CN104675426A - Gas outburst prevention construction method suitable for unprotected single coal seam mining - Google Patents

Gas outburst prevention construction method suitable for unprotected single coal seam mining Download PDF

Info

Publication number
CN104675426A
CN104675426A CN201410787384.6A CN201410787384A CN104675426A CN 104675426 A CN104675426 A CN 104675426A CN 201410787384 A CN201410787384 A CN 201410787384A CN 104675426 A CN104675426 A CN 104675426A
Authority
CN
China
Prior art keywords
gas
hole
coal
coal seam
drilling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410787384.6A
Other languages
Chinese (zh)
Inventor
姜旭
胡金亮
周欢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
In Build City And Build And Establish Group Co Ltd
Original Assignee
In Build City And Build And Establish Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by In Build City And Build And Establish Group Co Ltd filed Critical In Build City And Build And Establish Group Co Ltd
Priority to CN201410787384.6A priority Critical patent/CN104675426A/en
Publication of CN104675426A publication Critical patent/CN104675426A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F7/00Methods or devices for drawing- off gases with or without subsequent use of the gas for any purpose

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention relates to a gas outburst prevention construction method suitable for unprotected single coal seam mining. The method includes the steps: S100, constructing a floor roadway in a rock stratum nearby a coal seam floor; S200, constructing a plurality of crossing holes in the floor roadway towards the coal seam so as to perform first gas pre-drainage; S300, constructing a plurality of down-the-seam holes in a coal roadway working face towards the coal seam so as to perform second gas pre-drainage; S400, performing shallow-hole drainage and pressure relief in the coal roadway working face, and after the to-be-detected coal seam is a no-outburst-danger area, performing coal roadway excavation. By the construction method, outburst prevention effect can be improved effectively, and error in the effect test phase is eliminated.

Description

Be suitable for the control Gas Outburst construction method of unprotected single coal bed exploitation
Technical field
The present invention relates to field of coal mining, particularly relate to a kind of control Gas Outburst construction method being suitable for the exploitation of unprotected single coal bed.
Background technology
Comprehensive Gas Control is the most important thing of Safety Work in Colliery, and gas drainage under suction is then the basic effective measures of gas control, is the precondition of coal and gas outburst mine safety in production.
After " control coal and gas prominent regulation " (version in 2009) promulgates, the outburst prevention work guilding principle of China there occurs great transformation, and outburst prevention work will adhere to that region outburst prevention measures is leading, the basic principle that local prevent outburst measure supplements.When not having topping can exploit (single coal bed), how eliminating the single coal bed gas outburst risk that unprotect layer can adopt is a technical barrier in field of coal mining.
Summary of the invention
The object of this invention is to provide a kind of control Gas Outburst construction method being suitable for the exploitation of unprotected single coal bed; the single coal bed gas can adopted to overcome unprotect layer easily produces the technical problem of outburst hazard; and after drawing out methane at twice; carrying out shallow bore hole discharge release to coal road, to play the effect of control Gas Outburst further.
In order to solve the problems of the technologies described above, the invention provides a kind of control Gas Outburst construction method being suitable for the exploitation of unprotected single coal bed, comprising the steps:
Step S100, a floor roadway of constructing in the rock stratum near seat earth.
Step S200, some layer-through drillings of constructing to coal seam in described floor roadway, to carry out first time Gas pre-drainage.
Step S300, to construct to described coal seam the boring of some concordants at coal road work plane, to carry out second time Gas pre-drainage.
Step S400, carry out shallow bore hole discharge release to coal road work plane, described coal seam to be detected is without behind outburst dangerous area, carries out coal roadway tunneling.
Preferably, described floor roadway is perpendicular to 8-10m below seat earth.
Preferably, described layer-through drilling is 7, and is fan-shapedly uniformly distributed, and each layer-through drilling penetrates described coal seam at least 0.5m respectively; And the control line of boring is apart from the outer at least each 15m of both sides, the tunnel outline line of described floor roadway.
Preferably, described first time Gas pre-drainage identical with the method for second time Gas pre-drainage, and to comprise the steps:
Step S210, carries out sealing of hole, to form gas drainage under suction passage to layer-through drilling or concordant boring.
Step S220, is connected to an orifice flowmeter by the gas drainage pipe being positioned at each layer-through drilling or concordant boring and carries out extraction concentration and flow measurement, and carry out extraction by extraction main line.
Preferably, in order to solve the technical problem of upward hole sealing of hole, carry out sealing of hole to layer-through drilling or concordant boring in described step S210 to comprise with the method forming gas drainage under suction passage: upward hole sealing of hole, be embedded in layer-through drilling or concordant boring by Grouting Pipe and gas drainage pipe, and by Grouting Pipe to layer-through drilling or the slip casting of concordant bore inner, when the aperture of gas drainage pipe overflows cement paste, stop slip casting to cement slurry sets, then carry out gas drainage under suction.
Preferably, in order to solve down the technical problem to hole sealing of hole, in described step S210, layer-through drilling or concordant boring are carried out sealing of hole and are comprised with the method forming gas drainage under suction passage: under to hole sealing of hole, be embedded in layer-through drilling or concordant boring by gas drainage pipe, cement paste is poured into in hole from the aperture of layer-through drilling or concordant boring, when aperture overflows cement paste, stop grouting.
Preferably, in order to solve the technical problem of lateral aperture sealing of hole, carry out sealing of hole to layer-through drilling or concordant boring in described step S210 to comprise with the method forming gas drainage under suction passage: lateral aperture sealing of hole, be embedded in layer-through drilling or concordant boring by gas drainage pipe, Grouting Pipe, stack, and first, second sealing of hole layer is built in layer-through drilling or concordant boring, first, second sealing of hole floor described forms a slip casting room; Gas drainage pipe runs through first, second sealing of hole layer, and described stack, Grouting Pipe extend to described slip casting indoor through the first sealing of hole layer and carry out slip casting, when stack overflows cement paste, stops slip casting, then Grouting Pipe and the stack mouth of pipe are carried out shutoff.
Preferably, also comprise in described step S300, after second time Gas pre-drainage, carry out the method for residual gas assay, the method adopts three detection borings to carry out the remaining detection of gas, three are detected centre and the both sides that boring is arranged at coal road work plane respectively, and it is consistent with the tunneling direction of coal road work plane to be positioned at middle detection boring.
Preferably, the method for described shallow bore hole discharge release comprises:
When the thickness in distance coal seam of meeting head on is greater than 2.4m, be fan-shaped equally distributed dense shallow hole meeting head on to offer three rows; When the thickness in distance coal seam of meeting head on is less than 2.4m, be fan-shaped equally distributed dense shallow hole meeting head on to offer two rows; Wherein, each round number is 11, and the drainage radius of each boring is 0.7m, and the control line of boring is apart from the outer at least each 5m of both sides, the tunnel outline line of described coal road.
Another aspect, present invention also offers a kind of control Gas Outburst construction method, comprises the steps:
Step S1, a floor roadway of constructing in the rock stratum of the base plate vicinity in described coal seam;
Step S2, some layer-through drillings of constructing to described coal seam in floor roadway;
Step S3, takes out described coal-bed gas in advance in floor roadway, carries out first time release to the gas in coal seam;
Step S4, judges whether up to standard; If up to standard, then carry out S5 step; If not up to standard, then repeat S2 step, S3 step, namely encryption boring continues extraction;
Step S5, carries out the 1st sub-region verifying outburst prevention effect to described coal seam in floor roadway;
Whether step S6, check up to standard; If up to standard, then carry out S7 step; If not up to standard, then repeat S3 step, namely continue extraction;
Step S7, the coal road work plane in described coal seam is to the boring of this coal seam construction concordant;
Step S8, at the work plane of described coal road to this coal seam Gas pre-drainage, carries out second time release to the gas in coal seam;
Step S9, the 2nd sub-region verifying outburst prevention effect;
Whether step S10, check up to standard; If up to standard, then carry out S11 step; If not up to standard, then repeat S8 step, namely continue extraction;
Step S11, area validation;
Whether step S12, verify up to standard; If up to standard, then carry out S13 step; If not up to standard, then repeat S14 step;
Step S13, carries out coal roadway tunneling in described coal seam;
Step S14, at the work plane of described coal road to this coal seam drilling dense shallow hole, makes gas naturally discharge a period of time, carries out third time release to the gas in coal seam;
Step S15, carries out work plane verifying outburst prevention effect in described coal seam;
Whether step S16, check up to standard; If up to standard, then carry out S17 step; If not up to standard, then repeat S14 step;
Step S17, carries out coal roadway tunneling in described coal seam.
Beneficial effect of the present invention: the present invention first do two sub-region protrusion-dispellings try again local protrusion-dispelling, namely described two sub-region protrusion-dispellings comprise: floor roadway layer-through drilling takes out coal road gas region protrusion-dispelling in advance and this coal-bed gas region protrusion-dispelling is taken out in the boring of coal road work plane concordant in advance, and described local protrusion-dispelling is shallow bore hole discharge; Be specially, a floor roadway of first first constructing in the rock stratum near seat earth, some layer-through drillings of constructing in floor roadway, carry out gas drainage under suction; Again in this working face of coal seam construction once some concordant boring before coal roadway tunneling, carry out gas drainage under suction; Finally do the Local provisions of shallow bore hole discharge, after validity check is qualified, carry out coal roadway tunneling.This construction method effectively improves protrusion-dispelling effect, and the error of eradicating efficacy testing stage.
Accompanying drawing explanation
Below in conjunction with drawings and Examples, the present invention is further described.
Fig. 1 shows the flow chart of this construction method;
Fig. 2 shows the particular flow sheet of this construction method;
Fig. 3 shows floor roadway boring and arranges sectional schematic diagram;
Fig. 4 shows floor roadway boring plane of arrangement schematic diagram;
Fig. 5 shows to pre-extraction hole injection hole sealing schematic diagram;
Fig. 6 shows lower to pre-extraction hole injection hole sealing schematic diagram;
Fig. 7 shows lateral aperture injection hole sealing schematic diagram;
Fig. 8 shows coal roadway drilling construction floor map;
Fig. 9 shows coal road first and to circulate drilling construction A-A sectional schematic diagram;
Figure 10 shows coal road second and to circulate drilling construction B-B sectional schematic diagram;
Figure 11 shows the layout schematic diagram of regional effect inspection hole;
Figure 12 shows coal road work plane dense shallow hole floor map;
Figure 13 shows coal road work plane dense shallow hole C-C sectional schematic diagram;
Figure 14 shows the longitudinal profile schematic diagram of coal road work plane dense shallow hole.
Wherein, wait to dig coal road 101, coal seam 102, wait to dig coal road 103, floor roadway 201, both sides, tunnel outline line 202, the control line 203 of boring, layer-through drilling 301, gas drainage pipe 401, gas drainage under suction passage 402, cement paste 403, Grouting Pipe 404, cloth 405, grouting pump 406, valve 407, stack 408, as the concordant boring 501 of the first circulation boring, as the concordant boring 502 of the second circulation boring, regional effect inspection hole 503, range test test point 504, dense shallow hole 601, partial result inspection hole a, b, c.
Detailed description of the invention
In conjunction with the accompanying drawings, the present invention is further detailed explanation.These accompanying drawings are the schematic diagram of simplification, only basic structure of the present invention are described in a schematic way, and therefore it only shows the formation relevant with the present invention.
Before dangerous seam with potential 102 mining work, by being evenly distributed on layer-through drilling 301 and the concordant boring of the some in dangerous seam with potential 102, large area takes out coal seam 102 gas in advance at twice, reduces this pressure of coal seam 102, release coal body Elastic latent energy, eliminates gas outburst risk.The control Gas Outburst construction method (hereinafter referred to as construction method) being suitable for the exploitation of unprotected single coal bed described in this is mainly used in eliminating single coal bed 102 gas outburst risk that unprotect layer can be adopted.Control is outstanding referred to as protrusion-dispelling.
Fig. 1 shows the flow chart of this construction method.
As shown in Figure 1, a kind of control Gas Outburst construction method being suitable for the exploitation of unprotected single coal bed, comprises the steps:
Step S100, a floor roadway 201 of constructing in the rock stratum of coal seam 102 base plate vicinity.
Step S200, some layer-through drillings 301 of constructing to coal seam 102 in described floor roadway 201, to carry out first time Gas pre-drainage, to realize first time release;
Step S300, carries out shallow bore hole discharge release to coal road work plane, to construct the boring of some concordants, to carry out second time Gas pre-drainage, to realize release for the second time at coal road work plane to described coal seam 102;
Step S400, described coal seam 102 to be detected is without behind outburst dangerous area, carries out coal roadway tunneling.
This construction method adopts the protrusion-dispelling means of " 2+1 ", namely first does two sub-region protrusion-dispellings and to try again local protrusion-dispelling.Described two sub-region protrusion-dispellings comprise: floor roadway 201 layer-through drilling 301 takes out coal road gas region protrusion-dispelling in advance and this gas region, coal seam 102 protrusion-dispelling is taken out in the boring of coal road work plane concordant in advance, and described local protrusion-dispelling is that shallow bore hole 601 discharges; Concrete, a floor roadway 201 of first first constructing in the rock stratum apart from coal seam 102 base plate 8-10 rice, some layer-through drillings 301 of constructing in floor roadway 201, carry out gas drainage under suction; Again in this coal seam 102 work plane construction once some concordant boring before coal roadway tunneling, carry out gas drainage under suction; Finally do the Local provisions that shallow bore hole 601 discharges, after validity check is qualified, carry out coal roadway tunneling.This construction method effectively improves protrusion-dispelling effect, and the error of eradicating efficacy testing stage.Work plane is the development end in tunnel.
Fig. 2 shows the particular flow sheet of this construction method.
Control Gas Outburst construction method of the present invention concrete step launched in implementation process is as follows:
Step S1, a floor roadway of constructing in the rock stratum of the base plate vicinity in described coal seam;
Step S2, some layer-through drillings of constructing to described coal seam in floor roadway;
Step S3, takes out described coal-bed gas in advance in floor roadway, carries out first time release to the gas in coal seam;
Does step S4, judge whether up to standard? if up to standard, then carry out S5 step; If not up to standard, then repeat S2 step, S3 step (encryption boring continues extraction).
Step S5, carries out the 1st sub-region verifying outburst prevention effect to described coal seam in floor roadway;
Whether step S6, check up to standard? if up to standard, then carry out S7 step; If not up to standard, then repeat S3 step (continuation extraction).
Step S7, the coal road work plane in described coal seam is to the boring of this coal seam construction concordant;
Step S8, at the work plane of described coal road to this coal seam Gas pre-drainage, carries out second time release to the gas in coal seam;
Step S9, the 2nd sub-region verifying outburst prevention effect;
Whether step S10, check up to standard? if up to standard, then carry out S11 step; If not up to standard, then repeat S8 step (continuation extraction).
Step S11, area validation;
Whether step S12, verify up to standard? if up to standard, then carry out S13 step; If not up to standard, then repeat S14 step.
Step S13, carries out coal roadway tunneling in described coal seam;
Step S14, at the work plane of described coal road to this coal seam drilling dense shallow hole, makes gas naturally discharge a period of time, carries out third time release to the gas in coal seam;
Step S15, carries out work plane verifying outburst prevention effect in described coal seam;
Whether step S16, check up to standard? if up to standard, then carry out S17 step; If not up to standard, then repeat S14 step.
Step S17, carries out coal roadway tunneling in described coal seam.
To construct to coal seam 102 in described floor roadway 201 in described step S200 some layer-through drillings 301, as follows with the detailed description of the invention of carrying out first time Gas pre-drainage.
Fig. 3 shows floor roadway boring and arranges sectional schematic diagram.Wherein, 1,2,3,4,5,6,7 holes number being respectively layer-through drilling.
Fig. 4 shows floor roadway boring plane of arrangement schematic diagram.
Preferably, described layer-through drilling 301 is 7, and is fan-shapedly uniformly distributed, and each layer-through drilling 301 penetrates described coal seam 102 at least 0.5m respectively, and the control line 203 of boring is apart from the outer at least each 15m of both sides, the tunnel outline line of described floor roadway 201.
As shown in Figure 3 and Figure 4, the Specific construction step of described layer-through drilling 301 is as follows:
(1) described floor roadway 201 is perpendicular to 8-10m below the base plate of coal seam 102, and floor roadway 201 must perform the measure of " first visit and dig afterwards " in the process of driving, prevents from missing exposed coal layer 102 in excavation work.
(2) drilling construction adopts ZL-150 type mining hydraulic drilling rig.Boring aperture Ф 90mm
(3) adopt fan transfer mode, boring should control wholely to take out region in advance and even cloth hole, and the coal seam 102 that should investigate according to reality of the spacing of wells effectively drainage radius be determined.
(4) every section of boring detailed description of the invention along the tunnelling direction of floor roadway 201 comprises: every section 12 row, often arrange 7 borings, array pitch 5m, and every section of boring control range is: longitudinally (along tunnelling direction) 60m, and the control line 203 of boring is apart from the outer at least each 15m of both sides, tunnel outline line, be namely positioned at fan-shaped outermost two layer-through drillings 301 respectively with the distance of the both sides, tunnel of described floor roadway 201; For gently inclined seam 102 (lower same), the tunnel work plane of floor roadway 201 and coal seam 102 normal distance 8.4m (see Fig. 3, Fig. 4).Boring need penetrate coal seam 1020.5m.Data of holes drilled is in table 1.
(5) every row hole drilling construction complete after, gas drainage pipe 401 can be buried underground, sealing of hole, carry out gas drainage under suction.
Table 1 floor roadway 201 data of holes drilled
Parameter declaration (lower same): S2 refers to the distance of drilling orifice to center line, and S1 refers to that the distance of 1m to center line stepped back by drilling rod, Δ S=S2-S1.
Described first time, Gas pre-drainage was identical with the method for second time Gas pre-drainage, and comprised the steps:
Step S210, carries out sealing of hole, to form gas drainage under suction passage 402 to layer-through drilling 301 or concordant boring.Namely to bury after gas drainage pipe 401 sealing of hole again underground, carry out gas drainage under suction.Optionally, adopt mine polyurethane gas pore-sealing liquid and cloth 405 to carry out first sealing of hole, carry out secondary hole sealing by cement injection.Wherein, plugging equipment: adopt 2ZBQ-9/3 Pneumatic grouting pump 406 or the funneling grouting pump 406 of BFZ-10/1.2.Preferably, sealed borehole length: the sealing of hole segment length of layer-through drilling 301 must not be less than 5m, the sealing of hole segment length of concordant boring must not be less than 8m.
Step S220, is connected to an orifice flowmeter by the gas drainage pipe 401 being positioned at each layer-through drilling 301 or concordant boring and carries out extraction concentration and flow measurement, and carry out extraction by extraction main line.Concrete, drilling orifice extraction negative pressure must not be less than 13kPa; The concentration that draws out methane must not lower than 25%; This coal seam 102 take out after coal seam 102 residual gas content lower than 8m 3/ t.
Fig. 5 shows to pre-extraction hole injection hole sealing schematic diagram.
Fig. 6 shows lower to pre-extraction hole injection hole sealing schematic diagram.
Fig. 7 shows lateral aperture injection hole sealing schematic diagram.
In described step S210, layer-through drilling 301 or concordant boring are carried out sealing of hole and comprised with the method forming gas drainage under suction passage 402: be upward hole sealing of hole, lower to hole sealing of hole, lateral aperture sealing of hole three kinds of optional embodiments.
As shown in Figure 5, wherein, described upward hole sealing of hole, be embedded in layer-through drilling 301 or concordant boring by Grouting Pipe 404 and gas drainage pipe 401, and by Grouting Pipe 404 to layer-through drilling 301 or the slip casting of concordant bore inner, when the aperture of gas drainage pipe 401 overflows cement paste 403, stop slip casting solidifying to cement paste 403, then carry out gas drainage under suction.Concrete, connect with the slip casting steel pipe of diameter DN15 with cement injection pump 406, disposablely continuously cement mixing is starched in injection hole, when gas drainage pipe 401 aperture overflows cement paste 403, stop slip casting immediately, then Grouting Pipe 404 gate is turned off.Until slip casting after 1 day, namely reach 50% of design grade until cement paste 403 and afterwards access extraction again.
As shown in Figure 6, described lower to hole sealing of hole, be embedded in layer-through drilling 301 or concordant boring by gas drainage pipe 401, cement paste 403 poured into in hole from the aperture of layer-through drilling 301 or concordant boring, when aperture overflows cement paste 403, stops grouting.This sealing of hole mode can take out while injection hole sealing, save engineering time.
As shown in Figure 7, described lateral aperture sealing of hole, be embedded in layer-through drilling 301 or concordant boring by gas drainage pipe 401, Grouting Pipe 404, stack 408, and build first, second sealing of hole layer in layer-through drilling 301 or concordant boring, first, second sealing of hole floor described forms a slip casting room; Gas drainage pipe 401 runs through first, second sealing of hole layer, described stack 408, Grouting Pipe 404 extend to described slip casting indoor through the first sealing of hole layer and carry out slip casting, when stack 408 overflows cement paste 403, stop slip casting, then Grouting Pipe 404 and stack 408 mouth of pipe are carried out shutoff.This sealing of hole mode can take out while injection hole sealing, save engineering time.
Fig. 8 shows coal roadway drilling construction floor map.
Fig. 9 shows coal road first and to circulate drilling construction A-A sectional schematic diagram.
Figure 10 shows coal road second and to circulate drilling construction B-B sectional schematic diagram.
In Fig. 8 to Figure 10, numeral 1 to 24 represents the hole number of concordant boring.
As shown in Fig. 8 to Figure 10, to construct to described coal seam 102 boring of some concordants at coal road work plane in described step S300, as follows in the concrete mode of carrying out second time Gas pre-drainage:
(1) terminate in floor roadway 201 extraction control range (60m) extraction, in floor roadway 201, carry out first time regional effect inspection.After meeting the requirements, then in coal road work plane construction extraction boring, extraction is carried out to this coal seam 102, and carries out extraction concentration and flow detection.
(2) the outer at least 15m of control line distance both sides, tunnel outline line of concordant boring, the band length that boring controls is not less than 60m.Data of holes drilled is in table 2 and table 3.
Table 2 first circulation boring 501 parameter
Kong Hao S1 S2 △S Hole depth (m) Remarks
1、10、9、18 1.38 1.6 0.22 62
2、11、8、17 1.03 1.2 0.17 61
3、12、7、16 0.68 0.8 0.12 60
4、13、6、15 0.35 0.4 0.05 60
5、14 0 0 0 60
19、20 1.71 2 0.29 58
21、22 1.63 2 0.37 46 Exit 0.5m perforate
23、24 1.55 2 0.45 35 Exit 1m perforate
Table 3 second circulation boring 502 parameter
Figure 11 shows the layout schematic diagram of regional effect inspection hole.
Also comprise in described step S300, after second time Gas pre-drainage, carry out the method for residual gas assay, the method adopts three detection borings to carry out the remaining detection of gas, three are detected centre and the both sides that boring is arranged at described work plane respectively, and it is consistent with the tunneling direction of described work plane to be positioned at middle detection boring.Wherein, described detection boring is regional effect inspection hole.
Wherein, the remaining detection of gas adopts WP-1 coal seam 102 gas pressure (content) Quick testing instrument to measure.
Verification test point one be constructed meet head on concordant boring after regional effect inspection hole, coal seam 102 residual gas content is lower than 8m 3/ t just can recover drilling depth, is more than or equal to 8m 3/ t then must readopt region outburst prevention measures; Verification test point two is regional effect inspection hole when recovering drilling depth 20m position, lower than 8m 3/ t just can recover drilling depth, is more than or equal to 8m 3/ t then must readopt region outburst prevention measures; Verification test point three for tunnel drilling depth put in place after the pre-gaging hole of next race way outburst prevention measures.
Regional effect inspection hole adopts the construction of ZL-150 type mining hydraulic drilling rig.Boring aperture Ф 75mm.
Optionally, step S300 reach inspection up to standard after, carry out area validation prediction, this area validation prediction method, specifically comprise:
(1) drilling cuttings desorption of mash gas index K1 value, coal powder quantity of bore Smax and coal powder quantity of bore S value is adopted to carry out area validation.
The method of drilling index threshold of area validation outburst hazard is in table 4.
The method of drilling index tables of critical values of table 4 area validation outburst hazard
(2) when work plane enters this region, at least twice area validation is carried out continuously immediately;
(3) coal road work plane often advances 10 ~ 50m (take out in advance in complicated geological region or take coal seam 102 gas region outburst prevention measures and other necessary situation is appropriate to the occasion gets the small value) at least to carry out twice area validation;
(4) area validation is carried out continuously at structure destruction band;
(5) when adopting method of drilling index prediction coal road work plane outburst hazard, nearly level, gently inclined seam 102 work plane should forwards coal body at least construct 3 holes, at least construct 2 holes in inclination or half-edge coal seam 102, mensuration drilling cuttings desorption of mash gas index and coal powder quantity of bore.
(6) pre-gaging hole adopts wind coal borer to creep into, aperture Φ 42mm, hole depth 8 ~ 10m.
(7) boring is arranged respectively in driving face centre and both sides, should be arranged in soft layering as far as possible; Interstitial hole is parallel to coal road roadway workface direction, and two side holes is apart from lane side 0.3 ~ 0.5m, and whole hole should control the outer 2 ~ 4m of lane side outline line.
(8) pre-gaging hole often creeps into whole coal powder quantity of bore S that 1m measures this 1m section, often creeps into 2m and at least measures a drilling cuttings desorption of mash gas index K1 value.
(9) 1 advanced pre-gaging hole apart from being not less than 10m should also at least be made a call at coal road work plane, detection geological structure and the outstanding omen of observation.
(10) be all less than threshold if survey the coal powder quantity of bore S, all measured values of drilling cuttings desorption of mash gas index K1 that obtain, and do not find other abnormal conditions, then this work plane is predicted as without area of coal mining face with potential outburst danger, and namely area validation is up to standard; Otherwise, be area of coal mining face with potential outburst danger.
(11) area validation up to standard after, safety prevention measure arrangement can be taked to carry out coal roadway tunneling drilling depth, not up to standard, must local prevent outburst measure be adopted.
(12) local prevent outburst measure and coal roadway tunneling drilling depth all should carry out in time, in order to avoid this extra-regional gas permeation in coal seam 102 is come in, cause coal seam, one's respective area 102 gas bearing capacity and increase.
After area validation, carrying out local prevent outburst measure.
Described local prevent outburst measure comprises:
Work plane outburst hazard is predicted, the method that itself and area validation are predicted is similar, specifically comprises:
(1) according to boring along the maximum coal powder quantity of bore Smax of hole depth every meter and Desorption Index for Drill Cuttings K1 or Δ h2, prediction work face outburst hazard.This construction method adopts drilling cuttings desorption of mash gas index K1 value as prediction index.
(2) work plane outburst hazard critical indicator, in table 5.
Table 5. work plane outburst hazard critical indicator table
Geological structural belt comprises 20m scope before and after structural belt, coal seam 102 varied in thickness band, area of stress concentration etc.
(3) pre-gaging hole adopts wind coal borer to creep into, aperture Φ 42mm, hole depth 8 ~ 10m.
(4) often creep into 1m in drilling process and measure coal powder quantity of bore once, often creep into 2m and survey a Desorption Index for Drill Cuttings.
(5) each coal road work plane should make a call to 2 ~ 3 predictions boring (half-edge coal seam 102 makes a call to 2 holes).
(6) all prediction boring all should be arranged in the softest layering coal of work plane as far as possible, and ensures that pre-gaging hole creeps into all the time in this soft layering as far as possible.
(7) WTC Gas Outburst Parameters Instrument, is adopted to measure K1 value.The concrete operations of instrument, refer to " assay method of drilling cuttings desorption of mash gas index " (MT/T 641-1996) and " WTC Gas Outburst Parameters Instrument method of operating " (Chongqing Mei Ke institute).
Figure 12 shows coal road work plane dense shallow hole floor map.
Figure 13 shows coal road work plane dense shallow hole C-C sectional schematic diagram.
Figure 14 shows the longitudinal profile schematic diagram of coal road work plane dense shallow hole.
In Figure 12 to Figure 14, numeral 1 to 33 represents the hole number of shallow bore hole 601.
In described step S400 to coal road work plane carry out shallow bore hole discharge release method comprise:
When the thickness in distance coal seam 102 of meeting head on is greater than 2.4m, be fan-shaped equally distributed dense shallow hole 601 meeting head on to offer three rows; When the thickness in distance coal seam 102 of meeting head on is less than 2.4m, be fan-shaped equally distributed dense shallow hole 601 meeting head on to offer two rows; Wherein, each round number is 11, and the drainage radius of each boring is 0.7m, and the control line 203 of boring is apart from the outer at least each 5m of both sides, the tunnel outline line of described coal road.Wherein, dense shallow hole 601 can referred to as shallow bore hole 601.
The concrete steps of the outburst prevention measures of described coal road work plane are as follows:
(1) coal road work plane outburst prevention measures adopts dense shallow hole 601 to discharge release.
(2) this coal seam 102 extraction of coal road work plane is complete, carries out region measure effect inspection and area validation, after meeting the requirements, before coal roadway tunneling, then carries out shallow bore hole 601 at coal road work plane and naturally discharges.
(3) dense shallow hole 601 adopts mining hydraulic drilling rig to creep into, footpath Φ 75mm, hole depth 10 ~ 11m.
(4) arrange dense shallow hole 601 in construction three of meeting head on, hole count is 33, and the drainage radius of each boring is 0.7m, each 5m of control range roadway's sides, and when coal seam 102 thickness of meeting head on is lower than 2.4m, holes to put by two arrangements.
(5), shallow bore hole 601 bleeder off hole of coal road work plane arranges and sees Figure 11, Figure 12 and Figure 13, and data of holes drilled is in table 6.
(6), shallow bore hole 601 drain time of coal road work plane is chosen as 5-10 days.
Table 6 coal road work plane discharge shallow bore hole 601 parameter list
After the outburst prevention measures completing described coal road work plane, carry out validity check to the outburst prevention measures of this coal road work plane, this checking procedure comprises:
(1) dense shallow hole 601 is constructed complete, carries out nature and discharges a period of time, after reaching the scheduled time, then carries out outburst prevention measures validity check.
(2) method of drilling index is adopted to carry out the outburst prevention measures validity check of portion of district.
(3) partial result inspection hole adopts wind coal borer to creep into, aperture Φ 42mm, hole depth 10m.Control range roadway's sides 4m, is shown in that Figure 11, data of holes drilled are in table 6.
(4) outburst hazard critical indicator, with table 5 " prediction of work plane outburst hazard ".
(3) detection principle.
A, work as K1<0.7, during Smax<6kg/m, then prophylactico-therapeutic measures is effective, to guarantee to calculate apart from 5m projection in advance, allow drilling depth 4.5m according to the intensive drilling design of construction in front, tunnel.
B, before and after fault tectonic band and geological structure change band within the scope of 20m, work as K1<0.5, during S<5.4kg/m, only allow partial circulating drilling depth right overhead, i.e. a permission drilling depth 1.5m, must keep front to have the advanced distance of 7m.
If when c K1 >=0.7 or Smax >=6kg/m, must according to partial result inspection hole situation, complement 3 measure holes are carried out on the limit, hole of the partial result inspection hole of overcritical index, primary effect inspection is carried out again between complement measure hole, only when partial result inspection hole meets the requirement of cloth hole, three groups of not overcritical indexs of effect inspection index, then prophylactico-therapeutic measures is effective; Otherwise then must readopt region outburst prevention measures.
D, employing WTC Gas Outburst Parameters Instrument measure K1 value.
The foregoing is only preferred embodiment of the present invention, not in order to limit the present invention, within the spirit and principles in the present invention all, any amendment done, equivalent replacement, improvement etc., all should be included within protection scope of the present invention.

Claims (10)

1. be suitable for a control Gas Outburst construction method for unprotected single coal bed exploitation, comprise the steps:
Step S100, a floor roadway of constructing in the rock stratum near seat earth;
Step S200, some layer-through drillings of constructing to coal seam in described floor roadway, to carry out first time Gas pre-drainage;
Step S300, to construct to described coal seam the boring of some concordants at coal road work plane, to carry out second time Gas pre-drainage;
Step S400, carry out shallow bore hole discharge release to coal road work plane, described coal seam to be detected is without behind outburst dangerous area, carries out coal roadway tunneling.
2. control Gas Outburst construction method according to claim 1, is characterized in that,
Described floor roadway is perpendicular to 8-10m below seat earth.
3. control Gas Outburst construction method according to claim 2, is characterized in that,
Described layer-through drilling is 7, and is fan-shapedly uniformly distributed, and each layer-through drilling penetrates described coal seam at least 0.5m respectively, and the control line of boring is apart from the outer at least each 15m of both sides, the tunnel outline line of described floor roadway.
4. control Gas Outburst construction method according to claim 3, is characterized in that,
Described first time, Gas pre-drainage was identical with the method for second time Gas pre-drainage, and comprised the steps:
Step S210, carries out sealing of hole, to form gas drainage under suction passage to layer-through drilling or concordant boring;
Step S220, is connected to an orifice flowmeter by the gas drainage pipe being positioned at each layer-through drilling or concordant boring and carries out extraction concentration and flow measurement, and carry out extraction by extraction main line.
5. control Gas Outburst construction method according to claim 4, is characterized in that,
Carry out sealing of hole to layer-through drilling or concordant boring in described step S210 to comprise with the method forming gas drainage under suction passage: upward hole sealing of hole, be embedded in layer-through drilling or concordant boring by Grouting Pipe and gas drainage pipe, and by Grouting Pipe to layer-through drilling or the slip casting of concordant bore inner, when the aperture of gas drainage pipe overflows cement paste, stop slip casting to cement slurry sets, then carry out gas drainage under suction.
6. control Gas Outburst construction method according to claim 4, is characterized in that,
In described step S210, layer-through drilling or concordant boring are carried out sealing of hole and are comprised with the method forming gas drainage under suction passage: under to hole sealing of hole, be embedded in layer-through drilling or concordant boring by gas drainage pipe, cement paste is poured into in hole from the aperture of layer-through drilling or concordant boring, when aperture overflows cement paste, stop grouting.
7. control Gas Outburst construction method according to claim 4, is characterized in that,
Carry out sealing of hole to layer-through drilling or concordant boring in described step S210 to comprise with the method forming gas drainage under suction passage: lateral aperture sealing of hole, be embedded in layer-through drilling or concordant boring by gas drainage pipe, Grouting Pipe, stack, and first, second sealing of hole layer is built in layer-through drilling or concordant boring, first, second sealing of hole floor described forms a slip casting room;
Gas drainage pipe runs through first, second sealing of hole layer, and described stack, Grouting Pipe extend to described slip casting indoor through the first sealing of hole layer and carry out slip casting, when stack overflows cement paste, stops slip casting, then Grouting Pipe and the stack mouth of pipe are carried out shutoff.
8. according to the arbitrary described control Gas Outburst construction method of claim 5-7, it is characterized in that, also comprise in described step S300, after second time Gas pre-drainage, carry out the method for residual gas assay, the method adopts three detection borings to carry out the remaining detection of gas, and three are detected centre and the both sides that boring is arranged at coal road work plane respectively, and it is consistent with the tunneling direction of coal road work plane to be positioned at middle detection boring.
9. control Gas Outburst construction method according to claim 8, is characterized in that, the method for described shallow bore hole discharge release comprises:
When the thickness in distance coal seam of meeting head on is greater than 2.4m, be fan-shaped equally distributed dense shallow hole meeting head on to offer three rows;
When the thickness in distance coal seam of meeting head on is less than 2.4m, be fan-shaped equally distributed dense shallow hole meeting head on to offer two rows;
Wherein, each round number is 11, and the control line of boring is apart from the outer at least each 5m of both sides, the tunnel outline line of described coal road.
10. prevent and treat a Gas Outburst construction method, comprise the steps:
Step S1, a floor roadway of constructing in the rock stratum of the base plate vicinity in described coal seam;
Step S2, some layer-through drillings of constructing to described coal seam in floor roadway;
Step S3, takes out described coal-bed gas in advance in floor roadway, carries out first time release to the gas in coal seam;
Step S4, judges whether up to standard; If up to standard, then carry out S5 step; If not up to standard, then repeat S2 step, S3 step, namely encryption boring continues extraction;
Step S5, carries out the 1st sub-region verifying outburst prevention effect to described coal seam in floor roadway;
Whether step S6, check up to standard; If up to standard, then carry out S7 step; If not up to standard, then repeat S3 step, namely continue extraction;
Step S7, the coal road work plane in described coal seam is to the boring of this coal seam construction concordant;
Step S8, at the work plane of described coal road to this coal seam Gas pre-drainage, carries out second time release to the gas in coal seam;
Step S9, the 2nd sub-region verifying outburst prevention effect;
Whether step S10, check up to standard; If up to standard, then carry out S11 step; If not up to standard, then repeat S8 step, namely continue extraction;
Step S11, area validation;
Whether step S12, verify up to standard; If up to standard, then carry out S13 step; If not up to standard, then repeat S14 step;
Step S13, carries out coal roadway tunneling in described coal seam;
Step S14, at the work plane of described coal road to this coal seam drilling dense shallow hole, makes gas naturally discharge a period of time, carries out third time release to the gas in coal seam;
Step S15, carries out work plane verifying outburst prevention effect in described coal seam;
Whether step S16, check up to standard; If up to standard, then carry out S17 step; If not up to standard, then repeat S14 step;
Step S17, carries out coal roadway tunneling in described coal seam.
CN201410787384.6A 2014-12-16 2014-12-16 Gas outburst prevention construction method suitable for unprotected single coal seam mining Pending CN104675426A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410787384.6A CN104675426A (en) 2014-12-16 2014-12-16 Gas outburst prevention construction method suitable for unprotected single coal seam mining

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410787384.6A CN104675426A (en) 2014-12-16 2014-12-16 Gas outburst prevention construction method suitable for unprotected single coal seam mining

Publications (1)

Publication Number Publication Date
CN104675426A true CN104675426A (en) 2015-06-03

Family

ID=53310954

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410787384.6A Pending CN104675426A (en) 2014-12-16 2014-12-16 Gas outburst prevention construction method suitable for unprotected single coal seam mining

Country Status (1)

Country Link
CN (1) CN104675426A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105401976A (en) * 2015-12-30 2016-03-16 重庆南桐矿业有限责任公司 Outburst prevention measure in wire saw joint-cutting region of coal seam floor
CN105675815A (en) * 2016-01-25 2016-06-15 西南石油大学 Method for measuring widths of tunnel gas pre-discharge zone of coal mine working face
CN109578055A (en) * 2018-11-21 2019-04-05 张登龙 A kind of coal and CO2The control method of prominent accident
CN113216986A (en) * 2021-06-17 2021-08-06 袁勇猛 Method for rapidly tunneling close-distance coal seam and gas control method
CN115717529A (en) * 2022-11-23 2023-02-28 焦作煤业(集团)有限责任公司 Method for evaluating construction effect of protective layer in coal seam

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105401976A (en) * 2015-12-30 2016-03-16 重庆南桐矿业有限责任公司 Outburst prevention measure in wire saw joint-cutting region of coal seam floor
CN105675815A (en) * 2016-01-25 2016-06-15 西南石油大学 Method for measuring widths of tunnel gas pre-discharge zone of coal mine working face
CN109578055A (en) * 2018-11-21 2019-04-05 张登龙 A kind of coal and CO2The control method of prominent accident
CN113216986A (en) * 2021-06-17 2021-08-06 袁勇猛 Method for rapidly tunneling close-distance coal seam and gas control method
CN113216986B (en) * 2021-06-17 2024-05-24 袁勇猛 Rapid tunneling method and gas control method for close-range coal seam
CN115717529A (en) * 2022-11-23 2023-02-28 焦作煤业(集团)有限责任公司 Method for evaluating construction effect of protective layer in coal seam

Similar Documents

Publication Publication Date Title
CN104533511A (en) Construction method for preventing and treating coal and gas outburst in coal roadway heading process
Sui et al. Hydrogeological analysis and salvage of a deep coalmine after a groundwater inrush
CN101403314B (en) Coal mine down-hole drilling hydraulic fracturing anti-reflection mash gas extraction technique
CN103867229B (en) A kind of coal mine large-mining is dark prevents and treats comprehensive treatment method for water with lower group of coal mining
Nilsen Characteristics of water ingress in Norwegian subsea tunnels
CN104675426A (en) Gas outburst prevention construction method suitable for unprotected single coal seam mining
Wang et al. Theoretical and experimental study of external water pressure on tunnel lining in controlled drainage under high water level
CN110617072B (en) Tunnel excavation construction method for obliquely passing existing operation tunnel at minimum clear distance
CN103291325A (en) Method for preventing and controlling water burst of coal mining base board rock stratum on pressure bearing water body
CN108331573A (en) The abandoned well administering method of bank
Jun et al. Elimination of coal and gas outburst risk of low‐permeability coal seam using high‐pressure water jet slotting technology: a case study in Shihuatian Coal Mine in Guizhou Province, China
CN102678167A (en) Hydraulic-fracturing rock cross-cut coal uncovering method for short-distance coal beds
CN106988754A (en) Narrow space shield launching method
CN110295952A (en) More depth layer positions underground storage and its construction method based on the building of discarded pit shaft
CN104533512A (en) Construction method for preventing and treating gas outburst in coal roadway heading process
CN108757043A (en) One kind is for the anti-method of harnessing the river of getting working face
CN105089043B (en) Spatial isolation type runway pavement underlying goaf treatment method
CN106968664A (en) A kind of floor undulation destruction band deep drilling water filling detection method
CN114635748A (en) Shaft sinking water damage prevention method
Lawrence et al. The role of risk and assumption in the engineering geology of Crossrail
CN113217036A (en) Post-grouting construction method for tunnel structure at water burst section of fault fracture zone
CN108457306B (en) Pile tube cooperated vertical side wall horizontal bottom-making basin-shaped freezing water stop construction method for 4/6 pilot tunnel PBA construction method
CN112049105A (en) Construction method for sealing and stopping water of tunnel diaphragm wall by water-rich sand layer mining method
CN114542077B (en) Vertical well ground curtain grouting method combining grouting holes and slurry discharging holes
CN109707411A (en) A kind of technique of tunnel grouting construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20150603

WD01 Invention patent application deemed withdrawn after publication