CN104100002A - Connecting structure of floor and column - Google Patents

Connecting structure of floor and column Download PDF

Info

Publication number
CN104100002A
CN104100002A CN201410317026.9A CN201410317026A CN104100002A CN 104100002 A CN104100002 A CN 104100002A CN 201410317026 A CN201410317026 A CN 201410317026A CN 104100002 A CN104100002 A CN 104100002A
Authority
CN
China
Prior art keywords
floor
post
concrete
beard muscle
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410317026.9A
Other languages
Chinese (zh)
Inventor
张跃
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201410317026.9A priority Critical patent/CN104100002A/en
Publication of CN104100002A publication Critical patent/CN104100002A/en
Pending legal-status Critical Current

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The invention relates to a connecting structure of a floor and a column. The steel frame of the floor is connected with the column through bolts. The horizontal reinforcing bars of the floor is connected with the horizontal reinforcing bars of the column, and concrete post pouring is used for connection on site. The connecting structure is novel in structure, convenient to mount, high in connecting strength, safe and reliable.

Description

The syndeton of a kind of floor and post
Technical field
The present invention relates to technical field of buildings, be specifically related to the syndeton of a kind of floor and post.
Background technology
In traditional construction method, post is not directly connected with floor, generally on post, build or mounting rail, then at beam upper berth floor or cast in situs floor.The structure that this traditional post is connected indirectly with floor, existence construction is complicated, the engineering time is long, production efficiency is low, be not easy to the shortcomings such as modularization rapid-assembling.In steel building, floor and post generally adopt bolt to be connected to each other, but the building costs of this full steel structure is relatively higher than traditional construction method.Therefore, the present invention has designed a kind of novel floor with concrete ground, this floor adopts integrally welded by steel frame and steel mesh reinforcement, and build concrete and form, described concrete ground is positioned at the top of steel frame, very thin thickness, the side of concrete ground surrounding is provided with beard muscle, this novel floor with concrete ground had both possessed the low advantage of conventional concrete floor cost, possessing again steel work floor assembles rapidly, be easy to batch production large-scale production, intensity is high, build fireballing advantage, avoided the heaviness of concrete floor, intensity is low, the shortcoming that production cycle is long, avoided steel work floor cost higher simultaneously, the shortcoming that steel consumption amount is large.
But the new builing structure being connected with steel structure column or concrete column for the New Floor Slab with concrete ground, how to connect could effectively guarantee easy for installation, connect reliable, intensity is higher and can realize factory normalization and produce, and is a crucial difficult problem of current building field.
Summary of the invention
The object of the invention is for the deficiencies in the prior art, provide a kind of can factory normalization production, field module assembling, speed of application be fast, easy for installation, the new Joining Structure that connects reliable a kind of floor and post.
The present invention is achieved by the following technical programs:
The syndeton of a kind of floor and post, comprise post, floor, described floor is integrally welded and build concrete and form by steel frame and steel mesh reinforcement, steel frame and the post of described floor are bolted, and on described floor and post, be equipped with beard muscle, beard muscle on described floor and the beard muscle on post interconnect, and adopt at the scene the mode of watering after concrete to connect.
Further, the beard muscle on described floor and the beard muscle on post by welding, steel wire bundle, be spirally connected, any in the various ways such as snapping link together, the concrete watering after adopting after connecting fills up.
Further, described post is provided with for holding the floor Connection Block of floor, and described floor Connection Block is provided with the connecting hole of generalization modulus, on described floor, is also provided with corresponding connecting hole, and described floor is bolted on floor Connection Block.
Technique effect of the present invention is as follows:
The steel frame of floor of the present invention adopts high-strength bolt to be connected with post, beard muscle on floor is connected with the beard muscle on post simultaneously, by the mode of rear pouring concrete, connect again, the multiple connection novel structure that this three connects has simultaneously solved well with the New Floor Slab on concrete ground and a link technique difficult problem for post, adopt again floor Connection Block as support and connection, further strengthen intensity, the syndeton of this novel floor and post is not only easy for installation, connect reliable, intensity is higher, and can realize factory normalization produces, can realize high-speed modularization assembling construction.
Accompanying drawing explanation
Fig. 1 is structural representation of the present invention.
In accompanying drawing: 1-floor, 2-post, 3-concrete, 4-beard muscle, 5-connecting hole, 6-bolt, 7-floor Connection Block, 11-concrete ground, 12-steel frame, 13-steel mesh reinforcement.
The specific embodiment
As shown in Figure 1, the syndeton of a kind of floor 1 and post 2, comprises post 2, floor 1.Described floor 1 is integrally welded and build concrete 3 and form by steel frame 12 and steel mesh reinforcement 13.Described steel frame 12 consists of long girder truss and horizontal short girder truss, and described long girder truss and short girder truss are provided with the connecting hole 5 of the generalization modulus for being connected with post 2 or beam.Described steel mesh reinforcement 13 is comprised of the steel wire intersecting in length and breadth, be positioned at the middle and upper part of steel frame 12, the bottom of steel mesh reinforcement 13 and four limits adopt welding manner to be securely fixed on the long girder truss and short truss of steel frame 12, the side of steel mesh reinforcement 13 is provided with the beard muscle 4 with crotch, beard muscle 4 and steel mesh reinforcement 13 be by together with welding or steel wire bundle, then with concrete 3, builds and form concrete 11.Concrete ground 11 is positioned at the middle and upper part of floor 1, and is firmly connected with the steel frame 12 of floor 1, and the side on concrete ground 11 exposes a lot of beard muscle 4 with crotch.
Described post 2 is steel structure column or concrete column, and the floor Connection Block 7 that post 2 is provided with the connecting hole 5 matching with floor 1 and is used for holding floor 1 is also provided with the connecting hole 5 of generalization modulus on floor Connection Block 7.When the floor 1 with concrete ground 11 is connected with post 2, first floor 1 is lifted on the floor Connection Block 7 of post 2, again the connecting hole on the steel frame of floor 1 12 5 is alignd with the connecting hole 5 on post 2, with high-strength bolt 6, both are firmly connected, then the beard muscle 4 of the side on concrete ground 11 on floor 1 and the beard muscle 4 on post 2 are passed through to welding, steel wire bundle, be spirally connected, any in the various ways such as snapping links together, after connecting, adopt concrete 3 to fill up, build, making to form Connection Block between floor 1 and post 2 is connected, high-strength bolt 6 connects, beard muscle 4 connects, the firm structure of multiple connection that rear pouring concrete 3 connects.This multiple firm syndeton, it is a firmly integral body that steel frame 12, concrete ground 11, steel mesh reinforcement 13, beard muscle 4, post 2 are combined closely mutually, has solved well the link technique difficult problem with New Floor Slab 1 with the post 2 on concrete ground 11.Compare with the connected mode of post with existing floor, this multiple firm syndeton, not only low low, steel consumption is few, easy for installation, connect reliable, intensity is high, and can realize factory normalization and produce, and can realize high-speed modularization assembling construction.
Above embodiment is explanation of the invention, and non-limiting, and more than just part is given an example.Should be noted that, concerning the technician of the industry, simple transformation and the improvement according to basic principle of the present invention and structure, carried out, include within protection scope of the present invention.

Claims (3)

1. the syndeton of a floor and post, it is characterized in that: comprise post, floor, described floor is integrally welded and build concrete and form by steel frame and steel mesh reinforcement, steel frame and the post of described floor are bolted, and on described floor and post, be equipped with beard muscle, beard muscle on described floor and the beard muscle on post interconnect, and adopt at the scene the mode of watering after concrete to connect.
2. the syndeton of a kind of floor according to claim 1 and post, it is characterized in that: the beard muscle on described floor and the beard muscle on post by welding, steel wire bundle, be spirally connected, any in the various ways such as snapping link together, the concrete watering after adopting after connecting fills up.
3. the syndeton of a kind of floor according to claim 1 and post, it is characterized in that: described post is provided with for holding the floor Connection Block of floor, described floor Connection Block is provided with the connecting hole of generalization modulus, on described floor, be also provided with corresponding connecting hole, described floor is bolted on floor Connection Block.
CN201410317026.9A 2014-07-07 2014-07-07 Connecting structure of floor and column Pending CN104100002A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410317026.9A CN104100002A (en) 2014-07-07 2014-07-07 Connecting structure of floor and column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410317026.9A CN104100002A (en) 2014-07-07 2014-07-07 Connecting structure of floor and column

Publications (1)

Publication Number Publication Date
CN104100002A true CN104100002A (en) 2014-10-15

Family

ID=51668515

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410317026.9A Pending CN104100002A (en) 2014-07-07 2014-07-07 Connecting structure of floor and column

Country Status (1)

Country Link
CN (1) CN104100002A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104499565A (en) * 2014-11-25 2015-04-08 张跃 Assembled balcony
CN109138151A (en) * 2018-09-30 2019-01-04 华南理工大学 A kind of assembled architecture full-dry method construction concrete frame structure
CN110284594A (en) * 2019-06-25 2019-09-27 长安大学 It is a kind of to be bolted Assembled Building board group conjunction joist steel tubular column frame node and its forming method entirely

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020017571A (en) * 2000-08-31 2002-03-07 김희, 이방주 connection structure of fixing and connecting steel girder in reinforcement concrete column and construction method
CN1776128A (en) * 2005-11-25 2006-05-24 杨九龙 Plate and column connecting method for steel structure building
CN202023257U (en) * 2011-03-16 2011-11-02 东北石油大学 Joint between frame column and composite grid frame floor slab
CN203475609U (en) * 2013-08-16 2014-03-12 威海奥华钢结构有限公司 Connecting structure of composite floor slab and steel tube shear wall of building
CN203961022U (en) * 2014-07-07 2014-11-26 张跃 The syndeton of a kind of floor and post

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020017571A (en) * 2000-08-31 2002-03-07 김희, 이방주 connection structure of fixing and connecting steel girder in reinforcement concrete column and construction method
CN1776128A (en) * 2005-11-25 2006-05-24 杨九龙 Plate and column connecting method for steel structure building
CN202023257U (en) * 2011-03-16 2011-11-02 东北石油大学 Joint between frame column and composite grid frame floor slab
CN203475609U (en) * 2013-08-16 2014-03-12 威海奥华钢结构有限公司 Connecting structure of composite floor slab and steel tube shear wall of building
CN203961022U (en) * 2014-07-07 2014-11-26 张跃 The syndeton of a kind of floor and post

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104499565A (en) * 2014-11-25 2015-04-08 张跃 Assembled balcony
CN109138151A (en) * 2018-09-30 2019-01-04 华南理工大学 A kind of assembled architecture full-dry method construction concrete frame structure
CN109138151B (en) * 2018-09-30 2024-05-17 华南理工大学 Assembled building full-dry method construction concrete frame structure
CN110284594A (en) * 2019-06-25 2019-09-27 长安大学 It is a kind of to be bolted Assembled Building board group conjunction joist steel tubular column frame node and its forming method entirely

Similar Documents

Publication Publication Date Title
CN103556624B (en) Adapter sleeve, to produce and method of attachment containing the prefabricated units of this adapter sleeve and prefabricated units
CN204983171U (en) Prefabricated post connecting device
CN205024833U (en) Reinforcing bar concrete combination prefabricated component
CN106013441A (en) Connecting casing with steel structure
CN104100002A (en) Connecting structure of floor and column
CN203961022U (en) The syndeton of a kind of floor and post
CN203961026U (en) The syndeton of a kind of crossbeam and post
CN209685126U (en) A kind of steel vestibule integrally promotes lifting lug device
CN203559359U (en) Steel girder for reinforcing rigid frame arch bridge beam
CN204081087U (en) A kind of reinforced concrete column and reinforcing steel bar connecting device
CN203569485U (en) Steel truss beam elevation adjusting device
CN203729623U (en) Assembled machining shed for building construction
CN102864746A (en) Bearing frame for bridge construction
CN207121993U (en) The hinged joint that a kind of reinforced concrete frame structure bracing members are reinforced
CN202967874U (en) Overall girder transporting vehicle lifting spreader
CN201785764U (en) Steel pipe concrete structured tower mast foundation
CN205712747U (en) A kind of novel mixed structure steel bar connecting joints
CN204326490U (en) A kind of construction of lift well operating platform
CN204850046U (en) Many davits of both shoulders and crane beam connection structure
CN204899034U (en) Prefabricated wall post
CN203361596U (en) Auxiliary support of integrated lifting operation platform
CN202248510U (en) Horizontal brace rod type bailey
CN203782728U (en) Connecting piece between foundation pile and load-bearing platform
CN202705932U (en) T-beam reinforced hanger frame structure
CN104100006B (en) The syndeton of a kind of crossbeam and post

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent of invention or patent application
CB02 Change of applicant information

Address after: 410013 Changsha province through the opening of the city of Yuanda Road, big city, the three

Applicant after: Zhang Yue

Address before: 410013 South Shaoshan Road, Yuhua District, Hunan, 1, Changsha

Applicant before: Zhang Yue

C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20141015