CN105088971A - 一种波形钢腹板pc箱梁斜拉桥中跨合龙施工方法 - Google Patents

一种波形钢腹板pc箱梁斜拉桥中跨合龙施工方法 Download PDF

Info

Publication number
CN105088971A
CN105088971A CN201510569004.6A CN201510569004A CN105088971A CN 105088971 A CN105088971 A CN 105088971A CN 201510569004 A CN201510569004 A CN 201510569004A CN 105088971 A CN105088971 A CN 105088971A
Authority
CN
China
Prior art keywords
closure section
welded
wavelike steel
steel webplate
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510569004.6A
Other languages
English (en)
Other versions
CN105088971B (zh
Inventor
陈立生
叶智勇
赵国强
邓建新
徐伟忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Urban Construction Municipal Engineering Group Co Ltd
Original Assignee
Shanghai Urban Construction Municipal Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Urban Construction Municipal Engineering Group Co Ltd filed Critical Shanghai Urban Construction Municipal Engineering Group Co Ltd
Priority to CN201510569004.6A priority Critical patent/CN105088971B/zh
Publication of CN105088971A publication Critical patent/CN105088971A/zh
Application granted granted Critical
Publication of CN105088971B publication Critical patent/CN105088971B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

本发明公开了一种波形钢腹板PC箱梁斜拉桥中跨合龙施工方法,包括如下步骤:将合龙段两侧节段上的挂篮主桁架前上横梁经铁板焊接为一整体;在合龙段处分块安装波形钢腹板,将波形钢腹板的一端先行焊接,另一端则通过螺栓连接;在合龙段上分别设置内、外劲性骨架,并将内、外劲性骨架的一端同该侧节段进行焊接,该焊接端与波形钢腹板的焊接端相异;选择一天中温度最低时段或温度趋向最低时段,同时将波形钢腹板以及内、外劲性骨架的未焊接端同节段进行焊接;完成合龙段的混凝土浇筑;待合龙段的混凝土养护达到设计强度后,解除两侧挂篮主桁架前上横梁之间焊接的所述铁板,并拆除挂篮以及外劲性骨架,完成中跨合龙。本发明的优点是,安全可靠成本低。

Description

一种波形钢腹板PC箱梁斜拉桥中跨合龙施工方法
技术领域
本发明属于桥梁工程技术领域,具体涉及一种波形钢腹板PC箱梁斜拉桥中跨合龙施工方法。
背景技术
波形钢腹板PC箱梁由混凝土顶底板通过若干块波形钢腹板连接而成。我国对波形钢腹板PC箱梁桥的研究始于20世纪90年代,现已建成三十余座波形钢腹板PC箱梁桥,以中小跨径居多。近年来,波形钢腹板PC箱梁开始运用于大跨度连续梁桥与斜拉桥,常采用挂篮悬臂施工方法。合龙段施工作为挂篮悬臂施工的最后一道工序,也是最关键的一道工序,直接关系到主梁线性和桥梁整体受力状态。
因此,如何保证安全的前提条件下,快速、经济地实现中跨合龙,成为本领域技术人员亟待解决的问题。
发明内容
本发明的目的是根据上述现有技术的不足之处,提供一种波形钢腹板PC箱梁斜拉桥中跨合龙施工方法,该中跨合龙施工方法通过采用合龙段波形钢腹板先锁定,再浇筑混凝土完成中跨合龙。
本发明目的实现由以下技术方案完成:
一种波形钢腹板PC箱梁斜拉桥中跨合龙施工方法,其特征在于所述中跨合龙施工方法包括如下步骤:将合龙段两侧节段上的挂篮主桁架前上横梁经铁板焊接为一整体;在所述合龙段处分块安装波形钢腹板,将所述波形钢腹板的一端同该侧的所述节段进行焊接,另一端通过螺栓同该侧的所述节段进行连接;在所述合龙段上分别设置内、外劲性骨架,并将所述内、外劲性骨架的一端同该侧的所述节段进行焊接,该焊接端与所述波形钢腹板的焊接端相异;选择一天中温度最低时段或温度趋向最低时段,同时将所述波形钢腹板以及所述内、外劲性骨架的未焊接端同所述节段进行焊接,并在温度上升前完成所述合龙段的焊接锁定;完成所述合龙段的混凝土浇筑;待所述合龙段的混凝土养护达到设计强度后,解除两侧所述挂篮主桁架前上横梁之间焊接的所述铁板,并拆除所述挂篮以及所述外劲性骨架,完成中跨合龙。
所述内、外劲性骨架的两端部分别置于所述合龙段两侧的节段底板和顶板上,并分别与预埋于所述节段底板和顶板上的预埋件进行焊接。
所述内、外劲性骨架纵桥向布置,并与所述合龙段中的波形钢腹板位置一一对应。
所述合龙段的混凝土浇筑在一天中温度变化幅度最小且在浇筑后温度上升的时段内进行。
本发明的优点是,①中跨合龙段锁定采用“挂篮主桁架前上横梁铁板+内外劲性骨架”,既安全可靠又经济实用;②劲性骨架分阶段焊接,减少了施工过程中梁体温度变形对各劲性骨架受力的影响,保证合龙段锁定后各劲性骨架均匀受力;③先通过螺栓纵向连接波形钢腹板,最后才通过贴角焊完成纵向连接,避免了劲性骨架焊接和施工过程中梁体温度变形对合龙段波形钢腹板产生附加应力;④焊接两侧挂篮主桁架以及波形钢腹板上下翼缘,既保证了合龙段的线形又提供了额外的合龙段锁定;⑤劲性骨架与波形钢腹板焊接同时施工,可确保合龙段在适合的时段完成锁定;⑥外劲性骨架和挂篮前上横梁铁板可重复使用,可节省钢材,降低了成本。
附图说明
图1为本发明中波形钢腹板PC箱梁斜拉桥中跨合龙示意图;
图2为本发明中合龙段剖面视图。
具体实施方式
以下结合附图通过实施例对本发明的特征及其它相关特征作进一步详细说明,以便于同行业技术人员的理解:
如图1-2,图中标记1-8分别为:前上横梁1、主桁架2、铁板3、外劲性骨架4、内劲性骨架5、预埋件6、波形钢腹板7、合龙段8。
实施例:如图1、2所示,本实施例具体涉及一种波形钢腹板PC箱梁斜拉桥中跨合龙施工方法,该中跨合龙施工方法具体包括如下步骤:
(1)采用挂篮施工完成中跨合龙前N号节段的施工,即如图1中所示的N号节段、N-1号节段、N-2号节段……,调节合龙段8两侧的箱梁节段标高至设计值;
(2)合龙段8两侧的节段上分别设置有挂篮主桁架2,两主桁架2的前上横梁1之间设置有一块铁板3,通过铁板3以将两者临时焊接为一个整体,以提高两侧节段之间的结构稳定性和安全性;
(3)在合龙段8上分块安装波形钢腹板7,调整到位后焊接波形钢腹板7的上、下翼板接缝;之后将波形钢腹板7的一端同其对应侧的节段进行贴角焊接,另一端暂时只用螺栓连接而不焊接;
(4)分别在合龙段8的底板和顶板上布设内劲性骨架5和外劲性骨架4,内劲性骨架5和外劲性骨架4的两端搁置于两侧节段内的预埋件6上,需要说明的是,内劲性骨架5和外劲性骨架4的布置位置与合龙段8内的波形钢腹板7的布置位置一一对应,以提高合龙段8的结构稳定;将内劲性骨架5和外劲性骨架4的一端同对应侧节段内的预埋件6进行焊接,另一端暂不焊接,应注意内劲性骨架5和外劲性骨架4的焊接端应与波形钢腹板7的焊接端相异;
(5)选择一天中温度最低时段或温度趋向最低时段,将内劲性骨架5、外劲性骨架4以及波形钢腹板7的未焊接端同时进行焊接,且必须在温度上升前完成合龙段8的锁定;
(6)锁定后及时解除合龙段8主墩支座的临时约束;
(7)选择温度变化幅度最小且混凝土浇筑后温度上升的时段,完成合龙段8的混凝土浇筑;
(8)待合龙段8混凝土养护达到设计强度后,解除两侧挂篮主桁架2前上横梁1之间临时焊接的铁板3,并拆除挂篮主桁架2以及外劲性骨架4,完成波形钢腹板PC箱梁斜拉桥的中跨合龙施工;而位于合龙段8内的内劲性骨架5与底板混凝土相结合,成为合龙段8的永久构件之一。
本实施例的有益效果在于:
①中跨合龙段锁定采用“挂篮主桁架前上横梁铁板+内外劲性骨架”,既安全可靠又经济实用;
②劲性骨架分阶段焊接,减少了施工过程中梁体温度变形对各劲性骨架受力的影响,保证合龙段锁定后各劲性骨架均匀受力;
③先通过螺栓纵向连接波形钢腹板,最后才通过贴角焊完成纵向连接,避免了劲性骨架焊接和施工过程中梁体温度变形对合龙段波形钢腹板产生附加应力;
④焊接两侧挂篮主桁架以及波形钢腹板上下翼缘,既保证了合龙段的线形又提供了额外的合龙段锁定;
⑤劲性骨架与波形钢腹板焊接同时施工,可确保合龙段在适合的时段完成锁定;
⑥外劲性骨架和挂篮前上横梁铁板可重复使用,可节省钢材,降低施工成本。

Claims (4)

1.一种波形钢腹板PC箱梁斜拉桥中跨合龙施工方法,其特征在于所述中跨合龙施工方法包括如下步骤:将合龙段两侧节段上的挂篮主桁架前上横梁经铁板焊接为一整体;在所述合龙段处分块安装波形钢腹板,将所述波形钢腹板的一端同该侧的所述节段进行焊接,另一端通过螺栓同该侧的所述节段进行连接;在所述合龙段上分别设置内、外劲性骨架,并将所述内、外劲性骨架的一端同该侧的所述节段进行焊接,该焊接端与所述波形钢腹板的焊接端相异;选择一天中温度最低时段或温度趋向最低时段,同时将所述波形钢腹板以及所述内、外劲性骨架的未焊接端同所述节段进行焊接,并在温度上升前完成所述合龙段的焊接锁定;完成所述合龙段的混凝土浇筑;待所述合龙段的混凝土养护达到设计强度后,解除两侧所述挂篮主桁架前上横梁之间焊接的所述铁板,并拆除所述挂篮以及所述外劲性骨架,完成中跨合龙。
2.根据权利要求1所述的一种波形钢腹板PC箱梁斜拉桥中跨合龙施工方法,其特征在于所述内、外劲性骨架的两端部分别置于所述合龙段两侧的节段底板和顶板上,并分别与预埋于所述节段底板和顶板上的预埋件进行焊接。
3.根据权利要求1或2所述的一种波形钢腹板PC箱梁斜拉桥中跨合龙施工方法,其特征在于所述内、外劲性骨架纵桥向布置,并与所述合龙段中的波形钢腹板位置一一对应。
4.根据权利要求1所述的一种波形钢腹板PC箱梁斜拉桥中跨合龙施工方法,其特征在于所述合龙段的混凝土浇筑在一天中温度变化幅度最小且在浇筑后温度上升的时段内进行。
CN201510569004.6A 2015-09-09 2015-09-09 一种波形钢腹板pc箱梁斜拉桥中跨合龙施工方法 Active CN105088971B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510569004.6A CN105088971B (zh) 2015-09-09 2015-09-09 一种波形钢腹板pc箱梁斜拉桥中跨合龙施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510569004.6A CN105088971B (zh) 2015-09-09 2015-09-09 一种波形钢腹板pc箱梁斜拉桥中跨合龙施工方法

Publications (2)

Publication Number Publication Date
CN105088971A true CN105088971A (zh) 2015-11-25
CN105088971B CN105088971B (zh) 2017-02-01

Family

ID=54570231

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510569004.6A Active CN105088971B (zh) 2015-09-09 2015-09-09 一种波形钢腹板pc箱梁斜拉桥中跨合龙施工方法

Country Status (1)

Country Link
CN (1) CN105088971B (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107558376A (zh) * 2017-09-12 2018-01-09 中铁四局集团市政工程有限公司 一种桥梁合龙段波形钢腹板的安装方法
CN108867315A (zh) * 2018-07-11 2018-11-23 中国葛洲坝集团第二工程有限公司 大型桥梁钢混结合段预锁定方法
CN109778720A (zh) * 2019-03-18 2019-05-21 浙江兴土桥梁专用装备制造有限公司 基于挂篮施工的桥梁建设施工方法
CN112458900A (zh) * 2020-11-02 2021-03-09 上海市基础工程集团有限公司 用于钢混叠合梁斜拉桥合龙段桥面吊机联合吊装施工方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101195987A (zh) * 2007-12-27 2008-06-11 中交第二航务工程局有限公司 斜拉桥中跨顶推辅助合龙工艺及梁段拉移组合装置
CN101435182A (zh) * 2008-12-30 2009-05-20 中铁大桥局股份有限公司 刚构桥合拢临时锁定方法
JP2009144411A (ja) * 2007-12-13 2009-07-02 Central Nippon Expressway Co Ltd 張出し架設工法における移動作業車組立解体省略工法及びその工法に使用する波形鋼板
CN101691742A (zh) * 2009-10-10 2010-04-07 中铁十一局集团第四工程有限公司 斜腿刚构桥背索平衡单边悬臂灌筑梁体的施工方法
CN101935985A (zh) * 2010-09-19 2011-01-05 湖南路桥建设集团公司 一种斜拉桥钢箱梁中跨合拢方法
CN104278643A (zh) * 2014-10-17 2015-01-14 中铁建大桥工程局集团第五工程有限公司 一种应用于桥梁工程的连续刚构箱梁施工工艺

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009144411A (ja) * 2007-12-13 2009-07-02 Central Nippon Expressway Co Ltd 張出し架設工法における移動作業車組立解体省略工法及びその工法に使用する波形鋼板
CN101195987A (zh) * 2007-12-27 2008-06-11 中交第二航务工程局有限公司 斜拉桥中跨顶推辅助合龙工艺及梁段拉移组合装置
CN101435182A (zh) * 2008-12-30 2009-05-20 中铁大桥局股份有限公司 刚构桥合拢临时锁定方法
CN101691742A (zh) * 2009-10-10 2010-04-07 中铁十一局集团第四工程有限公司 斜腿刚构桥背索平衡单边悬臂灌筑梁体的施工方法
CN101935985A (zh) * 2010-09-19 2011-01-05 湖南路桥建设集团公司 一种斜拉桥钢箱梁中跨合拢方法
CN104278643A (zh) * 2014-10-17 2015-01-14 中铁建大桥工程局集团第五工程有限公司 一种应用于桥梁工程的连续刚构箱梁施工工艺

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张秋祥: "黄河大桥大跨波形钢腹板PC连续梁桥合龙施工技术", 《铁道建筑技术》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107558376A (zh) * 2017-09-12 2018-01-09 中铁四局集团市政工程有限公司 一种桥梁合龙段波形钢腹板的安装方法
CN107558376B (zh) * 2017-09-12 2019-07-19 中铁四局集团市政工程有限公司 一种桥梁合龙段波形钢腹板的安装方法
CN108867315A (zh) * 2018-07-11 2018-11-23 中国葛洲坝集团第二工程有限公司 大型桥梁钢混结合段预锁定方法
CN109778720A (zh) * 2019-03-18 2019-05-21 浙江兴土桥梁专用装备制造有限公司 基于挂篮施工的桥梁建设施工方法
CN109778720B (zh) * 2019-03-18 2020-11-06 浙江兴土桥梁专用装备制造有限公司 基于挂篮施工的桥梁建设施工方法
CN112458900A (zh) * 2020-11-02 2021-03-09 上海市基础工程集团有限公司 用于钢混叠合梁斜拉桥合龙段桥面吊机联合吊装施工方法

Also Published As

Publication number Publication date
CN105088971B (zh) 2017-02-01

Similar Documents

Publication Publication Date Title
CN105088969A (zh) 一种多塔单索面斜拉桥的合龙方法
CN102493360A (zh) 钢筋混凝土拱桥施工方法
CN108240069A (zh) 一种大跨度多截面组合式桁架屋面结构体系及其施工方法
CN105088971A (zh) 一种波形钢腹板pc箱梁斜拉桥中跨合龙施工方法
CN104389261B (zh) 预制超高性能混凝土π形梁单元、桥梁结构及其施工方法
CN201296900Y (zh) 波形钢腹板组合箱梁合拢段临时锁定装置
CN105484151A (zh) 一种增强预制混凝土节段间连接的构造及其施工方法
CN110067186A (zh) 一种钢管加劲腹板钢混组合箱梁
KR101868677B1 (ko) 메인 철골보와 보조 철골보를 연결하기 위한 연결 유닛 및, 이를 이용한 연결방법
CN110700103A (zh) 一种连续性组合梁施工方法
CN105604183A (zh) 一种桁架后焊节点的施工方法
CN105088961B (zh) 一种边跨合拢段与现浇段合并的施工方法
CN102493553A (zh) 钢筋混凝土梁与钢梁连接节点的构件及其施工方法
CN107574924A (zh) 一种用于钢接头连接的装配式混凝土框架的构件及施工方法
KR101673287B1 (ko) 보수, 보강 또는 리모델링시에 보의 단부에 작용하는 부모멘트에 대한 단면 내력을 증가시키는 방법
KR102066355B1 (ko) 측면 좌굴을 최소화한 강합성 거더 제조방법
CN104032861B (zh) 混合连肢墙型钢柱与非消能梁连接节点结构及其施工方法
CN117107623A (zh) 一种uhpc-波形钢腹板预制拼装变截面箱梁构造及施工方法
CN105133786A (zh) 空腹式快速施工组合梁及其建造方法
CN209039975U (zh) 一种可临时转永久的钢桥桥面结构
CN112376776A (zh) 一种带部分包覆组合梁的装配式屋盖及其施工方法
CN110373987B (zh) 一种箱梁快捷安装组合结构及其安装方法
CN205295915U (zh) 一种波形钢腹板导梁
CN109505237B (zh) 一种钢混组合桥梁伸缩缝处主梁纵向连接构造及施工方法
CN110273362A (zh) 一种正交u型钢桥面板

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant