CN104948833B - Mountainous region gas pipeline construction method - Google Patents

Mountainous region gas pipeline construction method Download PDF

Info

Publication number
CN104948833B
CN104948833B CN201510317275.2A CN201510317275A CN104948833B CN 104948833 B CN104948833 B CN 104948833B CN 201510317275 A CN201510317275 A CN 201510317275A CN 104948833 B CN104948833 B CN 104948833B
Authority
CN
China
Prior art keywords
pipe
road
stone
construction
gas pipeline
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510317275.2A
Other languages
Chinese (zh)
Other versions
CN104948833A (en
Inventor
戴斌
王可栋
陶志钧
柯向华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Energy Construction Group Co.,Ltd.
Original Assignee
Shanghai Gas No2 Pipeline Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Gas No2 Pipeline Engineering Co Ltd filed Critical Shanghai Gas No2 Pipeline Engineering Co Ltd
Priority to CN201510317275.2A priority Critical patent/CN104948833B/en
Publication of CN104948833A publication Critical patent/CN104948833A/en
Application granted granted Critical
Publication of CN104948833B publication Critical patent/CN104948833B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/028Laying or reclaiming pipes on land, e.g. above the ground in the ground

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The invention discloses a mountainous region gas pipeline construction method. The construction method comprises the following main steps of 1, construction operation zone cleaning, wherein large vegetation on a construction operation zone is removed, and static blasting is performed to shatter and remove stone on the construction operation zone; 2, construction road building, wherein a construction road is built beside a pipe ditch design line, the construction road on a flat mountain slope is in a linear shape, the construction road on a mountain slope is in the shape of a broken line, and operation platforms are arranged at the position, near a pipe ditch, on the construction road in the extending direction of the pipe ditch every a certain distance; 3, pipe ditch excavating, wherein the pipe ditch is excavated by utilizing an excavator according to the design line, and the bottom of the ditch is cleaned through manual cooperation; 4, pipeline lying, wherein steel pipes are transported and stacked on a mountain, and then placed in the excavated pipe ditch; 5, pipe ditch backfilling, wherein the pipe ditch is backfilled with backfill materials. By using the mountainous region gas pipeline construction method, the safety risk can be lowered, the construction progress can be sped up, and the cost can be saved.

Description

A kind of mountain region gas pipeline engineering method
Technical field
The present invention relates to a kind of construction method, and in particular to a kind of mountain region gas pipeline engineering method, belongs to gas pipeline Field of engineering technology.
Background technology
In domestic and international gas pipeline construction process in recent years, the more aobvious complexity of landform that pipeline passes through, the high slope in mountain is steep, ditch Gully in length and breadth, brings very big difficulty to construction it is impossible to play the advantage of mechanized continuous productive process.Especially carry out mountain region construction When, due to lacking mountain region construction technology and experience, when there is mountain region construction, speed is slow, the low problem of safety, serious restricts Pipeline construction progress.
Rational construction method is the premise determining working security, and the construction environment of safety can guarantee that work progress Be smoothed out, both are indispensable in whole work progress, complement each other.Selecting mountain region gas pipeline engineering method When, should be according to the factor of a series of impact safety such as different landform, landforms, the soft degree of soil property, emergency of the gradient and progress Start with, each detail in construction technology is given careful consideration, under the premise that security is guaranteed, using scientific and reasonable Construction method.The correct selection of mountain region construction method is the key improving mountain region efficiency of construction, rational mountain region construction method energy Enough reduction security risks, accelerating construction progress, cost-effective.
Content of the invention
The technical problem to be solved is: ensures gas pipeline smoothly laying in mountain region.
In order to solve above-mentioned technical problem, the invention provides a kind of mountain region gas pipeline engineering method, walk including following Rapid:
Step one, clears up construction operation band, removes the large-scale vegetation on construction operation band, using static blasting, construction is made The cubic meter of stone on industry band shatters removing.Using air compressor machine, the cubic meter of stone is holed, place cracking agent in the hole and carry out static blasting handle The cubic meter of stone shatters, and then using disintegrating apparatus, the cubic meter of stone is crushed again, until being easy to excavation function all remove the cubic meter of stone;Quick-fried Tumble direction setting prevention hole along the cubic meter of stone below breakpoint, play undertaking or cushioning effect when rock blasting tumbles, prevention hole Depth is the depth of pipe trench, and the width in prevention hole is 1.2 times of pipe trench width, and the length in prevention hole is not less than the length of slope.
Step 2, builds builder's road, builds builder's road, builder's road is on massif flat slope by piping design circuit For linear type, builder's road is fold-line-shaped on massif slope, presses pipe trench extending direction on builder's road near pipe trench Set operating platform at a certain distance.
Preferably, builder's road sets operating platform by pipe trench extending direction every 12 meters near pipe trench, operation Land lengths and width are all not less than 6 meters.Fold-line-shaped builder's road takies 35 meters of construction operation bandwidth, fold-line-shaped builder's road Local width is less than 4 meters.After fold-line-shaped builder's road molding, the gradient is less than or close to 15 degree.
Step 3, pipe canal digging, excavates pipe trench according to designed lines excavator, hand fit clears up bottom of trench.Pipe trench is opened After the completion of digging, the both sides heap along pipe trench bearing of trend builds sandbag;If on massif slope, sandbag heap is built height and is required more than mound height Degree;If on massif flat slope, sandbag heap is built height and is 1 meter.Pipe trench cross section is inverted trapezoidal, upper wide 3.8 meters, lower wide 1.6 meters, deep Degree is not less than 2.5 meters.
Step 4, pipeline laying, steel pipe is transported on mountain and stacks, then insert in the pipe trench having excavated.Steel pipe heap on mountain When putting, the mouth of pipe two ends bottom of steel pipe must be lined with sandbag, the mouth of pipe two ends of steel pipe pipe cap used when must dispatch from the factory using steel pipe Closure.
Step 5, backfilling of pipe canal, backfill pipe trench using backfilling material.Cubic meter of stone section backfilling of pipe canal material all using stone powder, Pipeline bottom overlays 0.2 meter of thickness of stone powder.
The invention has the beneficial effects as follows: can reduce security risk, accelerating construction progress, cost-effective.
Technique effect below with reference to design, concrete structure and generation to the present invention for the accompanying drawing is described further, with It is fully understood from the purpose of the present invention, feature and effect.
Brief description
Fig. 1 is the flow chart of a preferred embodiment of the present invention mountain region gas pipeline engineering method.
Specific embodiment
Example below is that the present invention is described in further detail, and embodiment is to be front with technical solution of the present invention Put and implemented, give detailed embodiment and specific operating process, but protection scope of the present invention is not limited to down State embodiment.
Step one, clears up construction operation band
Remove the large-scale vegetation on construction operation band, using static blasting, the cubic meter of stone on construction operation band is shattered removing. Using air compressor machine, the cubic meter of stone is holed, carry out static blasting in the hole placement cracking agent and the cubic meter of stone is shattered, then using broken Equipment crushes again to the cubic meter of stone, until being easy to excavation function all remove the cubic meter of stone.
Cubic meter of stone cleaning construction method is divided into three steps:
First small-sized air compressor handling used is gone up a hill to position (the Air Compressor Equipment intact symbol of need of the required cleaning cubic meter of stone Close used by safe construction, place place and need to steadily carry out non-skid feature).
Secondly the required removing cubic meter of stone is holed using small-sized air compressor (hole number with the actual determination of cubic meter of stone amount size, In addition operative employee need to carry out training and must wear anti-gray mask in construction).
Finally all after the completion of perforatings, explosive carries out the quiet quick-fried cubic meter of stone and shatters (also needing using big gun machine to the cubic meter of stone after shattering Cleared up again, until being easy to digging machine can all remove the cubic meter of stone).
Compared with general static blasting, the static blasting during gas pipeline engineering of mountain region, along the cubic meter of stone below blow-up point Tumble direction and preset special " prevention hole ", the cubic meter of stone tumbles and constantly plays the effect accepting mountain stone or buffering in explosion.
The size of the required pipe trench according to roughing-in, calculates the equivalent of cubic meter of stone static blasting." prevention therefore generally described above The dimensional depth in hole " is the depth of required pipe trench, and width is 1.2 times of required pipe trench width, and length is according to the actual feelings of slope Depending on condition.
Step 2, builds builder's road
For ready-made road, need to be lengthened and be built reinforcing, pit be carried out with paving and rockfills granulated slag tamping, to lobe Point with machinery and manually need to be excavated and the close granulated slag that rockfills is it is ensured that the heavy goods vehicle of construction material and equipment is safe, suitable Profit is current.
To mountain area Special zone line alignment optimization, determine the position of builder's road and temporary heap pipe field for effective control Investment, convenient construction and control duration will play significant role.Build builder's road by piping design circuit, builder's road exists It is linear type on massif flat slope, builder's road is fold-line-shaped on massif slope.
Builder's road sets operating platform by pipe trench extending direction every 12 meters near pipe trench, is easy to digging machine upper and lower Cornering operation and workmen when going up a hill in the middle of take a break.Operating platform length and width all not less than 6 meters, is easy to digging machine Operate, rotate, turn around required.Fold-line-shaped builder's road takies 35 meters of construction operation bandwidth, and fold-line-shaped builder's road itself is wide Degree is less than 4 meters.After fold-line-shaped builder's road molding, the gradient is less than or close to 15 degree.
Step 3, pipe canal digging
Excavate pipe trench according to designed lines excavator, hand fit clears up bottom of trench.After the completion of pipe canal digging, prolong along pipe trench The both sides heap stretching direction builds sandbag;If on massif slope, sandbag heap is built height and is required more than mound height;If in massif flat slope On, sandbag heap is built height and is 1 meter.Pipe trench cross section is inverted trapezoidal, upper wide 3.8 meters, lower wide 1.6 meters, and depth is not less than 2.5 meters.
As pipe canal digging side be close to massif and opposite side as massif slope, it must build sandbag by heap, its sandbag heap builds height Degree must try gradient size to meet live mound requirement (prior effect is to prevent massif soil erosion), and such as opposite side is Massif flat slope pipe trench institute earth excavation is stacked its peripheral sandbag heap and is built and highly general only needs 1 meter to can reach requirement (to prevent massif water Soil runs off).
As its position both sides of pipe canal digging are massif flat slope because also needing relative set in view of massif soil erosion problem Sandbag, and accomplish that sandbag heap is built height and can be met requirement for 1 meter.
Special zone also needs to build building concrete barricade and guarantees construction safety (comprising to prevent massif soil erosion problem), and it is built Build and require examination on-site actual situations to determine (its length high thickness must is fulfilled for construction safety).
Step 4, pipeline laying
Steel pipe is transported on mountain and stacks, then insert in the pipe trench having excavated.
Because on mountain, soil property is bad, placing of material especially notes protecting the cleannes in the insulating barrier of steel pipe and guarantee pipe, It is stacked main attention item and is divided at 3 points.
1st, on mountain, steel tube stacking position must rationally determine and carry out stacking platform arrangement (its position can not affect to apply in the future The normal pass of work passage).
2nd, on mountain, the mouth of pipe two side bottom of its steel pipe of steel tube stacking must be lined with sandbag and (and must carry out outside steel tube stacking Safety precautions prevents steel pipe from tumbling).
3rd, when on mountain, the closure of its mouth of pipe two ends of steel tube stacking must be dispatched from the factory using steel pipe, (it is unnecessary to prevent for pipe cap used Debris enter in pipe and prevent accidental impact from damaging the mouth of pipe).
Step 5, backfilling of pipe canal
Backfill pipe trench using backfilling material.Before backfill, enter the measurement of line pipe crest level first it is ensured that protective coating and looping portion Being damaged of position all has been obtained for repairing and have passed through enough hardening times, and is answered with leak detector Inspection.
The cubic meter of stone can not be stacked near the scene, otherwise produces great potential safety hazard, should be transported to outward appointed place and throw aside.Cause Live earth's surface no element soil is desirable, and all using stone powder, ttom of pipe overlays 0.2 meter of thickness of stone powder to cubic meter of stone section backfilling of pipe canal material.
The preferred embodiment of the present invention described in detail above.It should be appreciated that those of ordinary skill in the art is no Need creative work just can make many modifications and variations according to the design of the present invention.Therefore, all technology in the art It is available that personnel pass through logical analysis, reasoning, or a limited experiment under this invention's idea on the basis of existing technology Technical scheme, all should be in the protection domain being defined in the patent claims.

Claims (9)

1. a kind of mountain region gas pipeline engineering method is it is characterised in that described construction method comprises the following steps:
Step one, clears up construction operation band, removes the large-scale vegetation on construction operation band, using static blasting construction operation band On the cubic meter of stone shatter removing;Tumble direction setting prevention hole along the described cubic meter of stone below blow-up point, described prevention hole is in described stone Undertaking or cushioning effect are played in square explosion when tumbling;
Step 2, builds builder's road, builds builder's road, described builder's road is on massif flat slope by piping design circuit For linear type, described builder's road is fold-line-shaped on massif slope, presses pipe trench on described builder's road near pipe trench Extending direction interval sets operating platform;
Step 3, pipe canal digging, excavates pipe trench according to designed lines excavator, hand fit clears up bottom of trench;
Step 4, pipeline laying, steel pipe is transported on mountain and stacks, then insert in the pipe trench having excavated;
Step 5, backfilling of pipe canal, backfill pipe trench using backfilling material;
In step one, using air compressor machine, the described cubic meter of stone is holed, place cracking agent in the hole and carry out static blasting described The cubic meter of stone shatters, and then using disintegrating apparatus, the described cubic meter of stone is crushed again, until being easy to excavate described in the whole removing of function The cubic meter of stone;The depth in described prevention hole is the depth of described pipe trench, and the width in described prevention hole is 1.2 times of described pipe trench width, The length in described prevention hole is not less than the length of slope.
2. a kind of mountain region gas pipeline engineering method according to claim 1 is it is characterised in that in step 2, described Nearby operating platform is set by pipe trench extending direction every 12 meters near pipe trench, described operating platform length and width on builder's road All not less than 6 meters.
3. a kind of mountain region gas pipeline engineering method according to claim 1 is it is characterised in that in step 2, described folding Linear builder's road takies 35 meters of construction operation bandwidth, and described fold-line-shaped builder's road local width is less than 4 meters.
4. a kind of mountain region gas pipeline engineering method according to claim 1 is it is characterised in that in step 2, described folding After linear builder's road molding, the gradient is less than 15 degree.
5. a kind of mountain region gas pipeline engineering method according to claim 1 is it is characterised in that in step 3, described pipe Ditch cross section is inverted trapezoidal, upper wide 3.8 meters, lower wide 1.6 meters, and depth is not less than 2.5 meters.
6. a kind of mountain region gas pipeline engineering method according to claim 1 is it is characterised in that in step 3, described pipe After the completion of ditch excavates, the both sides heap along described pipe trench bearing of trend builds sandbag;If on massif slope, sandbag heap is built height and need to be surpassed Cross mound height;If on massif flat slope, sandbag heap is built height and is 1 meter.
7. a kind of mountain region gas pipeline engineering method according to claim 1 is it is characterised in that in step 4, steel pipe exists When stacking on mountain, the mouth of pipe two ends bottom of steel pipe must be lined with sandbag.
8. a kind of mountain region gas pipeline engineering method according to claim 1 is it is characterised in that in step 4, steel pipe exists When stacking on mountain, the pipe cap closure used when must be dispatched from the factory using steel pipe of the mouth of pipe two ends of steel pipe.
9. a kind of mountain region gas pipeline engineering method according to claim 1 is it is characterised in that in step 5, cubic meter of stone section All using stone powder, pipeline bottom overlays 0.2 meter of thickness of stone powder to backfilling of pipe canal material.
CN201510317275.2A 2015-06-10 2015-06-10 Mountainous region gas pipeline construction method Active CN104948833B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510317275.2A CN104948833B (en) 2015-06-10 2015-06-10 Mountainous region gas pipeline construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510317275.2A CN104948833B (en) 2015-06-10 2015-06-10 Mountainous region gas pipeline construction method

Publications (2)

Publication Number Publication Date
CN104948833A CN104948833A (en) 2015-09-30
CN104948833B true CN104948833B (en) 2017-01-18

Family

ID=54163737

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510317275.2A Active CN104948833B (en) 2015-06-10 2015-06-10 Mountainous region gas pipeline construction method

Country Status (1)

Country Link
CN (1) CN104948833B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105387273A (en) * 2015-12-10 2016-03-09 上海煤气第一管线工程有限公司 Method for constructing natural gas pipelines in mountain environment
CN105971055A (en) * 2016-05-31 2016-09-28 安庆供水集团公司 Clean construction method for urban secondary water supply
CN110688719A (en) * 2019-10-10 2020-01-14 中国人民解放军63926部队 Method for calculating maximum length of right-angle pipe trench passing through pipeline

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1558130A (en) * 2004-01-30 2004-12-29 胜利油田胜利石油化工建设有限责任公 Down-ditch construction method for laying heavy caliber pipeline
RU2477410C1 (en) * 2011-11-10 2013-03-10 Федеральное государственное бюджетное образовательное учреждение высшего профессионального образования "Санкт-Петербургский государственный горный университет" Method of pipeline laying in highlands rocks
CN103527846A (en) * 2012-12-31 2014-01-22 洛阳新奥华油燃气有限公司 Technology for conveying and storing gas by using phi1219/phi1016 natural gas pipeline

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0913357A (en) * 1995-06-27 1997-01-14 Nkk Corp Backfill method of buried article

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1558130A (en) * 2004-01-30 2004-12-29 胜利油田胜利石油化工建设有限责任公 Down-ditch construction method for laying heavy caliber pipeline
RU2477410C1 (en) * 2011-11-10 2013-03-10 Федеральное государственное бюджетное образовательное учреждение высшего профессионального образования "Санкт-Петербургский государственный горный университет" Method of pipeline laying in highlands rocks
CN103527846A (en) * 2012-12-31 2014-01-22 洛阳新奥华油燃气有限公司 Technology for conveying and storing gas by using phi1219/phi1016 natural gas pipeline

Also Published As

Publication number Publication date
CN104948833A (en) 2015-09-30

Similar Documents

Publication Publication Date Title
WO2016045440A1 (en) Mining method
CN104948833B (en) Mountainous region gas pipeline construction method
CN109736827B (en) Method for excavating urban subway hard rock stratum communication channel by high-pressure gas expansion fracturing
CN107859145A (en) A kind of drainpipe is plugged into construction method under water
CN107119624A (en) The countermeasure system and implementation of large-scale Dumping Sites in a kind of debris flow gully
CN105649000A (en) Back pressure backfilling shallow-buried excavation construction method for tunnel undercrossing gully
CN113832958A (en) Anti-slide pile construction method with mechanical cooperation with manual excavation
WO2022233162A1 (en) Waste slag field surface water infiltration, guiding, drainage and integral reinforcement structure and construction method
CN114875857A (en) Device and method suitable for comprehensive treatment of debris flow after burning of traces of land
CN107938680A (en) A kind of excavation of foundation pit safe construction method
CN207228038U (en) The countermeasure system of large-scale Dumping Sites in a kind of debris flow gully
CN105387273A (en) Method for constructing natural gas pipelines in mountain environment
CN107217674A (en) Cubic meter of stone foundation ditch enters rock non-explosive excavation construction method
CN110029632A (en) A kind of storage of general industrial solid waste, disposition field structure and its construction method
CN110093939B (en) Ecological restoration method for mining area side slope
CN106381878A (en) Environment-friendly dismantling construction method for two-layer steel sheet pile and soil core composite cofferdam
CN106761800A (en) Support System in Soft Rock Tunnels excavation construction process
CN113338924B (en) Control method for surface subsidence range by natural caving method
CN106012972A (en) High dam bank slope safety protection facility layout construction method
CN111719575A (en) Foundation pit anti-settling drainage method
CN112267452A (en) Method for repairing over-mined mine by using geosynthetic material
CN107326929A (en) A kind of method of Duo Cang undergrounds integrated pipe earth excavation under Larsen steel sheet pile supporting
El-Ashaal et al. Rehabilitation and upgrading of a zoned fill dike
SU1765400A1 (en) Method at sail mass reclamation during preparation of quarry sanitary-protection zone
CN108759598A (en) A kind of bench blasting for protecting lateral slungshot cooperates with construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address

Address after: No.162 Weifang Road, China (Shanghai) pilot Free Trade Zone, Pudong New Area, Shanghai, 200122

Patentee after: Shanghai Energy Construction Group Co.,Ltd.

Address before: 200122 No. 162, Weifang Road, Shanghai, Pudong New Area

Patentee before: SHANGHAI MUNICIPAL GAS NO.2 PIPELINES ENGINEERING Co.,Ltd.

CP03 Change of name, title or address