CN104695927B - Coiled tubing and production tubing combined string fracturing and well completion integrated method - Google Patents
Coiled tubing and production tubing combined string fracturing and well completion integrated method Download PDFInfo
- Publication number
- CN104695927B CN104695927B CN201510038874.0A CN201510038874A CN104695927B CN 104695927 B CN104695927 B CN 104695927B CN 201510038874 A CN201510038874 A CN 201510038874A CN 104695927 B CN104695927 B CN 104695927B
- Authority
- CN
- China
- Prior art keywords
- fracturing
- string
- construction
- production
- coiled tubing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000004519 manufacturing process Methods 0.000 title claims abstract description 25
- 238000000034 method Methods 0.000 title claims abstract description 19
- 238000010276 construction Methods 0.000 claims abstract description 17
- 239000012530 fluid Substances 0.000 claims abstract description 17
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 10
- 239000007788 liquid Substances 0.000 claims abstract description 10
- 239000010959 steel Substances 0.000 claims abstract description 10
- 238000005488 sandblasting Methods 0.000 claims abstract description 3
- 150000001875 compounds Chemical class 0.000 claims description 28
- 238000013461 design Methods 0.000 claims description 7
- 238000012360 testing method Methods 0.000 claims description 7
- ZRALSGWEFCBTJO-UHFFFAOYSA-N Guanidine Chemical compound NC(N)=N ZRALSGWEFCBTJO-UHFFFAOYSA-N 0.000 claims description 6
- 238000002347 injection Methods 0.000 claims description 6
- 239000007924 injection Substances 0.000 claims description 6
- CHJJGSNFBQVOTG-UHFFFAOYSA-N N-methyl-guanidine Natural products CNC(N)=N CHJJGSNFBQVOTG-UHFFFAOYSA-N 0.000 claims description 3
- 239000002253 acid Substances 0.000 claims description 3
- 230000015572 biosynthetic process Effects 0.000 claims description 3
- 230000000994 depressogenic effect Effects 0.000 claims description 3
- SWSQBOPZIKWTGO-UHFFFAOYSA-N dimethylaminoamidine Natural products CN(C)C(N)=N SWSQBOPZIKWTGO-UHFFFAOYSA-N 0.000 claims description 3
- 239000011159 matrix material Substances 0.000 claims description 3
- 238000003825 pressing Methods 0.000 claims description 3
- 238000005086 pumping Methods 0.000 claims description 3
- 238000007789 sealing Methods 0.000 claims description 2
- 239000000203 mixture Substances 0.000 claims 1
- 230000006378 damage Effects 0.000 abstract description 6
- 208000027418 Wounds and injury Diseases 0.000 description 3
- 238000005516 engineering process Methods 0.000 description 3
- 208000014674 injury Diseases 0.000 description 3
- 241000254175 Anthonomus grandis Species 0.000 description 2
- 230000008901 benefit Effects 0.000 description 2
- 238000012856 packing Methods 0.000 description 2
- 230000008569 process Effects 0.000 description 2
- 241000521257 Hydrops Species 0.000 description 1
- 206010030113 Oedema Diseases 0.000 description 1
- 238000004873 anchoring Methods 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 239000003795 chemical substances by application Substances 0.000 description 1
- 238000011109 contamination Methods 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 229930195733 hydrocarbon Natural products 0.000 description 1
- 150000002430 hydrocarbons Chemical class 0.000 description 1
- 238000005065 mining Methods 0.000 description 1
- 230000035699 permeability Effects 0.000 description 1
- 238000010998 test method Methods 0.000 description 1
- 230000009466 transformation Effects 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B43/00—Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
- E21B43/25—Methods for stimulating production
- E21B43/26—Methods for stimulating production by forming crevices or fractures
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B33/00—Sealing or packing boreholes or wells
- E21B33/10—Sealing or packing boreholes or wells in the borehole
- E21B33/12—Packers; Plugs
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B43/00—Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
- E21B43/11—Perforators; Permeators
- E21B43/114—Perforators using direct fluid action on the wall to be perforated, e.g. abrasive jets
Landscapes
- Life Sciences & Earth Sciences (AREA)
- Engineering & Computer Science (AREA)
- Geology (AREA)
- Mining & Mineral Resources (AREA)
- Physics & Mathematics (AREA)
- Environmental & Geological Engineering (AREA)
- Fluid Mechanics (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
- Earth Drilling (AREA)
Abstract
The invention belongs to the technical field of oil-gas field fracturing, and particularly relates to a coiled tubing and production tubing combined string fracturing and well completion integrated method, which comprises the following specific steps: 1) putting the combined pipe string; 2) setting the first layer section; 3) a first section of sand blasting perforation; 4) fracturing a first stratum; 5) injecting fracturing fluid; 6) after the fracturing is finished at the first section, lifting the fracturing pipe column to the second section of the designed perforation position, and repeating the steps 2) -5) to finish the subsequent fracturing construction of all construction intervals; 7) after construction is finished, lowering the fracturing string to the position of the artificial well bottom, and throwing steel balls from the well mouth to realize releasing by the hydraulic releasing; 8) and (6) draining liquid and putting into production. After fracturing is finished, the production string can be produced for one time, so that the operation period is shortened, and the damage to the reservoir stratum is reduced.
Description
Technical field
The invention belongs to oil-gas field fracturing technical field, and in particular to a kind of coiled tubing and production tube compound tube string pressure
Split and completion integral method.
Background technology
Hydraulic sand blasting fracturing technique beam hole, fracturing integrated, the agent technology as exploitation low permeability oil and gas field, with reference to
Coiled tubing can dragging with pressure the characteristics of, the number of plies is unrestricted with transformation, pit shaft keeps the conventional skill such as big orifice after pressure break
The incomparable advantage of art.
Wherein coiled tubing perforation, annular fracturing, the method for anchoring type mechanical packer packing have that packing is reliable, pressure break
The features such as discharge capacity is big, efficiency of construction is high, using relatively broad.But the technique pressure break has finished out fracturing string, on the one hand deposits
In larger construction risk, on the other hand, for low-voltage and low-yield gas well, it has hydro carbons condensed liquid or ground in process of production
Layer water flows into shaft bottom, and due to Large Diameter Pipeline oil pipe, its fluid-carrying capability is poor(Produced gas can not be reached and continuously take liquid because flow velocity is too small
Requirement), cause hydrops in pit shaft to be on the increase, shaft bottom back pressure constantly increases, sometimes even gas well can completely be killed so that
Closing well, the interval of severe contamination pressure break, causes the injury to reservoir, directly influences gas well yield and coefficient of mining.
The content of the invention
It is an object of the invention to provide a kind of coiled tubing and production tube compound tube string pressure break and completion integral method,
To simplify working procedure, injury of the kill-job to reservoir is reduced.
The technical scheme is that:
A kind of coiled tubing and production tube compound tube string pressure break and completion integral method, comprise the following steps:
Step 1)Under enter compound tube string:Connector, production tube, hydraulic pressure are connected with turn by coiled tubing lower end to lose
Hand, mechanical casing collar locator, injector, packer, guiding check valve are combined into compound tube string, in lower going-into-well cylinder;
Step 2)First interval sets:Positioned by casing collar locator (CCL), by injector alignment first paragraph design perforation
Then position, set packer carries the m of discharge capacity 1.03/ min, closes annular space gate, when pressure reaches more than 20MPa, termination of pumping 3
~ 5min, observes casing pressure stable case, if pressure does not drop, illustrates that packer is effective;
Step 3)First interval abrasive perforating:After testing seal about packer is qualified, sleeve gate is opened, from the injection of compound tube string
0.2m3/ min perforating fluids, when perforating fluid to injector nozzle is apart from 200m, improve discharge capacity to 1.0 m3/ min, abrasive perforating,
Perforating fluid is returned out from oil jacket annular space;
Step 4)First interval pressure break:After perforation is finished, sleeve gate, the m of control ring idle discharge amount 1.0 are closed3/ min, together
When compound tube string injection discharge capacity be maintained at 0.1 m3/ min carries out burst test, and subsequent construction is continued if the layer ruptures, if broken
Split it is unsuccessful, then continue perforation or acid filling liquid, until the layer rupture;
Step 5)After first interval formation fracture, fracturing fluid is injected from oil jacket annular space, while keeping the m of compound tube string 0.13/
Min injects base fluid;
Step 6)After pressure break finishes first paragraph, fracturing string is above carried to second segment and design perforating site, repeat step 2)-
5), complete the pressing crack construction of follow-up all construction intervals;
Step 7)After construction is finished, fracturing string is transferred to artificial bottom of a well position, steel ball is thrown from well head, treat that steel ball is dropped down onto
After hydraulic releasing, compound tube serially add be depressed into hydraulic releasing realize give up, the tool string below hydraulic releasing falls in artificial bottom of a well, so
Steel ball is flushed out pit shaft by oil jacket annular space huge discharge reacting cycle afterwards;
8)Compound tube string is above carried, coiled tubing and connector is unloaded, production tube wellhead assembly is hung on into, for oil gas
The discharge opeing of well and operation.
The packer is Y241 packers.
Step 5)The base fluid is guanidine matrix liquid.
The wellhead assembly is made up of boll-weevil hanger, production tree connection.
This coiled tubing that the present invention is provided and production tube compound tube string pressure break and completion integral method, Neng Goushi
Existing following effect:
Firstth, after pressure break is finished, underground tool string is given up and stays in artificial bottom of a well, and act coiled tubing and connector,
Production tube is suspended on into wellhead assembly directly to be produced, next time flow string can be lacked, shorten duty cycle;
Secondth, after pressure break is finished, it is not necessary to flow string under kill-job, reservoir damage can be reduced.
Brief description of the drawings
Fig. 1 is compound tube string structure schematic diagram.
In figure:1st, coiled tubing;2nd, connector;3rd, production tube;4th, hydraulic releasing;5th, mechanical casing box cupling positioning
Device;6th, injector;7th, packer;8th, guiding check valve;9th, wellhead assembly.
Specific embodiment
Embodiment 1:
It is an object of the invention to provide a kind of coiled tubing and production tube compound tube string pressure break and completion integral side
Method, to simplify working procedure, reduces injury of the kill-job to reservoir.
Present embodiments provide a kind of coiled tubing as shown in Figure 1 with production tube compound tube string pressure break with completion integrally
Change method, comprises the following steps:
Step 1)Under enter compound tube string:Connector 2, production tube 3, hydraulic pressure are connected with turn by the lower end of coiled tubing 1
Give up 4, mechanical casing collar locator 5, injector 6, Y241 packers, guiding check valve 8 is combined into compound tube string, under enter
In pit shaft;
Step 2)First interval sets:Positioned by casing collar locator (CCL), injector 6 is directed at first paragraph design perforation
Position, sets Y241 packers, then carries the m of discharge capacity 1.03/ min, closes annular space gate, when pressure reaches more than 20MPa,
Termination of pumping 3min, observes casing pressure stable case, if pressure does not drop, illustrates that Y241 packers are effective;
Step 3)First interval abrasive perforating:After packer 7 tests sealing lattice, sleeve gate is opened, from the injection of compound tube string
0.2m3/ min perforating fluids, when perforating fluid is to 6 nozzle distance 200m of injector, improve discharge capacity to 1.0 m3/ min, abrasive perforating,
Perforating fluid is returned out from oil jacket annular space;
Step 4)First interval pressure break:After perforation is finished, sleeve gate, the m of control ring idle discharge amount 1.0 are closed3/ min, together
When compound tube string injection discharge capacity be maintained at 0.1 m3/ min carries out burst test, and subsequent construction is continued if the layer ruptures, if broken
Split it is unsuccessful, then continue perforation or acid filling liquid, until the layer rupture;
Step 5)After first interval formation fracture, fracturing fluid is injected from oil jacket annular space, while keeping the m of compound tube string 0.13/
Min injects guanidine matrix liquid;
Step 6)After pressure break finishes first paragraph, fracturing string is above carried to second segment and design perforating site, repeat step 2)-
5), complete the pressing crack construction of follow-up all construction intervals;
Step 7)After construction is finished, fracturing string is transferred to artificial bottom of a well position, steel ball is thrown from well head, treat that steel ball is dropped down onto
After hydraulic releasing 4, compound tube serially add be depressed into hydraulic releasing 4 realize give up, the tool string below hydraulic releasing 4 falls in artificial well
Bottom, then oil jacket annular space huge discharge reacting cycle steel ball is flushed out into pit shaft;
8)Compound tube string is above carried, coiled tubing 1 and connector 2 is unloaded, production tube 3 is hung on into wellhead assembly 9, be used for
The discharge opeing of Oil/gas Well and operation.
Wellhead assembly 9 is made up of boll-weevil hanger, production tree connection, belongs to known technology.
In sum, it is of the invention compared with existing process method, with advantages below:
Firstth, after pressure break is finished, underground tool string is given up and stays in artificial bottom of a well, and act coiled tubing, by production oil
Pipe is suspended on wellhead assembly and is directly produced, and can lack next time flow string, shortens duty cycle;
Secondth, after pressure break is finished, it is not necessary to flow string under kill-job, reservoir damage can be reduced.
The method of testing that the present invention is not described in detail is conventional method of testing or existing method in the art, herein not
Describe one by one.
It is exemplified as above be only to of the invention for example, do not constitute the limitation to protection scope of the present invention, it is all
It is that design same or analogous with the present invention is belonged within protection scope of the present invention.
Claims (1)
1. a kind of coiled tubing and production tube compound tube string pressure break and completion integral method, it is characterised in that including with
Lower step:
Step 1)Under enter compound tube string:By coiled tubing(1)Lower end is connected with connector in turn(2), production tube(3), liquid
Pressure is given up(4), mechanical casing collar locator(5), injector(6), packer(7), guiding check valve(8)It is combined into combination
Pipe string, in lower going-into-well cylinder;
Step 2)First interval sets:Positioned by casing collar locator (CCL), by injector(6)Alignment first paragraph design perforation position
Put, set packer(7), then carry the m of discharge capacity 1.03/ min, closes annular space gate, when pressure reaches more than 20MPa, termination of pumping
3min, observes casing pressure stable case, if pressure does not drop, illustrates packer(7)Effectively;
Step 3)First interval abrasive perforating:Packer(7)After testing sealing lattice, sleeve gate is opened, from the injection of compound tube string
0.2m3/ min perforating fluids, when perforating fluid to injector(6)During nozzle distance 200m, discharge capacity to 1.0 m is improved3/ min, sandblasting is penetrated
Hole, perforating fluid is returned out from oil jacket annular space;
Step 4)First interval pressure break:After perforation is finished, sleeve gate, the m of control ring idle discharge amount 1.0 are closed3/ min, while combination
Pipe string injection discharge capacity is maintained at 0.1 m3/ min carries out burst test, if the layer rupture if continue subsequent construction, if rupture not into
Work(, then continue perforation or acid filling liquid, until layer rupture;
Step 5)After first interval formation fracture, fracturing fluid is injected from oil jacket annular space, while keeping the m of compound tube string 0.13/ min is noted
Enter base fluid;
Step 6)After pressure break finishes first paragraph, fracturing string is above carried to second segment and design perforating site, repeat step 2)-5),
Complete the pressing crack construction of follow-up all construction intervals;
Step 7)After construction is finished, fracturing string is transferred to artificial bottom of a well position, steel ball is thrown from well head, treat that steel ball drops down onto hydraulic pressure
Give up(4)Afterwards, compound tube is serially added and is depressed into hydraulic releasing(4)Realization is given up, hydraulic releasing(4)Following tool string falls in artificial well
Bottom, then oil jacket annular space huge discharge reacting cycle steel ball is flushed out into pit shaft;
8)Compound tube string is above carried, coiled tubing is unloaded(1)And connector(2), by production tube(3)Hang on wellhead assembly(9),
For the discharge opeing and operation of Oil/gas Well;
The packer(7)It is Y241 packers, step 5)The base fluid is guanidine matrix liquid, the wellhead assembly(9)By oil pipe
Hanger, production tree connection composition.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510038874.0A CN104695927B (en) | 2015-01-27 | 2015-01-27 | Coiled tubing and production tubing combined string fracturing and well completion integrated method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510038874.0A CN104695927B (en) | 2015-01-27 | 2015-01-27 | Coiled tubing and production tubing combined string fracturing and well completion integrated method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104695927A CN104695927A (en) | 2015-06-10 |
CN104695927B true CN104695927B (en) | 2017-07-07 |
Family
ID=53343428
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510038874.0A Active CN104695927B (en) | 2015-01-27 | 2015-01-27 | Coiled tubing and production tubing combined string fracturing and well completion integrated method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104695927B (en) |
Families Citing this family (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107654207B (en) * | 2017-11-16 | 2020-06-26 | 中国石油集团川庆钻探工程有限公司 | Section method for fixed-point preset sand plug of coiled tubing horizontal well |
CN107939376A (en) * | 2017-11-27 | 2018-04-20 | 中国石油集团川庆钻探工程有限公司长庆井下技术作业公司 | A kind of gas well gas testing operation integrated synthesis completion method |
CN108756845B (en) * | 2018-05-03 | 2023-05-12 | 肖毅 | Capacity-expansion increment deflagration fracturing method |
CN108952664A (en) * | 2018-08-22 | 2018-12-07 | 中国石油集团渤海钻探工程有限公司 | A kind of oil/gas well straight well orientation water-jet multistage fracturing method |
CN111206878B (en) * | 2018-11-21 | 2021-07-02 | 中国石油天然气股份有限公司 | Well completion method |
CN109630083A (en) * | 2018-11-22 | 2019-04-16 | 西南石油大学 | A kind of abrasive perforating annular fracturing ground control system and method |
CN109339855B (en) * | 2018-11-27 | 2020-11-24 | 中煤科工集团西安研究院有限公司 | Perforating and staged fracturing method for continuous pipe in long-drill-hole casing for gas extraction in coal mine |
CN110644954A (en) * | 2019-09-03 | 2020-01-03 | 中国石油集团川庆钻探工程有限公司长庆井下技术作业公司 | One-trip drilling operation pipe column for casing patching well and operation method |
CN111255427A (en) * | 2020-01-16 | 2020-06-09 | 中国石油天然气股份有限公司 | Method for mechanical separate-layer fracturing of oil well |
CN113530509A (en) * | 2020-04-15 | 2021-10-22 | 中国石油天然气股份有限公司 | Continuous separate-layer fracturing method for small well and fracturing pipe column |
CN111648754A (en) * | 2020-05-19 | 2020-09-11 | 中国石油天然气股份有限公司 | Coiled tubing fracturing and downhole throttling production integrated process pipe column and method thereof |
CN112431579B (en) * | 2020-08-11 | 2022-11-04 | 中国石油天然气股份有限公司 | Preset small-diameter pipe internal fracturing device and method for side drilling well and small-hole well |
CN112324415B (en) * | 2020-11-05 | 2023-04-07 | 中国石油天然气股份有限公司 | Combined segmented reconstruction method for selective repeated reconstruction of old well |
CN112282718B (en) * | 2020-11-05 | 2022-12-02 | 中国石油天然气股份有限公司 | Combined pipe string for sidetracking well and slim hole well and use method |
CN115217460B (en) * | 2021-04-21 | 2024-03-26 | 中国石油天然气股份有限公司 | Acidizing fracturing method |
CN113530517B (en) * | 2021-09-17 | 2021-12-14 | 中煤科工集团西安研究院有限公司 | Combined segmented fracturing device, asynchronous two-way extraction system and method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102562017A (en) * | 2010-12-29 | 2012-07-11 | 安东石油技术(集团)有限公司 | Sand blasting, perforating and fracturing method |
CN102562019A (en) * | 2011-12-13 | 2012-07-11 | 中国石油集团川庆钻探工程有限公司井下作业公司 | Sand jet perforation annular mechanical packing multilayer fracturing tool pipe column and modification process |
CN202645525U (en) * | 2012-05-16 | 2013-01-02 | 中国石油化工股份有限公司 | Fracturing string |
CN203321476U (en) * | 2013-06-05 | 2013-12-04 | 中国石油天然气股份有限公司 | Coiled tubing controllable packer process pipe column for old well repeated reconstruction |
CN104213890A (en) * | 2013-06-03 | 2014-12-17 | 中国石油天然气股份有限公司 | Coiled tubing fracturing string and fracturing process |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US7096954B2 (en) * | 2001-12-31 | 2006-08-29 | Schlumberger Technology Corporation | Method and apparatus for placement of multiple fractures in open hole wells |
GB0425216D0 (en) * | 2004-11-16 | 2004-12-15 | Qinetiq Ltd | Improvements in and relating to oil well perforators |
-
2015
- 2015-01-27 CN CN201510038874.0A patent/CN104695927B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102562017A (en) * | 2010-12-29 | 2012-07-11 | 安东石油技术(集团)有限公司 | Sand blasting, perforating and fracturing method |
CN102562019A (en) * | 2011-12-13 | 2012-07-11 | 中国石油集团川庆钻探工程有限公司井下作业公司 | Sand jet perforation annular mechanical packing multilayer fracturing tool pipe column and modification process |
CN202645525U (en) * | 2012-05-16 | 2013-01-02 | 中国石油化工股份有限公司 | Fracturing string |
CN104213890A (en) * | 2013-06-03 | 2014-12-17 | 中国石油天然气股份有限公司 | Coiled tubing fracturing string and fracturing process |
CN203321476U (en) * | 2013-06-05 | 2013-12-04 | 中国石油天然气股份有限公司 | Coiled tubing controllable packer process pipe column for old well repeated reconstruction |
Also Published As
Publication number | Publication date |
---|---|
CN104695927A (en) | 2015-06-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104695927B (en) | Coiled tubing and production tubing combined string fracturing and well completion integrated method | |
CN106014346B (en) | Method and device for water drainage and gas production by speed string matched with plunger gas lift | |
RU2460876C1 (en) | Method for performing pulse hydraulic fracturing of carbonate formation | |
WO2017121112A1 (en) | Method for evaluating performance of multistage hydraulic jet fracturing string | |
CN104564001B (en) | The method of many cluster pressure breaks of horizontal well and many cluster perforating and fracturing tubing strings of implementation the method | |
CN203081411U (en) | Anti-corrosion anti-scale and gas lift integrated well completion pipe string | |
CN104481489B (en) | Coiled tubing fracturing and well completion integrated process method for gas well vertical well | |
CN107489405B (en) | Method for dragging sand-blasting perforation and annular sand-filling staged fracturing by continuous oil pipe | |
CN103266875A (en) | Fracturing operation method of multistage hydraulic jet staged fracturing tubular column | |
CN203081417U (en) | Multifunctional integrated gas lift process pipe column | |
CN102242621A (en) | Negative pressure de-plugging and oil extraction process and device | |
CN104153753A (en) | Horizontal well volume fracturing tubular column and method based on conventional oil tube pressure dragging | |
CN105239984A (en) | Method for controlling coal mine underground fracturing crack propagation | |
CN106894783B (en) | Method for drilling and milling plug of coiled tubing | |
CN109723399A (en) | A kind of method of oil/gas well liquid nitrogen injection de-plugging anatonosis | |
CN104213895A (en) | Hydraulic sand-blasting perforation fracturing and sand-filling combined process method | |
CN103912257B (en) | A kind of dragging multiple fracturing device with pressure | |
CN103266876A (en) | Fracturing working method of multilevel hydraulic spraying segmentation fracturing tubular column | |
CN203394492U (en) | Coiled tubing perforation and mechanical packing fracturing string | |
CN110410053A (en) | Coal mine roof plate pressure relief method based on eyelet supporting | |
CN207004498U (en) | Infinite stages switching sliding sleeve fracturing tool | |
CN104373093A (en) | Underground nitrogen-making induced flow completion pipe string having pressure monitoring function | |
CN204041042U (en) | A kind of coiled tubing drag fracturing tubing string | |
CN114439450B (en) | Acid fracturing yield increasing technology for carbonate deep geothermal water reservoir | |
CN208122840U (en) | A kind of protection sleeve pipe volume fracturing tubing string |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |