CN104988930B - It is applicable to the construction method in the combined type cofferdam of Unfavorable geology deep basal pit - Google Patents

It is applicable to the construction method in the combined type cofferdam of Unfavorable geology deep basal pit Download PDF

Info

Publication number
CN104988930B
CN104988930B CN201510415681.2A CN201510415681A CN104988930B CN 104988930 B CN104988930 B CN 104988930B CN 201510415681 A CN201510415681 A CN 201510415681A CN 104988930 B CN104988930 B CN 104988930B
Authority
CN
China
Prior art keywords
cofferdam
concrete
concrete cofferdam
construction
inner support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510415681.2A
Other languages
Chinese (zh)
Other versions
CN104988930A (en
Inventor
贾卫中
潘东发
张爱花
覃勇刚
邓敬雄
许兆军
童林鸿
胡军
刘丹飞
郭全德
李亚民
赵发亮
谢喜峰
李严明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Major Bridge Engineering Group Co Ltd MBEC
Original Assignee
China Railway Major Bridge Engineering Group Co Ltd MBEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Major Bridge Engineering Group Co Ltd MBEC filed Critical China Railway Major Bridge Engineering Group Co Ltd MBEC
Priority to CN201510415681.2A priority Critical patent/CN104988930B/en
Publication of CN104988930A publication Critical patent/CN104988930A/en
Application granted granted Critical
Publication of CN104988930B publication Critical patent/CN104988930B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)
  • Foundations (AREA)

Abstract

The invention discloses the construction method in a kind of combined type cofferdam being applicable to Unfavorable geology deep basal pit, relate to field of bridge construction, the method comprises the following steps: the construction location of concrete cofferdam is carried out setting-out;Carrying out substrate on construction location to change and fill out, and lay support chock and steel cutting shoe, assembling reinforcement, casting concrete cofferdam, at the pre-buried anchor bar of top of concrete;First inner support is installed in concrete cofferdam;Concrete cofferdam is made to sink;Installing steel sheet pile at concrete cofferdam end face, install the second inner support in steel sheet pile, the second inner support is fixed with anchor bar, in the 3rd inner support installed above of the second inner support;Concrete cofferdam is made to continue to sink down into design altitude.Combined type cofferdam in the present invention disclosure satisfy that structure stress requirement, it is to avoid the building waste that produces when concrete cofferdam is removed, dust, the environmental pollution, beneficially green construction such as noise, effective accelerating construction progress, saves construction cost.

