CN104988945B - Hydroenergy storage station unit installation method and temporary support structure - Google Patents

Hydroenergy storage station unit installation method and temporary support structure Download PDF

Info

Publication number
CN104988945B
CN104988945B CN201510272500.5A CN201510272500A CN104988945B CN 104988945 B CN104988945 B CN 104988945B CN 201510272500 A CN201510272500 A CN 201510272500A CN 104988945 B CN104988945 B CN 104988945B
Authority
CN
China
Prior art keywords
steel
liner section
pit liner
section
big footpath
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510272500.5A
Other languages
Chinese (zh)
Other versions
CN104988945A (en
Inventor
罗成宗
孙领
何铮
赵志文
赵宏图
郭晓静
张飞
龙长波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG XIANJU PUMPED STORAGE CO Ltd
State Grid Corp of China SGCC
State Grid Xinyuan Co Ltd
Original Assignee
ZHEJIANG XIANJU PUMPED STORAGE CO Ltd
State Grid Corp of China SGCC
State Grid Xinyuan Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG XIANJU PUMPED STORAGE CO Ltd, State Grid Corp of China SGCC, State Grid Xinyuan Co Ltd filed Critical ZHEJIANG XIANJU PUMPED STORAGE CO Ltd
Priority to CN201510272500.5A priority Critical patent/CN104988945B/en
Publication of CN104988945A publication Critical patent/CN104988945A/en
Application granted granted Critical
Publication of CN104988945B publication Critical patent/CN104988945B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses efficient hydroenergy storage station unit installation method:The method is first to pour big footpath pit liner section, polishing processing seat ring;Complete after big footpath pit liner section pours, bracing members to be installed and simultaneously lifts base ring;Then pour path pit liner section;After seat ring polishing processing is completed, bracing members are removed, bolt connection and welding are carried out to base ring and seat ring.Temporary support structure constructed by foundation preceding method, including big footpath pit liner section (1) and path pit liner section (2);Big footpath pit liner section (1) is internally provided with seat ring (3), some bracing members and base ring (4), the internal diameter with diameter greater than path pit liner section (2) of base ring (4);Bracing members include encorbelment I-steel (5) and diagonal brace I-steel (6), and the angle of inclination of diagonal brace I-steel (6) is 25 °~35 °.The present invention not only has the advantages that safe, stability is high and efficiency of construction is high, additionally it is possible to the integral construction duration is greatly shortened.

Description

Hydroenergy storage station unit installation method and temporary support structure
Technical field
The present invention relates to a kind of hydroenergy storage station unit installation method and temporary support structure, particularly a kind of construction effect The high hydroenergy storage station unit installation method of rate and temporary support structure.
Background technology
During hydroenergy storage station unit installation, need first by machine cheat in seat ring each flange face and seam enter Row machining polishing, this generally 30~40 days operation polishing times, can just carry out the base ring and machine of the hydraulic turbine after the completion of polishing The bolt connection between seat ring and welding in hole.As the internal diameter of path pit liner section above is less than the straight of base ring Footpath, and base ring is overall structure, so existing hydroenergy storage station unit installation orientation is first to pour big footpath pit liner section, Then the polishing processing of seat ring is carried out, after the completion of polishing base ring is lifted into machine and is cheated and be connected with seat ring, finally pour path machine Hole back boxing section;So that the processing that pours of path pit liner section needs to wait base ring polishing to be carried out after machining again, cause to apply The prolongation of the idle and overall hydroenergy storage station unit installation duration of workman person.Therefore, existing hydroenergy storage station unit Construction method has that efficiency of construction is relatively low and the integral construction duration is longer.
The content of the invention
It is an object of the present invention to provide a kind of hydroenergy storage station unit installation method and temporary support structure.This It is bright not only to have the advantages that safe and efficiency of construction is high, additionally it is possible to shorten the integral construction duration.
Technical scheme:Hydroenergy storage station unit installation method, the method are first to carry out big footpath pit liner The concreting of section, carries out polishing processing to seat ring;After the concreting for completing big footpath pit liner section, steel is installed Support simultaneously lifts base ring on bracing members;After the completion of lifting base ring, the concreting of path pit liner section is carried out;Complete seat ring After polishing processing, bracing members are removed, base ring is lifted to seat ring carries out bolt connection and welding.
In aforesaid hydroenergy storage station unit installation method, the polishing processing of the seat ring is time-consuming 30~40 days.
According in the temporary support structure constructed by aforesaid hydroenergy storage station unit installation method, including big footpath machine hole Lining section and the path pit liner section positioned at big footpath pit liner section upper end;Big footpath pit liner section is internally provided with seat ring, The inside of big footpath pit liner section is also connected with base ring by some bracing members, base ring with diameter greater than path pit liner section Internal diameter;Each bracing members includes encorbelmenting I-steel and diagonal brace I-steel, diagonal brace I-steel be located at below I-steel of encorbelmenting and Connect I-steel of encorbelmenting, the angle of inclination of diagonal brace I-steel is 25 °~35 °.
In aforesaid temporary support structure, the I-steel of encorbelmenting includes the hanging section on the inside of big footpath pit liner section With twice of the length more than or equal to suspended length buried dress section, bury dress section on the outside of big footpath pit liner section.
In aforesaid temporary support structure, the angle of inclination of the diagonal brace I-steel is 30 °.
In aforesaid temporary support structure, the base ring and bracing members are respectively positioned on the top of seat ring, between base ring and seat ring The machine of being additionally provided with is cheated into people's gallery.
Compared with prior art, present invention improves over the construction method of hydroenergy storage station unit devising temporary support Structure;The concreting of big footpath pit liner section is first carried out, polishing processing is carried out to seat ring;Complete big footpath pit liner section Concreting after, bracing members are installed base ring are lifted on bracing members simultaneously;After the completion of lifting base ring, path pit liner is carried out The concreting of section;Complete seat ring polishing processing after, remove bracing members, base ring is lifted to seat ring carry out bolt connection and Welding.The present invention carries out temporary support to base ring by installing bracing members such that it is able to while seat ring polishing processing is carried out The concreting work of path pit liner section is carried out, efficiency of construction is improve;Pour the concrete of path pit liner section Build work 30~40 days in advance, the integral construction duration has been greatly shortened.The present invention sets I-steel of encorbelmenting by force analysis Bury dress segment length more than or equal to suspended length twice, it is ensured that can safely and effectively support base ring;By encorbelmenting Connect diagonal brace I-steel below I-steel, and the angle of inclination of diagonal brace I-steel is 25 °~35 °, improves the stability of structure, enters One step improves security.Therefore, the present invention not only has the advantages that safe, stability is high and efficiency of construction is high, additionally it is possible to The integral construction duration is greatly shortened.
Description of the drawings
Fig. 1 is the structural representation of the present invention;
Fig. 2 is the partial enlarged drawing in Fig. 1 at A.
Mark in accompanying drawing for:The big footpath pit liner sections of 1-, 2- path pit liner sections, 3- seat rings, 4- base rings, 5- are encorbelmented I-steel, 6- diagonal brace I-steel, the hanging sections of 7-, 8- bury dress section, and 9- machines are cheated into people's gallery.
Specific embodiment
With reference to embodiment, the present invention is further illustrated, but is not intended as the foundation limited to the present invention.
Embodiment.Hydroenergy storage station unit installation method, as shown in Figure 1, 2, the method is first carried out in big footpath machine hole The concreting of lining section 1, carries out polishing processing to seat ring 3;After the concreting for completing big footpath pit liner section 1, peace Steel loading supports and base ring 4 is lifted on bracing members;After the completion of lifting base ring 4, the concrete for carrying out path pit liner section 2 is poured Build;After completing the polishing processing of seat ring 3, bracing members are removed, base ring 4 is lifted to seat ring 3 carries out bolt connection and welding.
The polishing processing of the seat ring 3 is time-consuming 30~40 days.
According to the temporary support structure constructed by aforesaid hydroenergy storage station unit installation method, constitute such as Fig. 1,2 institutes Show, including big footpath pit liner section 1 and the path pit liner section 2 positioned at big 1 upper end of footpath pit liner section;Big footpath pit liner Section 1 is internally provided with seat ring 3, and the inside of big footpath pit liner section 1 is also connected with base ring 4, base ring 4 by the bracing members of 8 The internal diameter with diameter greater than path pit liner section 2;Each bracing members includes encorbelment I-steel 5 and diagonal brace I-steel 6, diagonal brace I-steel 6 is located at below I-steel 5 of encorbelmenting and connects I-steel 5 of encorbelmenting, and the angle of inclination of diagonal brace I-steel 6 is 25 °~35 °.
The I-steel 5 of encorbelmenting includes the hanging section 7 on the inside of big footpath pit liner section 1 and is located at big footpath pit liner Twice of the length more than or equal to 7 length of hanging section buried dress section 8, bury dress section 8 on the outside of section 1, the length for burying dress section 8 is 1m, 7 length of hanging section is 2m;The angle of inclination of the diagonal brace I-steel 6 is 30 °;The base ring 4 and bracing members are respectively positioned on seat ring 3 Top, the machine that is additionally provided between base ring 4 and seat ring 3 are cheated into people's gallery 9.
The present invention carries out temporary support to base ring 4 by installing bracing members such that it is able to carrying out the polishing processing of seat ring 3 The concreting work of path pit liner section 2 is carried out simultaneously, improves efficiency of construction;Make the mixed of path pit liner section 2 Solidifying soil pours work 30~40 days in advance, and the integral construction duration has been greatly shortened.The angle of inclination of diagonal brace I-steel 6 is 30 °, Not only guarantee to play larger supporting role to I-steel 5 of encorbelmenting, additionally it is possible to ensure diagonal brace I-steel 6 from big footpath machine hole Connective stability in lining section 1.
Safety analysis:
If the deadweight total load head of base ring 4 is 80t;Workmen is 5 people, and it is 5* that everyone calculates then load by body weight 75Kg 75Kg*10=3.75KN;Construction equipment load is 3KN;Dynamic load is 2KN;Other loads are 1KN;In view of nonuniformity coefficient 1.3 are taken, dynamic load coefficient takes 2.0, therefore total load head is G=800+ (3.75+3+2+1) * 1.3*2=825.35KN;Respectively Obtain to 8 I-steel 5 of encorbelmenting and 5 load of I-steel is encorbelmented per root for 103.17KN.
Take single I-steel 5 of encorbelmenting to be calculated:I-steel 5 of encorbelmenting selects I25b I-steel, and amplification coefficient of conducting oneself with dignity is 1.2, outer cantilever span presses 1m;Web total thickness 10mm, plasticity coefficient are 1.05, and integral stability factor is 0.6.By maximum wall Thick 13mm is obtained:Section tension resistance bending strength design load f=215MPa, section shearing strength design load fv=125MPa are cut Power maximum is 103.674KN, and moment of flexure maximum is 51.837KN.M, and maximum defluxion is 1.19146mm;Calculate maximum cut should Power is 48.0079MPa, and strength stress is 116.876MPa, and stable stress is 204.534MPa, is satisfied by.
Take single diagonal brace I-steel 6 to be calculated:Diagonal brace I-steel 6 selects I16 I-steel, and deadweight amplification coefficient is 1.2, Span is equal to the outer cantilever span of I-steel 5 of encorbelmenting;Maximum shear stress is obtained ibid for 30.0049MPa, strength stress is 29.2191MP, stable stress is 51.1334MPa.Safety coefficient is 204.534/51.1334=4, and safety coefficient improves 4 times, I.e. security improves 4 times, and safety and stability is good.

Claims (6)

1. hydroenergy storage station unit installation method, it is characterised in that:The method is the coagulation for first carrying out big footpath pit liner section Soil is poured, and carries out polishing processing to seat ring;After the concreting for completing big footpath pit liner section, bracing members are installed and in steel Base ring is lifted in support;After the completion of lifting base ring, the concreting of path pit liner section is carried out;Complete seat ring polishing processing Afterwards, bracing members are removed, base ring is lifted to seat ring carries out bolt connection and welding.
2. hydroenergy storage station unit installation method according to claim 1, it is characterised in that:The polishing of the seat ring adds Work is time-consuming 30~40 days.
3., according to the temporary support structure constructed by the hydroenergy storage station unit installation method described in claim 1 or 2, which is special Levy and be:Including big footpath pit liner section (1) and path pit liner section (2) positioned at big footpath pit liner section (1) upper end;Greatly Footpath pit liner section (1) is internally provided with seat ring (3), and the inside of big footpath pit liner section (1) also passes through some bracing members It is connected with base ring (4), the internal diameter with diameter greater than path pit liner section (2) of base ring (4);Each bracing members includes work of encorbelmenting Word steel (5) and diagonal brace I-steel (6), diagonal brace I-steel (6) is below I-steel of encorbelmenting (5) and connection is encorbelmented I-steel (5), The angle of inclination of diagonal brace I-steel (6) is 25 °~35 °.
4. temporary support structure according to claim 3, it is characterised in that:The I-steel of encorbelmenting (5) includes being located at greatly Hanging section (7) and burying on the outside of big footpath pit liner section (1) on the inside of footpath pit liner section (1) fills section (8), buries dress section (8) twice of the length more than or equal to hanging section (7) length.
5. temporary support structure according to claim 3, it is characterised in that:The angle of inclination of the diagonal brace I-steel (6) For 30 °.
6. the temporary support structure according to claim 3,4 or 5, it is characterised in that:The base ring (4) and the equal position of bracing members Machine is additionally provided between the top of seat ring (3), base ring (4) and seat ring (3) to cheat into people's gallery (9).
CN201510272500.5A 2015-05-25 2015-05-25 Hydroenergy storage station unit installation method and temporary support structure Active CN104988945B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510272500.5A CN104988945B (en) 2015-05-25 2015-05-25 Hydroenergy storage station unit installation method and temporary support structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510272500.5A CN104988945B (en) 2015-05-25 2015-05-25 Hydroenergy storage station unit installation method and temporary support structure

Publications (2)

Publication Number Publication Date
CN104988945A CN104988945A (en) 2015-10-21
CN104988945B true CN104988945B (en) 2017-04-05

Family

ID=54300827

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510272500.5A Active CN104988945B (en) 2015-05-25 2015-05-25 Hydroenergy storage station unit installation method and temporary support structure

Country Status (1)

Country Link
CN (1) CN104988945B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109268629B (en) * 2018-11-26 2024-01-19 国家电网有限公司 Temporary supporting structure for bottom ring of energy storage power station unit

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101392518B (en) * 2008-10-28 2012-09-19 成都阿朗科技有限责任公司 Diversion conduit rapid construction method of large hydraulic turbines
CN102296577B (en) * 2011-05-27 2012-07-04 长江勘测规划设计研究有限责任公司 Embedding technology of volute combination of large hydroelectric generating set
CN104100437B (en) * 2014-06-26 2015-04-01 中国葛洲坝集团股份有限公司 Lower bracket mounting foundation positioning device and method of hydroelectric generating set
CN204023608U (en) * 2014-08-18 2014-12-17 北京燃气能源发展有限公司 A kind of generating set of cold, heat and electricity triple supply is installed basis

Also Published As

Publication number Publication date
CN104988945A (en) 2015-10-21

Similar Documents

Publication Publication Date Title
CN105298100B (en) A kind of cylinder building cast-in-place flare structure of superelevation is encorbelmented the construction method of operation platform
CN106812328B (en) The whole two step lifting construction methods of string prestressed steel structure rack with hanging layer
CN203794498U (en) Built-in self-elevating tower crane device
CN102650261A (en) Segmental lifting method for impeller of high-power wind driven generator
CN105586867A (en) Installation method for over-length over-weight steel reinforcement cage
CN105133754A (en) Prefabricated concrete shear wallboard counterbore guide type mounting device and method
CN107165281A (en) A kind of high-altitude long-span overhung steel platform mould bases construction
CN105926855A (en) Super-high-rise core tube suspended steel rib column and construction method thereof
CN104988945B (en) Hydroenergy storage station unit installation method and temporary support structure
CN102691267A (en) High pier construction method for external whole operation platform
CN107130521B (en) A kind of dell precipice section large-section beam Bailey truss hoisting die construction method
CN104499706A (en) Elevator well template platform and construction method thereof
CN103552911B (en) A kind of movable boom hoisting and the construction installation method of use thereof
CN102661035A (en) Tool type wall connecting piece for exterior wall scaffold
CN109667228B (en) Straight beam type hanging basket and continuous beam cantilever pouring construction method
CN105040592B (en) A kind of horizontal drawing cable bridge and its erection method
CN108222006A (en) A kind of square construction method of underground continuous wall
CN204825924U (en) Square steel tube concrete waist rail
CN104746860A (en) Water tank cast-in-site method of inverted conical shell water tower cable-stayed formwork in air
CN106049972B (en) Reverse cone-shape water-tower water tank lifts system and method in place
CN106522542B (en) A kind of light engine position hydraulic climbing die block system and its method of climbing
CN106245531B (en) Steel structural bridge installation method is hung under bilateral derrick type
CN104989092A (en) Construction method of high-altitude overhang superposition type steel truss bearing platform
CN210288145U (en) Straight beam type hanging basket
CN107299713A (en) A kind of circular cone roofing integrally-lifting steel truss and its construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant