬富水地层具有很强的适用性。
附图说明
图1上软下硬富水地层基坑工程围护结构平面示意图;
图2上软下硬富水地层基坑工程围护结构施作钻孔灌注桩示意图;
图3上软下硬富水地层基坑工程围护结构高压旋喷桩或三轴搅拌桩止水帷幕示意图;
图4上软下硬富水地层基坑工程围护结构钻机钻孔示意图;
图5上软下硬富水地层基坑工程围护结构施作交界面止水帷幕示意图;
图6上软下硬富水地层基坑工程围护结构坑外施作首层帷幕注浆示意图;
图7上软下硬富水地层基坑工程围护结构开挖首层小导坑并施作首层初期支护示意图;
图8上软下硬富水地层基坑工程围护结构开挖首层中部核心土以及施作首层支撑体系示意图;
图9上软下硬富水地层基坑工程围护结构施作第二层帷幕注浆示意图;
图10上软下硬富水地层基坑工程围护结构施作第二层小导坑并施作第二层初期支护示意图;
图11上软下硬富水地层基坑工程围护结构开挖第二层中部核心土以及施作第二层支撑体系示意图;
图12上软下硬富水地层基坑工程围护结构施作第三层帷幕注浆示意图;
图13上软下硬富水地层基坑工程围护结构开挖第三层小导坑并施作第三层初期支护示意图;
图14上软下硬富水地层基坑工程围护结构开挖第三层中部核心土以及施作第三层支撑体系示意图;
图中构件及所对应的标记:土层1、岩层2、钻孔灌注桩3、高压旋喷桩或三轴搅拌桩4、钻孔5、软硬土层交界面止水帷幕6、帷幕注浆7、小导坑8、预留核心土9、初期支护10、横向钢横撑11、环向钢围檩12。
具体实施方式
如附图1所示,本发明的基坑围护结构特征包括:钻孔灌注桩3,高压旋喷桩或三轴搅拌桩4,软硬土层交界面止水帷幕6,深孔帷幕注浆7,初期支护10和支撑体系,支撑体系包括横向钢横撑11、环向钢围檩12。
如附图2所示,步骤1),首先进行钻孔灌注桩3施工,在基坑开挖线外侧地层设计位置,先利用钻机钻过土层1,钻至岩层2内设计位置,下放钢筋笼,灌注混凝土形成钻孔灌注桩3,完成基坑外侧第一层围护结构。
如附图3所示,步骤2),在钻孔灌注桩3的外侧,进行高压旋喷桩或三轴搅拌桩4的施作,深度需达到软硬土层交界面(即土层1与岩层2交界面)。
如附图4和图5所示,步骤3),在高压旋喷桩或三轴搅拌桩4的中心位置钻孔,钻孔5的深度到达岩层2设计位置处,然后用高压旋喷注浆或用袖阀管注浆,形成软硬土层交界面止水帷幕6,实现基坑开挖前主动止水。
如附图6所示,步骤4),施作首层深孔帷幕注浆7,深度需达到首层开挖基坑深度以下;
如附图7所示,步骤5),开挖首层小导坑8,在基坑的外周侧邻近钻孔灌注桩3处,开挖小导坑8,预留出基坑中部预留核心土9;
步骤6),对首层直立开挖面施作初期支护10,初期支护10包括铺设钢筋网和喷射混凝土;
步骤7),开挖首层基坑中预留核心土9;
如附图8所示,步骤8),设置首层横向钢制围檩12,架设钢制横撑11;
如附图9所示,步骤9)待围护结构达到预先设计强度,监控量测的结果正常,进入下一循环,首先在首层如附图施作首层帷幕注浆7之下施作下一层的帷幕部的注浆,形成第二层的帷幕注浆,重复步骤4)-步骤8),如附图10-附图14所示,此处不再赘述。
本发明的上软下硬富水地层基坑工程围护结构止水方法,能够保证上软下硬富水土层基坑工程在安全、快速、高效率开挖的基础上达到有效止水的效果。发明的核心在于主动止水和被动止水的结合,即基坑开挖前在围护结构外软硬地层交界面形成止水帷幕和随着基坑开挖分层分部施作深孔帷幕注浆达到防渗止水的效果。
以上实例的说明只是用于帮助理解本发明的核心思想;同时,对于本领域的一般技术人员,依据本发明的思想,在具体实施方式及应用范围上均会有改变之处,综上所述,本说明书内容不应理解为对本发明的限制。
Claims (4)
1.一种上软下硬富水地层基坑工程围护结构止水方法,其特征在于,包括以下步骤:步骤1),钻孔灌注桩施工,在基坑开挖线外侧地层设计位置,利用钻机钻过土层,钻至岩层内设计位置,下放钢筋笼,灌注混凝土形成钻孔灌注桩;
步骤2),在钻孔灌注桩的外侧,进行高压旋喷桩或者三轴搅拌桩的施作,深度需达到软硬土层交界面;
步骤3),在高压旋喷桩或者三轴搅拌桩中心位置钻孔,钻孔的深度到达岩层设计位置处,然后用高压旋喷注浆或用袖阀管注浆,形成软硬土层交界面止水帷幕,实现基坑开挖前主动止水;
步骤4),施作首层深孔帷幕注浆,帷幕注浆深度至开挖首层基坑深度以下;
步骤5),开挖首层小导坑,在基坑的外周侧邻近钻孔灌注桩处,开挖小导坑,预留出基坑中部预留核心土;
步骤6),对首层小导坑直立开挖面施作初期支护,初期支护包括铺设钢筋网和喷射混凝土;
步骤7),开挖首层基坑中预留核心土;
步骤8),设置首层横向钢制围檩,架设钢制横撑;
步骤9),待围护结构达到预先设计强度,监控量测的结果正常,进入下一循环,重复步骤4)-步骤8)。
2.根据权利要求1所述的一种上软下硬富水地层基坑工程围护结构止水方法,其特征在于,步骤4)中,首层深孔帷幕注浆可使用钻机从基坑内地面斜向操作也可以从基坑外地面竖向操作,而以后各层的深孔帷幕注浆需从小基坑内地面斜向操作。
3.根据权利要求1所述的一种上软下硬富水地层基坑工程围护结构止水方法,其特征在于,步骤4)中,帷幕注浆是注浆后形成较大范围的筒状封闭加固区,注浆机理可采用渗透注浆、劈裂注浆、压密注浆或者高压喷灌注浆。
4.根据权利要求1所述的一种上软下硬富水地层基坑工程围护结构止水方法,其特征在于,步骤8)中,横向钢制围檩和钢制横撑的钢架采用型钢钢架或者格栅钢架。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510310388.XA CN105178326B (zh) | 2015-06-03 | 2015-06-03 | 上软下硬富水地层基坑工程围护结构止水方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510310388.XA CN105178326B (zh) | 2015-06-03 | 2015-06-03 | 上软下硬富水地层基坑工程围护结构止水方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105178326A CN105178326A (zh) | 2015-12-23 |
CN105178326B true CN105178326B (zh) | 2017-05-31 |
Family
ID=54900715
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510310388.XA Expired - Fee Related CN105178326B (zh) | 2015-06-03 | 2015-06-03 | 上软下硬富水地层基坑工程围护结构止水方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105178326B (zh) |
Families Citing this family (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106545020A (zh) * | 2016-11-02 | 2017-03-29 | 鲲鹏建设集团有限公司 | 一种深基坑支护的施工方法 |
CN106592600B (zh) * | 2016-12-05 | 2019-12-27 | 中建六局土木工程有限公司 | 紧邻运行地铁复杂环境预警支护体系施工方法 |
CN107191207B (zh) * | 2017-07-12 | 2018-10-19 | 北京首尔工程技术有限公司 | 一种车站底部封水施工方法及车站底部封水构造 |
CN107605498B (zh) * | 2017-11-02 | 2023-08-22 | 中铁十局集团有限公司 | 富水砂卵石地层盾构隧道端头水平注浆加固结构施工方法 |
CN108019211B (zh) * | 2018-01-23 | 2023-09-12 | 中国铁路设计集团有限公司 | 一种富水砂卵石地层的导洞内截水帷幕及其施工方法 |
CN109469068A (zh) * | 2018-11-02 | 2019-03-15 | 福建工程学院 | 一种富水软弱地层基坑开挖与联合支护方法 |
CN109403333A (zh) * | 2018-11-02 | 2019-03-01 | 福建工程学院 | 一种上软下硬富水地层深基坑逆作施工方法 |
CN109252531A (zh) * | 2018-11-05 | 2019-01-22 | 深圳市工勘岩土集团有限公司 | 搅拌桩或旋喷桩与袖阀管注浆组合的止水帷幕施工方法 |
CN110306558A (zh) * | 2019-06-06 | 2019-10-08 | 中铁第四勘察设计院集团有限公司 | 基坑支护方法 |
CN110777832A (zh) * | 2019-11-08 | 2020-02-11 | 上海建工二建集团有限公司 | 水下通道基坑沿水两岸的端头处的止水帷幕 |
CN111411970B (zh) * | 2020-03-25 | 2022-05-13 | 中铁三局集团有限公司 | 一种富水砂层地质条件下盾构始发施工方法 |
CN111472804A (zh) * | 2020-05-29 | 2020-07-31 | 中铁隧道局集团有限公司 | 一种位于基坑中的上软下硬地层越江隧道进洞口施工方法 |
CN112343061B (zh) * | 2020-10-14 | 2021-08-31 | 中建三局第一建设工程有限责任公司 | 超深淤泥基坑横支撑施工装置及施工方法 |
CN112609707A (zh) * | 2020-12-09 | 2021-04-06 | 中铁二十局集团第六工程有限公司 | 基坑渗漏水处理方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003342948A (ja) * | 2002-05-28 | 2003-12-03 | Marufuji Sheet Piling Co Ltd | 土留杭とその杭を用いる土留工法 |
CN202969392U (zh) * | 2012-12-06 | 2013-06-05 | 中铁四局集团有限公司 | 复杂地质深基坑联合支护 |
CN103469798A (zh) * | 2013-08-28 | 2013-12-25 | 中国建筑第七工程局有限公司 | 一种基坑支护结构及其施工方法 |
CN103967016A (zh) * | 2013-02-06 | 2014-08-06 | 上海城地建设股份有限公司 | 一种新型竖向基坑围护结构及其施工方法 |
CN104631470A (zh) * | 2014-12-26 | 2015-05-20 | 合肥建工集团有限公司 | 高水位大粒径砂砾石地质深基坑组合支护施工方法 |
-
2015
- 2015-06-03 CN CN201510310388.XA patent/CN105178326B/zh not_active Expired - Fee Related
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003342948A (ja) * | 2002-05-28 | 2003-12-03 | Marufuji Sheet Piling Co Ltd | 土留杭とその杭を用いる土留工法 |
CN202969392U (zh) * | 2012-12-06 | 2013-06-05 | 中铁四局集团有限公司 | 复杂地质深基坑联合支护 |
CN103967016A (zh) * | 2013-02-06 | 2014-08-06 | 上海城地建设股份有限公司 | 一种新型竖向基坑围护结构及其施工方法 |
CN103469798A (zh) * | 2013-08-28 | 2013-12-25 | 中国建筑第七工程局有限公司 | 一种基坑支护结构及其施工方法 |
CN104631470A (zh) * | 2014-12-26 | 2015-05-20 | 合肥建工集团有限公司 | 高水位大粒径砂砾石地质深基坑组合支护施工方法 |
Non-Patent Citations (1)
Title |
---|
复杂环境下多种支护结构相结合的基坑工程设计与实践;谈永卫;《岩土工程学报》;20141130;第36卷;第103页1.1节至第105节1.2节及表2 * |
Also Published As
Publication number | Publication date |
---|---|
CN105178326A (zh) | 2015-12-23 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105178326B (zh) | 上软下硬富水地层基坑工程围护结构止水方法 | |
CN104612143B (zh) | 一种溶洞/土洞地质条件下的钻孔复合桩结构 | |
CN104099943B (zh) | 地下连续墙与废弃地下人防工程交会处理方法 | |
CN108677924B (zh) | 双排微型钢管桩注浆成墙隔断结构及方法 | |
CN209636826U (zh) | 富水砂砾石地层基坑止水结构 | |
CN107023300A (zh) | 一种采用棚护法建造地铁车站的施工方法 | |
CN113565525A (zh) | 一种新建盾构隧道超临近超浅埋上跨既有隧道的施工防护体系及施工方法 | |
CN102660955B (zh) | 一种基坑边坡支护的快速施工方法 | |
CN103775110A (zh) | 软土地区多层地下空间的暗挖施工方法 | |
CN104499479A (zh) | 一种穿越砂砾石回填层的挖孔桩施工方法 | |
CN203334300U (zh) | 树根桩支挡结构 | |
CN103572764A (zh) | 超深人工挖孔桩护壁止水结构及其施工方法 | |
CN105464685A (zh) | 一种洞桩法暗挖隧道止水帷幕及其施工方法 | |
CN107587512A (zh) | 一种岩溶和/或裂隙发育地层下基坑围护结构的施工方法 | |
CN107339122A (zh) | 一种钢管柱处理采空区工法 | |
CN108005662B (zh) | 一种地下水封洞库储库区地质破碎带的处理方法 | |
CN102011591A (zh) | 深井工作面注浆工艺 | |
CN206942786U (zh) | 一种高含水率黄土隧道的超前预加固结构 | |
CN108867673A (zh) | 一种基于抽水帷幕的基坑中地下水治理方法 | |
JP2019015100A (ja) | 山留壁の撤去方法 | |
CN204311456U (zh) | 基坑加固结构 | |
CN108071110A (zh) | 复杂地质条件下旋挖钻机嵌岩桩施工方法 | |
CN206721875U (zh) | 一种承压型卵砾石土层扩体锚杆 | |
CN207176700U (zh) | 一种复杂环境下的密排灌注桩内支撑基坑永久支护结构 | |
CN104831735B (zh) | 一种桩幕合一的止水支护结构及其施工方法和施工设备 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170531 Termination date: 20200603 |