Description

It is applicable to the construction method in the combined type cofferdam of Unfavorable geology deep basal pit
Technical field
The present invention relates to field of bridge construction, be specifically related to one and be applicable to the deep base of Unfavorable geology The construction method in the combined type cofferdam in hole.
Background technology
Traditional deep pit support gear safeguard structure typically has steel sheet pile, concrete cofferdam, steel-pipe pile Deng, steel sheet pile is the most reusable with steel-pipe pile, inserted to play, extracts easily, easy construction, fast Victory, shortcoming is as foundation depth and strengthens, and steel sheet pile and the flexible increase of steel-pipe pile, for opening Digging the Unfavorable geology foundation ditch that the degree of depth is bigger, the anchoring section of steel sheet pile and steel-pipe pile is all difficult to meet knot Structure force request;Concrete cofferdam structure stress situation is preferable, but there is sinking cycle length, one-tenth This is big, the later stage removes difficulty, be unfavorable for the problems such as green construction.
Summary of the invention
The invention aims to overcome the deficiency of above-mentioned background technology, it is provided that one is applicable to The construction method in the combined type cofferdam of Unfavorable geology deep basal pit, concrete cofferdam of first constructing, and After making concrete cofferdam sink down into original ground absolute altitude 0.8~1.2m, concrete cofferdam is installed Steel sheet pile, forms combined type cofferdam, then by combined type cofferdam integral sinking to designed elevation, Use the combined type cofferdam in the present invention to be not only able to meet structure stress requirement, and can keep away The building waste exempting to produce when concrete cofferdam is removed, dust, the environmental pollution such as noise, favorably In green construction, effective accelerating construction progress, save construction cost.
The present invention provides the construction party in a kind of combined type cofferdam being applicable to Unfavorable geology deep basal pit Method, comprises the following steps:
S1: construction basis drilled pile, construction location to concrete cofferdam above drilled pile Carry out setting-out;Described construction location is carried out after substrate changes and fill out, on substrate Shang Zhu island, Forward step S2 to;
S2: lay supporting pad wood and steel cutting shoe, assembling reinforcement on described construction location, pour Concrete cofferdam, the pre-buried some anchor bars of end face at concrete cofferdam, forward step S3 to;
S3: concrete cofferdam is carried out maintenance, treats that the concrete strength of concrete cofferdam end face reaches After design strength, the first inner support is installed in concrete cofferdam;Extract support chock, Carry out jetting in concrete cofferdam and inhale mud, making concrete cofferdam sink down into original ground absolute altitude 0.8~1.2m, forward step S4 to;
S4: the end face at concrete cofferdam installs steel sheet pile, by steel sheet pile and concrete cofferdam Junction is filled closely knit, installs the second inner support, the second inner support and anchoring steel in steel sheet pile Muscle is fixing to be connected, in the 3rd inner support installed above of the second inner support;In concrete cofferdam Proceed jetting and inhale mud, making concrete cofferdam continue to sink down into design altitude, terminating.
On the basis of technique scheme, in step S2 between adjacent two anchor bars Apart from equal.
On the basis of technique scheme, in step S2 between adjacent two anchor bars Distance is 2~2.8m.
On the basis of technique scheme, steel sheet pile described in step S4 and concrete cofferdam Junction use mortar fill closely knit.
Compared with prior art, advantages of the present invention is as follows:
First the present invention constructs concrete cofferdam, and make concrete cofferdam sink down into original ground mark After high 0.8-1.2m, concrete cofferdam is installed steel sheet pile, form combined type cofferdam, so After by combined type cofferdam integral sinking to designed elevation, use the combined type cofferdam in the present invention not But disclosure satisfy that structure stress requirement, and it can be avoided that produce when concrete cofferdam is removed builds The environmental pollutions, beneficially green construction such as building refuse, dust, noise, effectively accelerate to construct into Degree, saves construction cost.
Accompanying drawing explanation
Fig. 1 is that in the embodiment of the present invention, concrete cofferdam pours schematic diagram.
Fig. 2 is concrete cofferdam sinking schematic diagram in the embodiment of the present invention.
Fig. 3 is embodiment of the present invention Steel Sheet Pile scheme of installation.
Reference: 1-concrete cofferdam, 2-anchor bar, 3-the first inner support, 4-steel plate Stake, 5-the second inner support, 6-the 3rd inner support.
Detailed description of the invention
Below in conjunction with the accompanying drawings and the present invention is described in further detail by specific embodiment.
The embodiment of the present invention provides a kind of combined type cofferdam being applicable to Unfavorable geology deep basal pit Construction method, comprises the following steps:
S1: construction basis drilled pile, construction position to concrete cofferdam 1 above drilled pile Put and carry out setting-out;Described construction location is carried out after substrate changes and fill out, on substrate Shang Zhu island, Forward step S2 to.
S2: shown in Figure 1, lays supporting pad wood and steel cutting shoe on described construction location, Assembling reinforcement, casting concrete cofferdam 1, the pre-buried some anchorings of end face at concrete cofferdam 1 Reinforcing bar 2, the distance between adjacent two anchor bars 2 is equal, and generally 2~2.8m forward to Step S3.
S3: shown in Figure 2, carries out maintenance to concrete cofferdam 1, treats concrete cofferdam 1 After the concrete strength of end face reaches design strength, prop up in installing first in concrete cofferdam 1 Support 3;Extract support chock, and in concrete cofferdam 1, carry out jetting and inhale mud, make coagulation Earth cofferdam 1 sinks down into original ground absolute altitude 0.8~1.2m, forwards step S4 to.
S4: shown in Figure 3, the end face at concrete cofferdam 1 installs steel sheet pile 4, by steel It is closely knit that sheet pile 4 and the junction of concrete cofferdam 1 use mortar to fill, and pacifies in steel sheet pile 4 Filling the second inner support 5, the second inner support 5 is fixing with anchor bar 2 to be connected, and props up in second 3rd inner support 6 installed above of support 5;Jetting and suction is proceeded in concrete cofferdam 1 Mud, makes concrete cofferdam 1 continue to sink down into design altitude, terminates.
Those skilled in the art can carry out various modifications and variations to the embodiment of the present invention, if If these amendment and modification within the scope of the claims in the present invention and equivalent technologies thereof, then this A little amendments and modification are also within protection scope of the present invention.
The prior art that the content not described in detail in specification is known to the skilled person.

Claims (4)

1. being applicable to the construction method in the combined type cofferdam of Unfavorable geology deep basal pit, it is special Levy and be, comprise the following steps:
S1: construction basis drilled pile, executes concrete cofferdam (1) above drilled pile Station is put and is carried out setting-out;Described construction location is carried out after substrate changes and fill out, in substrate Build island, forward step S2 to;
S2: lay supporting pad wood and steel cutting shoe, assembling reinforcement on described construction location, pour Concrete cofferdam (1), the pre-buried some anchor bars of the end face (2) at concrete cofferdam (1), Forward step S3 to;
S3: concrete cofferdam (1) is carried out maintenance, treats the mixed of concrete cofferdam (1) end face After solidifying soil intensity reaches design strength, the first inner support (3) is installed in concrete cofferdam (1); Extract support chock, in concrete cofferdam (1), carry out jetting and inhale mud, making coagulation fortifield village Weir (1) sinks down into original ground absolute altitude 0.8~1.2m, forwards step S4 to;
S4: the end face at concrete cofferdam (1) installs steel sheet pile (4), by steel sheet pile (4) Fill closely knit with the junction of concrete cofferdam (1), in installing second in steel sheet pile (4) Supporting (5), the second inner support (5) is fixing with anchor bar (2) to be connected, and props up in second 3rd inner support (6) installed above of support (5);Proceed in concrete cofferdam (1) Jetting and suction mud, make concrete cofferdam (1) continue to sink down into design altitude, terminate.
It is applicable to the combined type cofferdam of Unfavorable geology deep basal pit the most as claimed in claim 1 Construction method, it is characterised in that: in step S2 between adjacent two anchor bars (2) away from From equal.
It is applicable to the combined type cofferdam of Unfavorable geology deep basal pit the most as claimed in claim 2 Construction method, it is characterised in that: in step S2 between adjacent two anchor bars (2) away from From for 2~2.8m.
It is applicable to Unfavorable geology deep basal pit the most as claimed any one in claims 1 to 3 The construction method in combined type cofferdam, it is characterised in that: steel sheet pile described in step S4 (4) with It is closely knit that the junction of concrete cofferdam (1) uses mortar to fill.
CN201510415681.2A 2015-07-16 2015-07-16 It is applicable to the construction method in the combined type cofferdam of Unfavorable geology deep basal pit Active CN104988930B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510415681.2A CN104988930B (en) 2015-07-16 2015-07-16 It is applicable to the construction method in the combined type cofferdam of Unfavorable geology deep basal pit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510415681.2A CN104988930B (en) 2015-07-16 2015-07-16 It is applicable to the construction method in the combined type cofferdam of Unfavorable geology deep basal pit

Publications (2)

Publication Number Publication Date
CN104988930A CN104988930A (en) 2015-10-21
CN104988930B true CN104988930B (en) 2016-09-07

Family

ID=54300812

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510415681.2A Active CN104988930B (en) 2015-07-16 2015-07-16 It is applicable to the construction method in the combined type cofferdam of Unfavorable geology deep basal pit

Country Status (1)

Country Link
CN (1) CN104988930B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105714833B (en) * 2016-03-01 2017-06-30 江苏东合南岩土科技股份有限公司 A kind of construction method of steel sheet pile open caisson supporting
CN106193075A (en) * 2016-08-24 2016-12-07 中国铁建大桥工程局集团有限公司 A kind of concrete cofferdam and steel sheet-pile cofferdam combination type cofferdam structure and construction method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102691302A (en) * 2012-06-03 2012-09-26 蒋凤昌 Concrete structure for supporting deep foundation pit
CN103015446A (en) * 2012-08-10 2013-04-03 中铁大桥局股份有限公司 Method for constructing bearing platform on deepwater and rigid impermeable layer
CN104594367A (en) * 2015-01-23 2015-05-06 中国建筑第七工程局有限公司 Combined cofferdam structure and construction method

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5712721A (en) * 1980-06-27 1982-01-22 Hazama Gumi Ltd Method for water cut off and shoring work
JP3567390B2 (en) * 1996-02-05 2004-09-22 清水建設株式会社 Retaining structure with continuous underground wall

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102691302A (en) * 2012-06-03 2012-09-26 蒋凤昌 Concrete structure for supporting deep foundation pit
CN103015446A (en) * 2012-08-10 2013-04-03 中铁大桥局股份有限公司 Method for constructing bearing platform on deepwater and rigid impermeable layer
CN104594367A (en) * 2015-01-23 2015-05-06 中国建筑第七工程局有限公司 Combined cofferdam structure and construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
富水砾石地层承台基坑钢筋混凝土围堰防护施工技术;谢阳平等;《北方交通》;20130628(第6期);第89-92页 *

Also Published As

Publication number Publication date
CN104988930A (en) 2015-10-21

Similar Documents

Publication Publication Date Title
CN104452809A (en) Ultra-shallow buried tunnel cover-excavation construction method
KR101640449B1 (en) Construction method for open cutting in tunnel portal area
KR101655217B1 (en) Construction method for open cutting in tunnel portal area
CN104988930B (en) It is applicable to the construction method in the combined type cofferdam of Unfavorable geology deep basal pit
KR101012640B1 (en) Method for constructing structure for underground tunnel
JP2011089361A (en) Slope reinforcing method
CN107044135A (en) A kind of tunnel portal excavates the construction method built
KR100976621B1 (en) Construction method for basement extention
CN110847047B (en) Open sea bare rock trestle construction method
CN108517893A (en) A kind of big cross section push pipe suitable under the conditions of shallow earthing wears river construction method
JP2018138738A (en) Invert construction method
KR20100113957A (en) Joint structure and method for constructing slab of underground structures using the same
CN105484270B (en) Reinforcement protection construction method of high steep old rubble retaining wall adjacent to deep foundation pit
JP2002364006A (en) Construction method for underwater foundation
JP6326294B2 (en) Construction method of earth retaining structure
KR100862387B1 (en) Tensional kit for top-down constructing of acupressure lasting anchor and top-down constructing method of acupressure lasting anchor using this
CN108589738A (en) Half gravity dam formula foundation pit enclosure structure and its construction method
CN105951874B (en) A kind of retaining wall reinforcement structure and its construction method
CN106120853A (en) A kind of inverted construction method of frame bridge
CN203684236U (en) Deep foundation pit support retaining wall
KR101375155B1 (en) Construction Method of Reinforced Bar Insert Type in-situ Concrete Pile
KR101069706B1 (en) Method for constructing structure for forming underground tunnel on boundary of rock bed
KR101254608B1 (en) Tunnel construction method with support walls
CN206986915U (en) A kind of fan platform installation foundation
KR20200088659A (en) Top-down type underground structure construction method using earth support plate

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant