CN104863030A - 一种高原高寒地区路基施工中水草地施工工艺 - Google Patents

一种高原高寒地区路基施工中水草地施工工艺 Download PDF

Info

Publication number
CN104863030A
CN104863030A CN201510255142.7A CN201510255142A CN104863030A CN 104863030 A CN104863030 A CN 104863030A CN 201510255142 A CN201510255142 A CN 201510255142A CN 104863030 A CN104863030 A CN 104863030A
Authority
CN
China
Prior art keywords
gravel
construction
water
meadow
water meadow
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510255142.7A
Other languages
English (en)
Inventor
胡秀军
杨春杰
张毅
解佩星
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
THIRD ENGINEERING Co Ltd OF CCCC SECOND HIGHWAY ENGINEERING BUREAU
Original Assignee
THIRD ENGINEERING Co Ltd OF CCCC SECOND HIGHWAY ENGINEERING BUREAU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by THIRD ENGINEERING Co Ltd OF CCCC SECOND HIGHWAY ENGINEERING BUREAU filed Critical THIRD ENGINEERING Co Ltd OF CCCC SECOND HIGHWAY ENGINEERING BUREAU
Priority to CN201510255142.7A priority Critical patent/CN104863030A/zh
Publication of CN104863030A publication Critical patent/CN104863030A/zh
Pending legal-status Critical Current

Links

Landscapes

  • Road Paving Structures (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

本发明公开了一种高原高寒地区路基施工中水草地施工工艺,包括以下步骤:1)填筑砂砾混合物;2)填筑双侧护坡道;3)对砂砾表面进行多次碾压;4)在填筑混合物的顶部设置一层整体加筋钢塑土工格栅;5)重复步骤1至步骤4,直至填筑完毕,确保水草地基础处理承载力和封水效果满足设计和规范要求,确保路基填筑质量。

Description

一种高原高寒地区路基施工中水草地施工工艺
技术领域
本发明涉及基建领域,特别涉及一种高原高寒地区路基施工中高原高寒地区路基施工中水草地施工工艺。
背景技术
水草地施工工艺,是草皮层下一般存在0.5~1m的腐殖土,其主要是由腐烂的植物以及动物粪便组成的一层混合物,过长时期腐烂发酵后和自然土壤混合而形成的一种特殊土质。由于腐殖土特殊的物理化学特性,决定了其含水率大、有机质含量高、液限及塑性指数大、不易压实的性质,因此,腐殖土层在路基施工中,对填筑及压实质量有着很大影响。
传统路基工艺,一部分采用直接填筑物,对基础没有做处理,容易因地基处理不当出现路基下陷或翻浆、反弹;另外一种对草皮进行开挖换填,后直接填筑,容易对草皮造成破坏,水草地表面的草皮可作为天然的土工格栅材料,能够起到封水和增加承载力的作用。
发明内容
本发明所要解决的技术问题是提供一种高原高寒地区路基施工中高原高寒地区路基施工中水草地施工工艺,根据填筑高度的不同采用不同的施工工艺,确保水草地基础处理承载力和封水效果满足设计和规范要求,确保路基填筑质量,以解决现有技术中导致的上述多项缺陷。
为实现上述目的,本发明提供以下的技术方案:一种水草地施工工艺,其特征在于,包括以下步骤:
1)填筑1.2-1.5m高砂砾、砾石和碎石的混合物;
2)填筑双侧宽度3m、高度1.2-1.5m加宽护坡道;
3)对砂砾表面进行多次碾压;
4)在填筑混合物的顶部设置一层整体加筋钢塑土工格栅;
5)重复步骤1至步骤4,直至填筑完毕。
优选的,所述步骤1)中,当填筑高度小于2.3m,水草地下覆植土深度为0.5~1m,路基填土高度小于2.3m时,对原地面采取超挖换填砂砾处理。
优选的,所述超挖深度为2.6-2.8m。
优选的,所述步骤5)中,再进行下一次填筑之前,加筋钢塑土工格栅的表面铺设一层隔水土工布。
优选的,所述步骤1)中,砂砾、砾石和碎石的重量比为2:3:1。
优选的,所述步骤1)中,砂砾、砾石和碎石的混合物为自上而下的砂砾层、砾石层和碎石层,砂砾层为0.5m高、砾石层为0.3-0.4m高、碎石层为0.3-0.7m高。
采用以上技术方案的有益效果是:通过上述施工工艺,可对水草地段落软基进行有效处理,根据不同的段落实施不同实施工艺,即起到了软基处理的效果,同时可以降低施工成本,提高施工效率。
本发明与传统措施相比:针对不同情况,采取不同的施工工作,做到高效、简便;基础处理效果好,经处理后路基沉降量小,基础稳固,施工质量可靠;有针对性的施工工艺,可以降低施工成本,提高施工效率。
具体实施方式
下面详细说明本发明的优选实施方式。
实施例1:
当填筑高度小于2.3m水草地施工段落,水草地下覆植土深度为0.5~1m,当路基填土高度小于2.3米时,水草地对路基稳定性影响大,对原地面采取超挖换填砂砾处理,超挖深度2.3m,确保路面底基层以下2米范围内填筑砂砾、砾石和碎石的混合物。双侧宽度3m、高度1.5m加宽护坡道同步填筑。然后采用QCY360型冲击碾压设备进行碾压,并采用水准仪进行观测。碾压次数以相邻两遍碾压下沉量小于5cm,并对压实度进行检测合格后,为合格标准进行确定。冲击碾压密实,提高基底承载力,同时为防止路基不均匀沉降,在砂砾顶部设置一层整体加筋钢塑土工格栅,在其表面铺设一层隔水土工布,继续进行填筑。每层填筑厚度需满足设计要求,并进行检测。
实施例2
当填筑高度大于2.3m水草地施工段落。水草地下覆植土深度为0.5~1m。当路基填高大于等于2.3米时,这时,水草地对路基稳定性影响较小,可利用水草地表面的草皮作为天然的土工格栅材料,采取地表不开挖直接填筑1.5米砂砾、砾石和碎石的混合物,双侧宽度3m、高度1.5m加宽护坡道同步填筑。然后采用QCY360型碾压设备进行碾压,并采用水准仪进行观测。碾压次数以相邻两遍碾压下沉量小于5cm,并对压实度进行检测合格后,为合格标准进行确定。冲击碾压密实,提高基底承载力,同时为防止路基不均匀沉降,在砂砾顶部设置一层整体加筋钢塑土工格栅,在其表面铺设一层隔水土工布,继续进行填筑。每层填筑厚度需满足设计要求,并进行检测。
砂砾、砾石和碎石的混合物为重量比为2:3:1的混合物,或者为自上而下的砂砾层、砾石层和碎石层,砂砾层为0.5m高、砾石层为0.4m高、碎石层为0.5m高。
上述施工工艺,可对水草地段落软基进行有效处理,根据不同的段落实施不同实施工艺,即起到了软基处理的效果,同时可以降低施工成本,提高施工效率。
本发明与传统措施相比:针对不同情况,采取不同的施工工作,做到高效、简便;基础处理效果好,经处理后路基沉降量小,基础稳固,施工质量可靠;有针对性的施工工艺,可以降低施工成本,提高施工效率。
以上所述的仅是本发明的优选实施方式,应当指出,对于本领域的普通技术人员来说,在不脱离本发明创造构思的前提下,还可以做出若干变形和改进,这些都属于本发明的保护范围。

Claims (6)

1.一种高原高寒地区路基施工中水草地施工工艺,其特征在于,包括以下步骤:
1)填筑1.2-1.5m高砂砾、砾石和碎石的混合物;
2)填筑双侧宽度3m、高度1.2-1.5m加宽护坡道;
3)对砂砾表面进行多次碾压;
4)在填筑混合物的顶部设置一层整体加筋钢塑土工格栅;
5)重复步骤1至步骤4,直至填筑完毕。
2.根据权利要求1所述的高原高寒地区路基施工中水草地施工工艺,其特征在于,所述步骤1)中,当填筑高度小于2.3m,水草地下覆植土深度为0.5~1m,路基填土高度小于2.3m时,对原地面采取超挖换填砂砾处理。
3.根据权利要求2所述的高原高寒地区路基施工中水草地施工工艺,其特征在于,所述超挖深度为2.6-2.8m。
4.根据权利要求1所述的高原高寒地区路基施工中水草地施工工艺,其特征在于,所述步骤5)中,再进行下一次填筑之前,加筋钢塑土工格栅的表面铺设一层隔水土工布。
5.根据权利要求1所述的高原高寒地区路基施工中水草地施工工艺,其特征在于,所述步骤1)中,砂砾、砾石和碎石的重量比为2:3:1。
6.根据权利要求1所述的高原高寒地区路基施工中水草地施工工艺,其特征在于,所述步骤1)中,砂砾、砾石和碎石的混合物为自上而下的砂砾层、砾石层和碎石层,砂砾层为0.5m高、砾石层为0.3-0.4m高、碎石层为0.3-0.7m高。
CN201510255142.7A 2015-05-19 2015-05-19 一种高原高寒地区路基施工中水草地施工工艺 Pending CN104863030A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510255142.7A CN104863030A (zh) 2015-05-19 2015-05-19 一种高原高寒地区路基施工中水草地施工工艺

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510255142.7A CN104863030A (zh) 2015-05-19 2015-05-19 一种高原高寒地区路基施工中水草地施工工艺

Publications (1)

Publication Number Publication Date
CN104863030A true CN104863030A (zh) 2015-08-26

Family

ID=53909170

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510255142.7A Pending CN104863030A (zh) 2015-05-19 2015-05-19 一种高原高寒地区路基施工中水草地施工工艺

Country Status (1)

Country Link
CN (1) CN104863030A (zh)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006037437A (ja) * 2004-07-26 2006-02-09 Maeda:Kk 彩色固化層を創出する防草及び地盤保護工法
KR20060072856A (ko) * 2004-12-24 2006-06-28 현대건설주식회사 Eps블럭을 이용한 초연약지반의 보강성토 구조
CN201614534U (zh) * 2009-04-08 2010-10-27 中铁二院工程集团有限责任公司 高速铁路短路基构造
CN103556558A (zh) * 2013-10-21 2014-02-05 马银华 路基分层全包的路面构造及其施工方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006037437A (ja) * 2004-07-26 2006-02-09 Maeda:Kk 彩色固化層を創出する防草及び地盤保護工法
KR20060072856A (ko) * 2004-12-24 2006-06-28 현대건설주식회사 Eps블럭을 이용한 초연약지반의 보강성토 구조
CN201614534U (zh) * 2009-04-08 2010-10-27 中铁二院工程集团有限责任公司 高速铁路短路基构造
CN103556558A (zh) * 2013-10-21 2014-02-05 马银华 路基分层全包的路面构造及其施工方法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘文娜: "多年冻土地区特殊路基的处理方法", 《交通建设与管理》 *
张涛,陈凯: "高原冻土地区公路路基设计方案浅析", 《露天采矿技术》 *

Similar Documents

Publication Publication Date Title
CN104088208B (zh) 一种湿软土地基处理方法
CN104358188A (zh) 湿陷性黄土路基填筑施工方法
CN204356594U (zh) 无砟轨道膨胀土路堑-基床构造
CN105569058A (zh) 一种膨胀土路堑结构及其施工方法
CN101634143A (zh) 含软弱粘土地层中的螺旋挤土灌注桩复合地基处理方法
CN106283944B (zh) 压填片石和/或块石加固浅层软基的方法
CN103290836B (zh) 一种真空降压击实固结软基处理施工方法
CN115288162B (zh) 一种软土地基填方边坡的加固方法
CN101598028A (zh) 高速铁路超大断面富水黄土隧道衬砌构造
CN102080381B (zh) 一种变电站边坡滑坡塌方治理方法
CN108166518A (zh) 地下管线基坑与软土地基同步处理的结构及其加固方法
CN110924254A (zh) 一种炭质页岩路基填筑施工工艺
CN103510504B (zh) 高饱和不均匀吹填土地基处理方法
CN110144783A (zh) 一种路基施工方法
CN101418565A (zh) 青藏铁路多年冻土湿地地基处理工艺方法
CN108625243A (zh) 适用于山区丘陵红黏土地区高填方路基填筑施工方法
CN206385525U (zh) 一种防止高回填土方下沉的木桩结构
CN203212963U (zh) 富冰、饱冰及含土冰层段高路基型高速公路陡坡路基
CN112681041A (zh) 盐渍土路基施工方法和盐渍土路基
CN108385651B (zh) 一种利用复合土工织物进行软基加固的设计和施工方法
CN217500288U (zh) 深厚填土场地高能级强夯和置换与管桩组合地基结构
AU2021102288A4 (en) Composite Replacement Structure and Treatment for Soft Base of Coastal Mudflat
CN104863030A (zh) 一种高原高寒地区路基施工中水草地施工工艺
CN207878494U (zh) 地下管线基坑与软土地基同步处理的结构
CN113005839A (zh) 一种不良土质路基的处理工艺

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Hu Xiujun

Inventor after: Yang Chunjie

Inventor after: Zhang Yi

Inventor after: Jie Peixing

Inventor after: Liu Yang

Inventor after: Shi Zhuqing

Inventor before: Hu Xiujun

Inventor before: Yang Chunjie

Inventor before: Zhang Yi

Inventor before: Jie Peixing

COR Change of bibliographic data
RJ01 Rejection of invention patent application after publication

Application publication date: 20150826

RJ01 Rejection of invention patent application after publication