CN106761800A - Support System in Soft Rock Tunnels excavation construction process - Google Patents

Support System in Soft Rock Tunnels excavation construction process Download PDF

Info

Publication number
CN106761800A
CN106761800A CN201611217070.8A CN201611217070A CN106761800A CN 106761800 A CN106761800 A CN 106761800A CN 201611217070 A CN201611217070 A CN 201611217070A CN 106761800 A CN106761800 A CN 106761800A
Authority
CN
China
Prior art keywords
face
blade
excavator
excavated
excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611217070.8A
Other languages
Chinese (zh)
Inventor
周纪卫
张兴春
张继平
李金永
周卫霞
伞志丰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
Original Assignee
First Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd filed Critical First Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
Priority to CN201611217070.8A priority Critical patent/CN106761800A/en
Publication of CN106761800A publication Critical patent/CN106761800A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/10Making by using boring or cutting machines
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F5/00Dredgers or soil-shifting machines for special purposes
    • E02F5/16Machines for digging other holes in the soil
    • E02F5/18Machines for digging other holes in the soil for horizontal holes or inclined holes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/28Small metalwork for digging elements, e.g. teeth scraper bits
    • E02F9/2883Wear elements for buckets or implements in general
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/04Driving tunnels or galleries through loose materials; Apparatus therefor not otherwise provided for

Abstract

The present invention relates to a kind of Support System in Soft Rock Tunnels excavation construction process.It is mainly big to country rock disturbance to solve current tunnel excavation, invent the problems such as damaged to preliminary bracing.It is carried out according to the following steps:Contour line point position is being released on the steelframe of face;Slot is welded in excavator-type shovel clamshell excavator both sides, steel plate is inserted in slot as blade, first dig the softer side of country rock, the side blade is installed, excavated in face with blade, another side blade is installed, the side face is excavated;Loading machine carries out excavation operation using blade when face is filled and is cut in face opposite side;When both sides are excavated to complete, carry out face middle part and excavate, operation is excavated in left or right side of the excavator in the middle part of face;Top contour line is repaired using bucket, left and right footing is repaired using the bucket tooth of excavator;Preliminary bracing is carried out, closing cyclization is carried out to country rock;Carry out the excavation construction of subsequent cycle.Advantage is small to country rock disturbance, will not destroy preliminary bracing.

Description

Support System in Soft Rock Tunnels excavation construction process
Technical field:
The present invention relates to tunnel excavation construction technology, more particularly to a kind of Support System in Soft Rock Tunnels excavation construction process.
Background technology:
Tunnel excavation method is generally divided into three kinds:Drilling and blasting method is excavated, mechanical equivalent of light excavation, hand excavation, except special geology is using artificial Excavate or manually with machinery to be combined excavation outer, generally excavated and mechanical equivalent of light excavation using drilling and blasting method.Excavated between drilling and blasting method and machine Soft rock between tool excavation, is often excavated using drilling and blasting method.The shortcoming of drilling and blasting method is big to the disturbance of country rock, and often because Explosion influences rock stability, causes disaster;In addition, blast working out break situation is difficult to control to, the duration is not only influenceed but also has caused Economic waste;There is explosion to produce pernicious gas again, be unfavorable for the improvement of tunnel construction environment.Using mechanical equivalent of light excavation, for dead-soft Rock mass effect is preferable, not only quick but also safety, but when having exceeded its allowed band to rock mass strength, efficiency of construction is low, influence The principal element of mechanical efficiency is exactly two aspects of area of length and bucket tooth with scar of bucket bucket tooth.In addition, using bucket When excavating vault, preliminary bracing that can be good to supporting is damaged.Therefore, a kind of disturbance that can reduce to country rock is studied, Energy safety, the method for rapid construction, very necessary again.
The content of the invention:
The technical problems to be solved by the invention are to provide one kind can meet Support System in Soft Rock Tunnels excavation construction, be greatly enhanced Support System in Soft Rock Tunnels excavation construction speed, disturbance when both having reduced excavation to country rock, the weakness that excavation quality is improve again is enclosed Rock tunnel excavation construction technology.
The object of the present invention is achieved like this:
Support System in Soft Rock Tunnels excavation construction process, is carried out according to the following steps:
First, preparation of construction:
Observation face country rock situation determines first to excavate which side;
2nd, surveying setting-out:
Release contour line point position on the steelframe of face in upper one circulation, and each point position of telling somebody what one's real intentions are super condition of owing a debt of gratitude;
The 3rd, left or right side blade is installed:
In each welding blade slot in excavator-type shovel clamshell excavator both sides, it is inserted in as blade using steel plate and replaces original bucket tooth in slot, is applied In man-hour, excavated using unilateral blade, first excavating left side or right side, to depend primarily on face left and right sides rock mass soft or hard Degree, first digs the softer side of country rock, installs the side blade, and such efficiency of construction is very high, can quickly give loading machine dress quarrel wound Make condition, parallel operations;
4th, blade excavates face left or right side:
A period of time first is excavated in face left or right side using blade, certain quarrel body is produced, is that loading machine dress quarrel creates bar Part;
The 5th, right or left side blade is installed:
Upper right or left side blade, mobile excavator to the face right side or left side are installed;
6th, blade excavates the face right side or left side:
Loading machine carries out excavation operation using blade when face left or right side fills and is cut on the face right side or left side, at this moment digs Pick machine and loading machine operation simultaneously;
When excavator is excavated close to left or right side wheel profile, observed, measured and contour line deviation using steel ruler if necessary, Whether both sides digging distance is identical, and adjusts in time;
7th, blade excavates face middle part:
When the left and right sides is excavated to be basically completed, carry out face middle part and excavate, at this moment both sides free face has been formed, excavator Operation is excavated in left or right side that will be in the middle part of face, and the body that is cut is placed on the position that can make loading machine parallel operations;
8th, top is repaired using bucket:
Large area quarrel body has been transported to spoil disposal area outside hole, and top contour line is repaired using bucket, now, priority control out break, Stand bottom observation vault whether out break, there is the collimation error, to borrow excavator and rise to vault, observe concrete condition;
9th, left and right footing is repaired using the bucket tooth of excavator:
After arch finishing is finished, the finishing of left and right footing is carried out;
Tenth, excavation contour line measurement detection, finishing:
Detect excavation contour line using instrument, such as deviation is larger, it is necessary to usage mining machine does up, such as deviation meet specification will Ask, into next process construction;
11, preliminary bracing is carried out:
Preliminary bracing is carried out, closing cyclization is carried out to country rock;
12, the excavation construction of subsequent cycle is carried out:
When upper one circulation construction is completed, preliminary bracing is completed, and carries out the excavation construction of subsequent cycle.
It is an advantage of the invention that:By the transformation of the way to excavator-type shovel clamshell excavator and left and right alternately excavate, blade reduce with Contact area between scar, increases pressure.Increase blade lengths, be more easy to go deep into inside country rock, substantially increase operating efficiency. The angle of blade is adjusted by bucket, destruction of the bucket back to the good steelframe of supporting when can avoid excavating vault with bucket tooth.
This method is particularly suitable for weak surrounding rock excavation construction, and speed of application is fast, reduces resource input, reduces and is constructed into This, while having prevented that the loss that disaster is brought may occur because of explosion, prevents explosion and produces toxic gas and flue dust, saves big Type equipment investment, effectively reduces the pollution to environment.
Specific embodiment:
Support System in Soft Rock Tunnels excavation construction process, is carried out according to the following steps:
First, preparation of construction:
Observation face country rock situation determines first to excavate which side;
2nd, surveying setting-out:
Release contour line point position on the steelframe of face in upper one circulation, and each point position of telling somebody what one's real intentions are super condition of owing a debt of gratitude;
3rd, install left(It is right)Side blade:
In each welding blade slot in excavator-type shovel clamshell excavator both sides, it is inserted in as blade by the use of steel plate and replaces original bucket tooth in slot, is applied In man-hour, excavated using unilateral blade, first excavating left side or right side, to depend primarily on face left and right sides rock mass soft or hard Degree, first digs the softer side of country rock, installs the side blade, quickly can so be created conditions to loading machine dress quarrel, parallel work Industry;
4th, blade excavates a face left side(It is right)Side:
It is first left in face using blade(It is right)A period of time is excavated in side, produces certain quarrel body, is that loading machine dress quarrel creates bar Part;
5th, install right(It is left)Side blade:
Install upper right(It is left)The blade of side, mobile excavator is right to face(It is left)Side;
6th, blade excavates the face right side(It is left)Side:
Loading machine is left in face(It is right)It is right in face using blade during the dress quarrel of side(It is left)Side carries out excavation operation, at this moment digs Pick machine and loading machine operation simultaneously;
When excavator is excavated close to a left side(It is right)During side wheel profile, observed, measured and contour line deviation using steel ruler if necessary, Whether both sides digging distance is identical, and adjusts in time;
7th, blade excavates face middle part:
When the left and right sides is excavated to be basically completed, carry out face middle part and excavate, at this moment both sides free face has been formed, excavator Left side that will be in the middle part of face(It is right)Operation is excavated in side, and the body that is cut is placed on the position that can make loading machine parallel operations;
8th, top is repaired using bucket:
Large area quarrel body has been transported to spoil disposal area outside hole, and top contour line is repaired using bucket, now, priority control out break, Stand bottom observation vault whether out break, there is the collimation error, to borrow excavator and rise to vault, observe concrete condition;
9th, left and right footing is repaired using the bucket tooth of excavator:
After arch finishing is finished, the finishing of left and right footing is carried out;
Tenth, excavation contour line measurement detection, finishing:
Detect excavation contour line using instrument, such as deviation is larger, it is necessary to usage mining machine does up, such as deviation meet specification will Ask, into next process construction;
11, preliminary bracing is carried out:
Preliminary bracing is carried out, closing cyclization is carried out to country rock;
12, the excavation construction of subsequent cycle is carried out:
When upper one circulation construction is completed, preliminary bracing is completed, and carries out the excavation construction of subsequent cycle.
Use the technology, it is to avoid backbreaking caused by explosion, reduce resource input, accelerate construction speed, reduce Construction cost, while having prevented that the loss that disaster is brought may occur because of explosion, saves 4 sets of large scale equipment;Prevent quick-fried Bankruptcy raw toxic gas and flue dust, reduce the discharge of pernicious gas, decrease waste gas, waste material of equipment generation etc. to ring The pollution in border, while also a saving substantial amounts of electric power resource;Construction speed rapid growth is realized, duration pressure is slow down, dropped The low security incident produced by unfavorable geology, achieves good economic and social benefit.

Claims (1)

1. Support System in Soft Rock Tunnels excavation construction process, it is characterized in that:Carry out according to the following steps:
First, preparation of construction:
Observation face country rock situation determines first to excavate which side;
2nd, surveying setting-out:
Release contour line point position on the steelframe of face in upper one circulation, and each point position of telling somebody what one's real intentions are super condition of owing a debt of gratitude;
The 3rd, left or right side blade is installed:
In each welding blade slot in excavator-type shovel clamshell excavator both sides, it is inserted in as blade using steel plate and replaces original bucket tooth in slot, is applied In man-hour, excavated using unilateral blade, first excavating left side or right side, to depend primarily on face left and right sides rock mass soft or hard Degree, first digs the softer side of country rock, installs the side blade;
4th, blade excavates face left or right side:
A period of time first is excavated in face left or right side using blade, certain quarrel body is produced, is that loading machine dress quarrel creates bar Part;
The 5th, right or left side blade is installed:
Upper right or left side blade, mobile excavator to the face right side or left side are installed;
6th, blade excavates the face right side or left side:
Loading machine carries out excavation operation using blade when face left or right side fills and is cut on the face right side or left side, at this moment digs Pick machine and loading machine operation simultaneously;
When excavator is excavated close to left or right side wheel profile, observed, measured and contour line deviation using steel ruler if necessary, Whether both sides digging distance is identical, and adjusts in time;
7th, blade excavates face middle part:
When the left and right sides is excavated to be basically completed, carry out face middle part and excavate, at this moment both sides free face has been formed, excavator Operation is excavated in left or right side that will be in the middle part of face, and the body that is cut is placed on the position that can make loading machine parallel operations;
8th, top is repaired using bucket:
Large area quarrel body has been transported to spoil disposal area outside hole, and top contour line is repaired using bucket, now, priority control out break, Stand bottom observation vault whether out break, there is the collimation error, to borrow excavator and rise to vault, observe concrete condition;
9th, left and right footing is repaired using the bucket tooth of excavator:
After arch finishing is finished, the finishing of left and right footing is carried out;
Tenth, excavation contour line measurement detection, finishing:
Detect excavation contour line using instrument, such as deviation is larger, it is necessary to usage mining machine does up, such as deviation meet specification will Ask, into next process construction;
11, preliminary bracing is carried out:
Preliminary bracing is carried out, closing cyclization is carried out to country rock;
12, the excavation construction of subsequent cycle is carried out:
When upper one circulation construction is completed, preliminary bracing is completed, and carries out the excavation construction of subsequent cycle.
CN201611217070.8A 2016-12-26 2016-12-26 Support System in Soft Rock Tunnels excavation construction process Pending CN106761800A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611217070.8A CN106761800A (en) 2016-12-26 2016-12-26 Support System in Soft Rock Tunnels excavation construction process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611217070.8A CN106761800A (en) 2016-12-26 2016-12-26 Support System in Soft Rock Tunnels excavation construction process

Publications (1)

Publication Number Publication Date
CN106761800A true CN106761800A (en) 2017-05-31

Family

ID=58925913

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611217070.8A Pending CN106761800A (en) 2016-12-26 2016-12-26 Support System in Soft Rock Tunnels excavation construction process

Country Status (1)

Country Link
CN (1) CN106761800A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111022062A (en) * 2019-12-06 2020-04-17 首钢滦南马城矿业有限责任公司 Construction method for clay layer section of ramp
CN111734421A (en) * 2020-07-09 2020-10-02 中国铁建重工集团股份有限公司 Drilling and splitting excavation construction method
CN114412495A (en) * 2022-02-07 2022-04-29 石家庄铁道大学 Novel peripheral meticulous excavation in weak surrounding rock tunnel device

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11270271A (en) * 1998-03-26 1999-10-05 Shimizu Corp Tunnel excavation method
CN202250096U (en) * 2011-08-05 2012-05-30 中铁十局集团西北工程有限公司 Bucket of tunnel excavator
CN103422865A (en) * 2013-08-16 2013-12-04 中铁二十一局集团有限公司 Tunnel excavation plastic cutter and tunnel arc-shaped excavation method for weak surrounding rock section
CN105065006A (en) * 2015-08-26 2015-11-18 中冶建工集团有限公司 Bucket and excavator
CN205189872U (en) * 2015-11-18 2016-04-27 中交一公局厦门工程有限公司 Instrument of regional cubic metre of earth of machine excavation tunnel steel bow member is dug in cooperation

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11270271A (en) * 1998-03-26 1999-10-05 Shimizu Corp Tunnel excavation method
CN202250096U (en) * 2011-08-05 2012-05-30 中铁十局集团西北工程有限公司 Bucket of tunnel excavator
CN103422865A (en) * 2013-08-16 2013-12-04 中铁二十一局集团有限公司 Tunnel excavation plastic cutter and tunnel arc-shaped excavation method for weak surrounding rock section
CN105065006A (en) * 2015-08-26 2015-11-18 中冶建工集团有限公司 Bucket and excavator
CN205189872U (en) * 2015-11-18 2016-04-27 中交一公局厦门工程有限公司 Instrument of regional cubic metre of earth of machine excavation tunnel steel bow member is dug in cooperation

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
宋延波: "胡麻岭隧道泥岩段改制机具施工技术", 《现代隧道技术》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111022062A (en) * 2019-12-06 2020-04-17 首钢滦南马城矿业有限责任公司 Construction method for clay layer section of ramp
CN111022062B (en) * 2019-12-06 2022-09-16 首钢滦南马城矿业有限责任公司 Construction method for clay layer section of ramp
CN111734421A (en) * 2020-07-09 2020-10-02 中国铁建重工集团股份有限公司 Drilling and splitting excavation construction method
CN111734421B (en) * 2020-07-09 2022-04-05 中国铁建重工集团股份有限公司 Drilling and splitting excavation construction method
CN114412495A (en) * 2022-02-07 2022-04-29 石家庄铁道大学 Novel peripheral meticulous excavation in weak surrounding rock tunnel device
CN114412495B (en) * 2022-02-07 2022-12-16 石家庄铁道大学 Novel peripheral meticulous excavation of weak country rock tunnel device

Similar Documents

Publication Publication Date Title
CN102182472B (en) Backfill repairing method for tunnel collapse cavity
CN103321644B (en) The method of tunneling is combined in machinery and controlled blasting
CN107842368B (en) City tunnel Drilling mills the non-quick-fried excavation technology of mechanical combination
CN103291308B (en) For boom-type roadheader and the method for tunnel construction of constructing tunnel
CN106246201A (en) The excavation in tunnel and karst cave treatment method when small-sized solution cavity is positioned at tunneling surrounding
CN101915105B (en) United method for tunneling super-strong or strong rock burst hole section of TBM construction tunnel
CN103899318B (en) The milling of medium ground tunnel is dug and supporting machinery construction
CN103643958B (en) Hydraulic breaking hammer excavation Modelling of Tunnel Excavation in Soft Rock method
CN106121675A (en) Small-sized solution cavity is positioned at tunnel excavation and karst cave treatment method time at the bottom of tunneling inverted arch
CN110924958B (en) Method for treating main tunnel door closing collapse by using service tunnel
CN106761800A (en) Support System in Soft Rock Tunnels excavation construction process
CN109989405A (en) Base pit stand construction under boulder site condition
CN102383813A (en) Construction method for ultralong loess accumulative roc tunnel
CN107489433A (en) A kind of tunnel CRD engineering methods anti-leakage structure and Antiseep method
CN104141500B (en) One hardens sand and gravel stratum cavern con struction method
CN106121659A (en) The narrow-bore tunnel excavation method of major urban arterial highway upper-soft lower-hard ground is worn under one
WO2019109602A1 (en) Short-face coal-pillar-free mining method having zero gangue discharge
CN204099720U (en) The protective housing that under soil stone combination geological condition, artificial pipe jacking construction method is used
CN110158609A (en) A kind of mechanization demolition reduction method of reinforced concrete brace in foundation pit
CN105065004B (en) A kind of Shallow Large Span rock tunnel Portal Section weak blast excavation construction method
CN105065006A (en) Bucket and excavator
CN107524124A (en) A kind of Pumped Storage Plant Underground Powerhouse Rock Crane Rail Support position excavation construction method
CN104315251B (en) Artificial pipe jacking construction method under soil stone combination geological conditions
CN109594995A (en) A kind of Support System in Soft Rock Tunnels micro-disturbance machinery branch driving engineering method
CN110030001A (en) A kind of construction method that mountain tunnel is appeared

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170531