CN105088960A - Tower crane foundation arrangement method applied on great bridge - Google Patents

Tower crane foundation arrangement method applied on great bridge Download PDF

Info

Publication number
CN105088960A
CN105088960A CN201510568918.0A CN201510568918A CN105088960A CN 105088960 A CN105088960 A CN 105088960A CN 201510568918 A CN201510568918 A CN 201510568918A CN 105088960 A CN105088960 A CN 105088960A
Authority
CN
China
Prior art keywords
tower crane
post strut
tower
king
built
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510568918.0A
Other languages
Chinese (zh)
Other versions
CN105088960B (en
Inventor
陈立生
黄永春
王兵
邓建新
张辉荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Urban Construction Municipal Engineering Group Co Ltd
Original Assignee
Shanghai Urban Construction Municipal Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Urban Construction Municipal Engineering Group Co Ltd filed Critical Shanghai Urban Construction Municipal Engineering Group Co Ltd
Priority to CN201510568918.0A priority Critical patent/CN105088960B/en
Publication of CN105088960A publication Critical patent/CN105088960A/en
Application granted granted Critical
Publication of CN105088960B publication Critical patent/CN105088960B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a tower crane foundation arrangement method applied on a great bridge. The tower crane foundation arrangement method is characterized by comprising the following steps that after concrete pouring of lower tower columns is completed, built-in fittings used for installing a tower crane are arranged on the top faces of the lower tower columns; steel bars and formworks are installed on the top faces of the lower tower columns, and concrete pouring of upper tower columns is completed; the built-in fittings located on the top faces of the lower tower columns are sprung out to be used for connecting foundation components of the tower crane, and then installation of the tower crane is completed on the foundation components. The tower crane foundation arrangement method has the advantages that the construction method is simple and convenient, operation is easy, and the construction cost can be effectively lowered.

Description

A kind of tower crane method to set up be applied on bridge
Technical field
The invention belongs to technical field of bridge engineering, be specifically related to a kind of tower crane method to set up be applied on bridge.
Background technology
For the setting of tower crane, extremely common in Bridges in Our Country is built.Especially be the problem of solution vertical transport in large bridge is built, tower crane be often set and solve this problem.But the basis of its tower crane generally all can be arranged on cushion cap foundation, so relatively more directly perceived, stressed also clearer and more definite.
But, cushion cap foundation arranges tower crane, generally may run into following problem:
1) when cushion cap area meet tower crane is set time, the side root meeting of tower crane " falls through ", at this moment, can solve with the interim bracket of encorbelmenting on suspended deck structure limit; Or the interim pile foundation of injection processes;
2) when lower king-post strut is higher, for solving the column stabilizing measures of tower crane, sometimes temporary rod system is set between lower king-post strut and tower crane pier shaft.Namely built-in fitting to be set between concrete column, adverse influence is brought to the presentation quality of concrete column;
3) when bridge floor design is comparatively wide, original structure design can be generally " vase " style column superstructure design, to meet the stable needs of cross-section of bridge; Like this, certain difficulty is brought to the setting of tower crane.
Therefore, be not very high structure to superstructure, need tower crane to solve the problem of vertical transport simultaneously, under the precondition ensured safety, high-quality, realize job site Perpendicular Problems fast, economically, become the problem that construction technical staff needs to solve.
Summary of the invention
The object of the invention is according to above-mentioned the deficiencies in the prior art part, a kind of tower crane method to set up be applied on bridge is provided, this tower crane method to set up, by by the end face of the basis instrument of tower crane in lower king-post strut, decreases the sections of tower crane tower body, reduces operating expenses.
The object of the invention realizes being completed by following technical scheme:
Be applied to the tower crane method to set up on bridge, it is characterized in that described tower crane method to set up comprises the steps: after the concrete placings of lower king-post strut, the end face of described lower king-post strut arranges the built-in fitting for installing tower crane; The end face of described lower king-post strut is installed reinforcing bar and template and completes the concrete placings of upper king-post strut; By the built-in fitting being positioned at described lower king-post strut end face ejecting the basic component being used for connecting described tower crane, on described basic component, complete the installation of described tower crane afterwards.
Described lower king-post strut is made up of to the limit binder arranged and middle binder the column vertically arranged and level, and described tower crane supporting is installed on described limit binder and described middle binder.
Described basic component is by welding iron plate to form interim location.
Advantage of the present invention is, (1) solve tower crane be arranged on cushion cap concrete basis or encorbelment on cushion cap foundation " bracket " structure time performance difficulty problem, economical and practical; (2) solving tower crane because of cushion cap area is arranged not, and uses interim injection pile foundation to arrange the operation at sea of tower crane, is conducive to reducing construction cost by reducing operation at sea; (3) because tower crane is arranged on the top of concrete column, decrease the sections of tower crane tower body, the tower body namely within the scope of stem height, because the position arranged is improved, decrease the tower body structure of this section, reduce the lease expenses of equipment.
Accompanying drawing explanation
Fig. 1 is 1/2 lower king-post strut top floor map in the present invention;
Fig. 2 is the positive elevational schematic view of 1/2 lower king-post strut in the present invention.
Detailed description of the invention
Feature of the present invention and other correlated characteristic are described in further detail by embodiment below in conjunction with accompanying drawing, so that the understanding of technician of the same trade:
Be respectively as marked 1-6 in Fig. 1-2, figure: column 1, limit binder 2, middle binder 3, built-in fitting 4, tower crane 5, lateral and diagonal brace 6.
Embodiment: as shown in Figure 1, 2, the present embodiment is specifically related to a kind of tower crane method to set up be applied on bridge, this bridge is the short tower girder stayed-cable bridge of six tower single cable plane, full-bridge has 6 king-towers, each king-tower substructure tower body height is 21-25M, symmetrical between two, king-post top is made up of 2 road binders.
This tower crane method to set up by by the basis instrument of tower crane in the end face of lower king-post strut to simplify construction method, and reduce construction cost, specifically comprise the steps:
(1) complete the concrete placings of lower king-post strut, lower king-post strut is made up of column 1, limit binder 2 and middle binder 3, and twice limit binder 2 is symmetricly set in middle binder 3 both sides, and three's horizontal cross is connected between twice vertical upright column 1; The reinforcing bar and template of building needed for upper king-post strut are installed at lower king-post strut end face; On limit binder 2 with middle binder 3, arrange built-in fitting 4 respectively afterwards, built-in fitting 4 is specially welding and is embedded in iron plate on limit binder 2 and middle binder 3 side in advance;
It should be noted that, these built-in fittings 4 some carry out welding or prefabricated in factory or concentrated processing place, when installing at the scene, will not weld with all kinds of reinforcing bars in column 1, limit binder 2 and middle binder 3, to avoid the intensity affecting lower king-post strut agent structure;
(2) complete the concrete placings construction of upper king-post strut, the intensity of upper king-post strut and modulus of elasticity must reach the requirement of concrete structure design;
(3) on the built-in fitting 4 preset before, eject the basic component for connecting tower crane, i.e. lateral and diagonal brace 6, and utilize iron plate to carry out temporary weld location;
(4) design drawing of foundation tower crane 5 completes the erecting and welding of tower crane 5;
(5) according to the administrative provisions of special equipment, carry out situ loading, and submit a report asking for relevant department and carry out an acceptance inspection.
The present embodiment has safe and reliable, convenient, economical and practical feature of constructing, and specifically comprises following beneficial effect:
(1) solve tower crane be arranged on cushion cap concrete basis or encorbelment on cushion cap foundation " bracket " structure time performance difficulty problem, economical and practical;
(2) solving tower crane because of cushion cap area is arranged not, and uses interim injection pile foundation to arrange the operation at sea of tower crane, is conducive to reducing construction cost by reducing operation at sea;
(3) because tower crane is arranged on the top of concrete column, decrease the sections of tower crane tower body, the tower body namely within the scope of stem height, because the position arranged is improved, decrease the tower body structure of this section, reduce the lease expenses of equipment.

Claims (3)

1. be applied to the tower crane method to set up on bridge, it is characterized in that described tower crane method to set up comprises the steps: after the concrete placings of lower king-post strut, the end face of described lower king-post strut arranges the built-in fitting for installing tower crane; The end face of described lower king-post strut is installed reinforcing bar and template and completes the concrete placings of upper king-post strut; By the built-in fitting being positioned at described lower king-post strut end face ejecting the basic component being used for connecting described tower crane, on described basic component, complete the installation of described tower crane afterwards.
2. a kind of tower crane method to set up according to claim 1, is characterized in that described lower king-post strut is made up of to the limit binder arranged and middle binder the column vertically arranged and level, and described tower crane supporting is installed on described limit binder and described middle binder.
3. a kind of tower crane method to set up according to claim 1, is characterized in that described basic component by welding iron plate to form interim location.
CN201510568918.0A 2015-09-09 2015-09-09 A kind of tower crane method to set up being applied on bridge Active CN105088960B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510568918.0A CN105088960B (en) 2015-09-09 2015-09-09 A kind of tower crane method to set up being applied on bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510568918.0A CN105088960B (en) 2015-09-09 2015-09-09 A kind of tower crane method to set up being applied on bridge

Publications (2)

Publication Number Publication Date
CN105088960A true CN105088960A (en) 2015-11-25
CN105088960B CN105088960B (en) 2017-03-29

Family

ID=54570220

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510568918.0A Active CN105088960B (en) 2015-09-09 2015-09-09 A kind of tower crane method to set up being applied on bridge

Country Status (1)

Country Link
CN (1) CN105088960B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114941284A (en) * 2022-03-04 2022-08-26 中建八局天津建设工程有限公司 Permanent-temporary combined tower crane foundation and construction method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201581409U (en) * 2009-12-25 2010-09-15 浙江中成建工集团有限公司 Combined tower crane foundation of cross beam supported by steel latticework columns in deep foundation pit
CN202787297U (en) * 2012-05-22 2013-03-13 实事集团建设工程有限公司 Tower crane base
CN203256761U (en) * 2013-05-17 2013-10-30 中建八局第三建设有限公司 Tower crane foundation arranged on top plate of basement
CN203334643U (en) * 2013-06-06 2013-12-11 浙江城建建设集团有限公司 Tower crane standard knot and structural steel combination high-altitude large-span operation frame device

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201581409U (en) * 2009-12-25 2010-09-15 浙江中成建工集团有限公司 Combined tower crane foundation of cross beam supported by steel latticework columns in deep foundation pit
CN202787297U (en) * 2012-05-22 2013-03-13 实事集团建设工程有限公司 Tower crane base
CN203256761U (en) * 2013-05-17 2013-10-30 中建八局第三建设有限公司 Tower crane foundation arranged on top plate of basement
CN203334643U (en) * 2013-06-06 2013-12-11 浙江城建建设集团有限公司 Tower crane standard knot and structural steel combination high-altitude large-span operation frame device

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张钧才: "《华南理工大学工程硕士学位论文》", 31 December 2012 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114941284A (en) * 2022-03-04 2022-08-26 中建八局天津建设工程有限公司 Permanent-temporary combined tower crane foundation and construction method thereof

Also Published As

Publication number Publication date
CN105088960B (en) 2017-03-29

Similar Documents

Publication Publication Date Title
CN103741604B (en) Totally-prefabricated assembling type reinforced concrete bridge splicing structure and attaching method thereof
CN106088326B (en) Assembling frame rod structure based on 3D printing
CN103215894B (en) Portable interim prestressed stretch-draw anchor block
CN103556749A (en) Hanging flexible connection of precast concrete infill wall
CN203947771U (en) A kind of Bailey beam pendent form support system
CN104594204B (en) Urban light rail viaduct mountain type U beam Construction Supporting System and construction method
CN104005338A (en) Three-directional temporary tower and girder consolidation structure of large-span cable-stayed bridge
JP2008274586A (en) Pillar head construction method
CN203487664U (en) Prefabricated concrete filled wall suspension type flexible connection
CN102605717A (en) Pier-top longitudinal support scaffolding method
CN102777044B (en) Hoisting method of steel-structured spraying layer of urea prilling tower
CN103469732A (en) Construction method of preformed holes for foundation bolts of bridge support
CN106032704A (en) Construction method for using concrete columns to support structures on both sides of post-pouring strip
CN101838986B (en) Disassembling tool type lattice column and construction method thereof
CN204475184U (en) Urban light rail viaduct mountain type U beam Construction Supporting System
CN202809494U (en) Bracket for pouring 0# block to rigid continuous girder bridge
CN105442453A (en) Construction method for suspension bridge tower crossbeam combination support
CN203475310U (en) Formwork for concrete slabs of composite steel-concrete box girders
CN202265906U (en) Fixing device for anchor bolts of embedded type steel tube concrete column feet
CN205369229U (en) But walking hoisting frame suitable for manual hole digging pile steel reinforcement cage is laid
CN104563525B (en) A kind of box steel arch beam Integral horizontal type group is to method
CN104961058B (en) A kind of double Z shaped support steel beam and crane supporting member and preparation method containing it
CN103967332A (en) Construction method of building site barrier
CN103615058B (en) A kind of constraint steel plate construction of super high-rise steel plate concrete shear wall and construction method thereof
CN105088960A (en) Tower crane foundation arrangement method applied on great bridge

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant