CN104594374A - Combination construction method for combined type communication tower footing - Google Patents
Combination construction method for combined type communication tower footing Download PDFInfo
- Publication number
- CN104594374A CN104594374A CN201410802250.7A CN201410802250A CN104594374A CN 104594374 A CN104594374 A CN 104594374A CN 201410802250 A CN201410802250 A CN 201410802250A CN 104594374 A CN104594374 A CN 104594374A
- Authority
- CN
- China
- Prior art keywords
- combination
- stretch
- draw
- column foot
- basic blocks
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/42—Foundations for poles, masts or chimneys
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0046—Production methods using prestressing techniques
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The invention relates to a combination construction method for a combined type communication tower footing. According to the method, firstly, cross combination localization of the combination center of foundation blocks of the combination tower footing is conducted, a prestress tension adjustment in-position forming process for combining a foundation is conducted twice, a prestress tension trolley and tension equipment are adopted for foundation combination, the thought of the method includes the steps that prefabricated blocks similar to coordinates on a center cross of the foundation are assembled firstly and tensioned into a whole through prestress reinforcing steel bars, an installation standard is provided for the whole foundation, and other foundation blocks are installed on the two sides of the cross at a time. By the adoption of the construction process, on the premise that the combination construction requirement is met, combination construction time is shortened to the maximum degree, and high efficiency and practicality of combined type communication tower footing construction are fully shown.
Description
Technical field
The present invention relates to building field, be related specifically to a kind of combination constructing method thereof of modular communications column foot.
Background technology
When setting up communication tower, machine room, needing the below building column foot at tower body or machine room, communication tower and machine room are fixed on column foot.A class column foot of the prior art adopts concrete cast in situs to become an entirety usually, cannot remove.When communication tower tower body and machine room need to change position, technique uses crane gear to play jack work, and mobility is strong, expends crane gear and uses.The column foot of building one can only be discarded in original place, cannot move to change position, not only movement can not be dismantled, and although cost of idleness, construction period are longer, also have a class column foot detachable, but need to excavate ground, column foot is imbedded underground, is unfavorable for reusing and is arbitrarily combined into different size column foot, and cannot position when vertical direction superposes.
Summary of the invention
The object of the invention is to overcome above-mentioned the deficiencies in the prior art, a kind of group technology for modular communications column foot and construction method are provided.Construction technology of the present invention wants the combination that can simplify communication column foot, improves combined efficiency and combination quality.
In order to reach foregoing invention object, the technical scheme that patent of the present invention provides is as follows:
A kind of combined type communication tower base comprises column foot body, described column foot body comprises several base unit blocks mutually spliced, relative side, described base unit block position is parallel to each other, have in the side of described base unit block on a side or two adjacent sides and be provided with spacing block set, the stopper slot that the spacing block set that three sides in addition or two adjacent sides are provided with base unit block mutually isostructural with another matches, described column foot body horizontal and vertical is provided with several for what run through base unit block and is connected and fixed bar (prestressed reinforcement).This column foot has and can carry out dismantling, is convenient to change column foot position, effectively improves column foot utilization rate, effectively the beneficial effect such as can positions to column foot.
A kind of combination constructing method thereof of modular communications column foot, each described modular communications column foot includes nine pieces of prefabricated basic blocks, these nine pieces prefabricated basic blocks are spliced into as integral type square block is as communication column foot, and it is characterized in that, this combination constructing method thereof includes following steps:
The first step, utilizes nine pieces of basic blocks of concrete prefabricated communication column foot, prepares the prestressed reinforcement of stretch-draw;
Second step, is first spliced into cross as coordinate using piece basic blocks of five wherein, forms a central cross shape combination, uses prestressed reinforcement stretch-draw integral;
3rd step, again remaining four pieces of basic blocks are snapped onto respectively the corresponding site at four angles of central cross shape combination, prestressed reinforcing bar, tensioning equipment is used to carry out initial tensioning to all directions prestressed reinforcement, the pulling force of initial tensioning is 10% of design pulling force, to adjust the fissure of displacement and mutual alignment between combination prefabricated foundation block;
4th step, carries out whole stretch-draw after adjusting each combination prefabricated foundation block, and the pulling force of whole stretch-draw is 100% of design pulling force, makes nine pieces of prefabricated foundation blocks be combined into a base integral.
In the combination constructing method thereof of modular communications column foot of the present invention, the combination of central cross shape combination is: one piece of prefabricated foundation block is placed in centre position, and four limits that all the other four pieces of prefabricated foundation blocks are close to centre position prefabricated foundation block are respectively placed.
In the combination constructing method thereof of modular communications column foot of the present invention, the modular communications column foot of the combination of central cross shape combination is adopted to include 9 basic blocks combinations, 16 basic blocks combinations, 25 basic blocks combinations and 36 basic blocks combinations.
In the combination constructing method thereof of modular communications column foot of the present invention, producing stretch-draw prestressing force is stretch-draw dolly and tensioning equipment, described stretch-draw dolly rear portion is provided with storage position, stretch-draw counter-force jack is carried by cantilever in front portion, is placed with the ballast weighed with described tensioning equipment etc. in described storage position.
In the combination constructing method thereof of modular communications column foot of the present invention, the bottom of described stretch-draw dolly is configured with multiple universal wheel that freely can promote to turn in construction.
Based on technique scheme, patent of the present invention compared with prior art has following technological merit:
The present invention is by the prefabricated section (similar coordinate) in first built-up foundation central cross, use prestressed reinforcement stretch-draw integral, whole column foot is made just to have had a benchmark installed, again from cross both sides all the other basic blocks of once mounting, above-mentioned construction technology is by orderly adjustment combination foundation block built-up sequence, stretch-draw adjustment piece has misplaced prestressed stretch-draw at twice, the stretch-draw dolly made according to this combination construction feature and tensioning equipment, under the prerequisite meeting combination construction requirement, farthest have compressed the combination construction time, fully demonstrate the highly effective of modular communications column foot construction.
Accompanying drawing explanation
Fig. 1 is the splicing schematic diagram on the hydraulic steering gear adopting cross piece basis of first making in the combination constructing method thereof of modular communications column foot of the present invention.
Fig. 2 is the follow-up splicing view being combined as basis in the combination constructing method thereof of modular communications column foot of the present invention with central cross shape.
Fig. 3 is that the combination constructing method thereof of modular communications column foot of the present invention has spliced later view.
Fig. 4 is the equipment schematic diagram carrying out prestressed stretch-draw in the combination constructing method thereof of modular communications column foot of the present invention.
Detailed description of the invention
We do with the combination constructing method thereof of specific embodiment to modular communications column foot of the present invention by reference to the accompanying drawings and further elaborate below; understand working method and equipment composition in the hope of more cheer and bright, but the protection domain of patent of the present invention can not be limited with this.
The present invention proposed the thought of combined type communication tower base before this, column foot body is provided with in this combined type communication tower base, described column foot body comprises several base unit blocks mutually spliced, relative side, described base unit block position is parallel to each other, have in the side of described base unit block on a side or two adjacent sides and be provided with spacing block set, the stopper slot that the spacing block set that three sides in addition or two adjacent sides are provided with base unit block mutually isostructural with another matches, described column foot body horizontal and vertical is provided with several for what run through base unit block and is connected and fixed bar (prestressed reinforcement).Combined tower base has and can carry out dismantling, is convenient to change column foot position, effectively improves column foot utilization rate, effectively the beneficial effect such as can positions to column foot.
The present invention is a kind of combination constructing method thereof of modular communications column foot, and each described modular communications column foot includes nine pieces of prefabricated basic blocks, and these nine pieces prefabricated basic blocks are spliced into as integral type square block is as communication column foot.The present invention combines column foot basic blocks combination center cross integrated positioning, and combination foundation twice prestressed stretch-draw adjusts moulding process in place, and combination foundation has used prestressed stretch-draw dolly and tensioning equipment.The thinking of the method is by the prefabricated section (similar coordinate) in first built-up foundation central cross, and use prestressed reinforcement stretch-draw integral, just there has been a benchmark installed on whole basis, then from cross both sides all the other basic blocks of once mounting.
Based on above-mentioned thinking, combination constructing method thereof of the present invention includes following detailed step:
The first step, utilizes nine pieces of basic blocks of concrete prefabricated communication column foot, and prepare the prestressed reinforcement of stretch-draw, prestressed reinforcement here can be fining twisted steel.
Second step, is first spliced into cross as coordinate using piece basic blocks of five wherein, forms a central cross shape combination, uses prestressed reinforcement stretch-draw integral; The combination of central cross shape combination is: one piece of prefabricated foundation block is placed in centre position, and four limits that all the other four pieces of prefabricated foundation blocks are close to centre position prefabricated foundation block are respectively placed, as shown in Figure 1.The effect of prestressed reinforcement is herein for connecting prefabricated foundation block, and connects at the two ends of prestressed reinforcement configuration nut pad.
3rd step, again remaining four pieces of basic blocks are snapped onto respectively the corresponding site at four angles of central cross shape combination, as shown in Figure 2, and then prestressed reinforcing bar, tensioning equipment is used to carry out initial tensioning to all directions prestressed reinforcement, the pulling force of initial tensioning is 10% of design pulling force, to adjust the fissure of displacement and mutual alignment between combination prefabricated foundation block.Initial tensioning is the object reaching pretension is whether the prefabricated section got togather in order to check groups has dislocation, and can adjust in good time, and twice split is the technique in order to how once check rectification, reduce single tension split shaping after cause due to the reason of the fissure of displacement do over again.
4th step, carries out whole stretch-draw after adjusting each combination prefabricated foundation block, and the pulling force of whole stretch-draw is 100% of design pulling force, makes nine pieces of prefabricated foundation blocks be combined into a base integral, as shown in Figure 3.
The combination constructing method thereof combined type basis of modular communications column foot of the present invention is assembled can be the combination even combination of 36 basic blocks of the combination of 9 basic blocks, the combination of 16 basic blocks, 25 basic blocks.As long as based on structure design and the combination operation that utilizes construction method of the present invention to carry out of modular communications column foot; owing to being the operation of globality; also be all to take such combination four and combination construction process, these contents should be all the protection domains belonging to patent of the present invention.
In the combination constructing method thereof of modular communications column foot of the present invention, producing stretch-draw prestressing force is stretch-draw dolly and tensioning equipment, as shown in Figure 4, described stretch-draw dolly 3 rear portion is provided with storage position, anterior carries stretch-draw counter-force jack 4 by cantilever, is placed with the ballast 5 heavy with described tensioning equipment etc. in described storage position.Tensioning equipment includes stretching oil pump and stretch-draw counter-force jack 4, and stretch-draw counter-force jack 4 belongs to a tensioning equipment part.Stretch-draw dolly 3 is placed on above basic blocks 1, can promote arbitrarily, and because stretch-draw counter-force jack 4 is tensioning equipment parts, stretch-draw counter-force jack 4 is enclosed within prestressed reinforcement 2 and is fixed with cap colalr gasket.Make stretch-draw counter-force jack 4 style of work to play the effect of prestressed reinforcement of tensioning 2 in basic blocks 1 by controlling stretching oil pump during stretch-draw, stretch-draw locks prestressed reinforcement 2 to when designing stretching force with nut.
The bottom of above-mentioned stretch-draw dolly 3 is configured with multiple universal wheel 6 that freely can promote to turn in construction.The combination foundation of communication column foot is with prestressed stretch-draw dolly and stretch-draw a complete set of equipment, according to the ballast formula stretch-draw dolly of construction characteristic configuration, the bottom of stretch-draw dolly 3 is equipped with universal wheel 6 and freely can promotes to turn in construction, farthest meet the construction requirement of modular communications column foot combination stretch-draw under all kinds of operating mode, stretch-draw dolly can at ballasts such as rear portion storage position place tool and tensioning equipments in the process of carrying out stretch-draw, ensure that uniform force after stretch-draw Plantago minuta, there will not be because stressed excessive the making it in front portion exists the danger of toppling, substantially increase the safety in work progress, meet construction requirement, convenient and practical, eliminate the use of the crane gears such as crane, the stretch-draw time is greatly reduced.
Combined communication column foot construction technology of the present invention is by orderly adjustment combination foundation block built-up sequence, stretch-draw adjustment piece has misplaced prestressed stretch-draw at twice, the stretch-draw dolly made according to this combination construction feature and tensioning equipment, under the prerequisite meeting combination construction requirement, farthest have compressed the combination construction time, fully demonstrate the highly effective of modular communications column foot construction.
Claims (5)
1. the combination constructing method thereof of a modular communications column foot, each described modular communications column foot includes nine pieces of prefabricated basic blocks, these nine pieces prefabricated basic blocks are spliced into as integral type square block is as communication column foot, and it is characterized in that, this combination constructing method thereof includes following steps:
The first step, utilizes nine pieces of basic blocks of concrete prefabricated communication column foot, prepares the prestressed reinforcement of stretch-draw;
Second step, is first spliced into cross as coordinate using piece basic blocks of five wherein, forms a central cross shape combination, uses prestressed reinforcement stretch-draw integral;
3rd step, again remaining four pieces of basic blocks are snapped onto respectively the corresponding site at four angles of central cross shape combination, prestressed reinforcing bar, tensioning equipment is used to carry out initial tensioning to all directions prestressed reinforcement, the pulling force of initial tensioning is 10% of design pulling force, to adjust the fissure of displacement and mutual alignment between combination prefabricated foundation block;
4th step, carries out whole stretch-draw after adjusting each combination prefabricated foundation block, and the pulling force of whole stretch-draw is 100% of design pulling force, makes nine pieces of prefabricated foundation blocks be combined into a base integral.
2. the combination constructing method thereof of a kind of modular communications column foot according to claim 1, it is characterized in that, the combination of central cross shape combination is: one piece of prefabricated foundation block is placed in centre position, and four limits that all the other four pieces of prefabricated foundation blocks are close to centre position prefabricated foundation block are respectively placed.
3. the combination constructing method thereof of a kind of modular communications column foot according to claim 1, it is characterized in that, producing stretch-draw prestressing force is stretch-draw dolly and tensioning equipment, described stretch-draw dolly rear portion is provided with storage position, stretch-draw counter-force jack is carried by cantilever in front portion, is placed with the ballast weighed with described tensioning equipment etc. in described storage position.
4. the combination constructing method thereof of a kind of modular communications column foot according to claim 3, is characterized in that, the bottom of described stretch-draw dolly is configured with multiple universal wheel that freely can promote to turn in construction.
5. the combination constructing method thereof of a kind of modular communications column foot according to claim 1, it is characterized in that, adopt the modular communications column foot of the combination of central cross shape combination to include 9 basic blocks combinations, 16 basic blocks combinations, 25 basic blocks combinations and 36 basic blocks combinations.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410802250.7A CN104594374A (en) | 2014-12-23 | 2014-12-23 | Combination construction method for combined type communication tower footing |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410802250.7A CN104594374A (en) | 2014-12-23 | 2014-12-23 | Combination construction method for combined type communication tower footing |
Publications (1)
Publication Number | Publication Date |
---|---|
CN104594374A true CN104594374A (en) | 2015-05-06 |
Family
ID=53120401
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410802250.7A Pending CN104594374A (en) | 2014-12-23 | 2014-12-23 | Combination construction method for combined type communication tower footing |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104594374A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108643219A (en) * | 2018-06-29 | 2018-10-12 | 华中科技大学 | A kind of assembled transmission line of electricity anchor rod static pressure Minitype pile foundation and its construction method |
CN109440799A (en) * | 2018-12-18 | 2019-03-08 | 南京工业大学 | Assembly type sheet pile composite foundation for power transmission line and construction method |
CN113006123A (en) * | 2019-12-20 | 2021-06-22 | 天戈通信科技股份有限公司 | Prefabricated foundation of communication tower |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102677688A (en) * | 2011-12-30 | 2012-09-19 | 深圳市海生机房技术有限公司 | Prefabricated concrete assembled foundation |
US20120291380A1 (en) * | 2011-05-18 | 2012-11-22 | Norman Tooman | Foundation for a Wind Turbine Utilizing a Slurry of Low Viscosity Grout |
CN103374924A (en) * | 2012-04-18 | 2013-10-30 | 彭宝安 | Full-symmetry prestressed assembled tower crane foundation |
CN103850265A (en) * | 2014-03-03 | 2014-06-11 | 中联重科股份有限公司 | Prefabricated assembled tower crane foundation |
CN203639930U (en) * | 2013-11-11 | 2014-06-11 | 于顺平 | Horizontal connecting mechanism for assembly type tower crane base of tower crane with maximum lifting load of less than 80 |
-
2014
- 2014-12-23 CN CN201410802250.7A patent/CN104594374A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20120291380A1 (en) * | 2011-05-18 | 2012-11-22 | Norman Tooman | Foundation for a Wind Turbine Utilizing a Slurry of Low Viscosity Grout |
CN102677688A (en) * | 2011-12-30 | 2012-09-19 | 深圳市海生机房技术有限公司 | Prefabricated concrete assembled foundation |
CN103374924A (en) * | 2012-04-18 | 2013-10-30 | 彭宝安 | Full-symmetry prestressed assembled tower crane foundation |
CN203639930U (en) * | 2013-11-11 | 2014-06-11 | 于顺平 | Horizontal connecting mechanism for assembly type tower crane base of tower crane with maximum lifting load of less than 80 |
CN103850265A (en) * | 2014-03-03 | 2014-06-11 | 中联重科股份有限公司 | Prefabricated assembled tower crane foundation |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108643219A (en) * | 2018-06-29 | 2018-10-12 | 华中科技大学 | A kind of assembled transmission line of electricity anchor rod static pressure Minitype pile foundation and its construction method |
CN109440799A (en) * | 2018-12-18 | 2019-03-08 | 南京工业大学 | Assembly type sheet pile composite foundation for power transmission line and construction method |
CN113006123A (en) * | 2019-12-20 | 2021-06-22 | 天戈通信科技股份有限公司 | Prefabricated foundation of communication tower |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201695321U (en) | Multifunctional propelled tunnel inverted arch trestle | |
CN103215894B (en) | Portable interim prestressed stretch-draw anchor block | |
CN104594374A (en) | Combination construction method for combined type communication tower footing | |
CN104533460A (en) | Construction method for concrete pouring of support-changing type formwork trolley and underground channel | |
CN203834361U (en) | Integral prefabricated molding bed of cross-sea bridge wide pier body steel reinforcement cage | |
CN104805960A (en) | Mould-stripping-free concrete beam and construction method thereof | |
CN103924526B (en) | A kind of bridge spanning the sea roomy pier shaft integral prefabricated moulding bed of steel reinforcement cage | |
CN204690763U (en) | Long side slope protection concrete continuous fast pouring drawing-die system | |
CN103790176A (en) | Embedded short limb column structure and construction method thereof | |
CN205188936U (en) | Novel manual work of combination formula is dug hole rectangle friction pile and is protected concrete wall | |
CN204754945U (en) | Mine method tunnel preliminary bracing lining cutting grid steel support make | |
CN202017197U (en) | Multi-section H-shaped reinforced concrete plate pile welding structure | |
CN203961415U (en) | Safety moving formula communication base station | |
CN202401469U (en) | Connection type prefabricated communication tower foundation | |
CN201695406U (en) | Assembly foundation of prefabricated member | |
CN203383563U (en) | Fast assembled communication iron tower | |
CN104100002A (en) | Connecting structure of floor and column | |
CN210660141U (en) | Assembling equipment for subway tunnel secondary lining structure | |
CN203961026U (en) | The syndeton of a kind of crossbeam and post | |
CN103388336B (en) | Main purline part for inner support | |
CN204199283U (en) | Construction work micro hydraulic hammer stake machine | |
CN204899034U (en) | Prefabricated wall post | |
CN202509490U (en) | Steel-concrete combined pile capable of being disassembled under load by segments and being repeatedly used | |
CN103787012B (en) | A kind of U-board stake cage muscle piles place system automatically | |
CN204252154U (en) | Foundation for tower crane |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20150506 |