CN104652425A - Technical method for reinforcing soil of shield end well through bamboo reinforcement concrete pouring pile - Google Patents

Technical method for reinforcing soil of shield end well through bamboo reinforcement concrete pouring pile Download PDF

Info

Publication number
CN104652425A
CN104652425A CN201310595818.8A CN201310595818A CN104652425A CN 104652425 A CN104652425 A CN 104652425A CN 201310595818 A CN201310595818 A CN 201310595818A CN 104652425 A CN104652425 A CN 104652425A
Authority
CN
China
Prior art keywords
bamboo
pile
rig
bamboo reinforcement
shield
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201310595818.8A
Other languages
Chinese (zh)
Inventor
王世友
杜亚明
张慧军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TIANJIN URBAN CONSTRUCTION TUNNEL CO Ltd
Original Assignee
TIANJIN URBAN CONSTRUCTION TUNNEL CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TIANJIN URBAN CONSTRUCTION TUNNEL CO Ltd filed Critical TIANJIN URBAN CONSTRUCTION TUNNEL CO Ltd
Priority to CN201310595818.8A priority Critical patent/CN104652425A/en
Publication of CN104652425A publication Critical patent/CN104652425A/en
Pending legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a technical method for reinforcing soil of shield end well through bamboo reinforcement concrete pouring pile. The method comprises the steps of (1) analyzing the environment; (2) preparing a scheme; (3) arranging a flat field for building a working platform; (4) mounting a drilling machine and a pressing sleeve to drill a hole; (5) positioning a bamboo reinforcement cage, arranging a guide pipe, and then pouring concrete; (6) mounting a pulling-drawing sleeve, and inspecting the quality of the formed pile after fixing for a period of time. With the adoption of the method, the economic benefit can be ensured, and the use safety can be improved; the sediment and underwater can be avoided flowing from a discharging hole into a working well during discharging a shield machine; the shield excavation can be performed smoothly; the wear of a shield end can be reduced, and the working efficiency can be increased.

Description

A kind of bamboo reinforcement concrete filling pile is at the technical method of shield end well soil stabilization
Technical field
The present invention is specially the technical method of a kind of bamboo reinforcement concrete filling pile at shield end well soil stabilization.
Background technology
Into and out of the critical process that hole end well strengthening construction is shield launching and arrival construction.Before shield launching, generally according to the stable case on stratum, hole, take treatment measures targetedly.Reservoir treating generally adopts method has: cement mixing pile, rotary churning pile, slip casting method, and SMW engineering method, freezing measure carry out stratum consolidation process.Select any method according to geology, underground water, covering layer, shield structure diameter, shield machine type, construction environment factor, also will should consider safety, application property, cost, schedule requirement simultaneously.Be in grit layer geological stratification in geology, in order to avoid silt particle when shield machine is appeared and underground water pour in active well from going out hole, ensure that shield driving is carried out smoothly, it has been decided through consideration and into and out of the stratum near the end well of hole, bamboo reinforcement concrete filling pile consolidation process has been carried out to shield structure.
Summary of the invention
Technical problem solved by the invention is the technical method providing a kind of bamboo reinforcement concrete filling pile at shield end well soil stabilization, to solve the problem proposed in above-mentioned background technology.
In order to achieve the above object, the present invention realizes by the following technical solutions: a kind of bamboo reinforcement concrete filling pile, at the technical method of shield end well soil stabilization, comprises the following steps:
(1) environmental analysis;
(2) develop programs;
(3) arrange out one piece of flat field ground, facilitate building platform;
(4) rigging up and gland pipe make drilling and forming hole, forbidden for preventing stake position, it is important in construction to reserve center and correct installation auger, to the rig having boring tower, the power of rig is first utilized to coordinate with neighbouring cage, drilling rod is moved and roughly locates, again with jack by frame jack-up, accurate location, make gin wheel, the hole clipping of drill bit or fixing drilling rod and casing center are on a vertical line, to ensure the verticality of rig, the deviation of rig position is not more than 2cm, behind align piles position, with tie plate horizontal drill machine crossbeam, and be symmetrical on drill axis at tower top and pull on cable wind rope,
(5) lay bamboo reinforcement cage, put into conduit after fluid concrete inward, because mao bamboon is diametrically lower uneven, to note the colligation of whole bamboo mid portion in bamboo reinforcement cage process of binding to the maximum position of pile body center stressed, thus be conducive to ensureing that pile body is stablized, during perfusion, concrete does not interrupt, otherwise easily occurs pile breaking phenomenon;
(6), after drawing sleeve pipe being installed, after a period of time is fixing, pile quality is checked;
Further, boring described in step (1) is because bamboo is that large therefore its buoyancy of diameter of hollow structure and bamboo is much larger than the buoyancy of reinforcing bar, be difficult to directly insert in insertion sludge process and therefore reduce buoyancy in bamboo body boring means, thus successfully bamboo cage is in place.
beneficial effect:
The inventive method also improves use safety while guarantee economic benefit, and when shield machine can be avoided to appear, silt particle and underground water pour in active well from going out hole, ensures that shield driving is carried out smoothly, reduces the wearing and tearing of shield end, increase work efficiency.
Detailed description of the invention
Reaching object to make technological means of the present invention, creation characteristic, workflow, using method and effect is easy to understand, below in conjunction with the specific embodiment of the invention, setting forth the present invention further.
Case study on implementation one:
Bamboo reinforcement concrete filling pile, at a technical method for shield end well soil stabilization, comprises following concrete steps:
(1) environmental analysis;
(2) develop programs;
(3) arrange out one piece of flat field ground, facilitate building platform;
(4) rigging up and gland pipe make drilling and forming hole, forbidden for preventing stake position, it is important in construction to reserve center and correct installation auger, to the rig having boring tower, the power of rig is first utilized to coordinate with neighbouring cage, drilling rod is moved and roughly locates, again with jack by frame jack-up, accurate location, make gin wheel, the hole clipping of drill bit or fixing drilling rod and casing center are on a vertical line, to ensure the verticality of rig, the deviation of rig position is 1cm, behind align piles position, with tie plate horizontal drill machine crossbeam, and be symmetrical on drill axis at tower top and pull on cable wind rope,
(5) lay bamboo reinforcement cage, put into conduit after fluid concrete inward, because mao bamboon is diametrically lower uneven, to note the colligation of whole bamboo mid portion in bamboo reinforcement cage process of binding to the maximum position of pile body center stressed, thus be conducive to ensureing that pile body is stablized, during perfusion, concrete does not interrupt, otherwise easily occurs pile breaking phenomenon;
(6), after drawing sleeve pipe being installed, after a period of time is fixing, pile quality is checked;
Further, boring described in step (1) is because bamboo is that large therefore its buoyancy of diameter of hollow structure and bamboo is much larger than the buoyancy of reinforcing bar, be difficult to directly insert in insertion sludge process and therefore reduce buoyancy in bamboo body boring means, thus successfully bamboo cage is in place.
Case study on implementation two:
Bamboo reinforcement concrete filling pile, at a technical method for shield end well soil stabilization, comprises following concrete steps:
(1) environmental analysis;
(2) develop programs;
(3) arrange out one piece of flat field ground, facilitate building platform;
(4) rigging up and gland pipe make drilling and forming hole, forbidden for preventing stake position, it is important in construction to reserve center and correct installation auger, to the rig having boring tower, the power of rig is first utilized to coordinate with neighbouring cage, drilling rod is moved and roughly locates, again with jack by frame jack-up, accurate location, make gin wheel, the hole clipping of drill bit or fixing drilling rod and casing center are on a vertical line, to ensure the verticality of rig, the deviation of rig position is 1.5cm, behind align piles position, with tie plate horizontal drill machine crossbeam, and be symmetrical on drill axis at tower top and pull on cable wind rope,
(5) lay bamboo reinforcement cage, put into conduit after fluid concrete inward, because mao bamboon is diametrically lower uneven, to note the colligation of whole bamboo mid portion in bamboo reinforcement cage process of binding to the maximum position of pile body center stressed, thus be conducive to ensureing that pile body is stablized, during perfusion, concrete does not interrupt, otherwise easily occurs pile breaking phenomenon;
(6), after drawing sleeve pipe being installed, after a period of time is fixing, pile quality is checked;
Further, boring described in step (1) is because bamboo is that large therefore its buoyancy of diameter of hollow structure and bamboo is much larger than the buoyancy of reinforcing bar, be difficult to directly insert in insertion sludge process and therefore reduce buoyancy in bamboo body boring means, thus successfully bamboo cage is in place.
Case study on implementation three:
Bamboo reinforcement concrete filling pile, at a technical method for shield end well soil stabilization, comprises following concrete steps:
(1) environmental analysis;
(2) develop programs;
(3) arrange out one piece of flat field ground, facilitate building platform;
(4) rigging up and gland pipe make drilling and forming hole, forbidden for preventing stake position, it is important in construction to reserve center and correct installation auger, to the rig having boring tower, the power of rig is first utilized to coordinate with neighbouring cage, drilling rod is moved and roughly locates, again with jack by frame jack-up, accurate location, make gin wheel, the hole clipping of drill bit or fixing drilling rod and casing center are on a vertical line, to ensure the verticality of rig, the deviation of rig position is 2cm, behind align piles position, with tie plate horizontal drill machine crossbeam, and be symmetrical on drill axis at tower top and pull on cable wind rope,
(5) lay bamboo reinforcement cage, put into conduit after fluid concrete inward, because mao bamboon is diametrically lower uneven, to note the colligation of whole bamboo mid portion in bamboo reinforcement cage process of binding to the maximum position of pile body center stressed, thus be conducive to ensureing that pile body is stablized, during perfusion, concrete does not interrupt, otherwise easily occurs pile breaking phenomenon;
(6), after drawing sleeve pipe being installed, after a period of time is fixing, pile quality is checked;
[0012]further, boring described in step (1) is because bamboo is that large therefore its buoyancy of diameter of hollow structure and bamboo is much larger than the buoyancy of reinforcing bar, be difficult to directly insert in insertion sludge process and therefore reduce buoyancy in bamboo body boring means, thus successfully bamboo cage is in place.
More than show and describe general principle of the present invention and principal character and advantage of the present invention; the technician of the industry should understand; the present invention is not restricted to the described embodiments; what describe in above-described embodiment and manual just illustrates principle of the present invention; without departing from the spirit and scope of the present invention; the present invention also has various changes and modifications; these changes and improvements all fall in the claimed scope of the invention, and application claims protection domain is defined by appending claims and equivalent thereof.

Claims (2)

1. bamboo reinforcement concrete filling pile is at a technical method for shield end well soil stabilization, it is characterized in that, comprises the following steps:
(1) environmental analysis;
(2) develop programs;
(3) arrange out one piece of flat field ground, facilitate building platform;
(4) rigging up and gland pipe make drilling and forming hole, forbidden for preventing stake position, it is important in construction to reserve center and correct installation auger, to the rig having boring tower, the power of rig is first utilized to coordinate with neighbouring cage, drilling rod is moved and roughly locates, again with jack by frame jack-up, accurate location, make gin wheel, the hole clipping of drill bit or fixing drilling rod and casing center are on a vertical line, to ensure the verticality of rig, the deviation of rig position is not more than 2cm, behind align piles position, with tie plate horizontal drill machine crossbeam, and be symmetrical on drill axis at tower top and pull on cable wind rope,
(5) lay bamboo reinforcement cage, put into conduit after fluid concrete inward, because mao bamboon is diametrically lower uneven, to note the colligation of whole bamboo mid portion in bamboo reinforcement cage process of binding to the maximum position of pile body center stressed, thus be conducive to ensureing that pile body is stablized, during perfusion, concrete does not interrupt, otherwise easily occurs pile breaking phenomenon;
(6), after drawing sleeve pipe being installed, after a period of time is fixing, pile quality is checked.
2. according to claim 1 a kind of bamboo reinforcement concrete filling pile at the technical method of shield end well soil stabilization, it is characterized in that, boring described in step (1) is because bamboo is that large therefore its buoyancy of diameter of hollow structure and bamboo is much larger than the buoyancy of reinforcing bar, be difficult to directly insert in insertion sludge process, therefore hole to reduce buoyancy at bamboo body, thus successfully bamboo cage is in place.
CN201310595818.8A 2013-11-25 2013-11-25 Technical method for reinforcing soil of shield end well through bamboo reinforcement concrete pouring pile Pending CN104652425A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310595818.8A CN104652425A (en) 2013-11-25 2013-11-25 Technical method for reinforcing soil of shield end well through bamboo reinforcement concrete pouring pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310595818.8A CN104652425A (en) 2013-11-25 2013-11-25 Technical method for reinforcing soil of shield end well through bamboo reinforcement concrete pouring pile

Publications (1)

Publication Number Publication Date
CN104652425A true CN104652425A (en) 2015-05-27

Family

ID=53244019

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310595818.8A Pending CN104652425A (en) 2013-11-25 2013-11-25 Technical method for reinforcing soil of shield end well through bamboo reinforcement concrete pouring pile

Country Status (1)

Country Link
CN (1) CN104652425A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110410098A (en) * 2019-07-29 2019-11-05 西安建筑科技大学 The supplementary structure and construction method of a kind of excessively underwater soil/rock stratum push pipe into transfer well

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004092025A (en) * 2002-08-29 2004-03-25 Daia Soil Kk Foundation pile and construction method thereof
KR20050094680A (en) * 2004-03-24 2005-09-28 이육훈 Steel-column pile recovery process

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004092025A (en) * 2002-08-29 2004-03-25 Daia Soil Kk Foundation pile and construction method thereof
KR20050094680A (en) * 2004-03-24 2005-09-28 이육훈 Steel-column pile recovery process

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
杨中波 等: "冲击钻和旋挖钻机结合成孔技术在灌注桩施工中的应用", 《城市建设理论研究(电子版)》 *
魏波: "竹筋水泥土搅拌桩支护墙在基坑围护中的应用", 《安徽建筑》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110410098A (en) * 2019-07-29 2019-11-05 西安建筑科技大学 The supplementary structure and construction method of a kind of excessively underwater soil/rock stratum push pipe into transfer well

Similar Documents

Publication Publication Date Title
CN104612698B (en) A kind of shallow-depth-excavation tunnel top bar interval wall construction method
CN102493822B (en) Method for performing curtain grouting construction on tunnel by water rich fault influence zone
CN104120731B (en) A kind of tunnel subsidence protector and construction method thereof
CN105274998B (en) Construction method of assembled pile-plate-anchor-beam combination type batholith support
CN102606162A (en) Quick construction method for weak surrounding rock shallowly-buried easily-collapsed area of tunnel
CN203080518U (en) Self-drilling type recoverable anchor wire
CN102296630A (en) Construction method of long-screw high-pressure mix jetting cement diaphragm wall
CN102286984A (en) Water-stop curtain and construction method thereof
CN104631475A (en) Safe and fast construction method of down-traversing river shallow depth bored tunnel
CN101886393B (en) Construction method of combined foundation ditch support
CN204253056U (en) A kind of shield machine export & import reinforcing structure
CN107386274A (en) Wear the compound isolation pile and its reinforced construction method of bridge pier in tunnel side
CN101586340A (en) Preconditioning process of continuous wall for weak weathering terrane grooving construction
CN110359540A (en) A kind of shallow earthing Large Diameter Pipeline high water level wears the artificial jacking construction engineering method of existing road
CN103410522A (en) Continuous close-range underpass railway bridge construction method employing shallow tunneling method
CN105569051A (en) Foundation pit support system of sandy pebble boulder geological stratification and construction method
CN104863183B (en) Damping pilework and construction method is isolated in large cross-section tunnel proximity architecture construction
CN201762702U (en) Drilling bitten pile
CN110055973A (en) Construction space foundation pit enclosure structure and water-stopping method under by high metal bridge in limited time
CN104453915B (en) Big cross section vertical shaft pre-pouring grout reinforces Rapid Excavation method
CN103422499B (en) Casing construction method inside and outside a kind of permafrost region pile foundation
CN203924043U (en) A kind of bamboo concrete stake
CN205444192U (en) Bridge stake is towards pile driving construction system
CN203891047U (en) Equipment equipped with steel platform for foundation construction of land bridge
CN203583501U (en) Deep-layer shear resistant device capable of preventing rock sliding

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20150527

WD01 Invention patent application deemed withdrawn after publication