CN105155857A - Construction and installation method of architectural engineering partition wall boards - Google Patents
Construction and installation method of architectural engineering partition wall boards Download PDFInfo
- Publication number
- CN105155857A CN105155857A CN201510487432.4A CN201510487432A CN105155857A CN 105155857 A CN105155857 A CN 105155857A CN 201510487432 A CN201510487432 A CN 201510487432A CN 105155857 A CN105155857 A CN 105155857A
- Authority
- CN
- China
- Prior art keywords
- partition wall
- construction
- partition board
- wall batten
- partition
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Abstract
The invention belongs to the field of architectural engineering and relates to a construction and installation method of architectural engineering partition wall boards. The top end of each partition wall slat is made into a fold-line end section, comprising slope top faces on two sides of the top end of the partition wall slat and an inverted-trapezoid groove in the top end of the partition wall slat; at the bottom of a mounting contact face of the partition wall slat corresponding to a center line of a whole partition wall board segment, a full-length inverted-trapezoid wooden batten is fixed through steel nails, the fixed inverted-trapezoid wood batten is clamped in the inverted-trapezoid groove in the top end of the partition wall slat; opposing trapezoidal wooden wedges at two ends of the whole partition wall board segment are symmetrically fastened for multiple times to implement tightening, and the fastening of the opposing trapezoidal wooden wedges at two ends of the whole partition wall board segment enables horizontal pre-compressive stress to occur in the plane of the whole partition wall board segment. The construction process and steps are simple, construction and installation are high in efficiency, a wall is smooth and clean, wall coloring caused by the fact that steel U-shaped clamps are rusted easily is avoided, the problem that cracks of the wall at vertical joints of the partition wall slats caused by the fact that the wall dries and shrinks easily can be effectively avoided, and the construction and installation cost is low.
Description
Technical field
The invention belongs to construction engineering technical field, particularly relate to a kind of construction installation method of partition board.
Background technology
Construction work partition board, has National Standard of the People's Republic of China " light partition board for building " (GB/T23451-2009) and People's Republic of China's construction industry industry standard " concrete light batten " (JG/T350-2011); National building standard design atlas has China Inst of Architectural Standard Design to edit " internal partition wall-light lath (one) " (10J113-1).The building standard design atlas of all parts of the country side has a lot, as Jiangsu Province's engineering construction standard design atlas (recommending figure) " Light trabs construction drawings " (light aggregate concrete mill for slats of center partition wall made (Soviet Union J/T15-2005 (four)), Xinjiang engineering construction standard design atlas " internal partition wall structure (light hollow slat) " (new 12J11-1) etc.
The construction installation method of currently available technology construction work partition board, visible above-mentioned standard and type design atlas.Partition board top is concordant, and partition board top and beam (or floor) bottom method of attachment adopt steel U-shaped to fasten; Partition board horizontal end leaves space (what have does not do any process, and what have is also adopt steel U-shaped to fasten).Mainly there is two large problems in prior art: first steel U-shaped card gets rusty easily and causes metope mordanting, affects appearance effect; It two is that the drying shrinkage of body of wall easily causes body of wall at the vertical edge joint position cracking of batten, and have a strong impact on sight, cause a large amount of customer complaints, repair process is very difficult, is difficult to tackle the problem at its root.These two reasons cause Construction Party to using the conflict of partition board, make this building materials application very difficulty being conducive to environmental protection, material-saving, efficient and high-quality.Therefore a kind of technical scheme is needed to solve these problems.
Summary of the invention
Technical problem to be solved by this invention is: the construction installation method providing a kind of construction work partition board, its construction technology and operation are simple, construction and installation work efficiency is high, metope neatly smooth, there is not steel U-shaped card and get rusty easily and cause metope mordanting, can effectively prevent the drying shrinkage of body of wall and produce the vertical edge joint position cracking of body of wall at partition wall batten, construction and installation cost is low.
A construction installation method for construction work partition board, is characterized in that:
One, the preparation before construction
Make partition wall batten, the top vertical cross-section of described partition wall batten is fold-line-shaped, and the both sides on partition wall batten top are domatic end face, and there is inverted trapezoidal groove middle part, top; Make inverted trapezoidal flitch and trapezoidal timber wedge; By the bottom of the installation contact surface of partition wall batten, flooring and cylinder or metope cleaning leveling;
Two, construction and installation
Unwrapping wire on the bottom of the installation contact surface of described step one partition wall batten, flooring and cylinder or metope, bottom the installation contact surface of partition wall batten, inverted trapezoidal flitch is fixed by the position of center line steel nail of corresponding whole section of partition board;
Order installation is carried out in the one end choosing whole section of partition wall, snaps in the inverted trapezoidal groove on partition wall batten top by the inverted trapezoidal flitch after fixing with steel nail, and partition wall batten and horizontal plane, by two correct trapezoidal timber wedge jack-up of arranging, are guaranteed in the bottom of partition wall batten; Two correct trapezoidal timber wedges arranged are adopted to isolate between partition wall batten and cylinder or metope, and two correct trapezoidal timber wedges arranged leave stroke fastening further, and form partition board end side surface space between partition wall batten and cylinder or metope, partition wall batten top and be formed with partition board head room clearance between installing bottom contact surface, is formed with space bottom partition board bottom partition wall batten and between flooring;
Before continuation order installs partition wall batten, in the edge joint position side of two pieces of partition wall battens, glue is cohered in brushing, installs partition wall batten according to aforesaid operations continuation order;
Partition board is installed to last block partition wall batten according to aforesaid operations, isolate between partition wall batten and cylinder or metope with two correct trapezoidal timber wedges arranged between partition wall batten and cylinder or metope, then the trapezoidal timber wedge correspondence that the enemy at whole section of partition board two ends arranges is carried out top solid, the trapezoidal timber wedge arranged by the enemy at whole section of partition wall two ends fastening, makes to produce the compressive pre-stress having horizontal direction in whole section of partition board plane;
By fastening for the correct trapezoidal timber wedge arranged of two bottom partition wall batten, the space of whole section of partition wall periphery comprised harsh concrete filling in space bottom partition board end side surface space, partition board head room clearance and partition board and hit tight;
The end of whole section of partition board be there is no to the position of cylinder or metope contact, using the correct trapezoidal timber wedge arranged solid by pushing up in fact to the center position of whole section of partition board respectively at the top of whole section of partition board end side surface and bottom, making in whole section of partition board plane, to produce the compressive pre-stress having horizontal direction;
Repeat above-mentioned steps to complete to partition board construction and installation.
The compressive pre-stress that described whole section of partition wall is formed in its board plane is horizontal direction.
The bottom that described partition wall batten installs contact surface is provided with inverted trapezoidal flitch.
By above-mentioned design scheme, the present invention can bring following beneficial effect: a kind of construction installation method of construction work partition board, its construction technology and operation are simple, construction and installation work efficiency is high, metope neatly smooth, there is not steel U-shaped card and get rusty easily and cause metope mordanting, can effectively prevent the drying shrinkage of body of wall from easily causing body of wall at the vertical edge joint position cracking of partition wall batten, construction and installation cost is low.The employing of this construction installation method, can reach the object of environmental protection, material-saving, of fine quality, efficient and low consumption in the application of construction work partition board.
Accompanying drawing explanation
Below in conjunction with the drawings and specific embodiments, the present invention is further illustrated:
Fig. 1 is the construction installation method partition board top vertical cross-section figure of a kind of construction work partition board of the present invention.
Fig. 2 is the construction installation method inverted trapezoidal flitch sectional view of a kind of construction work partition board of the present invention.
Fig. 3 is the trapezoidal timber wedge elevation of construction installation method of a kind of construction work of the present invention partition board.
Fig. 4 is the hole elevational schematic view before the construction installation method partition board construction and installation of a kind of construction work partition board of the present invention.
Fig. 5 is the construction installation method inverted trapezoidal flitch construction and installation elevational schematic view of a kind of construction work partition board of the present invention.
Fig. 6 is the A-A sectional drawing of the construction installation method inverted trapezoidal flitch construction and installation of a kind of construction work partition board of the present invention.
Fig. 7 is the B-B sectional drawing of the construction installation method inverted trapezoidal flitch construction and installation of a kind of construction work partition board of the present invention.
Fig. 8 is the elevational schematic view of the construction installation method partition wall first piece of partition board construction and installation of a kind of construction work of the present invention partition board.
Fig. 9 is the C-C sectional drawing of the construction installation method partition board construction and installation of a kind of construction work partition board of the present invention.
Figure 10 is the D-D sectional drawing of the construction installation method partition board construction and installation of a kind of construction work partition board of the present invention.
Figure 11 is the E-E sectional drawing of the construction installation method partition board construction and installation of a kind of construction work partition board of the present invention.
Figure 12 is the F-F sectional drawing of the construction installation method partition board construction and installation of a kind of construction work partition board of the present invention.
Figure 13 is the elevational schematic view of the construction installation method partition board construction and installation of a kind of construction work partition board of the present invention.
Figure 14 is the elevational schematic view after the construction installation method partition wall construction and installation of a kind of construction work partition board of the present invention.
Figure 15 is the G-G sectional drawing of the construction installation method partition board construction and installation of a kind of construction work partition board of the present invention.
Figure 16 is the H-H sectional drawing of the construction installation method partition board construction and installation of a kind of construction work partition board of the present invention.
Figure 17 is the J-J sectional drawing of the construction installation method partition board construction and installation of a kind of construction work partition board of the present invention.
Figure 18 is the elevational schematic view of the construction installation method partition wall end of a kind of construction work partition board of the present invention partition board construction and installation when having a hole.
Figure 19 is the construction installation method partition wall end of a kind of construction work partition board of the present invention hole edge bottom partial enlarged drawing K when having a hole.
Figure 20 is the construction installation method partition wall end of a kind of construction work partition board of the present invention hole edge top partial enlarged drawing L when having a hole.
1-partition wall batten in figure, 2-domatic end face, 3-inverted trapezoidal groove, 4-inverted trapezoidal flitch, the trapezoidal timber wedge of 5-, 6-install space, 13-harsh concrete bottom the bottom of contact surface, 7-flooring, 8-cylinder or metope, 9-steel nail, 10-partition board end side surface space, 11-partition board head room clearance, 12-partition board.
Detailed description of the invention
A construction installation method for construction work partition board, comprising:
As shown in Fig. 1 ~ Figure 20, concrete operation step of the present invention is as follows:
Prepare before step one, construction and installation
As shown in Figure 1, partition wall batten 1 is the partition wall batten that existing country and provincial standard and standard design drawing are concentrated, and make partition wall batten 1, the top vertical cross-section of described partition wall batten 1 is fold-line-shaped, the both sides on partition wall batten 1 top are domatic end face 2, and there is inverted trapezoidal groove 3 middle part, top.
As shown in Figure 2 and Figure 3, inverted trapezoidal flitch 4 and trapezoidal timber wedge 5 is made.
As shown in Figure 4, by bottom the installation contact surface of partition wall batten 16, flooring 7 and cylinder or metope 8 clear up leveling.
Step 2, construction and installation process
As shown in Fig. 5, Fig. 6 and Fig. 7, unwrapping wire on the bottom 6 of the installation contact surface of partition wall batten 1, flooring 7 and cylinder or metope 8, in the bottom 6 of the installation contact surface of partition wall batten 1, elongated inverted trapezoidal flitch 4 is fixed by the position of center line steel nail 9 of corresponding whole section of partition board.
As Fig. 8, Fig. 9, Figure 10, shown in Figure 11 and Figure 12, one end along whole section of partition wall starts to install, the inverted trapezoidal flitch 4 fixed is snapped in partition wall batten 1 top inverted trapezoidal groove 3, bottom partition wall batten 1 with two correct trapezoidal timber wedges 5 arranged gently by partition wall batten 1 jack-up, do not push up to obtain tension (surplus held out against further need be left), do not roll as principle with partition wall batten 1, isolate between partition wall batten 1 and cylinder or metope 8 gently with two correct trapezoidal timber wedges 5 arranged between partition wall batten 1 and cylinder or metope 8, two correct trapezoidal timber wedges 5 arranged do not push up to obtain tension (need leave the surplus held out against further), partition board end side surface space 10 is formed between partition wall batten 1 and cylinder or metope 8, partition board head room clearance 11 is formed between partition wall batten 1 top and the bottom 6 of installing contact surface, space 12 bottom partition board is formed bottom partition wall batten 1 and between flooring 7.
As shown in Figure 11, Figure 12 and Figure 13, before partition wall batten 1 is installed in continuation, in partition wall batten 1 side of two pieces of partition wall batten 1 edge joint positions, glue is cohered in brushing, and then installs partition wall batten 1, and process is identical with aforesaid operations step.
As shown in Figure 13 and Figure 16, after last block partition wall batten 1 of whole section of partition board is installed, isolate between partition wall batten 1 and cylinder or metope 8 gently with two correct trapezoidal timber wedges 5 arranged between partition wall batten 1 and cylinder or metope 8, then trapezoidal timber wedge 5 symmetry that the enemy at whole section of partition board two ends arranges is carried out repeatedly fastening enforcement to hold out against, fastening the making of the trapezoidal timber wedge 5 arranged by the enemy at whole section of partition wall two ends produces the compressive pre-stress having horizontal direction in whole section of partition board plane.
As shown in Figure 14, Figure 15 and Figure 17, by fastening for the correct trapezoidal timber wedge 5 arranged of two bottom partition wall batten 1, the space (bottom partition board end side surface space 10, partition board head room clearance 11, partition board space 12) of whole section of partition wall periphery filled with harsh concrete 13 and hits tight.
As shown in Figure 18, Figure 19 and Figure 20, to the situation (comprising hole place) that the end of whole section of partition board does not have cylinder or metope 8 to contact, then hold out against by reality with the center position of the correct trapezoidal timber wedge 5 arranged to whole section of partition board respectively at the top of whole section of partition board end side surface and bottom, make to produce the compressive pre-stress having horizontal direction in whole section of partition board plane, other construction and installation process is the same.
The construction and installation of partition board complete.
Claims (3)
1. a construction installation method for construction work partition board, is characterized in that:
Comprise the following steps
Preparation before step one, construction
Make partition wall batten (1), the top vertical cross-section of described partition wall batten (1) is fold-line-shaped, the both sides on partition wall batten (1) top are domatic end face (2), and there is inverted trapezoidal groove (3) middle part, top; Make inverted trapezoidal flitch (4) and trapezoidal timber wedge (5); By the bottom (6) of the installation contact surface of partition wall batten (1), flooring (7) and cylinder or metope (8) cleaning leveling;
Step 2, construction and installation
At the bottom (6) of the installation contact surface of described step one partition wall batten (1), flooring (7) and cylinder or the upper unwrapping wire of metope (8), bottom the installation contact surface of partition wall batten (1), inverted trapezoidal flitch (4) is fixed by the position of center line steel nail (9) of (6) corresponding whole section of partition board;
Order installation is carried out in the one end choosing whole section of partition wall, inverted trapezoidal flitch (4) after fixing with steel nail (9) is snapped in the inverted trapezoidal groove (3) on partition wall batten (1) top, partition wall batten (1) and horizontal plane, by two correct trapezoidal timber wedge (5) jack-up of arranging, are guaranteed in the bottom of partition wall batten (1); Two correct trapezoidal timber wedges (5) arranged are adopted to isolate between partition wall batten (1) and cylinder or metope (8), and two correct trapezoidal timber wedges (5) arranged leave stroke fastening further, and form partition board end side surface space (10) between partition wall batten (1) and cylinder or metope (8), partition wall batten (1) top and install bottom contact surface and be formed with partition board head room clearance (11) between (6), is formed with space bottom partition board (12) between partition wall batten (1) bottom and flooring (7);
Install partition wall batten (1) in continuation order front, in the edge joint position side of two pieces of partition wall battens (1), glue is cohered in brushing, installs partition wall batten (1) according to aforesaid operations continuation order;
Partition board is installed to last block partition wall batten (1) according to aforesaid operations, isolate between partition wall batten (1) and cylinder or metope (8) with two correct trapezoidal timber wedges (5) arranged between partition wall batten (1) and cylinder or metope (8), then trapezoidal timber wedge (5) correspondence that the enemy at whole section of partition board two ends arranges is carried out top solid, the trapezoidal timber wedge (5) arranged by the enemy at whole section of partition wall two ends fastening, makes to produce the compressive pre-stress having horizontal direction in whole section of partition board plane;
By fastening for two of partition wall batten (1) the bottom correct trapezoidal timber wedges (5) arranged, the space of whole section of partition wall periphery comprised space (12) harsh concrete (13) filling bottom partition board end side surface space (10), partition board head room clearance (11) and partition board and hit tight;
To the position that the end of whole section of partition board does not have cylinder or metope (8) to contact, using the correct trapezoidal timber wedge (5) arranged solid by pushing up in fact to the center position of whole section of partition board respectively at the top of whole section of partition board end side surface and bottom, making in whole section of partition board plane, to produce the compressive pre-stress having horizontal direction;
Repeat above-mentioned steps to complete to partition board construction and installation.
2. the construction installation method of a kind of construction work partition board according to claim 1, is characterized in that: the compressive pre-stress that described whole section of partition wall is formed in its board plane is horizontal direction.
3. the construction installation method of a kind of construction work partition board according to claim 1, is characterized in that: the bottom (6) that described partition wall batten (1) installs contact surface is provided with inverted trapezoidal flitch (4).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510487432.4A CN105155857B (en) | 2015-08-11 | 2015-08-11 | A kind of construction installation method of architectural engineering partition plate |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510487432.4A CN105155857B (en) | 2015-08-11 | 2015-08-11 | A kind of construction installation method of architectural engineering partition plate |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105155857A true CN105155857A (en) | 2015-12-16 |
CN105155857B CN105155857B (en) | 2017-04-05 |
Family
ID=54796866
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510487432.4A Expired - Fee Related CN105155857B (en) | 2015-08-11 | 2015-08-11 | A kind of construction installation method of architectural engineering partition plate |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105155857B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109024998A (en) * | 2018-08-06 | 2018-12-18 | 庐江荣睿建设工程有限公司 | A kind of mounting process of batten of internal partition for building |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2625244A1 (en) * | 1987-12-24 | 1989-06-30 | Bonnivard Guy | Wedging device for levelling a floor, ceiling, wall or panel |
CN102251606A (en) * | 2011-04-26 | 2011-11-23 | 北京城建五建设工程有限公司 | Outer partition wall built by adopting light concrete partition wall boards and construction method thereof |
CN102352660A (en) * | 2011-06-02 | 2012-02-15 | 南通建筑工程总承包有限公司 | Gypsum block masonry and construction method thereof |
CN102505862A (en) * | 2011-11-03 | 2012-06-20 | 中山建华墙体材料有限公司 | Installing process of lightweight internal partition wallboards |
-
2015
- 2015-08-11 CN CN201510487432.4A patent/CN105155857B/en not_active Expired - Fee Related
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2625244A1 (en) * | 1987-12-24 | 1989-06-30 | Bonnivard Guy | Wedging device for levelling a floor, ceiling, wall or panel |
CN102251606A (en) * | 2011-04-26 | 2011-11-23 | 北京城建五建设工程有限公司 | Outer partition wall built by adopting light concrete partition wall boards and construction method thereof |
CN102352660A (en) * | 2011-06-02 | 2012-02-15 | 南通建筑工程总承包有限公司 | Gypsum block masonry and construction method thereof |
CN102505862A (en) * | 2011-11-03 | 2012-06-20 | 中山建华墙体材料有限公司 | Installing process of lightweight internal partition wallboards |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109024998A (en) * | 2018-08-06 | 2018-12-18 | 庐江荣睿建设工程有限公司 | A kind of mounting process of batten of internal partition for building |
Also Published As
Publication number | Publication date |
---|---|
CN105155857B (en) | 2017-04-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107044179B (en) | Decorative panel and template integrated heat-preservation decorative composite wall and construction method thereof | |
CN106088471B (en) | A kind of pseudo-classic architecture beam column wood armored structure construction method | |
CN205024849U (en) | Wood structure building beam -column connection node structure | |
CN200992781Y (en) | Indoor decorative column or beam | |
CN102777040A (en) | Installation process of stagger-joint dual-wallboard inner partition wall and dual-wallboard inner partition | |
CN204919828U (en) | Archaize building's wooden frame and steel structure column's connection structure | |
CN105155857A (en) | Construction and installation method of architectural engineering partition wall boards | |
CN203603309U (en) | Mesh plate outer wall with mesh joints mutually staggered | |
CN105155836A (en) | Aluminum alloy formwork for buildings and method for applying aluminum alloy formwork | |
CN101392587B (en) | Wood grille decorative system | |
CN209603421U (en) | A kind of decorative heat-preservation plate used for building exterior wall | |
CN109537776A (en) | A kind of construction method of architectural engineering partition plate | |
CN207959768U (en) | A kind of connector and heat insulating decorative board | |
CN205637278U (en) | Modular ridge in room is moulded to environment -friendly wood | |
CN205476280U (en) | A hang subassembly futilely for ceramic sheet metal | |
CN204040360U (en) | Prefabricated Woodveneer structure | |
CN100390370C (en) | Rust-proof deform-proof wooden floor assembly and construction method thereof | |
CN208293977U (en) | Dry-hang wall brick system in a kind of assembled room | |
CN202831299U (en) | Double-wallboard staggered joint internal partition | |
CN202787714U (en) | Archaized architecture roof with rafters wrapped by aluminium veneers | |
CN112854553A (en) | Limiting method for free end of partition board | |
CN220318996U (en) | Stone wood veneer external corner node | |
CN105040864A (en) | Formwork supporting method for constructional column in limited space | |
CN215716756U (en) | Building outer wall marble slab of antidetonation crack control | |
CN207776119U (en) | A kind of connection structure of assembled wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20180925 Address after: 130000 Changying business center 1106, 1768 Hongqi Street, Changchun, Jilin. Patentee after: Jilin Ding Yuan Construction Co., Ltd. Address before: 130061 Room 405, four building, Star Street, 2577 building street, Changchun, Jilin. Patentee before: Meng Fanlin |
|
TR01 | Transfer of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170405 Termination date: 20200811 |
|
CF01 | Termination of patent right due to non-payment of annual fee |