CN104763423B - 利用反井方式凿岩采出粉矿的开采工艺 - Google Patents
利用反井方式凿岩采出粉矿的开采工艺 Download PDFInfo
- Publication number
- CN104763423B CN104763423B CN201510094187.0A CN201510094187A CN104763423B CN 104763423 B CN104763423 B CN 104763423B CN 201510094187 A CN201510094187 A CN 201510094187A CN 104763423 B CN104763423 B CN 104763423B
- Authority
- CN
- China
- Prior art keywords
- ore
- drilling
- rock drilling
- rock
- filling
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21C—MINING OR QUARRYING
- E21C41/00—Methods of underground or surface mining; Layouts therefor
- E21C41/16—Methods of underground mining; Layouts therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F13/00—Transport specially adapted to underground conditions
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F15/00—Methods or devices for placing filling-up materials in underground workings
Abstract
本发明涉及一种利用反井方式凿岩采出粉矿的开采工艺,包括将矿体划分为阶段,其特征在于在每个阶段的上、下水平设有凿岩硐室在下水平设置装矿联络巷,在矿体下盘与装矿联络巷之间设置粉矿聚矿槽,并画出矿带界线,将矿体划分为矿带,按矿带的奇数间隔在上水平凿岩硐室中进行导向孔,用凿岩刀盘磨蚀矿体,在水的作用下,将矿粉冲入粉矿聚矿槽沉淀后,装车,运输出去;将开采完的矿带采空区用废石填充后注入液态胶结材料,形成充填凝固体后再进行偶数矿带的反井方式凿岩采出粉矿的开采作业,周而复始。本发明具有免去了选矿厂的粗破碎、细破碎等工艺流程,开采过程无粉尘,开采安全,工艺简单地表无塌陷、无炮烟,绿色环保等等优点。
Description
技术领域
本发明属于选矿技术领域,特别涉及一种利用反井方式凿岩采出粉矿的开采工艺。
背景技术
目前国内外地下非煤矿山的开采,全部采用常规的爆破落矿开采工艺,比如空场法、崩落法、充填法等。但是,对于一些严格不允许进行爆破作业的部位,比如其周围有重要建筑设施必须被保护,并且非常稀少的重要战略资源必须采出时,无法采用常规方法开采时,需要一种更新的开采思路。
同时截至目前,国内外还没有一种直接采出粉矿的开采工艺。
发明内容:
本发明的目的是提供一种利用反井方式凿岩采出粉矿的开采工艺,开采时不进行爆破作业,只采用反井方式凿岩,在采场通过凿岩,直接采出粉矿的开采工艺。
本发明的目的是这样实现的。
按照本发明的一种利用反井方式凿岩采出粉矿的开采工艺,包括将矿体划分为阶段,其特征在于在每个阶段的上、下水平分别设有凿岩硐室,在上水平设有上水平凿岩硐室和凿岩联络巷道,在下水平上设有下水平凿岩硐室,在下水平每隔 8-10m垂直于矿体走向间隔设置装矿联络巷,在矿体下盘与装矿联络巷之间设置粉矿聚矿槽,并在每个阶段内沿矿体走向间隔划分出矿带,在矿带内,先按矿带的奇数间隔在上水平的凿岩硐室中进行导向孔作业,其导向孔是采用钻机从上向下钻孔,与下水平凿岩硐室钻透,形成导向孔,然后在下水平钻孔孔口部位的钻杆上安装反向凿岩刀盘,通过导向孔由下向上利用凿岩刀盘磨蚀矿体,使矿粉落入下水平的凿岩硐室中,使用高压水将矿粉冲入到粉矿聚矿槽,通过装矿联络巷,将粉矿装入矿车,通过阶段运输平巷运输出去;
将采空区用废石填充后,采用注浆方式将液态胶结材料均匀注入到填充废石中,静置15-30天,充填凝固成为充填凝固体后再进行偶数矿带的反井方式凿岩采出粉矿的开采作业,周而复始。
本发明所述的导向孔6直径为200 mm -300mm。
本发明所述的粉矿聚矿槽的宽度是装矿联络道的1.5-2倍,深度是1.5-2m。
本发明所述反向凿岩刀盘8的凿岩直径为2000-3000mm。
本发明的优点是:采用本发明的利用反井方式凿岩采出粉矿的开采工艺,由于从井下直接钻凿出粉矿,从而免去了选矿厂的粗破碎、细破碎等工艺流程,它不仅适用于急倾斜的极薄矿体的开采,也适用于厚矿体、稳固矿体的开采,同时还适用于节理裂隙发育等难采矿体的开采;开采过程无粉尘,开采安全,工艺简单地表无塌陷、无炮烟,绿色环保等等优点。
附图说明
图1是本发明的利用反井钻机粉矿开采工艺沿矿体走向方向的示意图。
图2为图1的A-A纵剖面图。
图3为图1的B-B横剖面图。
图4为图1的C-C横剖面图。
图5为图1的D-D横剖面图。
图中,1是阶段运输平巷、2是装矿联络巷、3是粉矿聚矿槽、4是下水平凿岩硐室、5是采空区、6是导向孔、7是充填凝固体、8是反向凿岩刀盘、9是凿机、10是凿岩联络巷道、11是矿带分离线、12是矿体界线、13是上水平凿岩硐室。
具体实施方式
下面结合附图对本发明作进一步说明。
如图1-图5所示,按照本发明的一种利用反井方式凿岩采出粉矿的开采工艺,包括将矿体划分为阶段,其特征在于在每个阶段的上水平上设有上水平凿岩硐室13和凿岩联络巷道10,在下水平上设有下水平凿岩硐室4,在下水平每隔 8-10m垂直于矿体走向设置装矿联络巷2,在矿体下盘与装矿联络巷2之间设置粉矿聚矿槽3,并在每个阶段内沿矿体走向间隔划分出矿带,每隔8m-15m划出矿带界线11,在矿带12内,先按矿带的奇数间隔在上水平凿岩硐室中进行导向孔6作业,其导向孔是采用钻机9从上向下钻孔,与下水平凿岩硐室钻透,形成导向孔,然后在下水平钻孔孔口部位的钻杆上安装反向凿岩刀盘8,使反向凿岩刀盘8与钻机9紧密连接,所述反向凿岩刀盘8的凿岩直径为2000 mm -3000mm,通过导向孔由下向上利用凿岩刀盘磨蚀矿体,使矿粉落入下水平的凿岩硐室4中,在凿岩用水的作用下,使用高压水将矿粉冲入到粉矿聚矿槽3,粉矿在粉矿聚矿槽中经过沉淀后,利用铲装设备,通过装矿联络巷2,将粉矿装入矿车,通过阶段运输平巷1运输出去;
将开采完的矿带采空区5用废石填充后采用注浆设备将注浆管伸入覆盖废石中,将液态胶结材料注入并均匀渗透到整个填充废石中,静置15-30天,充填凝固成为充填凝固体7后再进行偶数矿带的反井方式凿岩采出粉矿的开采作业,能确保开采时地表无塌陷、无炮烟,绿色环保;周而复始。
本发明图1和图2示出了一矿带与三矿带已经被充填凝固体7充填完毕,二矿带正在进行导向孔6作业 ,四矿带与六矿带凿岩联络道10已经形成,没有进行开帮,五矿带正在开采。
图3、图4所示,图中下水平凿岩硐室4宽度与矿体宽度基本一致,本发明所述的导向孔6直径为200 mm -300mm,以利于反向凿岩刀盘8的安装,保证开采效果。
本发明粉矿聚矿槽3的宽度是装矿联络道2的1.5-2倍,深度是1.5-2m。这种能保证反向凿岩刀盘8磨蚀的矿体在粉矿聚矿槽3沉淀,利用铲装设备,通过装矿联络巷2,将粉矿装入矿车,通过阶段运输平巷1运输出去。
采用上述反井钻机钻凿的方法可以直接开采出粉矿。
Claims (3)
1.一种利用反井方式凿岩采出粉矿的开采工艺,包括将矿体划分为阶段,其特征在于在每个阶段的上、下水平分别设有凿岩硐室,在上水平设有上水平凿岩硐室和凿岩联络巷道,在下水平上设有下水平凿岩硐室,在下水平每隔 8-10m垂直于矿体走向间隔设置装矿联络巷,在矿体下盘与装矿联络巷之间设置粉矿聚矿槽,并在每个阶段内沿矿体走向间隔划分出矿带,在矿带内,先按矿带的奇数间隔在上水平的凿岩硐室中进行导向孔作业,其导向孔是采用钻机从上向下钻孔,与下水平凿岩硐室钻透,形成导向孔,然后在下水平钻孔孔口部位的钻杆上安装反向凿岩刀盘,通过导向孔由下向上利用凿岩刀盘磨蚀矿体,使矿粉落入下水平的凿岩硐室中,使用高压水将矿粉冲入到粉矿聚矿槽,通过装矿联络巷,将粉矿装入矿车,通过阶段运输平巷运输出去,所述的粉矿聚矿槽的宽度是装矿联络道的1.5-2倍,深度是1.5-2m;
将采空区用废石填充后,采用注浆方式将液态胶结材料均匀注入到填充废石中,静置15-30天,充填凝固成为充填凝固体后再进行偶数矿带的反井方式凿岩采出粉矿的开采作业,周而复始。
2.根据权利要求1所述的利用反井方式凿岩采出粉矿的开采工艺,其特征在于所述的导向孔直径为200 mm -300mm。
3.根据权利要求1所述的利用反井方式凿岩采出粉矿的开采工艺,其特征在于所述反向凿岩刀盘的凿岩直径为2000-3000mm。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510094187.0A CN104763423B (zh) | 2015-03-04 | 2015-03-04 | 利用反井方式凿岩采出粉矿的开采工艺 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510094187.0A CN104763423B (zh) | 2015-03-04 | 2015-03-04 | 利用反井方式凿岩采出粉矿的开采工艺 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104763423A CN104763423A (zh) | 2015-07-08 |
CN104763423B true CN104763423B (zh) | 2017-01-25 |
Family
ID=53645477
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510094187.0A Active CN104763423B (zh) | 2015-03-04 | 2015-03-04 | 利用反井方式凿岩采出粉矿的开采工艺 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104763423B (zh) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113374478B (zh) * | 2021-07-02 | 2023-12-01 | 中国煤炭科工集团太原研究院有限公司 | 边帮特厚煤层分层开采及填充方法 |
CN114412467B (zh) * | 2022-01-25 | 2022-10-25 | 长沙矿山研究院有限责任公司 | 一种薄矿体上下中深孔嗣后充填采矿法 |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2235206C1 (ru) * | 2002-12-17 | 2004-08-27 | ОАО "Научно-исследовательский институт по проблемам КМА им. Л.Д. Шевякова" | Способ разработки глубокозалегающих месторождений полезных ископаемых |
CN101328809A (zh) * | 2008-06-25 | 2008-12-24 | 深圳市中金岭南有色金属股份有限公司凡口铅锌矿 | 无底柱深孔后退式采矿方法 |
CN101858217A (zh) * | 2010-05-18 | 2010-10-13 | 中南大学 | 房柱变换式盘区上向分层充填采矿法 |
CN102128033A (zh) * | 2011-04-29 | 2011-07-20 | 北京矿冶研究总院 | 一种连续崩落采矿方法 |
CN102226396A (zh) * | 2011-05-19 | 2011-10-26 | 中南大学 | 非爆破开挖再造人工群柱深孔崩矿嗣后充填采矿法 |
CN102562065A (zh) * | 2012-01-12 | 2012-07-11 | 北京科技大学 | 一种分段空场嗣后充填采矿方法 |
CN102587916A (zh) * | 2012-02-01 | 2012-07-18 | 金建工程设计有限公司 | 一种崩矿嗣后充填采矿方法 |
CN102678121A (zh) * | 2012-05-21 | 2012-09-19 | 山东黄金矿业(莱州)有限公司三山岛金矿 | 无盘区中深孔留矿分层控顶嗣后充填采矿法 |
CN102953732A (zh) * | 2011-08-17 | 2013-03-06 | 彭康 | 房柱式大直径深孔倒台阶状分段侧向崩矿嗣后充填采矿法 |
CN103089267A (zh) * | 2013-01-22 | 2013-05-08 | 鞍钢集团矿业公司 | 薄矿体无底柱浅孔留矿法 |
-
2015
- 2015-03-04 CN CN201510094187.0A patent/CN104763423B/zh active Active
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2235206C1 (ru) * | 2002-12-17 | 2004-08-27 | ОАО "Научно-исследовательский институт по проблемам КМА им. Л.Д. Шевякова" | Способ разработки глубокозалегающих месторождений полезных ископаемых |
CN101328809A (zh) * | 2008-06-25 | 2008-12-24 | 深圳市中金岭南有色金属股份有限公司凡口铅锌矿 | 无底柱深孔后退式采矿方法 |
CN101858217A (zh) * | 2010-05-18 | 2010-10-13 | 中南大学 | 房柱变换式盘区上向分层充填采矿法 |
CN102128033A (zh) * | 2011-04-29 | 2011-07-20 | 北京矿冶研究总院 | 一种连续崩落采矿方法 |
CN102226396A (zh) * | 2011-05-19 | 2011-10-26 | 中南大学 | 非爆破开挖再造人工群柱深孔崩矿嗣后充填采矿法 |
CN102953732A (zh) * | 2011-08-17 | 2013-03-06 | 彭康 | 房柱式大直径深孔倒台阶状分段侧向崩矿嗣后充填采矿法 |
CN102562065A (zh) * | 2012-01-12 | 2012-07-11 | 北京科技大学 | 一种分段空场嗣后充填采矿方法 |
CN102587916A (zh) * | 2012-02-01 | 2012-07-18 | 金建工程设计有限公司 | 一种崩矿嗣后充填采矿方法 |
CN102678121A (zh) * | 2012-05-21 | 2012-09-19 | 山东黄金矿业(莱州)有限公司三山岛金矿 | 无盘区中深孔留矿分层控顶嗣后充填采矿法 |
CN103089267A (zh) * | 2013-01-22 | 2013-05-08 | 鞍钢集团矿业公司 | 薄矿体无底柱浅孔留矿法 |
Also Published As
Publication number | Publication date |
---|---|
CN104763423A (zh) | 2015-07-08 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108894727B (zh) | 地面水平定向钻孔注浆封堵覆岩导水裂隙主通道的保水方法 | |
CN108625856B (zh) | 一种地下矿山相邻两个采场一条出矿巷的采矿方法 | |
CN103557002B (zh) | 一种盘区机械化集中溜井上向水平分层充填采矿法 | |
CN111828007B (zh) | 一种地下矿山采空区遗留间柱的回采方法 | |
CN104481540A (zh) | 一种利用高位钻孔注浆控制多种煤矿开采灾害的方法 | |
CN104632220B (zh) | 缓倾斜中厚矿体条柱再造采场结构尺寸可调可控采矿方法 | |
CN104481543B (zh) | 阶段留矿崩落采矿法 | |
CA2986062C (en) | Fully mechanized mining-filling mixed mining working face filling section length determination method | |
CN105626071A (zh) | 一种缓倾斜薄矿体采矿方法 | |
CN104074541A (zh) | 一种水体下固体充填开采设计方法 | |
CN102720500A (zh) | 一种急倾斜薄矿体机械化地下开采方法 | |
CN103184870A (zh) | 深孔凿岩阶段空场嗣后充填采矿法 | |
CN106761750B (zh) | 急倾斜煤层纵向长壁刨铣建槽式开采方法 | |
CN104775816A (zh) | 切眼侧局部压煤覆岩隔离注浆充填不迁村开采方法 | |
CN111058847B (zh) | 一种厚大矿体连续大孔径深孔爆破机械化开采方法 | |
CN105736009A (zh) | 用于急倾斜薄矿体的留矿堆浸嗣后充填采矿方法 | |
CN101285384B (zh) | 大直径深孔不拉底采矿法 | |
CN112593853A (zh) | 一种煤矿矸石充填与减水开采的施工方法 | |
CN104847401A (zh) | 一种区域性防治煤与瓦斯突出煤层采煤工作面突出的方法 | |
CN107120137A (zh) | 一种煤巷掘进沿煤层底板深孔预裂爆破抽采方法 | |
CN103557001B (zh) | 一种低段高无底柱留矿嗣后充填采矿法 | |
CN107152309B (zh) | 一种煤层为主含水层的高水高排水害防治方法 | |
CN105952492A (zh) | 一种高瓦斯煤层工作面钻采预抽瓦斯方法 | |
CN104763423B (zh) | 利用反井方式凿岩采出粉矿的开采工艺 | |
CN105804752A (zh) | 一种煤矿条带开采中覆岩离层注浆减沉工艺 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
EXSB | Decision made by sipo to initiate substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB02 | Change of applicant information |
Address after: 114001 Anshan District, Liaoning, No. 219 Road, No. 39, Tiedong Applicant after: Anshan Iron and steel group mineral company Co., Ltd. Address before: 114001 Anshan District, Liaoning, No. 219 Road, No. 39, Tiedong Applicant before: Angang Group Mine Company |
|
COR | Change of bibliographic data | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |