CN104847018A - Integral assembly method of precast concrete box structure building - Google Patents

Integral assembly method of precast concrete box structure building Download PDF

Info

Publication number
CN104847018A
CN104847018A CN201510035120.XA CN201510035120A CN104847018A CN 104847018 A CN104847018 A CN 104847018A CN 201510035120 A CN201510035120 A CN 201510035120A CN 104847018 A CN104847018 A CN 104847018A
Authority
CN
China
Prior art keywords
cast
concrete
building
concrete box
situ
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510035120.XA
Other languages
Chinese (zh)
Inventor
万里波
易延春
张九峰
余稚明
陈鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yunnan Institute of Building Research
Original Assignee
YUNNAN INSTITUTE OF BUILDING RESEARCH
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by YUNNAN INSTITUTE OF BUILDING RESEARCH filed Critical YUNNAN INSTITUTE OF BUILDING RESEARCH
Priority to CN201510035120.XA priority Critical patent/CN104847018A/en
Publication of CN104847018A publication Critical patent/CN104847018A/en
Pending legal-status Critical Current

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

An integral assembly method of a precast concrete box structure building comprises the steps of: 1) precasting and decorating concrete box bodies, 2) horizontally connecting boxes in a concrete cast-in-place belt manner, 3) vertically connecting the boxes in a sleeve connecting manner, and 4) forming the whole building, and supplementing partial decoration, wherein each concrete box is lack of one or two side faces and a bottom face. The method has the significant advantages that the method reduces turnover of construction materials, achieves standard factory manufacturing of the building, improves house quality and construction efficiency, shortens a cycle, reduces manpower, is environment-friendly, energy-saving and water-saving, reduces formation of concrete cracks and increases an assembly rate of the building.

Description

A kind of monolithic assembly method of precast concrete box structure building
Technical field
The invention belongs to the monolithic assembly method technical field of a kind of precast concrete box structure building.
Background technology
Current China builds the mode in house also mainly based on wet trade, have waste of material, winter construction difficulty, the ash and other building wastes are more, dust from construction sites affects urban air-quality, construction quality is difficult to obtain effective guarantee of landing, finishing may destroy the problems such as original structure.
The prefabricated concrete structure form of current domestic appearance has two kinds substantially.The first form is: form monolithic architecture by the mode of cast-in-situ concrete with dry wall, prefabricated post, prefabricated superimposed sheet for unit.Although this mode decreases the impact of wet trade, prefabrication and assembly construction rate is still lower.The second form is: prefabricated whole concrete box, solves box connection up and down, to form monolithic architecture by the mode of Weak link.Although this mode substantially increases prefabrication and assembly construction rate, whether house meets the demands and there is no method and determine, cannot promote.
Summary of the invention
Object of the present invention is just in order to overcome defect that above-mentioned prior art exists and not enough and provide a kind of assembly rate both having improved building, the monolithic assembly method of a kind of precast concrete box structure building making again house be met.
The object of the invention is to realize by following technical solution.
A monolithic assembly method for precast concrete box structure building, the present invention is characterised in that: step is:
1), prefabricated and fit up concrete casing; Wherein concrete chest lacks a side or two sides, lacks bottom surface;
2) level connection joint of prefabricated panel between casing, is completed in the mode of concrete cast-in-situ band; Wherein, cast-in-situ concrete joint pin is located between two blocks of wallboards, the connecting end surface of wallboard is provided with matsurface or toothed surfaces, cast-in-situ concrete joint pin is longitudinally provided with longitudinal reinforcement, anchor ring is provided with in cast-in-situ concrete joint pin, stirrup is provided with from top to bottom, then cast-in-situ concrete level connection joint two wallboard on longitudinal on whole cast-in-situ concrete joint pin;
3), the vertical connection between casing is completed in the mode of sleeve connection; Wherein, be provided with cast-in-place collar tie beam, cast-in-place collar tie beam has keyway or matsurface between upper and lower two wallboards, upper and lower two wallboards adopt vertical dowel to be connected by slurry anchor sleeve connection or slurry anchor overlap joint;
4), form whole building, supplementary portion divides finishing.
beneficial effect of the present invention and being compared with the prior art (outstanding advantages):
1, a large amount of minimizing construction circulation material;
2, building standard chemical plant can be realized manufacture, improve housing quality, improve efficiency of construction, reduce the cycle, reduce artificial;
3, environmental protection and energy saving water saving (reducing the building wastes such as dust, noise, concrete block);
4, can industrial waste be utilized, turn waste into wealth, economize the land resource and other material;
5, decorate disposable putting in place, prevent pollution and the waste of secondary decoration;
6, the formation of distress in concrete is reduced.
One aspect of the present invention improves the assembly rate of building, and house also can be met on the other hand, without the need to adopting superimposed sheet, compared with common prefabricated concrete structure, improves prefabrication and assembly construction rate.Connect chest by the mode of ater-casting, compared with box-shaped structure, improve house.
Accompanying drawing explanation
Fig. 1 is one of prefabricated box room structural representation;
Fig. 2 is prefabricated chest floor horizontal connection structure schematic diagram;
Fig. 3 is body of wall horizontal connection structure schematic diagram between prefabricated chest;
Fig. 4 is body of wall vertical connection structure schematic diagram between prefabricated chest.
Detailed description of the invention
A monolithic assembly method for precast concrete box structure building, the present invention is characterised in that: step is:
1), prefabricated and fit up concrete casing; Wherein concrete chest lacks a side or two sides, lacks bottom surface;
2) level connection joint of prefabricated panel between casing, is completed in the mode of concrete cast-in-situ band; Wherein, cast-in-situ concrete joint pin is located between two blocks of wallboards, the connecting end surface of wallboard is provided with matsurface or toothed surfaces, cast-in-situ concrete joint pin is longitudinally provided with longitudinal reinforcement, anchor ring is provided with in cast-in-situ concrete joint pin, stirrup is provided with from top to bottom, then cast-in-situ concrete level connection joint two wallboard on longitudinal on whole cast-in-situ concrete joint pin;
3), the vertical connection between casing is completed in the mode of sleeve connection; Wherein, be provided with cast-in-place collar tie beam, cast-in-place collar tie beam has keyway or matsurface between upper and lower two wallboards, upper and lower two wallboards adopt vertical dowel to be connected by slurry anchor sleeve connection or slurry anchor overlap joint;
4), form whole building, supplementary portion divides finishing.

Claims (1)

1. a monolithic assembly method for precast concrete box structure building, is characterized in that: step is:
1), prefabricated and fit up concrete casing; Wherein concrete chest lacks a side or two sides, lacks bottom surface;
2) level connection joint of prefabricated panel between casing, is completed in the mode of concrete cast-in-situ band; Wherein, cast-in-situ concrete joint pin is located between two blocks of wallboards, the connecting end surface of wallboard is provided with matsurface or toothed surfaces, cast-in-situ concrete joint pin is longitudinally provided with longitudinal reinforcement, anchor ring is provided with in cast-in-situ concrete joint pin, stirrup is provided with from top to bottom, then cast-in-situ concrete level connection joint two wallboard on longitudinal on whole cast-in-situ concrete joint pin;
3), the vertical connection between casing is completed in the mode of sleeve connection; Wherein, be provided with cast-in-place collar tie beam, cast-in-place collar tie beam has keyway or matsurface between upper and lower two wallboards, upper and lower two wallboards adopt vertical dowel to be connected by slurry anchor sleeve connection or slurry anchor overlap joint;
4), form whole building, supplementary portion divides finishing.
CN201510035120.XA 2015-01-23 2015-01-23 Integral assembly method of precast concrete box structure building Pending CN104847018A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510035120.XA CN104847018A (en) 2015-01-23 2015-01-23 Integral assembly method of precast concrete box structure building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510035120.XA CN104847018A (en) 2015-01-23 2015-01-23 Integral assembly method of precast concrete box structure building

Publications (1)

Publication Number Publication Date
CN104847018A true CN104847018A (en) 2015-08-19

Family

ID=53846968

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510035120.XA Pending CN104847018A (en) 2015-01-23 2015-01-23 Integral assembly method of precast concrete box structure building

Country Status (1)

Country Link
CN (1) CN104847018A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105297905A (en) * 2015-10-14 2016-02-03 云南省建筑科学研究院 Method for connecting prefabricated floor and prefabricated vertical component
CN107143065A (en) * 2017-07-14 2017-09-08 湖北宇辉中工建筑产业化有限公司 Prefabricated load bearing concrete wall panel combining structure and construction method
CN113417381A (en) * 2021-03-04 2021-09-21 山东中信华安建设集团有限公司 Assembled integral few reinforced concrete shear wall structure

