CN207211388U - The vertical connection structure of precast shear wall - Google Patents

The vertical connection structure of precast shear wall Download PDF

Info

Publication number
CN207211388U
CN207211388U CN201720731192.2U CN201720731192U CN207211388U CN 207211388 U CN207211388 U CN 207211388U CN 201720731192 U CN201720731192 U CN 201720731192U CN 207211388 U CN207211388 U CN 207211388U
Authority
CN
China
Prior art keywords
shear wall
precast shear
cast
grout sleeve
vertical connection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720731192.2U
Other languages
Chinese (zh)
Inventor
李小斌
全文林
吴仲勤
钱宏远
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Yu Hui Housing Industry Co Ltd
Original Assignee
Jiangsu Yu Hui Housing Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Yu Hui Housing Industry Co Ltd filed Critical Jiangsu Yu Hui Housing Industry Co Ltd
Priority to CN201720731192.2U priority Critical patent/CN207211388U/en
Application granted granted Critical
Publication of CN207211388U publication Critical patent/CN207211388U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model discloses a kind of vertical connection structure of precast shear wall, precast shear wall is installed on cast-in-place structural plate, the bottom of precast shear wall is provided with grout sleeve, grout sleeve is provided with the injected hole for extending precast shear wall, slurry outlet, precast shear wall is provided with the upper extension reinforcing bar for stretching into grout sleeve, cast-in-place structural plate is provided with the lower extension reinforcing bar for extending to grout sleeve, grout sleeve is perfused with sleeve grouting material, there is horizontal joint between precast shear wall and cast-in-place structural plate, horizontal joint is followed successively by grouting material structure sheaf by indoor side towards outdoor side, gum filler, cavity body, PE filler rods, weather-resistant glue.The beneficial effects of the utility model are:Precast shear wall vertical connection structure construction is more convenient, and structural stability is strong.

Description

The vertical connection structure of precast shear wall
Technical field
Precast concrete construction field is the utility model is related to, vertical more particularly, to a kind of precast shear wall connects Binding structure.
Background technology
Precast concrete is needed after the completion of precast factory is prefabricated, then is transported to scene and installed.Prefabricated shearing Need to complete vertical connection when wall is installed at the scene, and existing mounting structure is complex, construction is more inconvenient.
Utility model content
The purpose of this utility model is exactly to solve the above problems, there is provided a kind of vertical connection knot of precast shear wall Structure, its is easy for construction, and structural stability is high.
In order to solve the above technical problems, embodiment of the present utility model provides a kind of vertical connection of precast shear wall Structure, precast shear wall are installed on cast-in-place structural plate, and the bottom of precast shear wall is provided with grout sleeve, and grout sleeve is set There are the injected hole for extending precast shear wall, slurry outlet, precast shear wall is provided with the upper extension reinforcing bar for stretching into grout sleeve, existing Pour structural slab and be provided with the lower extension reinforcing bar for extending to grout sleeve, grout sleeve is perfused with sleeve grouting material, precast shear wall There is horizontal joint between cast-in-place structural plate, horizontal joint is followed successively by grouting material structure sheaf towards outdoor side by indoor side, filled out Fill adhesive tape, cavity body, PE filler rods, weather-resistant glue.
Further, be lower precast shear wall or lower cast-in-place shear wall below cast-in-place structural plate, lower precast shear wall or Lower cast-in-place shear wall is provided with the lower extension reinforcing bar for extending to grout sleeve.
Further, the groove of installation PE filler rods is provided with the top of lower precast shear wall or at the top of lower cast-in-place shear wall.
Further, the carbon fiber wire arranged along barred body bearing of trend is provided with PE filler rods
The utility model has the advantages that:More convenient, the structure of precast shear wall vertical connection structure construction Stability is strong.
Brief description of the drawings
Fig. 1 is the vertical connection structure schematic diagram of precast shear wall in first embodiment.
Fig. 2 is the vertical connection structure schematic diagram of precast shear wall in second embodiment.
Embodiment
In order that technological means, creation characteristic, reached purpose and effect that the utility model is realized are easy to understand, under In conjunction with specific embodiments, the utility model is expanded on further in face.
First embodiment of the present utility model provides a kind of vertical connection structure of precast shear wall, referring to Fig. 1, in advance Shear wall 1 processed is installed on cast-in-place structural plate 2, and is lower precast shear wall Q below cast-in-place structural plate, the bottom of precast shear wall Be provided with grout sleeve 3, the grout sleeve is embedded in advance when precast shear wall is prefabricated, grout sleeve be provided with extend it is prefabricated Injected hole 4, the slurry outlet 5 of shear wall, injected hole are located at the lower section of grout sleeve, and slurry outlet is located at the top of grout sleeve, in advance Shear wall processed is provided with the upper extension reinforcing bar S1 for stretching into grout sleeve, and cast-in-place structural plate 2, which is provided with, to be extended under grout sleeve Extend reinforcing bar S2, and the reinforcing bar of lower extension reinforcing bar S2 from the lower precast shear wall extends to, grout sleeve is perfused with sleeve filling Slurry, has horizontal joint between precast shear wall and cast-in-place structural plate, horizontal joint is followed successively by by indoor side towards outdoor side Grouting material structure sheaf 6, gum filler 7, cavity body 8, PE filler rods 9, weather-resistant glue 10.
The groove of installation PE filler rods is provided with the top of lower precast shear wall, the diameter of the PE filler rods is more than horizontal joint Highly, and the surface of PE filler rods can set some fold-like structures.
Second embodiment of the present utility model provides a kind of vertical connection structure of precast shear wall, referring to Fig. 2, in advance Shear wall 1 processed is installed on cast-in-place structural plate 2, is lower cast-in-place shear wall E below cast-in-place structural plate, the bottom of precast shear wall is set Grout sleeve 3 is equipped with, grout sleeve is provided with the injected hole 4 for extending precast shear wall, slurry outlet 5, and precast shear wall is set There is the upper extension reinforcing bar S1 for stretching into grout sleeve, cast-in-place structural plate 2 is provided with the lower extension reinforcing bar S2 for extending to grout sleeve, fills Slurry sleeve is perfused with sleeve grouting material, has horizontal joint between precast shear wall and cast-in-place structural plate, horizontal joint is by indoor side Grouting material structure sheaf 6, gum filler 7, cavity body 8, PE filler rods 9, weather-resistant glue 10 are followed successively by towards outdoor side.Under cast-in-place cut Power wall top portion is provided with the groove of installation PE filler rods.
Can be with addition, the carbon fiber wire arranged along barred body bearing of trend can be set in PE filler rods, after installation is in place By testing, whether two ends of PE filler rods are conductive to judge whether PE filler rods are broken.
It will be understood by those skilled in the art that the respective embodiments described above are to realize specific reality of the present utility model Apply example, and in actual applications, can to it, various changes can be made in the form and details, without departing from essence of the present utility model God and scope.

Claims (4)

1. a kind of vertical connection structure of precast shear wall, precast shear wall are installed on cast-in-place structural plate, it is characterised in that institute The bottom for stating precast shear wall is provided with grout sleeve, the grout sleeve be provided with extend precast shear wall injected hole, Slurry outlet, the precast shear wall are provided with the upper extension reinforcing bar for stretching into grout sleeve, and the cast-in-place structural plate is provided with extension To the lower extension reinforcing bar of grout sleeve, the grout sleeve is perfused with sleeve grouting material, the precast shear wall and cast-in-place structural There is horizontal joint between plate, the horizontal joint by indoor side towards outdoor side be followed successively by grouting material structure sheaf, gum filler, Cavity body, PE filler rods, weather-resistant glue.
2. the vertical connection structure of precast shear wall according to claim 1, it is characterised in that under the cast-in-place structural plate Side is lower precast shear wall or lower cast-in-place shear wall, and the lower precast shear wall or lower cast-in-place shear wall are provided with and extended to The lower extension reinforcing bar of grout sleeve.
3. the vertical connection structure of precast shear wall according to claim 2, it is characterised in that the lower precast shear wall The groove of installation PE filler rods is provided with the top of top or lower cast-in-place shear wall.
4. the vertical connection structure of precast shear wall according to claim 1, it is characterised in that set in the PE filler rods It is equipped with the carbon fiber wire arranged along barred body bearing of trend.
CN201720731192.2U 2017-06-22 2017-06-22 The vertical connection structure of precast shear wall Active CN207211388U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720731192.2U CN207211388U (en) 2017-06-22 2017-06-22 The vertical connection structure of precast shear wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720731192.2U CN207211388U (en) 2017-06-22 2017-06-22 The vertical connection structure of precast shear wall

Publications (1)

Publication Number Publication Date
CN207211388U true CN207211388U (en) 2018-04-10

Family

ID=61812054

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720731192.2U Active CN207211388U (en) 2017-06-22 2017-06-22 The vertical connection structure of precast shear wall

Country Status (1)

Country Link
CN (1) CN207211388U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110835979A (en) * 2019-11-29 2020-02-25 上海宝冶集团有限公司 Assembled wall reinforcing steel sleeve grouting process
CN111779140A (en) * 2020-07-22 2020-10-16 青岛中建联合建设工程有限公司 Building assembled concrete wall and major structure connecting device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110835979A (en) * 2019-11-29 2020-02-25 上海宝冶集团有限公司 Assembled wall reinforcing steel sleeve grouting process
CN111779140A (en) * 2020-07-22 2020-10-16 青岛中建联合建设工程有限公司 Building assembled concrete wall and major structure connecting device

Similar Documents

Publication Publication Date Title
CN103132656B (en) Connecting structure for vertical reinforcement bars of prefabricated wall parts
US20180002885A1 (en) Rock anchor foundation structure suitable for mountain photovoltaic module and construction method of rock anchor foundation structure
CN207194006U (en) A kind of prefabricated concrete retaining wall
CN104631432B (en) Flexible supporting system for prestress anchor supporting plate of sheet-pile retaining wall and construction method thereof
CN107288138B (en) The control structure and construction method of the rock side slope containing weak intercalated layer
CN102864777A (en) Fast prestress anchor stock structure and construction method
CN207211388U (en) The vertical connection structure of precast shear wall
CN206616827U (en) One kind box filled piece of built-in line of building
CN106284999A (en) Assembled architecture haydite concrete batten of internal partition mounting process
CN209114658U (en) A kind of precast concrete partition plate structure for staircase
CN104762967A (en) Improved anchor rod static pressure pile sealing device and construction method
CN104452757A (en) Quick presressed anchor rod structure and construction method
CN108867361A (en) A kind of half grout sleeve connection prefabricated assembling type reinforced concrete side crashproof guardrail
CN108412081A (en) It is applied with the building construction method of horizontal prestressed masonry structure and masonry
CN109024973A (en) A kind of connection structure and its construction method for precast shear wall
CN205954675U (en) Prefabricated pipeline concrete buttress
CN108222656A (en) The construction method of Prefabricated enclosure wall
CN204152113U (en) Masonry panel balustrade pre-buried structure
CN209260588U (en) A kind of Bridge Crack filling clamping device
CN207812739U (en) One kind being applied with horizontal prestressed masonry structure
CN103498573B (en) Set up the existing frame strengthening method of band frame bracing members
CN103243913B (en) The method for blocking of fabricated shear wall architectural lower floor junction grout blanket
CN206707763U (en) A kind of pre-buried channel flow component for subway tunnel
CN205857455U (en) The fabricated shear wall structure that a kind of prestressing force connects
CN207160449U (en) Stair fix hinge end mounting structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant