CN104846833A - Backfilling hardening method for open pit ore face sludge - Google Patents

Backfilling hardening method for open pit ore face sludge Download PDF

Info

Publication number
CN104846833A
CN104846833A CN201510198741.XA CN201510198741A CN104846833A CN 104846833 A CN104846833 A CN 104846833A CN 201510198741 A CN201510198741 A CN 201510198741A CN 104846833 A CN104846833 A CN 104846833A
Authority
CN
China
Prior art keywords
mud
sludge
backfilling
hardening method
casting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510198741.XA
Other languages
Chinese (zh)
Inventor
李伟
李继
潘博
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huaneng Yimin Coal and Electricity Co Ltd
Original Assignee
Huaneng Yimin Coal and Electricity Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huaneng Yimin Coal and Electricity Co Ltd filed Critical Huaneng Yimin Coal and Electricity Co Ltd
Priority to CN201510198741.XA priority Critical patent/CN104846833A/en
Publication of CN104846833A publication Critical patent/CN104846833A/en
Pending legal-status Critical Current

Links

Abstract

The invention discloses a backfilling hardening method for open pit ore face sludge. The backfilling hardening method for the open pit ore face sludge comprises the following steps that firstly, damming is conducted on the periphery to block the sludge; secondly, a sand material applied to casting is discharged into a sludge pit defined by a dam to be mixed with the sludge. By the adoption of the backfilling hardening method, the characteristic that the sand material can neutralizes the sludge is utilized, the sand material applied to casting is mixed with the sludge according to a proportion, in this way, the water content of the sludge is reduced, the property of material is greatly improved, the sludge can be compacted and buried, and the compacted and buried sludge can be used as a foundation.

Description

The backfill method for curing of outdoor ore faces mud
Technical field
The present invention relates to opencast mining field, particularly a kind of backfill method for curing of outdoor ore faces mud.
Background technology
At present, each opencut is in time needing to lay various facility on mud, and the method extensively taked is, utilizes casting to build a dam body in mud surrounding, is prohibited within the specific limits by mud circle, then utilize the refuse dump discrepancy in elevation, presses the mode of burying to solve.
But the darker mud of on-the-spot mud foundation ditch is more sometimes, and casting cannot be pressed and be buried, on the contrary by more crowded for mud higher, finally overflow out of control.And this conventional method is directly pressed and is buried, and often can not meet the pressure-bearing needs as substrate.
The information being disclosed in this background technology part is only intended to increase the understanding to general background of the present invention, and should not be regarded as admitting or imply in any form that this information structure has been prior art that persons skilled in the art are known.
Summary of the invention
The object of the present invention is to provide a kind of backfill method for curing of outdoor ore faces mud of simple and reasonable steps, the backfill method for curing of this outdoor ore faces mud utilize sand material can in and the ins and outs of mud, material sand used for casting is mixed in proportion with mud, thus reduce mud water content, its material property is significantly promoted, can not only press and bury mud, and the position after pressure can be made to bury meet as the needs of substrate.
For achieving the above object, the invention provides the backfill method for curing of outdoor ore faces mud, comprise the following steps: first, surrounding is built a dam shutoff mud; Then, material sand used for casting is entered in the mud hole that dam body surrounds and mix with mud.
Preferably, in technique scheme, the mixed proportion of casting material sand used and mud is 4:1.
Compared with prior art, the present invention has following beneficial effect: the backfill method for curing of this outdoor ore faces mud utilize sand material can in and the ins and outs of mud, material sand used for casting is mixed in proportion with mud, thus reduce mud water content, its material property is significantly promoted, can not only press and bury mud, and the position after pressure can be made to bury meet as the needs of substrate.
Accompanying drawing explanation
Fig. 1 is that the surrounding of the backfill method for curing of outdoor ore faces mud of the present invention is built a dam schematic diagram;
Fig. 2 be material sand and the mud of the backfill method for curing of outdoor ore faces mud of the present invention mix schematic diagram.
Detailed description of the invention
Below in conjunction with accompanying drawing, the specific embodiment of the present invention is described in detail, but is to be understood that protection scope of the present invention not by the restriction of detailed description of the invention.
Clearly represent unless otherwise other, otherwise in whole manual and claims, term " comprise " or its conversion as " comprising " or " including " etc. by be understood to include the element of stating or ingredient, and do not get rid of other element or other ingredient.
According to the backfill method for curing of the outdoor ore faces mud of the specific embodiment of the invention by changing casting material, utilize sand material ins and outs, its can in and mud, reduce mud water content.Refer and synthesize in proportion.Mud water content reduces the most at last, its material property is significantly promoted, meets substrate needs.This backfill method for curing comprises the following steps:
First, surrounding is built a dam shutoff mud.
As shown in Figure 1, adopt surrounding to build a dam the mode of shutoff, namely to build a dam body 2 in the surrounding of mud 1, when extruding to prevent casting, mud is extruded.
Then, material sand used for casting is entered in the mud hole that dam body surrounds and mix with mud.
As shown in Figure 2, material sand 3 used for casting is entered in the mud hole 4 that dam body 2 surrounds, make material sand 3 be 4:1 with the mixed proportion of mud 1.Constantly be discharged into mud hole by sand, sand absorbs moisture and gets more and more, and mud water content is fewer and feweri, and material property is more and more stronger.Final satisfied with substrate needs.
To sum up, the backfill method for curing of this outdoor ore faces mud utilize sand material can in and the ins and outs of mud, material sand used for casting is mixed in proportion with mud, thus reduce mud water content, its material property is significantly promoted, can not only press and bury mud, and the position after pressure can be made to bury meet as the needs of substrate.
The aforementioned description to concrete exemplary of the present invention is to illustrate and the object of illustration.These descriptions not want the present invention to be defined as disclosed precise forms, and obviously, according to above-mentioned instruction, can much change and change.The object selected exemplary embodiment and describe is to explain certain principles of the present invention and practical application thereof, thus those skilled in the art can be realized and utilize various different exemplary of the present invention and various different selection and change.Scope of the present invention is intended to limited by claims and equivalents thereof.

Claims (2)

1. a backfill method for curing for outdoor ore faces mud, is characterized in that, comprise the following steps:
First, surrounding is built a dam shutoff mud;
Then, material sand used for casting is entered in the mud hole that dam body surrounds and mix with mud.
2. the backfill method for curing of outdoor ore faces mud according to claim 1, is characterized in that, the mixed proportion of described casting material sand used and mud is 4:1.
CN201510198741.XA 2015-04-24 2015-04-24 Backfilling hardening method for open pit ore face sludge Pending CN104846833A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510198741.XA CN104846833A (en) 2015-04-24 2015-04-24 Backfilling hardening method for open pit ore face sludge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510198741.XA CN104846833A (en) 2015-04-24 2015-04-24 Backfilling hardening method for open pit ore face sludge

Publications (1)

Publication Number Publication Date
CN104846833A true CN104846833A (en) 2015-08-19

Family

ID=53846792

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510198741.XA Pending CN104846833A (en) 2015-04-24 2015-04-24 Backfilling hardening method for open pit ore face sludge

Country Status (1)

Country Link
CN (1) CN104846833A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114033379A (en) * 2021-09-30 2022-02-11 华能伊敏煤电有限责任公司 Treatment method for ultra-large-volume sludge area of strip mine
CN114086538A (en) * 2021-12-14 2022-02-25 万宝矿产有限公司 Method for replacing open pit bottom sludge by utilizing waste rock partition alternate extrusion

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101314532A (en) * 2007-05-29 2008-12-03 上海海马海洋生物科技开发有限公司 Industry method of oil backfilling by manufacturing alkaline residue after the entire cleaning of the alkaline residue pool
CN103145383A (en) * 2013-04-02 2013-06-12 连云港港口工程设计研究院有限公司 Building material utilizing seabed sludge and preparation method of building material
CN103510522A (en) * 2013-10-23 2014-01-15 中国建筑一局(集团)有限公司 Construction method of sludge soil texture deep foundation pit excavation and pumping sand compacted backfilling
KR101357829B1 (en) * 2013-04-16 2014-02-06 (주)서해산업개발 Recycling material of industrial sludge for use of fill material, cover material and subbase material and method for producing the same
CN102733349B (en) * 2011-04-15 2014-10-15 浙江科技学院 Method for de-silting lake and constructing lake center island
CN104358271A (en) * 2014-11-17 2015-02-18 句容华源电器设备有限公司 High-voltage tower pole foundation construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101314532A (en) * 2007-05-29 2008-12-03 上海海马海洋生物科技开发有限公司 Industry method of oil backfilling by manufacturing alkaline residue after the entire cleaning of the alkaline residue pool
CN102733349B (en) * 2011-04-15 2014-10-15 浙江科技学院 Method for de-silting lake and constructing lake center island
CN103145383A (en) * 2013-04-02 2013-06-12 连云港港口工程设计研究院有限公司 Building material utilizing seabed sludge and preparation method of building material
KR101357829B1 (en) * 2013-04-16 2014-02-06 (주)서해산업개발 Recycling material of industrial sludge for use of fill material, cover material and subbase material and method for producing the same
CN103510522A (en) * 2013-10-23 2014-01-15 中国建筑一局(集团)有限公司 Construction method of sludge soil texture deep foundation pit excavation and pumping sand compacted backfilling
CN104358271A (en) * 2014-11-17 2015-02-18 句容华源电器设备有限公司 High-voltage tower pole foundation construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114033379A (en) * 2021-09-30 2022-02-11 华能伊敏煤电有限责任公司 Treatment method for ultra-large-volume sludge area of strip mine
CN114086538A (en) * 2021-12-14 2022-02-25 万宝矿产有限公司 Method for replacing open pit bottom sludge by utilizing waste rock partition alternate extrusion

Similar Documents

Publication Publication Date Title
CN201334669Y (en) Anchoring structure of tailings reservoir preliminary dam top leakproof geomembrane
CN203742623U (en) Water-pressure-resistant composite structure for tunnel
CN103573274B (en) Soft foundation shield tunnel subsidence controls steel sleeve grouting and reinforcing device
CN103321256A (en) Anti-pollution three-dimensional composite seepage-proofing barrier system
CN104846833A (en) Backfilling hardening method for open pit ore face sludge
CN101713197A (en) Method for sealing foundation pit pressure reduction well
CN104878739A (en) Drainage material assembly capable of being transversely connected with plastic drainage boards and method for constructing drainage material assembly
CN102912807A (en) Open caisson jacking deviation correcting method
CN202678902U (en) Novel assembly type reinforced concrete cable groove
CN108086255B (en) Seepage-proofing method for midline-type tailing damming dam body and midline-type tailing dam
CN102071675A (en) Soft soil foundation consolidation method combining drainage pile loading prepressing and deep mixing piles
CN206486875U (en) One kind sizing channel
CN207700221U (en) A kind of prefabricated pipe gallery steel plate cast-in-place concrete sealing connection structure
CN204825969U (en) Inspection shaft subsides prevents and treats structure
CN108000699A (en) A kind of urban water-through type storm sewer and its preparation process
CN204875755U (en) Drainage body and solidification stratum society foundation structure
CN204267041U (en) A kind of tunnel portal structure adopting embedded cover arch
CN207812410U (en) A kind of middle wire type tailing dam
CN100422447C (en) Technique for quickly reinforcing soft soil foundation
CN105625444A (en) Impermeable surface layer structure for soil slope
CN105178322B (en) A kind of grouting construction method
CN204849847U (en) Basement terrace prevention of seepage water structure
CN202564898U (en) Novel assembling type reinforced concrete cable trench
CN103999592A (en) Method for avoiding vegetation degradation of acid mine waste rock yard
CN205206055U (en) Basement outer wall post -cast strip thickening anti -seepage waterstop structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20150819