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2332560A1 (en) * 1972-12-29 1974-07-04 Taie Spa METHOD AND DEVICE FOR CONSTRUCTION OF MULTI-STORY BUILDINGS WITH PRE-FABRICATED ELEMENTS
US4228623A (en) * 1978-03-03 1980-10-21 Ennio Menosso Prefabricated self-supporting modular room elements
CN2319463Y (en) * 1998-01-08 1999-05-19 刘凤新 Integral net structure for connecting box shape house
CN102535738A (en) * 2012-02-14 2012-07-04 黄昆 Prefabricated house wallboards, fully prefabricated house using wallboards, and installation method for fully prefabricated house

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2332560A1 (en) * 1972-12-29 1974-07-04 Taie Spa METHOD AND DEVICE FOR CONSTRUCTION OF MULTI-STORY BUILDINGS WITH PRE-FABRICATED ELEMENTS
US4228623A (en) * 1978-03-03 1980-10-21 Ennio Menosso Prefabricated self-supporting modular room elements
CN2319463Y (en) * 1998-01-08 1999-05-19 刘凤新 Integral net structure for connecting box shape house
CN102535738A (en) * 2012-02-14 2012-07-04 黄昆 Prefabricated house wallboards, fully prefabricated house using wallboards, and installation method for fully prefabricated house

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
唐庆民: "国外预制盒子结构建筑综述", 《建筑施工 》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105297905A (en) * 2015-10-14 2016-02-03 云南省建筑科学研究院 Method for connecting prefabricated floor and prefabricated vertical component
CN107143065A (en) * 2017-07-14 2017-09-08 湖北宇辉中工建筑产业化有限公司 Prefabricated load bearing concrete wall panel combining structure and construction method
CN113417381A (en) * 2021-03-04 2021-09-21 山东中信华安建设集团有限公司 Assembled integral few reinforced concrete shear wall structure
CN113417381B (en) * 2021-03-04 2023-09-01 山东中信华安建设集团有限公司 Assembled integral few muscle concrete shear wall structure

Similar Documents

Publication Publication Date Title
CN204252269U (en) A kind of Prefabricated steel construction integration assembling green building Component composition assembly unit
CN103993679B (en) Low layer assembling combined wall house bolt connection node structure
CN101967851A (en) Board-mixing structure assembly type house and building method thereof
CN103216024A (en) Self-heat-preservation mortar-free block masonry shear wall system and construction method thereof
CN101649656A (en) Overlapped shear wall with prefabricated part and cast-in-situ part and manufacturing method thereof
CN103266662B (en) The assembled house of light steel composite board
CN106499045A (en) A kind of prefabricated composite construction parapet and construction method
CN104847018A (en) Integral assembly method of precast concrete box structure building
CN1888344B (en) Composite thermal insulation concrete load-bearing wall
CN104060720A (en) Heat insulation structure prefabricated integrated assembly wall panel and overall building forming method
CN107747378A (en) The body composite board processing method of Fast Installation heat insulation decorative load-bearing one
CN203296209U (en) Self-insulation mortarless block masonry shear wall system
CN206205139U (en) A kind of prefabricated composite construction parapet
CN202596025U (en) Preformed frame light big wall plate
CN202117166U (en) Shape steel gypsum combined type building structure
CN111236481A (en) Fabricated concrete slab wall structure reinforcing steel bar dodges and is connected L shape node with enhancement
CN206616695U (en) A kind of concrete panel and girt strip floor dry type connecting node
CN102146702A (en) Profile steel gypsum combined building structure
CN206408743U (en) A kind of assembly concrete node
CN111236482A (en) Fabricated concrete slab wall structure reinforcing steel bar avoidance and reinforced connection linear node
CN107762055B (en) Install bearing heat preservation fast and decorate integrative composite sheet
CN205894354U (en) Assembled coincide wallboard
CN205577171U (en) Cast -in -place light composite wall that builds of assembled non -bearing
CN109296074A (en) A kind of assembly concrete column beam connecting node
CN111254937A (en) Installation method of fabricated building

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20160125

Address after: 650223 Kunming City, Yunnan Province University Road, No. 150

Applicant after: Yunnan Institute of Building Research

Applicant after: Kunming Asia Real Estate Development Co., Ltd.

Address before: 650223 Kunming City, Yunnan Province University Road, No. 150

Applicant before: Yunnan Institute of Building Research

RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20150819