CN104975878A - 隧道排水沟施工方法 - Google Patents
隧道排水沟施工方法 Download PDFInfo
- Publication number
- CN104975878A CN104975878A CN201510401426.2A CN201510401426A CN104975878A CN 104975878 A CN104975878 A CN 104975878A CN 201510401426 A CN201510401426 A CN 201510401426A CN 104975878 A CN104975878 A CN 104975878A
- Authority
- CN
- China
- Prior art keywords
- water discharging
- air bag
- cover plate
- drainage ditch
- gutter
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
本发明涉及隧道排水沟施工方法,包括顺序进行的以下步骤:修筑排水沟下部的铺底层;搭建仰拱层的模板,然后浇注形成仰拱层,仰拱层留出排水沟空间;在排水沟空间放入气囊,并且对气囊充气,所述气囊尺寸与排水沟内径相适配;在气囊上部设置排水沟盖板钢筋网,浇筑排水沟盖板;所述排水沟盖板凝固达到强度标准后,气囊放气,将气囊从所述排水沟空间取出。本施工方法,采用橡胶气囊代替传统的模板框架设置在预留的排水沟空间中,并且对气囊充气,随后在气囊上部设置排水沟盖板钢筋网,浇注排水沟盖板,待排水沟盖板基本凝固,即可让气囊排气,将气囊从排水沟空间中取出,不需要采用多块模板拼接形成排水沟的框架,本方法更为简便、快捷。
Description
技术领域
本发明涉及排水沟施工,具体的是采用气囊辅助修筑隧道排水沟的方法。
背景技术
隧道施工时,需要在隧道底部的地面下设置排水沟,传统的排水沟修筑方法,是土方开挖完成后,采用木模板搭建形成排水沟的空腔,随后在木模板周围浇注仰拱层;木模板搭建的空腔上部设置排水沟盖板钢筋网,浇注排水沟盖板;随后还有在仰拱层和排水沟盖板上部浇注平整层等工序,待仰拱层和排水沟盖板都凝固满足强度标准后,拆除原来的木模版,即得到需要的排水沟。
由于隧道的排水沟长度较长,采用上述实施方式时,需要使用大量模板、木枋,搭建和拆除模板框架也需要消耗很多工时。
发明内容
本发明所要解决的技术问题是:提供一种隧道排水沟施工方法,采用橡胶气囊代替传统的模板框架,排水沟施工更为简便。
本发明解决其技术问题所采用的技术方案是:
隧道排水沟施工方法,包括顺序进行的以下步骤:
A、修筑排水沟下部的铺底层;
B、搭建仰拱层的模板,然后浇注形成仰拱层,仰拱层留出排水沟空间;
C、在排水沟空间放入气囊,并且对气囊充气,所述气囊尺寸与排水沟内径相适配;
D、在气囊上部设置排水沟盖板钢筋网,浇筑排水沟盖板;
E、所述排水沟盖板凝固达到强度标准后,气囊放气,将气囊从所述排水沟空间取出。
进一步的,所述步骤C中,对气囊充气之前或之后,向气囊内注水。
进一步的,所述步骤E中,所述排水沟盖板凝固达到设计强度的30%~40%时,气囊放气,将气囊从所述排水沟空间取出。
进一步的,所述步骤E之后,还包括在所述排水沟盖板和仰拱层上部修筑整平层的步骤。
本发明的有益效果是:使用上述隧道排水沟施工方法,在修筑仰拱层时,预留出排水沟空间,然后采用橡胶气囊代替传统的模板框架设置在预留的排水沟空间中,并且对气囊充气,随后在气囊上部设置排水沟盖板钢筋网,浇注排水沟盖板,待排水沟盖板基本凝固,即可让气囊排气,并且将气囊从排水沟空间中取出,由于不需要采用多块模板拼接形成排水沟的框架,本施工方法更为简便、快捷。
附图说明
图1是采用本发明施工方法一种实施例的隧道截面示意图;
图2是采用本发明施工方法另一种实施例的隧道截面示意图;
图中附图标记为:铺底层1、仰拱层2、仰拱层左侧部21、排水沟空间3、气囊31。
具体实施方式
下面结合附图和实施例对本发明进一步说明:
隧道排水沟施工方法,包括顺序进行的以下步骤:
A、修筑排水沟下部的铺底层1;
B、搭建仰拱层2的模板,然后浇注形成仰拱层2,仰拱层2留出排水沟空间3;
C、在排水沟空间3放入气囊31,并且对气囊31充气,所述气囊31尺寸与排水沟内径相适配;
D、在气囊31上部设置排水沟盖板钢筋网,浇筑排水沟盖板;
E、所述排水沟盖板凝固达到强度标准后,气囊31放气,将气囊31从所述排水沟空间3取出。
如图1所示:本发明的隧道排水沟施工方法,基本特点在于采用充气的气囊31代替传统方式的木模版搭建排水沟的空腔。并且在气囊31上设置排水沟盖板钢丝网,并且浇注排水沟盖板,当排水沟盖板凝固后,即可让气囊31放气,并且从原来的空腔将气囊31取出,排水沟修筑完成。
具体的,先按照常规方式,修筑排水沟下部的铺底层1,搭建仰拱层2的模板,然后浇注形成仰拱层2,在修筑仰拱层2时,需要在设计的排水沟位置留出排水沟空间3。
随后在排水沟空间3中放入气囊31,并且对气囊31充气。优选的,气囊31可以是采用比较厚的橡胶气囊,防止破损。气囊31尺寸要与排水沟内径相适配,即是气囊31的外部尺寸与设计的排水沟内部尺寸基本相等。气囊31充气的方式,优选的可以是直接使用隧道施工时设置的风管中的风压进行充气。
等气囊31内部充满,在气囊31上部设置排水沟盖板钢筋网,然后浇筑形成排水沟盖板,排水沟盖板凝固达到强度标准后,例如达到设计强度的30%~40%时,让气囊31放气,将气囊31从所述排水沟空间3取出,排水沟修筑完成。后续的,还可以继续在排水沟盖板和仰拱层上部修筑整平层等。
进一步优选的,对气囊31充气之前或之后,可以向气囊31内注入一定量的水,注水的量根据实际情况选择,让水的重力可以压住气囊31,防止后续浇注时气囊31上浮。
如图1所示实施例,其施工过程是,先在底部修筑铺底层1,随后搭建模板框架在铺底层1上部浇注出两块仰拱层2,两块仰拱层2中间留出了排水沟空间3,然后在排水沟空间3中放入气囊31,并且对气囊31充气;在气囊31上部设置排水沟盖板的钢筋网,然后浇注形成排水沟盖板和整平层等。
如图2所示实施例,其施工过程是,先在隧道左侧按照常规方法修筑了仰拱层左侧部21,然后在仰拱层左侧部21右边,按照本发明的方法,修筑铺底层1、仰拱层2,并且留出了排水沟空间3,然后在排水沟空间3中放入气囊31,并且对气囊31充气;在气囊31上部设置排水沟盖板的钢筋网,然后浇注形成排水沟盖板和整平层等。
本发明的排水沟施工方法,可以大大减少木模板使用,节省相应的材料、人工和机械费用,施工效率也更为提高。
Claims (4)
1.隧道排水沟施工方法,其特征在于,包括顺序进行的以下步骤:
A、修筑排水沟下部的铺底层(1);
B、搭建仰拱层(2)的模板,然后浇注形成仰拱层(2),仰拱层(2)留出排水沟空间(3);
C、在排水沟空间(3)放入气囊(31),并且对气囊(31)充气,所述气囊(31)尺寸与排水沟内径相适配;
D、在气囊(31)上部设置排水沟盖板钢筋网,浇筑排水沟盖板;
E、所述排水沟盖板凝固达到强度标准后,气囊(31)放气,将气囊(31)从所述排水沟空间(3)取出。
2.如权利要求1所述的隧道排水沟施工方法,其特征在于,所述步骤C中,对气囊(31)充气之前或之后,向气囊(31)内注水。
3.如权利要求1所述的隧道排水沟施工方法,其特征在于,所述步骤E中,所述排水沟盖板凝固达到设计强度的30%~40%时,气囊(31)放气,将气囊(31)从所述排水沟空间(3)取出。
4.如权利要求1所述的隧道排水沟施工方法,其特征在于,所述步骤E之后,还包括在所述排水沟盖板和仰拱层上部修筑整平层的步骤。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510401426.2A CN104975878B (zh) | 2015-07-09 | 2015-07-09 | 隧道排水沟施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510401426.2A CN104975878B (zh) | 2015-07-09 | 2015-07-09 | 隧道排水沟施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104975878A true CN104975878A (zh) | 2015-10-14 |
CN104975878B CN104975878B (zh) | 2017-11-24 |
Family
ID=54272794
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510401426.2A Active CN104975878B (zh) | 2015-07-09 | 2015-07-09 | 隧道排水沟施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104975878B (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105604606A (zh) * | 2016-01-22 | 2016-05-25 | 山东大学 | 一种隧道污水沟气囊整体施工方法 |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU620553A1 (ru) * | 1977-02-01 | 1978-08-25 | Львовский политехнический институт | Устройство дл бестраншейного изготовлени трубопровода |
DE102008005992A1 (de) * | 2008-01-24 | 2009-07-30 | U.C.M. Heidelberg Gmbh | Verfahren zur Herabsetzung der Versinterung von Drainagerohren |
CN102011597A (zh) * | 2010-11-29 | 2011-04-13 | 成都中铁隆工程有限公司 | 隧道软弱围岩支护方法及支护结构 |
-
2015
- 2015-07-09 CN CN201510401426.2A patent/CN104975878B/zh active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU620553A1 (ru) * | 1977-02-01 | 1978-08-25 | Львовский политехнический институт | Устройство дл бестраншейного изготовлени трубопровода |
DE102008005992A1 (de) * | 2008-01-24 | 2009-07-30 | U.C.M. Heidelberg Gmbh | Verfahren zur Herabsetzung der Versinterung von Drainagerohren |
CN102011597A (zh) * | 2010-11-29 | 2011-04-13 | 成都中铁隆工程有限公司 | 隧道软弱围岩支护方法及支护结构 |
Non-Patent Citations (3)
Title |
---|
刘晓树: "采用充气芯膜法施作隧道水沟", 《铁道建筑》 * |
刘苗苗等: "乌池坝隧道整体式水沟施工方案的优化", 《华南港工》 * |
苏海峰: "气囊法在公路隧道路面边沟中的应用", 《隧道建设》 * |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105604606A (zh) * | 2016-01-22 | 2016-05-25 | 山东大学 | 一种隧道污水沟气囊整体施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN104975878B (zh) | 2017-11-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105201106B (zh) | 变形缝处双剪力墙模板支模施工方法 | |
CN105696599A (zh) | 一种通过利用气囊封堵装置的加压注浆方法 | |
CN104260198A (zh) | 混凝土预制墙体及其竖向浇筑孔留置方法 | |
CN106088591B (zh) | 带有凸起的混凝土工程变形缝垂直止水型腔模 | |
CN104314048B (zh) | 气囊式混凝土工程变形缝止水型腔模的制造及施工方法 | |
CN205712093U (zh) | 一种对土钉及锚杆进行加压注浆的气囊封堵装置 | |
CN104975878A (zh) | 隧道排水沟施工方法 | |
CN111379418B (zh) | 一种超长不设缝混凝土结构及其施工方法 | |
CN109339089A (zh) | 一种杯口独立基础杯芯成型方法 | |
CN105951679B (zh) | 一种混凝土工程型腔模气囊的制造方法 | |
CN208734344U (zh) | 折叠式隧道中央水沟施工用模板 | |
CN206144574U (zh) | 隧道中心排水沟模板台车 | |
CN206359897U (zh) | 一种铰接式钢芯模单元 | |
CN204097970U (zh) | 一种混凝土工程变形缝垂直止水型腔模 | |
CN208148139U (zh) | 一种充气橡胶芯模 | |
CN207033471U (zh) | 隧道边墙仰拱混凝土成环浇注自行移动全弧模板 | |
CN202572613U (zh) | 一种预制板梁橡胶充气芯模 | |
CN112681289B (zh) | 一种桩板墙的拱板及其制作方法 | |
CN216765856U (zh) | 高承压水地层全套管全回转止水咬合桩 | |
ITMO20060130A1 (it) | Procedimento per la fabbricazione di elementi da costruzione per la realizzazione di muri con riempimento di materiale di riporto, particolarmente terra o simili. | |
CN105386777A (zh) | 一种隧道现浇欧米伽形边沟的施工方法 | |
CN103085160B (zh) | 一种组合式预制柱基础芯模及其制作芯体的方法 | |
CN204212301U (zh) | 应用于现浇空心楼板的气囊式芯模 | |
JPH0813455B2 (ja) | 筒状コンクリート製品の製造方法および筒状コンクリート製品製造用の型枠 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20171025 Address after: 710000 Shaanxi province Xi'an City Road, Yanta Beilin District No. 1 Applicant after: Zhongtie No.1 Bureau Group Co., Ltd. Applicant after: No.4 Engineering Co., Ltd., Zhongtie Co., Ltd., Bureau Group Address before: 721006 Baoji province Shaanxi city Weibin District Zhongtan Road No. 4, No. 9 Building 4 unit 4 Building No. 11 Applicant before: Yao Zhijun |
|
TA01 | Transfer of patent application right | ||
GR01 | Patent grant | ||
GR01 | Patent grant |