CN105002905A - Embedded anchor bar joint - Google Patents

Embedded anchor bar joint Download PDF

Info

Publication number
CN105002905A
CN105002905A CN201510317955.4A CN201510317955A CN105002905A CN 105002905 A CN105002905 A CN 105002905A CN 201510317955 A CN201510317955 A CN 201510317955A CN 105002905 A CN105002905 A CN 105002905A
Authority
CN
China
Prior art keywords
anchor
node clamp
embedded
clamp
paste
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510317955.4A
Other languages
Chinese (zh)
Other versions
CN105002905B (en
Inventor
梁枫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Liu Jing
Liu Tong
Original Assignee
Chengdu Jiameijia Science and Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Jiameijia Science and Technology Co Ltd filed Critical Chengdu Jiameijia Science and Technology Co Ltd
Priority to CN201510317955.4A priority Critical patent/CN105002905B/en
Publication of CN105002905A publication Critical patent/CN105002905A/en
Application granted granted Critical
Publication of CN105002905B publication Critical patent/CN105002905B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses an embedded anchor bar joint. The embedded anchor bar joint comprises an upper anchor joint clamping plate and a lower anchor joint clamping plate which are connected through a pitch factice layer. The lower anchor joint clamping plate and the upper anchor joint clamping plate are both connected to the pitch factice layer in a clamping manner. Two embedded plates are vertically arranged in the pitch factice layer. The tops of the embedded plates penetrate the pitch factice layer to be connected with the upper anchor joint clamping plate. The bottoms of the embedded plates both penetrate the pitch factice layer and the lower anchor joint clamping plate. An additional layer is transversely arranged between the two embedded plates. The two ends of the additional layer penetrate the two embedded plates respectively. Embedded pipes are connected between the additional layer and the upper anchor joint clamping plate. According to the embedded anchor bar joint, anchorage devices are omitted, construction is easier, and accordingly the requirement for constructors is accordingly lowered; the construction quality is higher in reliability, the embedding effect is quite good, and the good supporting performance is achieved; and due to the enhancement effect of the additional structural layer, the waterproof effect of the embedded anchor bar joint can be more obvious, and the leakage phenomenon is not prone to appearing.

Description

Embedded anchor bar node
Technical field
The present invention relates to a kind of anchor pole node, particularly a kind of embedded anchor bar node.
Background technology
Bolt support is a kind of its support reinforcement mode adopted in the earth's surface engineerings such as side slope, ground deep foundation ditch and the construction of the underground chamber such as tunnel, stope, roofbolt is made with metalwork, wooden piece, polymer member or other materials, squeeze in earth's surface rock mass or the pre-drilled hole of chamber surrounding rock body, utilize special tectonic and the afterbody supporting plate of its head, the body of rod, or depend on bonding effect and country rock and rock mass stability are combined and produces suspension effectiveness, compound beam effect and reinforcing effect, to reach the object of supporting.Anchor pole is provided with node, can better play reinforcement by connection effect, general anchor pole nodal function is single, easily occurs obscission, can not better play pre-buried effect, needs to carry out corresponding improvement to it, can better be applied in bolt support.
Summary of the invention
The technical problem to be solved in the present invention is: overcome the problems referred to above, provides one to eliminate ground tackle, constructs simpler, the requirement of constructor is also decreased, reliable construction quality is higher, and pre-buried effect is very good, has the embedded anchor bar node of good support performance.
To achieve these goals, the technical solution used in the present invention is such: embedded anchor bar node of the present invention, comprise anchor node clamp and the node clamp that casts anchor, upper anchor node clamp and casting anchor between node clamp is connected by coal tar layer of paste, cast anchor node clamp and upper anchor node clamp is all connected in coal tar layer of paste, vertically embedded board is installed in coal tar layer of paste, embedded board top is connected with upper anchor node clamp through coal tar layer of paste, coal tar layer of paste and the node clamp that casts anchor setting is each passed through bottom it, embedded board is two, laterally extra play is provided with between two embedded boards, extra play two ends are each passed through two embedded boards and arrange, built-in pipe is connected with between extra play and upper anchor node clamp, arrange through extra play bottom built-in pipe, its top is arranged through upper anchor node clamp.
Further, as a kind of concrete form of structure, upper anchor node clamp of the present invention and the node clamp that casts anchor all adopt nonmetals to make.
Further, as a kind of concrete form of structure, upper anchor node clamp soffit of the present invention and the node clamp upper surface that casts anchor all have draw-in groove.
Further, as a kind of concrete form of structure, in upper anchor node clamp soffit of the present invention and the node clamp draw-in groove that casts anchor, all slide rail is installed.
Further, as a kind of concrete form of structure, the equal soffit of coal tar layer of paste upper surface of the present invention is all placed in anchor node clamp soffit and casts anchor in the draw-in groove of node clamp, and coal tar layer of paste and upper anchor node clamp soffit and node clamp junction of casting anchor are provided with advance ball, advance ball is placed in draw-in groove.
Further, as a kind of concrete form of structure, coal tar layer of paste thickness of the present invention is between five to ten centimetres.
Compared with prior art, the invention has the advantages that: this embedded anchor bar node eliminates ground tackle, construct simpler, also decrease the requirement of constructor, reliable construction quality is higher, and pre-buried effect is very good, there is good support performance, in addition the humidification of additional structure layers, makes its waterproof effect more obvious, not easily occurs Seepage.
Accompanying drawing explanation
Below in conjunction with drawings and Examples, the present invention is further described.
Fig. 1 is structural representation of the present invention; In figure: 1. go up anchor node clamp; 2. embedded board; 3. built-in pipe; 4. extra play; 5. coal tar layer of paste; 6. cast anchor node clamp.
Detailed description of the invention
In conjunction with the accompanying drawings, the present invention is further detailed explanation, and these accompanying drawings are the schematic diagram of simplification, only basic structure of the present invention is described in a schematic way, and therefore it only shows the formation relevant with the present invention.
The preferred embodiment of embedded anchor bar node of the present invention as shown in Figure 1, comprise anchor node clamp 1 and the node clamp 6 that casts anchor, upper anchor node clamp 1 and casting anchor between node clamp 6 is connected by coal tar layer of paste 5, cast anchor node clamp 1 and upper anchor node clamp 6 is all connected in coal tar layer of paste 5, in coal tar layer of paste 5, embedded board 2 is vertically installed, embedded board 2 top is connected with upper anchor node clamp 1 through coal tar layer of paste 5, coal tar layer of paste 5 is each passed through and the node clamp 6 that casts anchor is arranged bottom it, embedded board 2 is two, laterally extra play 4 is provided with between two embedded boards 2, extra play 4 two ends are each passed through two embedded boards 2 and arrange, built-in pipe 3 is connected with between extra play 4 and upper anchor node clamp 1, 4 are established to put through extra play bottom built-in pipe 3, its top is arranged through upper anchor node clamp 1, described upper anchor node clamp 1 and the node clamp 6 that casts anchor all adopt nonmetals to make, described upper anchor node clamp 1 soffit and node clamp 6 upper surface that casts anchor all have draw-in groove, all slide rail is installed in described upper anchor node clamp 1 soffit and node clamp 6 draw-in groove that casts anchor, the equal soffit of described coal tar layer of paste 5 upper surface is all placed in anchor node clamp 1 soffit and casts anchor in the draw-in groove of node clamp 6, and coal tar layer of paste 5 is provided with advance ball with upper anchor node clamp 1 soffit and node clamp 6 junction of casting anchor, advance ball is placed in draw-in groove, described coal tar layer of paste 5 thickness is between five to ten centimetres.
Embedded anchor bar node of the present invention eliminates ground tackle, construct simpler, also decrease the requirement of constructor, reliable construction quality is higher, and pre-buried effect is very good, there is good support performance, in addition the humidification of additional structure layers, makes its waterproof effect more obvious, not easily occurs Seepage, described upper anchor node clamp 1 and the node clamp 6 that casts anchor all adopt nonmetals to make, and alleviate self structure weight, described upper anchor node clamp 1 soffit and node clamp 6 upper surface that casts anchor all have draw-in groove, all slide rail is installed in described upper anchor node clamp 1 soffit and node clamp 6 draw-in groove that casts anchor, the equal soffit of described coal tar layer of paste 5 upper surface is all placed in anchor node clamp 1 soffit and casts anchor in the draw-in groove of node clamp 6, and coal tar layer of paste 5 is provided with advance ball with upper anchor node clamp 1 soffit and node clamp 6 junction of casting anchor, advance ball is placed in draw-in groove, can be slidably connected, and switching performance is stablized, there will not be obscission, connect secure rigid more, described coal tar layer of paste 5 thickness is between five to ten centimetres, and actual field result of use is better.
With above-mentioned according to desirable embodiment of the present invention for enlightenment, by above-mentioned description, relevant staff completely can in the scope not departing from this invention technological thought, carry out various change and amendment, the technical scope of this invention is not limited to the content on manual, must determine its technical scope according to right.

Claims (1)

1. an embedded anchor bar node, comprise anchor node clamp and the node clamp that casts anchor, it is characterized in that: upper anchor node clamp and casting anchor between node clamp is connected by coal tar layer of paste, cast anchor node clamp and upper anchor node clamp is all connected in coal tar layer of paste, vertically embedded board is installed in coal tar layer of paste, embedded board top is connected with upper anchor node clamp through coal tar layer of paste, coal tar layer of paste and the node clamp that casts anchor setting is each passed through bottom it, embedded board is two, laterally extra play is provided with between two embedded boards, extra play two ends are each passed through two embedded boards and arrange, built-in pipe is connected with between extra play and upper anchor node clamp, arrange through extra play bottom built-in pipe, its top is arranged through upper anchor node clamp, described upper anchor node clamp and the node clamp that casts anchor all adopt nonmetals to make, described upper anchor node clamp soffit and the node clamp upper surface that casts anchor all have draw-in groove, all slide rail is installed in described upper anchor node clamp soffit and the node clamp draw-in groove that casts anchor, the equal soffit of described coal tar layer of paste upper surface is all placed in anchor node clamp soffit and casts anchor in the draw-in groove of node clamp, and coal tar layer of paste and upper anchor node clamp soffit and node clamp junction of casting anchor are provided with advance ball, advance ball is placed in draw-in groove, described coal tar layer of paste thickness is between five to ten centimetres.
CN201510317955.4A 2015-06-11 2015-06-11 Embedded anchor bar node Expired - Fee Related CN105002905B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510317955.4A CN105002905B (en) 2015-06-11 2015-06-11 Embedded anchor bar node

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510317955.4A CN105002905B (en) 2015-06-11 2015-06-11 Embedded anchor bar node

Publications (2)

Publication Number Publication Date
CN105002905A true CN105002905A (en) 2015-10-28
CN105002905B CN105002905B (en) 2017-03-01

Family

ID=54375749

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510317955.4A Expired - Fee Related CN105002905B (en) 2015-06-11 2015-06-11 Embedded anchor bar node

Country Status (1)

Country Link
CN (1) CN105002905B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111075031A (en) * 2019-12-24 2020-04-28 常州工学院 Civil engineering construction pre-buried equipment

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6401407B1 (en) * 1999-05-26 2002-06-11 Stay-Put Safety Plate Distribution, Inc. Cover plate ground anchor
CN2529905Y (en) * 2002-03-18 2003-01-08 柳州市建筑机械总厂 Heading anchor-boom anchor device
CN201280726Y (en) * 2008-08-06 2009-07-29 青岛海川建设集团有限公司 Combination anti-floating piled anchor node water-proof structure
CN104153802A (en) * 2014-07-18 2014-11-19 成都绿迪科技有限公司 Anchor rod structure
CN204326072U (en) * 2014-12-11 2015-05-13 李骁春 A kind of anti-float anchor rod node

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6401407B1 (en) * 1999-05-26 2002-06-11 Stay-Put Safety Plate Distribution, Inc. Cover plate ground anchor
CN2529905Y (en) * 2002-03-18 2003-01-08 柳州市建筑机械总厂 Heading anchor-boom anchor device
CN201280726Y (en) * 2008-08-06 2009-07-29 青岛海川建设集团有限公司 Combination anti-floating piled anchor node water-proof structure
CN104153802A (en) * 2014-07-18 2014-11-19 成都绿迪科技有限公司 Anchor rod structure
CN204326072U (en) * 2014-12-11 2015-05-13 李骁春 A kind of anti-float anchor rod node

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111075031A (en) * 2019-12-24 2020-04-28 常州工学院 Civil engineering construction pre-buried equipment

Also Published As

Publication number Publication date
CN105002905B (en) 2017-03-01

Similar Documents

Publication Publication Date Title
CN102352632B (en) Anchor rod sheet pile combined structure and method for reinforcing high filling body on one side of slope
CN104652419B (en) A kind of underground anti-seepage reserves the construction method of grout curtain pipe within the walls
CN205778903U (en) A kind of soft-rock tunnel pucking preventing and treating device
CN207567757U (en) A kind of novel prefabricated steel-pipe pile
CN207278276U (en) Cross the shallow-depth-excavation tunnel supporting construction of ground fissure crushed zone
CN109505641A (en) A kind of soft-rock tunnel bottom plate anchor pouring reinforcement method
CN103243724A (en) Bedding cutting high slope closing reinforcement structure
CN105155548A (en) Cable double-row pile (wall) supporting structure
CN108316328A (en) A kind of pressurization sinking device and its construction method for open caisson construction
CN105133641A (en) Thin-wall continuous-wall-type foundation reinforcing structure and method
CN208701666U (en) The barbed implantable steel tube anchor rod of building foundation pit side slope
CN105002905A (en) Embedded anchor bar joint
CN204940271U (en) Embedded anchor bar node
CN107237645A (en) A kind of improved Self-propelled grouting anchoring-bolt
CN207878441U (en) A kind of ruggedized construction of soft soil foundation
CN207211388U (en) The vertical connection structure of precast shear wall
CN202755385U (en) Anti-floating structure of shallow-buried shield tunnel
CN205295920U (en) An area supporting beam's thin wall abutment structure
CN204023569U (en) A kind of bellows enlarged footing anchor bolt support
CN208604615U (en) A kind of pressurization sinking device for open caisson construction
CN207974834U (en) A kind of Tunnel Engineering pipe curtain support construction
CN204645033U (en) Head for anchor shaft
CN204418208U (en) Anchor rod foundation
CN207646732U (en) It is segmented self-tightening type anchor pole
CN205591246U (en) A railway roadbed contact net column foundation structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
CB03 Change of inventor or designer information

Inventor after: Liu Tong

Inventor after: Liu Jing

Inventor after: Hu Baojun

Inventor after: Cheng Chunling

Inventor after: Zhang Chunfang

Inventor after: Zhou Xiaolu

Inventor before: Liang Feng

COR Change of bibliographic data
TA01 Transfer of patent application right

Effective date of registration: 20161202

Address after: 050000 Hebei City, Shijiazhuang Province West Bridge Road, No. 9, building 2, unit 101, No. 72

Applicant after: Liu Tong

Applicant after: Liu Jing

Applicant after: Hu Baojun

Applicant after: Cheng Chunling

Applicant after: Zhang Chunfang

Applicant after: Zhou Xiaolu

Address before: 610000 Sichuan Province, Qingyang District, Jinyang Road, No. 7, building 6, building 19, No. 112

Applicant before: CHENGDU JIAMEIJIA SCIENCE & TECHNOLOGY CO., LTD.

GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170301