CN107299713A - A kind of circular cone roofing integrally-lifting steel truss and its construction - Google Patents

A kind of circular cone roofing integrally-lifting steel truss and its construction Download PDF

Info

Publication number
CN107299713A
CN107299713A CN201610229785.9A CN201610229785A CN107299713A CN 107299713 A CN107299713 A CN 107299713A CN 201610229785 A CN201610229785 A CN 201610229785A CN 107299713 A CN107299713 A CN 107299713A
Authority
CN
China
Prior art keywords
truss
steel
lifting
steel truss
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610229785.9A
Other languages
Chinese (zh)
Inventor
刘建军
杨叶
李证吉
白杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Bureau Fifth Construction Engineering Co Ltd
Original Assignee
China Construction Fourth Bureau Fifth Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fourth Bureau Fifth Construction Engineering Co Ltd filed Critical China Construction Fourth Bureau Fifth Construction Engineering Co Ltd
Priority to CN201610229785.9A priority Critical patent/CN107299713A/en
Publication of CN107299713A publication Critical patent/CN107299713A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B7/00Roofs; Roof construction with regard to insulation
    • E04B7/08Vaulted roofs
    • E04B7/10Shell structures, e.g. of hyperbolic-parabolic shape; Grid-like formations acting as shell structures; Folded structures
    • E04B7/105Grid-like structures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明公开了一种圆锥屋面整体升降式钢桁架及其施工工法,该钢桁架主要由中心圆盘(1)、主杆架(2)、上线杆件(3)、下弦杆件(4)、拉杆(5)和斜撑杆件(16)等组成。其施工工法包括如下步骤:桁架设计与加工;桁架组装;桁架初次整体提升2m;安装桁架下部操作吊架;桁架提升;安装牛腿并与桁架连接牢固;搭设桁架上支撑架支撑板、绑扎钢筋;浇筑混凝土;待混凝土强度达100%后进行桁架御落和拆除。该整体升降式钢桁架工期效果明显,且钢桁架取代了满堂支撑架,减少周转材料的大量投入和搭设。钢桁架的安装及拆除工艺简洁,易于操作。钢桁架还具有一次投入,多次周转的特点。

This invention discloses an integral lifting steel truss for a conical roof and its construction method. The steel truss mainly consists of a central disc (1), main frame (2), upper line members (3), lower chord members (4), tie rods (5), and diagonal bracing members (16). The construction method includes the following steps: truss design and fabrication; truss assembly; initial overall lifting of the truss by 2m; installation of the lower operating scaffold of the truss; truss lifting; installation of corbels and secure connection with the truss; erection of the upper support frame and binding of reinforcing bars; pouring concrete; and dismantling and removing the truss after the concrete strength reaches 100%. This integral lifting steel truss has a significant time efficiency improvement, and the steel truss replaces the full-span support frame, reducing the large investment and erection of turnover materials. The installation and dismantling process of the steel truss is simple and easy to operate. The steel truss also features the characteristic of one-time investment and multiple reuses.

Description

一种圆锥屋面整体升降式钢桁架及其施工工法A conical roof integral lifting steel truss and its construction method

技术领域technical field

本发明涉及一种圆锥屋面整体升降式钢桁架及其施工工法,属于建筑工程技术领域。The invention relates to an integral lifting type steel truss on a conical roof and a construction method thereof, belonging to the technical field of construction engineering.

背景技术Background technique

中央储备粮库的设计,大多采用筒仓结构,便于滑模施工技术应用,屋面设计没有具体要求,大多采用圆锥型、曲线型,相应的屋面施工没有统一要求,常见的屋面支撑架施工方法有:满堂支撑架、钢平台上搭设支撑架和钢桁架作为支撑架的施工方法。The design of the central storage grain storage mostly adopts the silo structure, which is convenient for the application of slip-form construction technology. There is no specific requirement for the roof design, and most of them adopt conical and curved shapes. There is no uniform requirement for the corresponding roof construction. Common roof support frame construction methods are: The construction method of setting up support frame and steel truss as support frame on full hall support frame, steel platform.

整体式钢桁架是根据锥形屋面特点设计一种支撑体系,由桁架主体、桁架升降、支撑结构组成。其特点是,设计一个钢桁架,把模板、混凝土、钢筋等荷载通过钢桁架传到支撑牛腿上。施工过程为:工作人员在仓底板上拚装钢桁架,桁架拚装完成后,用电动葫芦整体提升至牛腿位置,安装牛腿,桁架上搭设支架,支模板、绑钢筋、浇注混凝土,混凝土达到设计强度后整体下降钢桁架,底板上拆除钢桁架。此工法具有较大的发展潜力。The integral steel truss is a supporting system designed according to the characteristics of the conical roof, which consists of the main body of the truss, the lifting and lowering of the truss, and the supporting structure. Its characteristic is that a steel truss is designed to transmit the loads of formwork, concrete, steel bars, etc. to the supporting corbels through the steel truss. The construction process is as follows: the staff assembles the steel truss on the bottom of the warehouse. After the truss is assembled, the electric hoist is used to lift it to the position of the corbel. After reaching the design strength, the steel truss is lowered as a whole, and the steel truss is removed from the bottom plate. This construction method has great potential for development.

发明内容Contents of the invention

本发明的目的在于提供一种圆锥屋面整体升降式钢桁架及其施工工法,使圆锥屋面整体升降式钢桁架结构受力合理,施工工法简单、易于操做,以克服现有技术的不足。The object of the present invention is to provide a conical roof integrated lifting steel truss and its construction method, so that the force of the conical roof integral lifting steel truss structure is reasonable, the construction method is simple and easy to operate, so as to overcome the shortcomings of the prior art.

本发明的技术方案是这样的:Technical scheme of the present invention is such:

本发明首先提出了一种圆锥屋面整体升降式钢桁架,它包括中心圆盘,中心圆盘的上方设有一个圆盘型楼盖,该圆盘型楼盖的直径大于中心圆盘的直径,该圆盘型楼盖的圆心在中心圆盘上的投影与中心圆盘的圆心重合;在圆盘型楼盖的一侧半圆部分向中心圆盘所在平面上延伸出若干根主杆架,主杆架以圆盘型楼盖和中心圆盘的圆心的连线为轴呈环向均布设置;在圆盘型楼盖的另一侧半圆部分向中心圆盘所在平面上延伸出若干根与对侧的主杆架相对应的上弦杆件;所述主杆架与上弦杆件在中心圆盘所在的平面上连接点构成一个完整的大圆盘,该大圆盘的直径大于圆盘型楼盖的直径;上述三个圆盘及连接他们的主杆架、上弦杆件和其它连接杆件共同构成了圆锥屋面整体升降式钢桁架的结构。The present invention firstly proposes a conical roof integrated lift-type steel truss, which includes a central disc, and a disc-shaped floor is arranged above the central disc, and the diameter of the disc-shaped floor is larger than the diameter of the central disc. The projection of the center of the disc-shaped floor on the central disc coincides with the center of the central disc; a number of main rods extend from the semicircle part of the disc-shaped floor to the plane where the central disc is located. The pole frames are evenly distributed in the circumferential direction on the axis of the connection line between the disc-shaped floor and the center of the central disc; on the other side of the disc-shaped floor, a number of rods are extended to the plane where the central disc is located. The upper chord member corresponding to the main rod frame on the opposite side; the connection point between the main rod frame and the upper chord member on the plane where the central disc is located forms a complete large disc, the diameter of which is larger than that of the disc type The diameter of the floor; the above-mentioned three discs and the main rod frame, the upper chord member and other connecting rods that connect them together constitute the structure of the conical roof integral lifting steel truss.

其中,其它连接杆件至少包括用于连接大圆盘和中心圆盘的下弦杆件、用于连接主杆架和中心圆盘的拉杆、用于连接中心圆盘和圆盘型楼盖的斜撑架杆。Among them, other connecting rods include at least the lower chord member used to connect the large disk and the central disk, the tie rod used to connect the main rod frame and the central disk, and the inclined rod used to connect the central disk and the disk-shaped floor. Support rod.

该圆锥屋面整体升降式钢桁架的施工工法用于不同直径圆锥形筒仓的屋面施工,该工法包括如下步骤:桁架设计与加工;桁架组装;桁架初次整体提升2m;安装桁架下部操作吊架;桁架提升;安装牛腿并与桁架连接牢固;搭设桁架上支撑架支撑板、绑扎钢筋;浇筑混凝土;待混凝土强度达100%后进行桁架御落和拆除。The construction method of the integral lifting steel truss on the conical roof is used for the roof construction of conical silos with different diameters. The construction method includes the following steps: truss design and processing; The truss is lifted; the corbels are installed and firmly connected with the truss; the upper support plate of the truss is erected and the steel bars are tied;

其中,圆仓仓筒施工完成后,在仓筒底板组装钢桁架;用先期搭设的浅圆仓外脚手架支撑天沟模板作为操作平台,在浅圆筒仓壁顶端安装吊装葫芦钢构吊具,安装吊装电动葫芦,及配套吊装葫芦连接电缆线及总控制箱;利用电动吊装葫芦将桁架提升到设计标高后,钢桁架与牛腿连接固定,桁架吊装完成;完成混凝土浇筑达到设计强度后,钢构桁架拆除用电动葫芦,电动葫芦的钢铰链均穿过仓顶屋面板预留孔,与钢结构架体连接牢固并保持钢结构架体的平衡,将钢桁架降落至筒仓底板面后人工拆除。Among them, after the construction of the round silo is completed, steel trusses are assembled on the bottom of the silo; the shallow round silo external scaffolding is used to support the gutter formwork as an operating platform, and hoisting hoist steel structure spreaders are installed on the top of the shallow round silo wall. Install the hoisting electric hoist, and the supporting hoisting hoist to connect the cables and the main control box; use the electric hoisting hoist to lift the truss to the design level, connect and fix the steel truss to the corbel, and complete the hoisting of the truss; after the concrete pouring reaches the design strength, the steel truss The electric hoist is used for dismantling the truss. The steel hinges of the electric hoist pass through the reserved holes on the roof panel of the silo, and are firmly connected with the steel structure frame and maintain the balance of the steel structure frame. tear down.

其中,桁架组装时按如下步骤进行:钢桁架加工完成后运到施工现场,进行复检、编号,利用塔吊将桁架散件吊入圆锥形筒仓内底板,按照以下顺序进行安装:加固架杆→主架杆→斜撑架杆→中心圆盘→拉杆。Among them, the truss assembly is carried out according to the following steps: After the steel truss is processed, it is transported to the construction site, re-inspected and numbered, and the truss parts are hoisted into the inner bottom plate of the conical silo by a tower crane, and the installation is carried out in the following order: Reinforce the frame bar →Main frame rod→Diagonal bracing rod→Central disc→Tie rod.

其中,安装牛腿并与桁架连接牢固时按如下步骤进行:利用浅圆仓天沟施工时搭设的外脚手架作操作平台,在筒仓壁顶安装吊装葫芦吊具及配套吊装葫芦连接电缆线及总控制箱,利用外脚手架和钢桁架下面吊架在仓壁预留位置安装牛腿。Among them, when the corbels are installed and firmly connected with the truss, the steps are as follows: use the outer scaffolding erected during the construction of the shallow round silo gutter as the operating platform, and install the hoisting hoist spreader and the supporting hoisting hoist connection cable on the top of the silo wall. For the main control box, use the outer scaffolding and the hanger under the steel truss to install the corbel at the reserved position on the warehouse wall.

本发明的整体式钢桁架是根据锥形屋面特点设计一种支撑体系,由桁架主体、桁架升降、支撑结构组成。其特点是,设计一个钢桁架,把模板、混凝土、钢筋等荷载通过钢桁架传到支撑牛腿上。施工过程为:工作人员在仓底板上拚装钢桁架,桁架拚装完成后,用电动葫芦整体提升至牛腿位置,安装牛腿,桁架上搭设支架,支模板、绑钢筋、浇注混凝土,混凝土达到设计强度后整体下降钢桁架,底板上拆除钢桁架。此工法具有结构受力合理、简单、易于操做。The integral steel truss of the present invention is a supporting system designed according to the characteristics of the conical roof, and is composed of a truss main body, a truss lifting and a supporting structure. Its characteristic is that a steel truss is designed to transmit the loads of formwork, concrete, steel bars, etc. to the supporting corbels through the steel truss. The construction process is as follows: the staff assembles the steel truss on the bottom of the warehouse. After the truss is assembled, the electric hoist is used to lift it to the position of the corbel. After the design strength is reached, the steel truss is lowered as a whole, and the steel truss is removed from the bottom plate. This construction method has the advantages of reasonable structural force, simple and easy to operate.

本发明具有如下技术效果:The present invention has following technical effect:

首先,整体升降式钢桁架前期加工不占用直接工期,钢桁架安装、拆除占用少量工期,工期效果明显。First of all, the preliminary processing of the integral lifting steel truss does not occupy the direct construction period, and the installation and removal of the steel truss occupy a small amount of construction period, and the construction period effect is obvious.

其次,钢桁架取代了满堂支撑架,减少周转材料的大量投入和搭设,钢桁架加工时便确定了屋面的坡度,工程质量容易得到保证。Secondly, the steel truss replaces the supporting frame of the whole hall, which reduces the investment and erection of a large amount of turnover materials. The slope of the roof is determined during the processing of the steel truss, and the project quality is easily guaranteed.

再次,钢桁架的安装及拆除工艺简洁,易于操作。Thirdly, the installation and removal process of the steel truss is simple and easy to operate.

最后,钢桁架具有一次投入,多次周转的特点,对多个圆锥形屋面的施工工程成本降低显著,有着良好的社会效益和发展前景。Finally, the steel truss has the characteristics of one investment and multiple turnovers, which significantly reduces the construction cost of multiple conical roofs, and has good social benefits and development prospects.

附图说明Description of drawings

图1是本发明的钢桁架立面图;Fig. 1 is a steel truss elevation view of the present invention;

图2是本发明的钢桁架上弦平面图;Fig. 2 is the upper chord plan view of the steel truss of the present invention;

图3是本发明的钢桁架下弦平面图;Fig. 3 is the lower chord plan view of the steel truss of the present invention;

图4是吊具与牛腿安装时卡具安装图;Figure 4 is the fixture installation diagram when the spreader and the corbel are installed;

图5是吊具与牛腿安装时吊具侧视图;Figure 5 is a side view of the spreader when the spreader and the corbel are installed;

图6是吊具与牛腿安装时牛腿安装图;Fig. 6 is an installation diagram of the corbel when the spreader and the corbel are installed;

图7是钢桁架拆除时卸电动葫芦钢梁剖视图;Figure 7 is a cross-sectional view of the electric hoist steel beam when the steel truss is removed;

图8是钢桁架拆除时卸电动葫芦钢梁平面图。Fig. 8 is a plane view of unloading the electric hoist steel beam when the steel truss is removed.

附图标记说明:1-中心圆盘,2-主杆架,3-上弦杆件,4-下弦杆件,5-拉杆,6-筒仓壁,7-槽钢,8-预留吊孔,9-卡具螺栓,10-高强螺栓,11-吊孔,12-固定钢板,13-工字钢,14-预留洞口,15-筒仓顶板,16-斜撑架杆。Explanation of reference signs: 1-central disc, 2-main rod frame, 3-upper chord member, 4-lower chord member, 5-tie rod, 6-silo wall, 7-channel steel, 8-reserved lifting hole , 9-fixture bolts, 10-high-strength bolts, 11-hanging holes, 12-fixed steel plates, 13-I-beams, 14-reserved holes, 15-silo roof, 16-diagonal bracing rods.

具体实施方式detailed description

下面结合附图和实施例对本发明作进一步的详细说明。The present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments.

先看图1, 图1展示本发明的这种钢桁架的立面图,图2和图3分别展示了该钢桁架的上弦和下弦平面图。从图1中可以看出,一种圆锥屋面整体升降式钢桁架,它包括中心圆盘1,中心圆盘1的上方设有一个圆盘型楼盖,该圆盘型楼盖的直径大于中心圆盘1的直径,该圆盘型楼盖的圆心在中心圆盘1上的投影与中心圆盘1的圆心重合;在圆盘型楼盖的一侧半圆部分向中心圆盘1所在平面上延伸出若干根主杆架2,主杆架2以圆盘型楼盖和中心圆盘1的圆心的连线为轴呈环向均布设置;在圆盘型楼盖的另一侧半圆部分向中心圆盘1所在平面上延伸出若干根与对侧的主杆架2相对应的上弦杆件3;所述主杆架2与上弦杆件3在中心圆盘1所在的平面上连接点构成一个完整的大圆盘,该大圆盘的直径大于圆盘型楼盖的直径;上述三个圆盘及连接他们的主杆架2、上弦杆件3和其它连接杆件共同构成了圆锥屋面整体升降式钢桁架的结构。其中,其它连接杆件至少包括用于连接大圆盘和中心圆盘1的下弦杆件4、用于连接主杆架2和中心圆盘1的拉杆5、用于连接中心圆盘1和圆盘型楼盖的斜撑架杆16。First look at Fig. 1, Fig. 1 shows the elevation view of the steel truss of the present invention, and Fig. 2 and Fig. 3 respectively show the plan view of the upper chord and the lower chord of the steel truss. It can be seen from Fig. 1 that a conical roof integral lifting steel truss includes a central disc 1, and a disc-shaped floor is arranged above the central disc 1, and the diameter of the disc-shaped floor is larger than that of the center. The diameter of the disk 1, the projection of the center of the disk-shaped floor on the center disk 1 coincides with the center of the circle of the center disk 1; A number of main rod frames 2 are extended, and the main rod frames 2 are uniformly distributed around the axis of the connection line between the disc-shaped floor and the center of the central disc 1; on the other side of the disc-shaped floor On the plane where the central disc 1 is located, several upper chord members 3 corresponding to the main rod frame 2 on the opposite side are extended; the main rod frame 2 and the upper chord member 3 are connected on the plane where the central disc 1 is Constitute a complete large disc, the diameter of which is greater than the diameter of the disc-shaped floor; the above three discs and the main rod frame 2, the upper chord member 3 and other connecting rods together form a conical The structure of the whole roof lifting steel truss. Among them, other connecting rods include at least the lower chord member 4 for connecting the large disc and the central disc 1, the tie rod 5 for connecting the main rod frame 2 and the central disc 1, and the tie rod 5 for connecting the central disc 1 and the central disc 1. Diagonal bracing bar 16 of dish type floor.

实施例1:Example 1:

中国建筑第四工程局有限公司承建中央储备粮昆明直属库的施工,该项目位于昆明市晋宁县工业园区青山片区,由12座内径25m浅圆仓及其配套工程组成,仓容储量为10万吨的粮仓(单座浅圆仓储量为8350吨),筒仓顶为钢筋混凝土圆锥型屋面,200毫米厚钢筋混凝土屋面板,屋面顶标高32.97m。在多个方案的比较后采用本发明的整体升降式钢桁架作为层面模板支撑体系,通过12个仓的锥型屋面的实施完成。China Construction Fourth Engineering Bureau Co., Ltd. undertook the construction of the central grain reserve warehouse in Kunming. The project is located in Qingshan District, Jinning County Industrial Park, Kunming City. It consists of 12 shallow round warehouses with an inner diameter of 25m and supporting projects, with a storage capacity of 100,000 tons The granary (single-seat shallow round storage capacity is 8,350 tons), the roof of the silo is a reinforced concrete conical roof, a 200mm thick reinforced concrete roof panel, and the roof elevation is 32.97m. After the comparison of multiple schemes, the integral elevating steel truss of the present invention is used as the level formwork support system, which is completed through the implementation of the conical roof of 12 warehouses.

一、施工顺序及主要方法1. Construction sequence and main methods

(一)、钢桁架图设计(1) Steel truss design

1.钢桁架根据工程的实际特点进行设计,包括中心圆盘1的大小,斜撑架杆16的长度和规格,主架杆2的长度和规格,拉杆5的长度和规格等。设计时考虑圆仓直径、圆锥形高度、屋面混凝土的厚度,保证桁架在施工过程中满足安全性,并尽量节省钢材的用量。1. The steel truss is designed according to the actual characteristics of the project, including the size of the central disc 1, the length and specification of the diagonal bracing rod 16, the length and specification of the main frame rod 2, and the length and specification of the tie rod 5, etc. The diameter of the silo, the height of the cone, and the thickness of the roof concrete are considered in the design to ensure the safety of the truss during construction and to save the amount of steel as much as possible.

2.计算工具、荷载工况及计算模型2. Calculation tools, load cases and calculation models

2.1计算工具2.1 Calculation tools

本工法采用有限元软件MIDAS进行建模分析,软件具有对结构的强度,刚度和稳定性进行分析计算,关且在后期的处理中能看到失稳模态图,以及荷载----位移变形过程跟踪曲线。This construction method adopts the finite element software MIDAS for modeling analysis. The software can analyze and calculate the strength, stiffness and stability of the structure, and in the later processing, you can see the instability mode diagram, as well as the load----displacement The deformation process traces the curve.

2.2荷载工况2.2 Load Cases

设计砼荷载计算:Design concrete load calculation:

[2.238/40.698×3.14×4.512×(9.022+9.02×3.25+3.252)/3+10.337+22.55][2.238/40.698×3.14×4.512×(9.022+9.02×3.25+3.252)/3+10.337+22.55]

×24/491=3.12kN/m2 ×24/491=3.12kN/ m2

钢筋荷载计算:35×10/491=0.71kN/m2 Steel load calculation: 35×10/491=0.71kN/m 2

设计支撑架体荷载计算:1407×0.0358/491=0.11kN/m2 Design support frame load calculation: 1407×0.0358/491=0.11kN/m 2

设计模板木方荷载计算Design formwork timber load calculation

615.99×0.085/491=0.11kN/m2 615.99×0.085/491=0.11kN/m 2

设计施工荷载(不含砼重量) 2.5kN/m2 Design construction load (excluding concrete weight) 2.5kN/m 2

设计总荷载:q=1.2×(3.12+0.71+0.11+0.11)+1.4×2.5=8.36kN/m2,取9kN/m2计算。Design total load: q=1.2×(3.12+0.71+0.11+0.11)+1.4×2.5=8.36kN/m 2 , take 9kN/m 2 for calculation.

施工临时设施,不计算大风和地震作用。The construction of temporary facilities does not count the effects of strong winds and earthquakes.

结构布置为上下两个圆环,上小下大,圆环间用径向型钢连接,组成圆台体系,整个构造分20个对称单元,加上支撑拉杆构成稳定体系。The structure is arranged as two circular rings, the upper one is smaller and the lower one is larger, and the rings are connected by radial section steel to form a circular platform system. The whole structure is divided into 20 symmetrical units, plus supporting rods to form a stable system.

2.3计算模型2.3 Calculation model

通过上述有限元分析结果可以得出:钢桁架平台X方向最大位移为0.89mm,Y方向最大位移为0.893mm,Z方向最大位移为16.95mm,可见变形较小,可以满足施工要求。钢桁架平台最大应力为133.31MP,最大应力发生在平台中心斜交梁处,小于钢材的屈服强度235MP和345MP,可见此钢平台能满足承载力要求。Through the above finite element analysis results, it can be concluded that the maximum displacement of the steel truss platform in the X direction is 0.89mm, the maximum displacement in the Y direction is 0.893mm, and the maximum displacement in the Z direction is 16.95mm. It can be seen that the deformation is small and can meet the construction requirements. The maximum stress of the steel truss platform is 133.31MP, and the maximum stress occurs at the oblique beam in the center of the platform, which is less than the yield strength of the steel 235MP and 345MP. It can be seen that the steel platform can meet the bearing capacity requirements.

(二)、钢桁架加工(2) Steel truss processing

设计完成后进行桁架的加工,加工完成后进行厂内试拚装,验收构件,达到设计要求后方可运到工地。After the design is completed, the processing of the truss is carried out. After the processing is completed, the trial assembly is carried out in the factory, and the components are checked and accepted. They can only be transported to the construction site after meeting the design requirements.

(三)、钢桁架安装(3) Steel truss installation

钢桁架运到施工现场,复检、编号,利用塔吊将桁架散件吊入仓内底板,按照以下顺序进行安装:加固架杆(上弦杆件3、下弦杆件4)→主架杆2→斜撑架杆16→中心圆盘1→拉杆5。The steel truss is transported to the construction site, re-inspected and numbered, and the truss parts are hoisted into the bottom plate of the warehouse by tower crane, and the installation is carried out in the following order: reinforced frame rod (upper chord member 3, lower chord member 4) → main frame rod 2 → Diagonal bracing rod 16→central disk 1→pull rod 5.

(四)、牛腿测量定位(4) Corbel measurement and positioning

在施工仓筒过程中根据桁架和牛腿的设计确定牛腿预留孔的位置,准确定位,保证桁架吊点与牛腿位吻合。During the construction of the silo, the positions of the reserved holes for the corbels are determined according to the design of the trusses and corbels, and the positions are accurately positioned to ensure that the lifting points of the trusses coincide with the positions of the corbels.

(五)、吊具和牛腿安装(5) Installation of spreaders and corbels

利用浅圆仓天沟施工时搭设的外脚手架作操作平台,在筒仓壁顶安装吊装葫芦吊具及配套吊装葫芦连接电缆线及总控制箱,利用外脚手架和钢桁架下面吊架在仓壁预留位置安装牛腿。卡具、吊具、牛腿安装如图4、图5和图6所示。图4中,卡具通过槽钢7从两边卡住筒仓壁6,卡具的一侧设有若干根卡具螺栓9,并且设有预留吊孔8。图6中,牛腿的钢板通过高强螺栓10从筒仓内侧穿过筒仓壁6到达筒仓外侧后拧紧固定,使牛腿固定在筒仓内侧的筒仓壁上以承受上方传递的力。Use the external scaffolding built during the construction of the shallow round silo gutter as the operating platform, install hoisting hoist spreaders and supporting hoisting hoist connection cables and the main control box on the top of the silo wall, and use the outer scaffolding and the hanger under the steel truss to hang on the silo wall Reserve a place to install the corbel. The installation of clamps, spreaders and corbels is shown in Figure 4, Figure 5 and Figure 6. In Fig. 4, the fixture clamps the silo wall 6 from both sides through the channel steel 7, and several fixture bolts 9 are provided on one side of the fixture, and a reserved lifting hole 8 is provided. In Fig. 6, the steel plate of the corbel passes through the silo wall 6 from the inside of the silo to the outside of the silo through high-strength bolts 10 and is then tightened and fixed, so that the corbel is fixed on the silo wall inside the silo to withstand the force transmitted from above.

(六)、桁架提升(6), truss lifting

利用吊具上安装葫芦同步整体提升桁架,桁架整体初始同步提升2米,在桁架下弦安装整圈操作吊架、防护网、兜底网。继续提升钢构桁架至设计标高,利用桁架下面操作平台安装支撑桁架牛腿。钢桁架与牛腿连接固定,桁架吊装完成。然后在桁架上安装支撑架和模板绑钢筋、浇筑混凝土。The hoist is used to install the hoist on the spreader to lift the truss synchronously as a whole. The whole truss is initially synchronously lifted by 2 meters, and the whole ring operation hanger, protective net and bottom net are installed on the lower chord of the truss. Continue to raise the steel truss to the design elevation, and use the operating platform under the truss to install the supporting truss corbel. The steel truss and the corbel are connected and fixed, and the hoisting of the truss is completed. Then install the support frame and formwork on the truss to tie the steel bars and pour the concrete.

(七)、钢桁架拆除(7) Steel truss removal

混凝土达到设计强度后进行桁架的拆除。如图7和图8所示,拆除时,在筒仓顶板15和筒仓壁6之间设有一个预留洞口14,分别在筒仓壁6顶部和筒仓顶板15顶部用膨胀螺丝各固定一块500×500、12厚的固定钢板12,然后用一根12#工字钢13将两块固定钢板12连接起来,工字钢13下方设有一块伸入预留洞口14中的钢板,该钢板上设有一个吊孔11。从图8所示的平面图可以看到它们的位置关系。拆除时使用电动葫芦御钢桁架,每台电动葫芦的钢铰链均穿过筒仓顶板15的吊孔11,与钢结构架体连接牢固并保持钢结构架体的平衡,然后利用电动葫芦吊将桁架降落到仓底板,利用电焊工和工人操作扳手等工具,将整个滑模平台分解、切割从仓底板门洞口运出。After the concrete reaches the design strength, the trusses are removed. As shown in Figures 7 and 8, when dismantling, a reserved hole 14 is provided between the silo roof 15 and the silo wall 6, and the top of the silo wall 6 and the top of the silo roof 15 are respectively fixed with expansion screws. A 500×500, 12 thick fixed steel plate 12, and then use a 12# I-shaped steel 13 to connect the two fixed steel plates 12, a steel plate extending into the reserved hole 14 is provided under the I-shaped steel 13, the A hanging hole 11 is provided on the steel plate. Their positional relationship can be seen from the plan view shown in Figure 8. When dismantling, use the steel truss of the electric hoist. The steel hinge of each electric hoist passes through the lifting hole 11 of the silo roof 15, and is firmly connected with the steel structure frame to keep the balance of the steel structure frame. The truss is lowered to the bottom of the warehouse, and the entire sliding form platform is disassembled, cut and transported out of the door opening of the bottom of the warehouse by using tools such as welders and workers to operate wrenches.

当然,以上只是本发明的具体应用范例,本发明还有其他的实施方式,凡采用等同替换或等效变换形成的技术方案,均落在本发明所要求的保护范围之内。Certainly, the above are only specific application examples of the present invention, and there are other implementation modes in the present invention, and all technical solutions formed by equivalent replacement or equivalent transformation all fall within the scope of protection required by the present invention.

Claims (6)

1. a kind of circular cone roofing integrally-lifting steel truss, it is characterised in that:It includes center disk(1), center disk(1)'s Top is more than center disk provided with a collar plate shape superstructure, the diameter of the collar plate shape superstructure(1)Diameter, the collar plate shape superstructure The center of circle is in center disk(1)On projection and center disk(1)The center of circle overlap;Collar plate shape superstructure side semi-circular portions to Center disk(1)Extend some main rod hangers in the plane(2), main rod hanger(2)With collar plate shape superstructure and center disk(1) The line in the center of circle be uniformly arranged in ring for axle;Collar plate shape superstructure opposite side semi-circular portions to center disk(1)Place Extend the main rod hanger of some and offside in plane(2)Corresponding upper cord member(3);The main rod hanger(2)With top boom Part(3)In center disk(1)Tie point constitutes a complete big disk in the plane at place, and the diameter of the big disk is more than circle The diameter of dish-type superstructure;Above three disk and the main rod hanger for connecting them(2), upper cord member(3)It is common with other connecting rods With the structure for constituting circular cone roofing integrally-lifting steel truss.
2. circular cone roofing integrally-lifting steel truss according to claim 1, it is characterised in that:Other connecting rods At least include being used to connect big disk and center disk(1)Lower edge rod member(4), for connecting main rod hanger(2)And center disk (1)Pull bar(5), for connecting center disk(1)With the diagonal brace hack lever of collar plate shape superstructure(16).
3. a kind of construction of circular cone roofing integrally-lifting steel truss as claimed in claim 1, the engineering method is used for difference The roofing construction in diameter conical tube storehouse, it is characterised in that comprise the following steps:Truss Design and processing;Truss assembling;Truss First overall lifting 2m;Operation suspension bracket in truss bottom is installed;Truss is lifted;Bracket is installed and is connected firmly with truss;Set up purlin Frame upper support frame supporting plate, assembling reinforcement;Casting concrete;Drive and remove up to progress truss after 100% after concrete strength.
4. the construction of circular cone roofing integrally-lifting steel truss according to claim 3, it is characterised in that:Circle Cang Cang After the completion of tube construction, in storehouse, tube end plate assembles steel truss;Gutter template conduct is supported with the silo external scaffolding set up in advance Operating platform, lifting cucurbit steel structure suspender is installed on shallow cylinder bulkhead top, installs lifting electric block, and supporting lifting cucurbit Connecting cable and total control box;Truss is lifted to after designed elevation using electronic lifting cucurbit, steel truss is connected with bracket Fixed, truss lifting is completed;Complete concreting to reach after design strength, steel structure truss dismounting electric block, electronic calabash The steel hinge of reed both passes through silo roof roof boarding preformed hole, and the balance of steel construction support body is connected firmly and kept with steel construction support body, Steel truss is drop to manual demolition after silo base surface.
5. the construction of circular cone roofing integrally-lifting steel truss according to claim 3, it is characterised in that truss group Carried out as follows during dress:Steel truss transports to job site after machining, and is rechecked, numbered, using tower crane by truss Loose mail hangs in conical silo inner bottom plating, is installed in the following order:Reinforce hack lever → body frame bar(2)→ diagonal brace hack lever (16)→ center disk(1)→ pull bar(5).
6. the construction of circular cone roofing integrally-lifting steel truss according to claim 3, it is characterised in that install ox Leg is simultaneously carried out when being connected firmly with truss as follows:The external scaffolding set up when being constructed using silo gutter operates flat Platform, installs lifting cucurbit suspender and supporting lifting cucurbit connecting cable and total control box on silo wall top, utilizes external scaffolding Bracket is installed in bulkhead reserved location with suspension bracket below steel truss.
CN201610229785.9A 2016-04-14 2016-04-14 A kind of circular cone roofing integrally-lifting steel truss and its construction Pending CN107299713A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610229785.9A CN107299713A (en) 2016-04-14 2016-04-14 A kind of circular cone roofing integrally-lifting steel truss and its construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610229785.9A CN107299713A (en) 2016-04-14 2016-04-14 A kind of circular cone roofing integrally-lifting steel truss and its construction

Publications (1)

Publication Number Publication Date
CN107299713A true CN107299713A (en) 2017-10-27

Family

ID=60137107

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610229785.9A Pending CN107299713A (en) 2016-04-14 2016-04-14 A kind of circular cone roofing integrally-lifting steel truss and its construction

Country Status (1)

Country Link
CN (1) CN107299713A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109025249A (en) * 2018-09-14 2018-12-18 白琳琳 A kind of snow fort mold and snow fort method of construction
CN112012389A (en) * 2020-07-20 2020-12-01 中建三局集团有限公司 Support system for conical concrete roof of squat silo and installation method
CN113006469A (en) * 2021-03-17 2021-06-22 中国建筑一局(集团)有限公司 Curved surface concrete structure supporting platform and construction method
CN117145200A (en) * 2023-10-18 2023-12-01 湖南省西湖建筑集团有限公司 Shallow silo top cone shell formwork structure and its construction technology
CN119349412A (en) * 2024-11-14 2025-01-24 中建港航局集团有限公司 A lifting method for an arc-shaped silo integral lifting device

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003193424A (en) * 2001-12-28 2003-07-09 Kajima Corp Composite truss bridge and its construction method
CN101476410A (en) * 2009-01-13 2009-07-08 杭州萧宏建设集团有限公司 Mounting and demounting method roof plate formwork support platform of concrete silo
CN202401807U (en) * 2011-12-31 2012-08-29 中平能化建工集团有限公司土建处 Oblique-cone top cover supporting device of large-diameter high silo
CN104074348A (en) * 2014-06-25 2014-10-01 广州市恒盛建设工程有限公司 Cylindrical silo top truss platform descending system and control method of cylindrical silo top truss platform descending system
CN104389433A (en) * 2014-10-21 2015-03-04 北京建工土木工程有限公司 Integral hoisting system and construction method for steel truss support concrete heavy roof system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003193424A (en) * 2001-12-28 2003-07-09 Kajima Corp Composite truss bridge and its construction method
CN101476410A (en) * 2009-01-13 2009-07-08 杭州萧宏建设集团有限公司 Mounting and demounting method roof plate formwork support platform of concrete silo
CN202401807U (en) * 2011-12-31 2012-08-29 中平能化建工集团有限公司土建处 Oblique-cone top cover supporting device of large-diameter high silo
CN104074348A (en) * 2014-06-25 2014-10-01 广州市恒盛建设工程有限公司 Cylindrical silo top truss platform descending system and control method of cylindrical silo top truss platform descending system
CN104389433A (en) * 2014-10-21 2015-03-04 北京建工土木工程有限公司 Integral hoisting system and construction method for steel truss support concrete heavy roof system

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109025249A (en) * 2018-09-14 2018-12-18 白琳琳 A kind of snow fort mold and snow fort method of construction
CN112012389A (en) * 2020-07-20 2020-12-01 中建三局集团有限公司 Support system for conical concrete roof of squat silo and installation method
CN113006469A (en) * 2021-03-17 2021-06-22 中国建筑一局(集团)有限公司 Curved surface concrete structure supporting platform and construction method
CN117145200A (en) * 2023-10-18 2023-12-01 湖南省西湖建筑集团有限公司 Shallow silo top cone shell formwork structure and its construction technology
CN119349412A (en) * 2024-11-14 2025-01-24 中建港航局集团有限公司 A lifting method for an arc-shaped silo integral lifting device
CN119349412B (en) * 2024-11-14 2025-09-05 中建港航局集团有限公司 A lifting method for an arc-shaped silo integral lifting device

Similar Documents

Publication Publication Date Title
CN111270852A (en) Construction method of a new formwork support system for reinforced concrete silo domes
CN102535845A (en) Construction method of bearing frame of corridor structure
CN104989109B (en) It is a kind of at the same lift room beam purlin method
CN104453197A (en) High-altitude large-cantilever concrete structure structural steel supporting platform
CN104032967B (en) Prefabricated assembled frame structure component construction method for hanging
CN107299713A (en) A kind of circular cone roofing integrally-lifting steel truss and its construction
CN205772984U (en) A kind of hanging apparatus of monolithic steel truss
CN206692235U (en) A kind of steel structure dome lifts by crane erecting device
CN111236688A (en) Liftable construction platform for reinforcing circular silo in vitro
CN104847102A (en) Wall attaching method and device of attached self-lifting scaffold on retraction section of building outer wall
CN204001652U (en) The portable exterior wall operating platform of fabricated shear wall structure
CN207268073U (en) Novel flexible formwork bearing frame
CN201362953Y (en) Construction platform for pouring concrete silo roof
CN103615111A (en) Silo top construction method
CN102767282B (en) Prefabricated high formwork construction method for cantilever beam of oversized special-shaped conversion layer
CN103291116B (en) For the netted shuttering supporting operating platform of construction of water tank on top of inverted-cone water tower
CN210316599U (en) A curtain wall annular track for roof frame beams
CN207512610U (en) A kind of assembled bridge pier construction operation platform
CN211949737U (en) A liftable construction platform for external reinforcement of circular silos
CN205530902U (en) Whole over -and -under type steel truss of circular cone roofing
CN105822066B (en) Underground large span large space superelevation is without post steel-structure tube truss construction engineering method
CN113846543A (en) A door-rigid type coal conveying trestle bridge corridor overall structure and installation method thereof
CN107965193B (en) Roof construction method for large diameter silo structure
CN219548382U (en) Empty layer hanging template system of granulating tower
CN207332305U (en) Climbing frame in a kind of king-post construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20171027

RJ01 Rejection of invention patent application after publication