CN104947926A - 一种核心筒内筒上部模架体系硬防护装置及其施工方法 - Google Patents

一种核心筒内筒上部模架体系硬防护装置及其施工方法 Download PDF

Info

Publication number
CN104947926A
CN104947926A CN201510376127.8A CN201510376127A CN104947926A CN 104947926 A CN104947926 A CN 104947926A CN 201510376127 A CN201510376127 A CN 201510376127A CN 104947926 A CN104947926 A CN 104947926A
Authority
CN
China
Prior art keywords
hard protection
construction
walls structure
structure inner
inner core
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510376127.8A
Other languages
English (en)
Other versions
CN104947926B (zh
Inventor
李彦贺
周予启
薛刚
贺茂军
姚富成
王鸿章
孙若晖
赵越
来交交
魏健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction First Group Corp Ltd
China Construction First Group Construction and Development Co Ltd
Original Assignee
China Construction First Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction First Group Corp Ltd filed Critical China Construction First Group Corp Ltd
Priority to CN201510376127.8A priority Critical patent/CN104947926B/zh
Publication of CN104947926A publication Critical patent/CN104947926A/zh
Application granted granted Critical
Publication of CN104947926B publication Critical patent/CN104947926B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

本发明公开了一种核心筒内筒上部模架体系硬防护装置及施工方法,包括核心筒内筒,所述核心筒内筒设置有模架施工预埋装置,所述模架施工预埋装置上固定有钢牛腿,所述钢牛腿上设置有提升葫芦,所述提升葫芦上设置有起吊钢丝绳,所述起吊钢丝绳的下端连接有硬防护施工平台,所述硬防护施工平台上搭设有操作脚手架,利用核心筒内筒上部模架体系施工时的模架施工预埋装置固定钢牛腿,再将硬防护施工平台固定在钢牛腿上,在核心筒墙体先行施工时,硬防护施工平台可以在提升葫芦的带动之下、随其下部核心筒楼板作业面自行爬升,确保爬模底部作业面的安全施工,提高了工效。

Description

一种核心筒内筒上部模架体系硬防护装置及其施工方法
技术领域
本发明涉及一种,尤其适用于核心筒内筒上部模架体系下方硬防护装置及其施工方法。
背景技术
在当前超高层施工过程中,核心筒墙体则多采用自爬升模板施工的方式,其中,自爬升模板是依附在已经完成的核心筒墙体上,随着核心筒施工而逐层上升的一种模板体系,当混凝土达到拆模强度而脱模后,模板不落地,依靠机械设备和支承物将模板和爬模装置向上爬升一层,定位紧固,反复循环施工。
为了最大限度地挖掘关键线路的潜力,科学利用工作面,多数采用核心筒墙体先行,核心筒内梁板及外框楼板紧跟其后施工的施工部署,但其存在的安全问题在于:由于核心筒墙体先行,尤其是核心筒模架体系爬升时,平台防坠坠翻板需要打开,这阶段无法完全避免核心筒模架平台上的小块物料发生坠物现象,下部核心筒梁板硬防护施工平台存在极大的安全隐患,同时工效降低,不利于工期的保障。
发明内容
本发明的目的在于:针对上述不足之处,提供一种确保超高层建筑核心筒内部钢构件及材料的吊运、安装、施工效率,同时施工安全、避免核心筒内发生坠物现象发生的核心筒内筒上部模架体系硬防护装置及其施工方法。
为了实现上述发明目的,本发明提供了以下技术方案:
一种核心筒内筒上部模架体系硬防护装置,包括核心筒内筒,所述核心筒内筒设置有模架施工预埋装置,所述模架施工预埋装置上固定有钢牛腿,所述钢牛腿上设置有提升葫芦,所述提升葫芦上设置有起吊钢丝绳,所述起吊钢丝绳的下端连接有硬防护施工平台,所述硬防护施工平台上搭设有操作脚手架。
优选的,所述模架施工预埋装置为预埋件或预埋点,所述核心筒内筒对置的两个筒壁上四个角部各设置有至少一个模架施工预埋装置。
优选的,所述硬防护施工平台包括至少两根主梁,各主梁的两端分别搭接于提升葫芦下方的两个模架施工预埋装置上,所述主梁的上方还搭接有若干根次梁,所述次梁与主梁相互垂直,所述次梁搭接于主梁上。
优选的,所述次梁的上方设置有若干根相互平行的操作架支撑钢管,所述操作架支撑钢管平行于主梁设置,所述次梁的上方还设置有钢管剪刀撑。
优选的,所述硬防护施工平台在设置有模架施工预埋装置的两侧设置有用于钢牛腿和提升葫芦安装操作的挂座安装脚手架,所述挂座安装脚手架的顶部高于其上方的模架施工预埋装置,所述硬防护施工平台的另外两侧设置有用于核心筒内筒壁预埋水平结构钢筋提前剃凿施工的脚手架。
优选的,所述钢牛腿和主梁上均设置有至少三个钢丝绳卡扣,所述起吊钢丝绳的两端通过钢丝绳卡扣与钢牛腿和主梁连接。
优选的,所述模架施工预埋装置包括爬锥,所述钢牛腿包括垂直于爬锥核心筒内筒筒壁设置的两个第一槽钢,所述两个第一槽钢开口相背设置,各第一槽钢的下方设置有斜撑槽钢,所述两个第一槽钢之间设置有第一钢筋和第二钢筋,所述第一钢筋穿过第一槽钢的腹板并与腹板相互焊接固定,所述第二钢筋与两个第一槽钢的上翼缘相互焊接固定。
一种上述核心筒内筒上部模架体系硬硬防护施工平台的施工方法,包括以下几个步骤:
步骤a、以模架施工的方法完成核心筒内筒的墙体施工,所述模架施工时在核心筒内筒的墙体上设置有模架施工预埋装置。
步骤b、在核心筒内筒中搭建硬防护施工平台,所述硬防护施工平台位于待剃凿施工的墙体的下部。
步骤c、作业人员通过所述硬防护施工平台安装钢牛腿,所述钢牛腿设置于待剃凿施工的墙体上方的模架施工预埋装置上。
步骤d、在钢牛腿上设置提升葫芦,并将提升葫芦的起吊钢丝绳与硬防护施工平台连接。
步骤e、作业人员通过所述硬防护施工平台对核心筒内筒墙体上预埋的钢筋进行剃凿施工。
步骤f、通过提升葫芦将硬防护施工平台提升至下一个待剃凿施工的墙体的下部。
步骤g、重复步骤c至步骤f,直至完成核心筒内筒所有墙体上预埋的钢筋的剃凿施工。
优选的,所述步骤c中,完成一个墙体的剃凿施工后,将该墙体下部的钢牛腿拆卸,通过硬防护施工平台随提升葫芦转运至下一个待剃凿施工的墙体并进行安装。
由于采用了上述技术方案,本发明的有益效果是:利用核心筒内筒上部模架体系施工时的模架施工预埋装置作为受力点固定钢牛腿,并通过设置于钢牛腿上的电动葫芦整体提升硬防护施工平台、实现自爬升,不仅能够通过硬防护施工平台确保爬模底部作业面的安全施工,施工人员还可以在硬防护施工平台上提前剔凿先前预留、预埋在墙体里的钢筋,提高了工效;另外,在核心筒墙体先行施工时,硬防护施工平台可以在提升葫芦的带动之下、随其下部核心筒楼板作业面自行爬升,进一步提升了核心筒内部钢构件及材料吊运、安装的施工效率。
附图说明
图1为本发明中硬防护施工平台的平面示意图;
图2为本发明中硬防护施工平台的钢管布置示意图;
图3为本发明中硬防护施工平台的操作架平面布置示意图;
图4为本发明中硬防护施工平台及操作架的立面示意图;
图5为本发明中提升葫芦挂点处拉结详图;
图6为本发明中用于提升葫芦挂点的节点结构示意图;
图7为图6的侧视图。
图中标记:核心筒内筒—1;模架施工预埋装置—2;钢牛腿—3;起吊钢丝绳—4;硬防护施工平台—5;主梁—5a;次梁—5b;支撑钢管—5c;钢管剪刀撑—5d;挂座安装脚手架—6;脚手架—7;第一槽钢—8;斜撑槽钢—9;待剃凿施工的墙体—10;爬锥—11。
具体实施方式
下面结合试验例及具体实施方式对本发明作进一步的详细描述。但不应将此理解为本发明上述主题的范围仅限于以下的实施例,凡基于本发明内容所实现的技术均属于本发明的范围。
如图1至图6所示,本实施例核心筒内筒上部模架体系硬防护装置,包括核心筒内筒1,核心筒内筒1设置有模架施工预埋装置2,模架施工预埋装置2上固定有钢牛腿3,钢牛腿3上设置有提升葫芦,提升葫芦上设置有起吊钢丝绳4,起吊钢丝绳4的下端连接有硬防护施工平台5,在整个平台提升以及固定过程中,主梁5a与钢牛腿3间设置的钢丝绳固定作为保险绳,硬防护施工平台5上搭设有操作脚手架,本实施例模架施工预埋装置2为预埋件或预埋点,核心筒内筒1对置的两个筒壁上各设置有至少一个模架施工预埋装置2,硬防护施工平台5可以随着核心筒楼板作业面向上自爬升,不仅为核心筒模架体系下部提供了安全的施工作业面,而且作业人员可以在该硬防护上提前剔凿预留预埋在墙体里的梁板钢筋,核心筒墙体和核心筒梁板可以同步安全施工,互不影响,每层可提前0.5-1天工期,大大提高了工效,有利于施工工期。
具体如图2和图3所示,本实施例中,硬防护施工平台5采用工字钢、钢管、钢跳板相结合的体系,施工时利用原先模架施工时的预埋点、即:模架施工预埋装置2,固定一个钢牛腿3,通过钢丝绳将硬防护固定在钢牛腿3上,提升时采用电动葫芦提升硬防护至上一层钢牛腿3上,具体的,本实施例中在硬防护施工平台5包括至少两根主梁5a,各主梁5a的两端分别搭接于提升葫芦下方的两个模架施工预埋装置2上,主梁5a的上方还搭接有若干根次梁5b,次梁5b与主梁5a相互垂直,次梁5b搭接于主梁5a上,次梁5b的上方设置有若干根相互平行的操作架支撑钢管5c,操作架支撑钢管5c平行于主梁5a设置,次梁5b的上方还设置有钢管剪刀撑5d,本实施例中,为了防止施工人员剔凿施工时硬防护施工平台5晃动,硬防护施工平台5的各个角上均设置有两个U型托,所述U型托支撑在核心筒内筒1的墙体上。
如图4、图5所示,本实施例在设置有模架施工预埋装置2的两侧设置有用于钢牛腿3和提升葫芦安装操作的挂座安装脚手架6,挂座安装脚手架6的顶部高于其上方的模架施工预埋装置2,硬防护施工平台5的另外两侧设置有用于核心筒内筒壁预埋水平结构钢筋提前剃凿施工的脚手架7,钢牛腿3和主梁5a上均设置有至少三个钢丝绳卡扣,起吊钢丝绳4的两端通过钢丝绳卡扣与钢牛腿3和主梁5a连接。
如图6、图7所示,本实施例中模架施工预埋装置2包括爬锥11,钢牛腿3包括垂直于爬锥11核心筒内筒1筒壁设置的两个第一槽钢8,两个第一槽钢8开口相背设置,各第一槽钢8的下方设置有斜撑槽钢9,两个第一槽钢8之间设置有第一钢筋和第二钢筋,第一钢筋穿过第一槽钢8的腹板并与腹板相互焊接固定,第二钢筋与两个第一槽钢8的上翼缘相互焊接固定。
上述核心筒内筒1上部模架体系硬硬防护施工平台5的施工方法,包括以下几个步骤:
步骤a、以模架施工的方法完成核心筒内筒1的墙体施工,模架施工时在核心筒内筒1的墙体上设置有模架施工预埋装置2。
步骤b、在核心筒内筒1中搭建硬防护施工平台5,硬防护施工平台5位于待剃凿施工的墙体10的下部。
步骤c、作业人员通过硬防护施工平台5安装钢牛腿3,钢牛腿3设置于待剃凿施工的墙体10上方的模架施工预埋装置2上。
步骤d、在钢牛腿3上设置提升葫芦,并将提升葫芦的起吊钢丝绳4与硬防护施工平台5连接。
步骤e、作业人员通过硬防护施工平台5对核心筒内筒1墙体上预埋的钢筋进行剃凿施工。
步骤f、通过提升葫芦将硬防护施工平台5提升至下一个待剃凿施工的墙体10的下部。
步骤g、重复步骤c至步骤f,直至完成核心筒内筒1所有墙体上预埋的钢筋的剃凿施工。
优选的,步骤c中,完成一个墙体的剃凿施工后,将该墙体下部的钢牛腿3拆卸,通过硬防护施工平台5随提升葫芦转运至下一个待剃凿施工的墙体10并进行安装。
本发明并不局限于前述的具体实施方式。本发明扩展到任何在本说明书中披露的新特征或任何新的组合,以及披露的任一新的方法或过程的步骤或任何新的组合。

Claims (9)

1.一种核心筒内筒上部模架体系硬防护装置,其特征在于:包括核心筒内筒,所述核心筒内筒设置有模架施工预埋装置,所述模架施工预埋装置上固定有钢牛腿,所述钢牛腿上设置有提升葫芦,所述提升葫芦上设置有起吊钢丝绳,所述起吊钢丝绳的下端连接有硬防护施工平台,所述硬防护施工平台上搭设有操作脚手架。
2.根据权利要求1所述的核心筒内筒上部模架体系硬防护装置,其特征在于:所述模架施工预埋装置为预埋件或预埋点,所述核心筒内筒对置的两个筒壁上各设置有至少一个模架施工预埋装置。
3.根据权利要求1所述的核心筒内筒上部模架体系硬防护装置,其特征在于:所述硬防护施工平台包括至少两根主梁,各主梁的两端分别搭接于提升葫芦下方的两个模架施工预埋装置上,所述主梁的上方还搭接有若干根次梁,所述次梁与主梁相互垂直,所述次梁搭接于主梁上。
4.根据权利要求3所述的核心筒内筒上部模架体系硬防护装置,其特征在于:所述次梁的上方设置有若干根相互平行的操作架支撑钢管,所述操作架支撑钢管平行于主梁设置,所述次梁的上方还设置有钢管剪刀撑。
5.根据权利要求1至4中任一所述的核心筒内筒上部模架体系硬防护装置,其特征在于:所述硬防护施工平台在设置有模架施工预埋装置的两侧设置有用于钢牛腿和提升葫芦安装操作的挂座安装脚手架,所述挂座安装脚手架的顶部高于其上方的模架施工预埋装置,所述硬防护施工平台的另外两侧设置有用于核心筒内筒壁预埋水平结构钢筋提前剃凿施工的脚手架。
6.根据权利要求5所述的核心筒内筒上部模架体系硬防护装置,其特征在于:所述钢牛腿和主梁上均设置有至少三个钢丝绳卡扣,所述起吊钢丝绳的两端通过钢丝绳卡扣与钢牛腿和主梁连接。
7.根据权利要求6所述的核心筒内筒上部模架体系硬防护装置,其特征在于:所述模架施工预埋装置包括爬锥,所述钢牛腿包括垂直于爬锥核心筒内筒筒壁设置的两个第一槽钢,所述两个第一槽钢开口相背设置,各第一槽钢的下方设置有斜撑槽钢,所述两个第一槽钢之间设置有第一钢筋和第二钢筋,所述第一钢筋穿过第一槽钢的腹板并与腹板相互焊接固定,所述第二钢筋与两个第一槽钢的上翼缘相互焊接固定。
8.一种如权利要求1至7中任一项所述的核心筒内筒上部模架体系硬防护装置的施工方法,包括以下几个步骤:
步骤a、以模架施工的方法完成核心筒内筒的墙体施工,所述模架施工时在核心筒内筒的墙体上设置有模架施工预埋装置;
步骤b、在核心筒内筒中搭建硬防护施工平台,所述硬防护施工平台位于待剃凿施工的墙体的下部;
步骤c、作业人员通过所述硬防护施工平台安装钢牛腿,所述钢牛腿设置于待剃凿施工的墙体上方的模架施工预埋装置上;
步骤d、在钢牛腿上设置提升葫芦,并将提升葫芦的起吊钢丝绳与硬防护施工平台连接;
步骤e、作业人员通过所述硬防护施工平台对核心筒内筒墙体上预埋的钢筋进行剃凿施工;
步骤f、通过提升葫芦将硬防护施工平台提升至下一个待剃凿施工的墙体的下部;
步骤g、重复步骤c至步骤f,直至完成核心筒内筒所有墙体上预埋的钢筋的剃凿施工。
9.如权利要求8所述的核心筒内筒上部模架体系硬硬防护施工平台的施工方法,其特征在于:所述步骤c中,完成一个墙体的剃凿施工后,将该墙体下部的钢牛腿拆卸,通过硬防护施工平台随提升葫芦转运至下一个待剃凿施工的墙体并进行安装。
CN201510376127.8A 2015-07-01 2015-07-01 一种核心筒内筒上部模架体系硬防护装置及其施工方法 Active CN104947926B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510376127.8A CN104947926B (zh) 2015-07-01 2015-07-01 一种核心筒内筒上部模架体系硬防护装置及其施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510376127.8A CN104947926B (zh) 2015-07-01 2015-07-01 一种核心筒内筒上部模架体系硬防护装置及其施工方法

Publications (2)

Publication Number Publication Date
CN104947926A true CN104947926A (zh) 2015-09-30
CN104947926B CN104947926B (zh) 2017-03-01

Family

ID=54162938

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510376127.8A Active CN104947926B (zh) 2015-07-01 2015-07-01 一种核心筒内筒上部模架体系硬防护装置及其施工方法

Country Status (1)

Country Link
CN (1) CN104947926B (zh)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105484484A (zh) * 2015-12-31 2016-04-13 成都市第三建筑工程公司 电梯井移动硬防护操作平台
CN105821977A (zh) * 2016-03-23 2016-08-03 中冶建工集团有限公司 一种超高层建筑核心筒梁柱牛腿结构
CN105822055A (zh) * 2016-05-17 2016-08-03 安徽宝翔建设集团有限责任公司 高层建筑高空连廊施工支架
CN107035156A (zh) * 2017-04-19 2017-08-11 上海建工建集团有限公司 核心筒水平结构自爬式防护平台
CN108589925A (zh) * 2018-05-17 2018-09-28 林再颐 一种超高层建筑核心筒轴结构
CN108678443A (zh) * 2018-05-22 2018-10-19 四川石油天然气建设工程有限责任公司 一种天然气处理厂多维度施工方法和施工系统
CN109057321A (zh) * 2018-11-16 2018-12-21 上海建工集团股份有限公司 整体钢平台模架超大承载力附墙系统及施工方法
CN111502318A (zh) * 2020-05-04 2020-08-07 璐句附 一种建筑内部核心筒施工的防护结构
CN115492387A (zh) * 2022-09-15 2022-12-20 中建八局第一建设有限公司 一种爬模集成式物料吊装系统及其施工方法

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB0516033D0 (en) * 2004-08-25 2005-09-14 Can Internat Ltd Lightweight rope access work platform
GB0520718D0 (en) * 2004-10-13 2005-11-23 Baglin Neil E Buildings roof valley safety unit
CN201695681U (zh) * 2010-07-01 2011-01-05 中建三局建设工程股份有限公司 自升式电梯井整体筒模
CN202090580U (zh) * 2011-05-30 2011-12-28 中国葛洲坝集团股份有限公司 伸缩式操作平台
CN202099992U (zh) * 2011-05-25 2012-01-04 中建七局安装工程有限公司 烟囱钢内筒施工中的措施性装置
CN202359805U (zh) * 2011-11-25 2012-08-01 安徽桑铌科技股份有限公司 威金斯干式气柜的施工平台
CN202810175U (zh) * 2012-07-31 2013-03-20 中天建设集团有限公司天津分公司 筒体结构模板施工跟进平台
CN103243930A (zh) * 2013-04-23 2013-08-14 重庆大学 超高层钢结构模块化施工系统及其方法
CN103556823A (zh) * 2013-10-28 2014-02-05 山西省第二建筑工程公司 筒仓滑膜操作平台作顶盖板模板支撑体系的施工方法
CN104213508A (zh) * 2013-09-02 2014-12-17 中铁十六局集团第一工程有限公司 一种利用横撑和体外索控制塔柱位移的方法
CN204876516U (zh) * 2015-07-01 2015-12-16 中建一局集团建设发展有限公司 一种核心筒内筒上部模架体系硬防护装置

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB0516033D0 (en) * 2004-08-25 2005-09-14 Can Internat Ltd Lightweight rope access work platform
GB0520718D0 (en) * 2004-10-13 2005-11-23 Baglin Neil E Buildings roof valley safety unit
CN201695681U (zh) * 2010-07-01 2011-01-05 中建三局建设工程股份有限公司 自升式电梯井整体筒模
CN202099992U (zh) * 2011-05-25 2012-01-04 中建七局安装工程有限公司 烟囱钢内筒施工中的措施性装置
CN202090580U (zh) * 2011-05-30 2011-12-28 中国葛洲坝集团股份有限公司 伸缩式操作平台
CN202359805U (zh) * 2011-11-25 2012-08-01 安徽桑铌科技股份有限公司 威金斯干式气柜的施工平台
CN202810175U (zh) * 2012-07-31 2013-03-20 中天建设集团有限公司天津分公司 筒体结构模板施工跟进平台
CN103243930A (zh) * 2013-04-23 2013-08-14 重庆大学 超高层钢结构模块化施工系统及其方法
CN104213508A (zh) * 2013-09-02 2014-12-17 中铁十六局集团第一工程有限公司 一种利用横撑和体外索控制塔柱位移的方法
CN103556823A (zh) * 2013-10-28 2014-02-05 山西省第二建筑工程公司 筒仓滑膜操作平台作顶盖板模板支撑体系的施工方法
CN204876516U (zh) * 2015-07-01 2015-12-16 中建一局集团建设发展有限公司 一种核心筒内筒上部模架体系硬防护装置

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105484484A (zh) * 2015-12-31 2016-04-13 成都市第三建筑工程公司 电梯井移动硬防护操作平台
CN105821977A (zh) * 2016-03-23 2016-08-03 中冶建工集团有限公司 一种超高层建筑核心筒梁柱牛腿结构
CN105821977B (zh) * 2016-03-23 2018-01-26 中冶建工集团有限公司 一种超高层建筑核心筒梁柱牛腿结构
CN105822055A (zh) * 2016-05-17 2016-08-03 安徽宝翔建设集团有限责任公司 高层建筑高空连廊施工支架
CN107035156A (zh) * 2017-04-19 2017-08-11 上海建工建集团有限公司 核心筒水平结构自爬式防护平台
CN108589925B (zh) * 2018-05-17 2020-01-07 浙江绿创新拓建筑规划设计有限公司 一种超高层建筑核心筒轴结构
CN108589925A (zh) * 2018-05-17 2018-09-28 林再颐 一种超高层建筑核心筒轴结构
CN108678443A (zh) * 2018-05-22 2018-10-19 四川石油天然气建设工程有限责任公司 一种天然气处理厂多维度施工方法和施工系统
CN108678443B (zh) * 2018-05-22 2020-07-03 四川石油天然气建设工程有限责任公司 一种天然气处理厂多维度施工方法和施工系统
CN109057321A (zh) * 2018-11-16 2018-12-21 上海建工集团股份有限公司 整体钢平台模架超大承载力附墙系统及施工方法
CN109057321B (zh) * 2018-11-16 2019-02-15 上海建工集团股份有限公司 整体钢平台模架超大承载力附墙系统及施工方法
CN111502318A (zh) * 2020-05-04 2020-08-07 璐句附 一种建筑内部核心筒施工的防护结构
CN115492387A (zh) * 2022-09-15 2022-12-20 中建八局第一建设有限公司 一种爬模集成式物料吊装系统及其施工方法
CN115492387B (zh) * 2022-09-15 2023-08-11 中建八局第一建设有限公司 一种爬模集成式物料吊装系统及其施工方法

Also Published As

Publication number Publication date
CN104947926B (zh) 2017-03-01

Similar Documents

Publication Publication Date Title
CN104947926A (zh) 一种核心筒内筒上部模架体系硬防护装置及其施工方法
CN106760529B (zh) 屋盖钢桁架滑移拼装施工平台及安装方法
CN102444203A (zh) 一种高空大跨度悬挑连廊型钢混凝土结构及施工方法
CN105298100B (zh) 一种筒体建筑超高现浇外飘结构悬挑施工平台的施工方法
CN102587659A (zh) 一种以混凝土柱支顶后浇带两侧结构的施工方法
CN103410320B (zh) 圆筒仓柔性平台双筒连滑施工方法
CN103669655A (zh) 变形缝两侧墙体混凝土浇筑施工工艺
CN104631822A (zh) 高层钢筋混凝土电梯井施工方法
CN204876516U (zh) 一种核心筒内筒上部模架体系硬防护装置
CN107246073A (zh) 核心筒纵横结构同步施工结构及方法
CN206692235U (zh) 一种钢结构穹顶起吊安装装置
CN109057321B (zh) 整体钢平台模架超大承载力附墙系统及施工方法
CN109457951A (zh) 收分剪力墙模架系统及其施工方法
CN102337782A (zh) 一种高大空间顶部施工桁架平台提升系统及其施工方法
CN106032704A (zh) 一种以混凝土柱支顶后浇带两侧结构的施工方法
CN108277994B (zh) 上跨高铁营运线安全防护棚快速拆除方法
CN203285050U (zh) 滑模携带升降的组合式贝雷架多功能平台
CN107217831B (zh) 超高层建筑核心筒水平结构施工方法
CN106522541B (zh) 一种钢平台的模板吊点承重梁及模板系统的吊装方法
CN104453228A (zh) 一种大跨度超大截面钢板墙梁施工方法
CN104499706A (zh) 电梯井模板平台及其施工方法
CN209211877U (zh) 爬升钢平台支撑装置
CN104831928B (zh) 高空大跨度混凝土连体结构模板支撑钢平台施工方法
CN109162447A (zh) 爬升钢平台支撑装置及其使用方法
CN210369895U (zh) 一种房建室内超高大模板贝雷梁支撑体系

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Zhou Yuqi

Inventor after: Wei Jian

Inventor after: Li Yanhe

Inventor after: Xue Gang

Inventor after: He Maojun

Inventor after: Yao Fucheng

Inventor after: Wang Hongzhang

Inventor after: Sun Ruohui

Inventor after: Zhao Yue

Inventor after: Lai Jiaojiao

Inventor before: Li Yanhe

Inventor before: Wei Jian

Inventor before: Zhou Yuqi

Inventor before: Xue Gang

Inventor before: He Maojun

Inventor before: Yao Fucheng

Inventor before: Wang Hongzhang

Inventor before: Sun Ruohui

Inventor before: Zhao Yue

Inventor before: Lai Jiaojiao

COR Change of bibliographic data
GR01 Patent grant
GR01 Patent grant