CN104612718B - A kind of support chassis for overlapping shield tunnel construction and support table system - Google Patents

A kind of support chassis for overlapping shield tunnel construction and support table system Download PDF

Info

Publication number
CN104612718B
CN104612718B CN201510074563.XA CN201510074563A CN104612718B CN 104612718 B CN104612718 B CN 104612718B CN 201510074563 A CN201510074563 A CN 201510074563A CN 104612718 B CN104612718 B CN 104612718B
Authority
CN
China
Prior art keywords
support
door frame
chassis
shield tunnel
tunnel construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510074563.XA
Other languages
Chinese (zh)
Other versions
CN104612718A (en
Inventor
和孙文
李光耀
钱兴喜
张述毕
惠世前
缪买和
刘士诚
庞林军
杨光武
张磊
刘才平
刘琨阳
周跃飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 14 Co Ltd
Original Assignee
Sinohydro Bureau 14 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 14 Co Ltd filed Critical Sinohydro Bureau 14 Co Ltd
Priority to CN201510074563.XA priority Critical patent/CN104612718B/en
Publication of CN104612718A publication Critical patent/CN104612718A/en
Application granted granted Critical
Publication of CN104612718B publication Critical patent/CN104612718B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/40Devices or apparatus specially adapted for handling or placing units of linings or supporting units for tunnels or galleries

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a kind of support chassis for overlapping shield tunnel construction and support table system, it is desirable to provide a kind of support chassis effectively improving efficiency of construction and support table system.Chassis is supported to include vehicle frame, walking mechanism and hydraulic support mechanism;Vehicle frame includes two door frames, connects the bottom girder of two door frame side lower ends, connects the articulated beam on two door frame side tops, is arranged at the platform that door frame top connects two door frames, and the regulation on setting bottom girder supports;Walking mechanism includes being arranged at the road wheel group of lower sill beam, drive wheel group, rail clamping device, and is arranged at the motor with drive wheel group drive connection on bottom girder;Hydraulic support mechanism is symmetricly set on two door frames, including multiple support cylinders being arranged at along tunnel radial direction outside door frame, it is arranged at the bracket of support cylinder end, is arranged at the Rubber washer on bracket end face, and be arranged on platform for driving the pumping plant of support cylinder.

Description

A kind of support chassis for overlapping shield tunnel construction and support table system
Technical field
The present invention relates to technical field of mechanical equipment for tunnel construction, especially relate to a kind of overlapping shield tunnel that is used for and construct Support chassis.
Background technology
At present, Urban Traffic Jam Based is on the rise, and significantly impacts civic trip, alleviates urban traffic pressure Effectively approach is to greatly develop urban public tranlport system, especially has large conveying quantity, speed fast, safe and reliable, on schedule The City Rail Transit System of comfortable the features such as, the construction of urban track traffic is increasingly accepted by citizen.
City Rail Transit System is predominantly located at below urban road, builds limited space, especially some circuits are in order to keep away Open down and wear the impact to existing bridge of residential area or other constructions of structures, reduction, investment reduction, build in urban track traffic If in, the design of superimposing thread tunnel line is more and more.
Shield method is the Fully-mechanized construction method of one of shallow mining method, and it has safe and reliable, ground adaptability By force, work efficiency is high, traffic above-ground and building is disturbed little, can pass through rivers, lake and existing railway, highway, subway, bridge, The features such as passage, pipeline, be in current constructing metro tunnel up-to-date enter construction method.
Shield method is applied to superimposing thread(Overlapping)During constructing tunnel, especially originating terminal and receiving terminal position, upper and lower two tunnels Vertical dimension about 2m, requires according to superimposing thread shield-tunneling construction, offline tunnel of first constructing, then tunnel of reaching the standard grade of constructing.Reaching the standard grade, tunnel is applied Man-hour, to offline tunnel certain limit(Each 10m correspondence position below tunnel shield body of reaching the standard grade and before and after shield body)Setting supports, to protect Demonstrate,prove the structure safety in offline tunnel.
According to past construction experiences, using conventional support system(Shape steel bracket, full hall scaffold etc.), exist and set up shifting The problems such as dynamic difficult, upper and lower threaded list road can not tunnel simultaneously, affects larger on the shield driving duration.
Content of the invention
Instant invention overcomes shortcoming of the prior art, there is provided a kind of conveniently moving, efficiency of construction can be effectively improved, contracting The short construction period, the support chassis for overlapping shield tunnel construction that in realization, offline shield tunnel is constructed simultaneously;Same with this When, present invention also offers a kind of high support table system of efficiency of construction.
In order to solve above-mentioned technical problem, the present invention is achieved by the following technical solutions:
A kind of support chassis for overlapping shield tunnel construction, is walked with track cooperation and is used for propping up of tunnel duct piece Support, it includes vehicle frame, walking mechanism and hydraulic support mechanism;
Described vehicle frame includes two door frames, connects the bottom girder of two door frame side lower ends, connects on two door frame sides The articulated beam in portion, is arranged at the platform that door frame top connects two door frames, and the regulation on setting bottom girder supports;
Described walking mechanism includes being arranged at the road wheel group of lower sill beam, drive wheel group, rail clamping device, and is arranged at bottom Motor with drive wheel group drive connection on beam;
Described hydraulic support mechanism is symmetricly set on two door frames, is arranged at door frame including multiple along tunnel radial direction The support cylinder in outside, is arranged at support cylinder end for supporting the bracket of tunnel duct piece side wall and roof, is arranged at bracket Rubber washer on end face, and be arranged on platform for driving the pumping plant of support cylinder.
Preferably, the side of two described door frames is provided with the hound connecting door frame, the side setting of described door frame There is the cat ladder of connecting platform, between described bottom girder, be provided with crossbeam.
Preferably, on two described door frames relative to bracket between a hinged connecting rod.
Preferably, all at least provided with one group of gear wheel mechanism, described gear wheel mechanism bag on the bottom girder of described door frame both sides Include the gear wheel frame being fixedly connected with bottom girder, be arranged at the gear wheel of gear wheel frame lower end inside, during assembling, described gear wheel and track is outer Side overlaps.
Preferably, the both sides of described door frame are all hinged with pull bar, on the other end of pull bar and tunnel duct piece during use Screw end head connects.
Preferably, the head room of described door frame is 2.56m.
Preferably, described track is P43 type track.
Preferably, described door frame respectively arranges five support cylinders, door frame both sides stringcourse downward 15 ° each, top Vertical one, top is to both sides 40 ° each.
Preferably, described motor passes through decelerator and chain-wheel mechanism is connected with drive wheel group.
A kind of support table system for overlapping shield tunnel construction, it includes more piece and supports chassis as above, More piece supports chassis to be linked in sequence.
Compared with prior art, the invention has the advantages that:
Present invention can apply to upper and lower double line shield tunnel(Especially small interval double line shield tunnel)Construction, upper When lower two tunnels tunnel, both can ensure that offline tunnel was normally open to traffic construction simultaneously, can play when reaching the standard grade constructing tunnel pair again Offline tunnel plays the purpose of temporary support.
Brief description
In order to be illustrated more clearly that the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing Have technology description in required use accompanying drawing be briefly described it should be apparent that, drawings in the following description be only this Some embodiments of invention, for those of ordinary skill in the art, without having to pay creative labor, also may be used So that other accompanying drawings are obtained according to these accompanying drawings.
Structural representation cuts open in office when Fig. 1 constructs for the present invention.
Fig. 2 is the enlarged drawing of part A in Fig. 1.
Fig. 3 is the enlarged drawing of part B in Fig. 1.
Fig. 4 is the side view of the present invention.
Specific embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Site preparation description is it is clear that described embodiment is only a part of embodiment of the present invention, rather than whole embodiments.It is based on Embodiment in the present invention, it is every other that those of ordinary skill in the art are obtained under the premise of not paying creative work Embodiment, broadly falls into the scope of protection of the invention.
For the support chassis of overlapping shield tunnel construction shown in Fig. 1-4, walk and be used for tunneltron with track 50 cooperation The support of piece 30, it includes vehicle frame, walking mechanism and hydraulic support mechanism;
Described vehicle frame includes two door frames 5, connects the bottom girder 4 of two door frame 5 side lower ends, connects two door frame 5 sides The articulated beam 6 on side top, is arranged at the platform 7 that door frame 5 top connects two door frames 5, and the regulation on setting bottom girder 4 supports 14;
Described walking mechanism includes being arranged at the road wheel group 2 of bottom girder 4 bottom, drive wheel group 3, rail clamping device 1, and setting The motor 19 with drive wheel group 3 drive connection on bottom girder 4;
Described hydraulic support mechanism is symmetricly set on two door frames 5, is arranged at door including multiple along tunnel radial direction The support cylinder 16 in frame 5 outside, is arranged at support cylinder 16 end for supporting the bracket 11 of tunnel duct piece 30 side wall and roof, It is arranged at the Rubber washer 12 on bracket 11 end face, and be arranged on platform 7 for driving the pumping plant 20 of support cylinder 16.
Wherein, the side of two described door frames 5 is provided with the hound 8 connecting door frame 5, the side setting of described door frame 5 Have the cat ladder 9 of connecting platform 7, between described bottom girder 4, be provided with crossbeam 10, crossbeam be three it is ensured that the left and right pillar of door frame not To middle excessive deformation, it is connected with bottom girder it may be necessary to take apart with bolt, allow battery locomotive 40 to pass through.Two described door frames 5 A hinged connecting rod 6 between upper relative bracket 11, limits bracket 11 and rotates in small range, construction is more convenient.Described door frame 5 both sides Bottom girder 4 on be provided with three groups of gear wheel mechanisms, described gear wheel mechanism includes the gear wheel frame 17 being fixedly connected with bottom girder 4, setting In the gear wheel 21 of gear wheel frame 17 lower end inside, during assembling, the lateral overlap of described gear wheel 21 and track 50 is it is clear that gear wheel mechanism Quantity suitably can be increased and decreased according to construction requirement.The both sides of described door frame 5 are all hinged with pull bar 18, and during use, pull bar 18 is another One end is connected with the screw end head on tunnel duct piece 30, for resisting door frame deformation., the head room of described door frame 5 is 2.56m, the walking that can meet battery locomotive 40 requires.Described track 50 preferably employs P43 type track, and its gauge is 2.23m.
In the present embodiment, described door frame 5 respectively arranges five support cylinders 16, downward 15 ° each one of door frame 5 both sides stringcourse Only, top vertical one, to both sides 40 ° each, it is hinged with support cylinder 16 end that described bracket 11 passes through pin 15, glue at top The thickness of leather packing is advisable with 10, during constructing operation, if there is a faulting of slab ends phenomenon section of jurisdiction, needs optionally interim cushioning again on bracket Rubber washer, to ensure that whole bracket surface contacted well with section of jurisdiction.Rubber washer can be connected with bracket by screw.Support cylinder Preferably model HSGK01-110/80E-4621-200*177.
Described motor 19 passes through decelerator 22 and chain-wheel mechanism is connected with drive wheel group 3.Described walking mechanism preferred Configuration is as follows:
1. motor:Model:YZ132M1, power P=2.2kw, rotating speed n=935r/min;
2. reductor:Model:WHS12.5-50- I (II), gear ratio is 50, sprocket ratio i=Z2/Z1=38/19=2, Resultant gear ratio=50*2=100;
3. the speed of travel:V=8.8m/min.
During construction, in the current state of battery locomotive, the crossbeam on bottom girder needs to remove, and the globality intensity decreases of door frame are This, each two groups about four groups of gear wheel mechanism door frames of special setting, with track for relying on, under the effect of gear wheel mechanism, can constrain door Frame is not deformed.Three groups of drag link mechanisms are respectively set in left and right bottom girder, the pull bar other end is connected to section of jurisdiction connecting screw rod end simultaneously Head is it is also possible to opposing door frame is possible to the deformation producing.
A kind of support table system for overlapping shield tunnel construction, it includes five sections and support example described in is performed as described above Chassis, five sections support chassis to be linked in sequence.Often section support chassis effective support length be 6m, previous section supporting table tailstock portion with after One section supporting table car head distance be 0.68m, using common rail compartment connected mode it is clear that support chassis quantity can root Reasonably increased and decreased according to construction requirement.
Support table system installation and operation instruction as follows:
1)The installation of chassis
1. to supporting chassis correlation drawing to be familiar with, then according to drawing assembles to chassis successively, the group of chassis Step from the bottom up followed by dress, first carries out preassembling on ground, is split, lifting is gone into the well, by storage battery after acceptance(check) Locomotive transportation to installment work face carries out installing in tunnel, supports the lifting of chassis merogenesis to go into the well using 50t truck crane and 45 tons of doors Machine cooperation completes, tunnel internal is assembled support chassis when, from inside outwards assembled successively, final section support the bracket of chassis away from From hole about 0.5m, installing in hole needs measurement to carry out measurement tasks.
2., after all parts install, need, to supporting chassis to carry out an acceptance inspection, can come into operation after acceptance(check).
3. main installation tool:Chain block, spanner etc.;
2)Table system is supported to use
1. support table system(Five sections support chassis)Bearing length be about 30m, that is, each below shield body and before and after shield body 10m scope, each displacement is 1.5m~3m(1~2 section section of jurisdiction)It is desirable to before right line is mobile during finally a piece of pipe sheet assembling The interior translation work completing left threaded list road, requires to accomplish that shield machine stops driving, synchronous grouting also will complete, forbid simultaneously Support in chassis moving process and slip casting or synchronous grouting are carried out to section of jurisdiction;
2. small interval overlapping tunnel supports chassis to support scope to give superimposing thread for design drawing and supports scope;
3., during supporting chassis to use, monitoring to be strengthened to section of jurisdiction, in order to avoid causing section of jurisdiction because jacking thrust is excessive Deformation, dislocation;
4. when support chassis shift position determine after, need to fix with section of jurisdiction connecting bolt by drag link mechanism, simultaneously Rail clamping device clips;
5., after supporting chassis to fix, need to hold out against adjusting support with orbital plane, for guarantee track, shape does not occur Become it is proposed that the cushioning lumps of wood below in rail;
When 6. shutting down mobile support chassis every time, Section of four supporting table tailstock portion 4.8m of shield cutter distance from top, every time Mobile 1.5~3m;
7. during right line shield launching, 1~No. 5 support chassis is in place from portal 0.5 position once mounting, applies prestressing force When it is assumed that it is 1 that portal position first support chassis is numbered, then supporting chassis apart from the farthest section of portal, to number be 5, to 1 When~No. 5 support chassis apply prestressing force, it is principle according to each 5KN that increases, classification applies, the maximum gross thrust that applies is each Support cylinder 45KN, pre-applied force needs segment deformation situation is monitored during applying, and unusual circumstance stops in time Pre-applied force, in order to avoid being once added to position and making section of jurisdiction produce moderate finite deformation;
8. pre-applied force applying order:Each supports chassis to amount to 5 support cylinders, and the order of applying power is first top axis Position support cylinder, then apply the support cylinder of the top left and right sides(Apply simultaneously), finally apply two support cylinders of waist Pre-applied force(Apply simultaneously).
9. in shield tunneling process, carry out the monitoring of section of jurisdiction, recorded the data variation of oil cylinder simultaneously, treated first Section test section completes, and summarizes, analyzes, determines final prestressing force load condition;
10. the stress sequence of unloading before moving:The support force of a support chassis can only be unloaded every time(Unloading unloads by several times, Unload the support force of two support cylinders on 40 degree of directions for the first time, unload the downward 15 degree of direction loinss of stringcourse two for second Support force, finally support force on unloading axis direction, being offloaded to axle power every time is to stop when zero, after each completion of discharge, be to pipe Piece is monitored measuring;
For ensureing the construction safety of offline shield tunnel, a section can only be moved every time and support chassis, treat that a section supports After chassis movement finishes and installs, just can carry out the movement that next section supports chassis, the chassis being not in mobile status must Stress must be in.
The foregoing is only presently preferred embodiments of the present invention, not in order to limit the present invention, all essences in the present invention Within god and principle, any modification, equivalent substitution and improvement made etc., should be included within the scope of the present invention.

Claims (10)

1. a kind of support chassis for overlapping shield tunnel construction, is walked with track cooperation and is used for the support of tunnel duct piece, It is characterized in that:Including vehicle frame, walking mechanism and hydraulic support mechanism;
Described vehicle frame includes two door frames, connects the bottom girder of two door frame side lower ends, connects two door frame side tops Articulated beam, is arranged at the platform that door frame top connects two door frames, and the regulation on setting bottom girder supports;
Described walking mechanism includes being arranged at the road wheel group of lower sill beam, drive wheel group, rail clamping device, and is arranged on bottom girder Motor with drive wheel group drive connection;
Described hydraulic support mechanism is symmetricly set on two door frames, is arranged at outside door frame along tunnel radial direction including multiple Support cylinder, be arranged at support cylinder end for supporting the bracket of tunnel duct piece side wall and roof, be arranged at bracket end face On Rubber washer, and be arranged on platform and be used for driving the pumping plant of support cylinder.
2. according to claim 1 be used for overlapping shield tunnel construction support chassis it is characterised in that:Two described door frames Side be provided with the hound connecting door frame, the side of described door frame is provided with the cat ladder of connecting platform, between described bottom girder It is provided with crossbeam.
3. according to claim 1 be used for overlapping shield tunnel construction support chassis it is characterised in that:Two described door frames A hinged connecting rod between upper relative bracket.
4. according to claim 1 be used for overlapping shield tunnel construction support chassis it is characterised in that:Described door frame both sides Bottom girder on all at least provided with one group of gear wheel mechanism, described gear wheel mechanism includes the gear wheel frame being fixedly connected with bottom girder, setting In the gear wheel of gear wheel frame lower end inside, the lateral overlap of described gear wheel and track during assembling.
5. according to claim 1 be used for overlapping shield tunnel construction support chassis it is characterised in that:The two of described door frame Side is all hinged with pull bar, and during use, the other end of pull bar is connected with the screw end head on tunnel duct piece.
6. according to claim 1 be used for overlapping shield tunnel construction support chassis it is characterised in that:Described door frame net Outage degree is 2.56m.
7. according to claim 1 be used for overlapping shield tunnel construction support chassis it is characterised in that:Described track is P43 type track.
8. according to claim 1 be used for overlapping shield tunnel construction support chassis it is characterised in that:Each on described door frame Five support cylinders of setting, door frame both sides stringcourse downward 15 ° each, top vertical one, top is to both sides 40 ° each.
9. according to claim 1 be used for overlapping shield tunnel construction support chassis it is characterised in that:Described motor passes through Decelerator and chain-wheel mechanism are connected with drive wheel group.
10. a kind of support table system for overlapping shield tunnel construction it is characterised in that:It includes more piece such as claim Support chassis described in any one of 1-9, more piece supports chassis to be linked in sequence.
CN201510074563.XA 2015-02-12 2015-02-12 A kind of support chassis for overlapping shield tunnel construction and support table system Active CN104612718B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510074563.XA CN104612718B (en) 2015-02-12 2015-02-12 A kind of support chassis for overlapping shield tunnel construction and support table system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510074563.XA CN104612718B (en) 2015-02-12 2015-02-12 A kind of support chassis for overlapping shield tunnel construction and support table system

Publications (2)

Publication Number Publication Date
CN104612718A CN104612718A (en) 2015-05-13
CN104612718B true CN104612718B (en) 2017-03-08

Family

ID=53147343

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510074563.XA Active CN104612718B (en) 2015-02-12 2015-02-12 A kind of support chassis for overlapping shield tunnel construction and support table system

Country Status (1)

Country Link
CN (1) CN104612718B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL2035454B1 (en) * 2023-03-07 2024-09-20 China Railway Electrification Eng Group Co Ltd Support trolley, pipe joint correction method and supporting method for overlapping shield tunnels

Families Citing this family (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105221169B (en) * 2015-10-21 2018-03-27 中铁科工集团轨道交通装备有限公司 A kind of crawler type section of jurisdiction secondary lining equipment
CN105240030B (en) * 2015-10-30 2017-12-15 中建三局第一建设工程有限责任公司 A kind of overlapping tunnel bracing members
CN106401592A (en) * 2016-06-17 2017-02-15 中铁十八局集团第五工程有限公司 Construction method for tunnel boring off-contact sending and receiving platform of up-down overlapped tunnel
CN106368718B (en) * 2016-10-25 2018-05-01 陕西铁路工程职业技术学院 Subway deep tunnel reinforced concrete segment removes Operation Van
CN107725066B (en) * 2017-09-30 2023-08-11 中铁第四勘察设计院集团有限公司 Prefabricated box culvert and layout method thereof
CN107701195B (en) * 2017-11-16 2024-06-21 中铁建设投资集团有限公司 TBM connecting bridge multifunctional traveling device and control method thereof
CN108590679A (en) * 2018-04-18 2018-09-28 重庆建工第七建筑工程有限责任公司 Utilize the construction method for walking support truck jumbo overlapping tunnel
CN111456770B (en) * 2018-12-05 2021-12-14 莆田城厢振达宸贸易有限公司 Movable tunnel segment supporting device for subway construction
CN109519199B (en) * 2018-12-12 2024-05-31 中铁十四局集团有限公司 Shield tunnel segment supporting trolley
CN109505646B (en) * 2018-12-29 2020-04-24 中铁一局集团有限公司 Method for reversely hauling trolley in tunnel
CN110159300A (en) * 2019-04-29 2019-08-23 同济大学 A kind of shield tunnel repairing and reinforcement platform and reinforcement means
CN111911211B (en) * 2020-07-06 2022-06-28 中铁十六局集团北京轨道交通工程建设有限公司 Visual automatic supporting walking trolley for shield overlapping tunnel construction and construction method
CN111794779B (en) * 2020-07-10 2022-07-12 中国建筑第二工程局有限公司 Assembly type trolley for supporting tunnel shield segments and using method thereof
CN111828024B (en) * 2020-07-17 2021-09-14 青岛理工大学 Adjustable receiving platform of tunnel boring equipment
CN112253188A (en) * 2020-09-28 2021-01-22 北京韩建水利水电工程有限公司 Tunnel steel tile transportation and adjustment device
JP6906116B1 (en) * 2021-01-22 2021-07-21 株式会社東宏 How to move the underground work trolley and the underground work trolley
CN112983487A (en) * 2021-03-04 2021-06-18 北京市政建设集团有限责任公司 In-hole inner supporting device
CN113700515B (en) * 2021-07-19 2023-06-30 中铁十六局集团第三工程有限公司 Method, device and equipment for using ultra-large cross-tunnel support and readable storage medium
CN114233360B (en) * 2021-12-21 2024-10-18 中铁十九局集团有限公司勘察设计院分公司 Double-layer traveling trolley, ventilator parallel traveling system and use method of ventilator parallel traveling system
CN114991830B (en) * 2022-07-18 2022-10-21 中铁电气化局集团有限公司 Subway construction mobile tunnel segment supporting trolley
CN116044456B (en) * 2022-11-16 2024-01-16 南京康泰建筑灌浆科技有限公司 Robot for tunnel reinforcement and tunnel reinforcement system

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011058314A (en) * 2009-09-11 2011-03-24 Daiei Koki Kk Portal frame and center truck
CN101712323B (en) * 2009-12-17 2012-10-03 中铁一局集团有限公司 Movable wheel type trolley supporting system for long-distance overlapping shield tunnel of small clear distance
CN103541744A (en) * 2013-11-11 2014-01-29 中铁四局集团机电设备安装有限公司 Tire walking full-hydraulic lining trolley
CN104033166B (en) * 2014-06-26 2016-09-07 湖南五新隧道智能装备股份有限公司 A kind of portal frame system of tunnel lining trolley
CN204591302U (en) * 2015-02-12 2015-08-26 中国水利水电第十四工程局有限公司 A kind of support chassis for overlapping shield tunnel construction and brace table truck system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL2035454B1 (en) * 2023-03-07 2024-09-20 China Railway Electrification Eng Group Co Ltd Support trolley, pipe joint correction method and supporting method for overlapping shield tunnels

Also Published As

Publication number Publication date
CN104612718A (en) 2015-05-13

Similar Documents

Publication Publication Date Title
CN104612718B (en) A kind of support chassis for overlapping shield tunnel construction and support table system
CN204591302U (en) A kind of support chassis for overlapping shield tunnel construction and brace table truck system
CN103334381B (en) Full-bracket track-bogie bearing and moving device and construction method for installing steel box girders
CN104195952A (en) Steel box girder erection method applied to steel and concrete hybrid girder cable-stayed bridge
CN110230261B (en) Mounting construction method for upper frame beam of double-layer synchronous beam
CN107060823B (en) Non-dismantling trolley for tunnel anchor section secondary lining concrete construction
CN206680871U (en) Boom device is transported on a kind of four rail beams
CN108979664A (en) Existing subway tunnel based on mobile casting platform protects steel structure pouring construction method
CN105178179B (en) A kind of method and device of railway bridge maintenance conditions around bridge pier
CN109930435A (en) Straddle-type monorail PC track beam construction method in a kind of circular cross section tunnel
CN100515910C (en) Portal lifting composite device for car body transportation
CN108130864B (en) Integrally-assembled bridge whole-span beam transportation and erection equipment
CN102101480B (en) Track traffic lane changing equipment
CN206941386U (en) A kind of inspection car running mechanism with revolute function
CN103410104B (en) The bearing replacement method and apparatus of overhead road of city
CN206928193U (en) A kind of Frame Pier swivel bridges for taking into account traffic above-ground
CN105822315B (en) The anti-battery truck car slipping crash device of shield machine and method
CN102493358B (en) Highway and railway two-purpose bridge girder erection machine
CN112938773B (en) Method and system for installing underground engineering section and installation crane
CN114508052A (en) Pier-beam assembly type integrated construction method
CN210738584U (en) Space rigid frame trolley suitable for existing line crossing construction
CN212925808U (en) Vertical and longitudinal connecting device for bridge erecting machine
CN111139742B (en) Method for mounting and dismounting highway bridge girder erection machine
CN100534890C (en) Bridge type lifting composite device for car body transportation
CN107268452A (en) Mobile formwork bed die work car and excessively hole construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant