CN104500123B - A kind of distance tunnel construction phase quick ventilation and exhaust device and method - Google Patents

A kind of distance tunnel construction phase quick ventilation and exhaust device and method Download PDF

Info

Publication number
CN104500123B
CN104500123B CN201410810707.9A CN201410810707A CN104500123B CN 104500123 B CN104500123 B CN 104500123B CN 201410810707 A CN201410810707 A CN 201410810707A CN 104500123 B CN104500123 B CN 104500123B
Authority
CN
China
Prior art keywords
air
ventilation
distance
tunnel
air door
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410810707.9A
Other languages
Chinese (zh)
Other versions
CN104500123A (en
Inventor
冯兴龙
胡泉光
郭少军
陈恩瑜
朱泽浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Gezhouba Group No 3 Engineering Co Ltd
Original Assignee
China Gezhouba Group No 3 Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Gezhouba Group No 3 Engineering Co Ltd filed Critical China Gezhouba Group No 3 Engineering Co Ltd
Priority to CN201410810707.9A priority Critical patent/CN104500123B/en
Publication of CN104500123A publication Critical patent/CN104500123A/en
Application granted granted Critical
Publication of CN104500123B publication Critical patent/CN104500123B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F1/00Ventilation of mines or tunnels; Distribution of ventilating currents
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F1/00Ventilation of mines or tunnels; Distribution of ventilating currents
    • E21F1/10Air doors
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F5/00Means or methods for preventing, binding, depositing, or removing dust; Preventing explosions or fires
    • E21F5/20Drawing-off or depositing dust

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Ventilation (AREA)

Abstract

One distance tunnel construction phase quick ventilation and exhaust device of the present invention, including gantry support, it is separately positioned on the fixed throttle of gantry support upper end and the movable air door of its side, the propeller fan arranged through fixed throttle and jet blower, and electric machine control system;Fixed throttle with launch after movable air door match the most distinguished and the most admirable for cut off in tunnel;The air intake vent of propeller fan and the air outlet of jet blower are arranged on the fixed throttle side near the scope of operation, and the air outlet of propeller fan connects flexible air duct, and the air outlet of flexible air duct extends to outside tunnel.Ventilation smoke exhaust method of the present invention, arrange in tunnel and cut off the most distinguished and the most admirable air door, the pollution space of safe space and closing is formed respectively in air door both sides, ventilation installation is utilized to be pumped to outside hole by the air exhaust passage closed with air-flow by the pollutant polluted in space, utilize blast apparatus by safe space air blast in polluting space, make pollutant add the entrance of flow speed and direction ventilation installation.

Description

A kind of distance tunnel construction phase quick ventilation and exhaust device and method
Technical field
The present invention relates to tunnel construction technology, a kind of distance tunnel construction phase quickly ventilates Smoke extractor and method.
Background technology
Along with the high speed stable development of China's economic construction, (such as the row such as water power, highway in engineering construction Industry) occur in that increasing distance tunnel, these distance tunnels are using conventional drilling and blasting method excavation Construction time, one of difficult problem of a ventilation smoke exhaust problem always puzzlement engineering.For a long time, in distance During Tunnel excavation, when excavation scope of operation distance tunnel mouth is more than 2~after 3Km, and excavation ventilates Smoking problem is difficult to solve, especially after Excavation blasting operation, containing substantial amounts of CO, NO, NO2 In toxic and harmful and dust, use traditional draft type, these toxic and harmfuls and dust from Bursting work face starts, and need to flow through whole hole section of having excavated and discharge, and dirty wind injection is whole has excavated hole section, Ventilation smoke exhaust was for up to 3~4 hours, or having excavated air near the scope of operation does not flows or flow Slowly, ventilation smoke exhaust weak effect, in addition, it is also difficult to solve High-geotemperature problem near the scope of operation, construction is made Industry bad environments.Therefore, the ventilation condition that the construction time is bad the most then makes numerous operating personnels be in for a long time Working in severe underground environment, life and health is affected, and the life of operating personnel in heavy then serious threat Life health and safety, even has influence on construction of tunnel progress and duration.
Summary of the invention
For problems of the prior art, the present invention provides a kind of reasonable in design, safe and reliable, behaviour Facilitating, ventilation smoke exhaust efficiency is high, can be effectively improved the distance tunnel construction of underground construction working environment Phase quick ventilation and exhaust device and method.
The present invention is to be achieved through the following technical solutions:
One distance tunnel construction phase quick ventilation and exhaust device of the present invention, including gantry support, respectively It is arranged on the fixed throttle of gantry support upper end and the movable air door of its side, is arranged on through fixed throttle The propeller fan of the upper end of gantry support and jet blower, and movable air door, propeller fan and penetrate The electric machine control system of flow fan;Fixed throttle matches for cutting off tunnel with the movable air door after expansion In the most distinguished and the most admirable;The air intake vent of propeller fan and the air outlet of jet blower are arranged on fixed throttle and lean on The side of the nearly scope of operation, the air outlet of propeller fan connects flexible air duct, and the air outlet of flexible air duct prolongs Reach outside tunnel.
Preferably, gantry support includes support platform and support post, and support platform is frame structure, under End is at least symmetrical arranged four support posts, and upper end is coated with the gripper shoe being fixedly installed;Adjacent tunnel is same Between the support post that one sidewall is arranged, the frame structure inside with support platform forms triangle by bracing piece Supporting construction;The support post bottom that the same sidewall of adjacent tunnel is arranged is fixed on jointly puts down with canal axes On the connecting plate that row is arranged.
Further, the hydraulic cylinder being respectively arranged to altitude mixture control on pillar, support post and connecting plate are supported Connect cylinder body and the piston rod of hydraulic cylinder respectively;The hydraulic control system of hydraulic cylinder is arranged on gantry support On, for controlling linkage operation or the separate operaton of each hydraulic cylinder.
Preferably, electric machine control system includes the motor this locality switch board being arranged on gantry support, and It is arranged on the motor long-distance control cabinet of home beyond blast area;Motor this locality switch board and motor are long-range Switch board is by wirelessly or non-wirelessly connecting communication.
Further, movable air door is arranged on the side of propeller fan air outlet, uses layer flexible air curtain Or it is provided with the shutter door of chute.
Preferably, propeller fan is arranged on gantry support upper center, and jet blower is symmetricly set on axle The both sides of flow blow;The air intake vent of propeller fan and the air outlet of jet blower are respectively arranged with protection Net.Flexible air duct is arranged along the hanging of tunnel top, and it arranges rigidity wind at corner more than 15 degree when turning round Cylinder transition connects.
One distance tunnel construction phase quick ventilation smoke exhaust method of the present invention, arranges partition axle in tunnel To distinguished and admirable air door, between work surface and air door, form the pollution space of closing, at air door to tunnel Interruption-forming safe space;Then the ventilation installation of air door it is utilized through by the pollutant that pollute in space with gas Flow and be pumped to outside hole by the air exhaust passage closed, be utilized through the blast apparatus of air door by safety simultaneously Space air blast in polluting space, makes pollutant add the entrance of flow speed and direction ventilation installation.
Preferably, air door includes superposed standing part and lower removable part, at non-blasting procedure Construction period, it is possible to open movable air door, keep the ventilation installation through standing part and blast apparatus Normal operation, for working face cooling and carry out blowdown operation in real time.
Preferably, the position that air door is arranged is more than or equal to 50 meters from the distance of work surface, and less than logical The ventilation critical distance of wind devices and the air blast critical distance of blast apparatus.
Compared with prior art, the present invention has a following useful technique effect:
Device of the present invention, by arrange fixed throttle and movable air door form mutual cooperation, The most distinguished and the most admirable in tunnel is cut off, thus defines the space of two relative closures, to pollutant Natural excrement block and isolate, and by gantry support, two air doors are supported, fixing and Location, it is ensured that its action effect and structural strength;By the control of movable air door, it is possible at satisfied partition While requirement, it is ensured that avoid its installing, transport, interference and shadow to other operations when using Ring;Dirt is stirred and pressurizes by the jet blower that recycling is arranged, it is possible to gather axial flow rapidly The air intake vent of ventilation blower, is pumped to outside hole through flexible air duct by its guiding, it is achieved fast to dirt Speed is discharged, and safe and reliable, simple to operate, efficiency of construction is greatly improved, and closely needs 10~20 minutes with regard to energy Poisonous and hazardous dust and the discharge of gas in enough completing hole, and accelerate the gas flowing of work surface, carry High exchange rate, reduces work surface temperature, it is ensured that the working environment that safety is good;Range Extensively, it is possible to meet the distance tunnel construction of the various sections such as gateway opening shape, the shape of a hoof, rectangle, circle The requirement of period quick ventilation smoke exhaust.
Further, arranged by the support platform of frame structure, it is possible to fixed throttle, the axle to top Flow blow and jet blower carry out stable and support location reliably, simultaneously to movable air door below There is provided install and fixed position, gripper shoe can to forming good supplementary partition between two air doors, if The triangular support configurations put can improve the overall rigidity of structure of gantry support and intensity;The company being equipped with Plate, it is possible to ensure the mutual balance and stability between support post.
Further, utilize the hydraulic cylinder arranged to carry out the regulation of height, fixed throttle can not only be ensured With combining closely of tunnel top, and can adapt to and meet the bottom surface situation of different tunnel, improve it Adaptation can, quick and easy for installation, utilize its hydraulic control system can realize flexibly being synchronized with the movement or It it is individually regulation.
Further, the electric machine control system that split is arranged is utilized, it is possible to meeting what motor controlled in time On the basis of, it is achieved remote control, it is ensured that personnel are perfectly safe.
Further, by the setting of shutter door, it is possible to complete quickly and easily movable air door function and Operation, is that vertical tunnel can carry out closing cooperation to middle and lower part, can by the flexible air curtain of multilamellar Realize intercepting and blocking to the tunnel of other form of fractures, meet the folding and unfolding of movable air door and stop requirement.
Further, utilize the distribution to propeller fan and jet blower to be equipped with, improve it The effect of pump drainage and efficiency, utilize the protection network set up can preferably protect the work of equipment to pacify simultaneously Entirely, and dependability and life-span;By the hanging of flexible air duct is arranged, it is to avoid to tunnel its Its equipment and personnel and the interference of construction, by the transition of rigidity air duct, it is ensured that it is smooth and easy that it ventilates With pump drainage speed.
Method of the present invention, first carries out cutting off subregion by tunnel, thus by be diffused Dirt carries out stopping isolation, and concentrates in a less closing space, it is possible to increase its air pressure inside While, it is to avoid leaking and pollution to other regions of dirt;Again by blast apparatus to polluting sky While interior air blast ensures discharge pressure, pollutant are stirred, additionally it is possible to accelerate work surface and carry out The speed of heat exchange, utilizes ventilation installation that by air exhaust passage, the gas stream of pollution of high concentration is discharged to hole Outward, thus ensure that safe space is the most contaminated, its interior operation can synchronize to carry out, and pollutes sky Between dirt discharge thoroughly, quickly, working face cooling is obvious, provides good work for subsequent handling Environment and working condition.
Further, it is possible in the case of opening movable part, cooling and the reality to a small amount of dirt are completed Time discharge;And the distance arranged not only ensure that the safety of air door, and meets ventilation volume air blast Job requirement, it is ensured that working effect, it is possible to elapse work surface and discharge fume operation the most continuously Operation.
Accompanying drawing explanation
Fig. 1 is the structure front view of device described in present example.
Fig. 2 is the structural side view of Fig. 1.
Fig. 3 is the structure front view of gantry support described in present example.
Fig. 4 is the structural side view of Fig. 3.
Fig. 5 is quick ventilation smoke exhaust fundamental diagram after blasting procedure described in the embodiment of the present invention.
Fig. 6 is A-A profile in Fig. 5.
Fig. 7 is other operation construction period ventilation smoke exhaust fundamental diagram in the embodiment of the present invention.
Fig. 8 is B-B profile in Fig. 7.
Fig. 9 is view during quick ventilation and exhaust device transfer in the embodiment of the present invention.
Figure 10 is C-C profile in Fig. 9.
In figure: 1 is gantry support;2 is movable air door;3 is jet blower;4 is propeller fan; 5 is fixed throttle;6 is hydraulic cylinder;7 is hydraulic control system;8,9,10 is control activity respectively Motor this locality switch board of air door, jet blower and propeller fan;11 is motor long-distance control cabinet; 12 is H type I-steel;13 is bracing piece;14 is connecting plate;15 is gripper shoe;16 is flexible wind Cylinder;17 is protection network.
Specific embodiment
The present invention is described in further detail below in conjunction with the accompanying drawings, described in be explanation of the invention and It not to limit.
One distance tunnel construction phase quick ventilation and exhaust device of the present invention, as depicted in figs. 1 and 2, It includes gantry support 1, the ventilation unit being arranged on gantry support 1 and air door group, and controls respectively Ventilation unit processed and the electric machine control system of air door group;As shown in Figure 3 and Figure 4, this preferred embodiment is adopted Illustrate as a example by welding the support platform of gantry support 1 and support post with H type I-steel 12, its Middle utilize channel-section steel to make bracing piece 13 gantry support 1 to do the bearing diagonal strengthened, forms gusseted knot Structure;Arrange the 14 pairs of gantry of winning in succession using double flute steel to make to prop up in the bottom of gantry support 1 support post Frame 1 plays the effect that auxiliary supports, and the gripper shoe 15 using steel plate to make is welded on gantry support 1 Support platform upper surface;Ventilation unit includes being arranged on the propeller fan 4 in the middle part of gripper shoe 15 and right Claim the jet blower 3 being arranged on propeller fan 4 both sides;Air door group includes being arranged on gantry support 1 The fixed throttle 5 of end and the movable air door 2 being arranged on gantry support 1 side.
Wherein, as depicted in figs. 1 and 2, electric machine control system include motor this locality switch board 8,9, 10, and motor long-distance control cabinet 11 two parts, for control movable air door 2 corresponding respectively, penetrate Flow fan 3 and propeller fan 4;Motor this locality switch board 8,9,10 is arranged on gantry support 1 time Side, portion, is respectively used to control movable air door 2, jet blower 3 and propeller fan 4;Motor is long-range Switch board 11 is arranged on the home beyond blast area, and general and scope of operation distance is more than 200m.Its In, propeller fan 4 be respectively welded with the air inlet of jet blower 3 be provided with together with reinforcing bar protection network; The power of motor of propeller fan 4 is not less than 30Kw, uses conversion system to start;Jet blower 3 He The power of motor of movable air door 2 is not more than 30Kw, and employing directly initiates mode and starts.
In the present invention, as shown in figures 1 and 3, hydraulic cylinder 6 it is respectively provided with four of gantry support 1 Support post bottom, for controlling the lifting of gantry support 1 column;On gantry support 1, hydraulic pressure is installed Control system 7, for controlling the linkage between each hydraulic cylinder 6 or separate operaton, it is possible to meet gantry and prop up Frame 1 synchronization lifting or carry out the needs of angle adjustment.In this preferred embodiment, use hydraulic jack conduct Hydraulic cylinder 6 is arranged on gantry support 1 column distance ground 0.6m and highly locates, and its rated load weight is 8~10t, stroke is not less than 1.0m.
In this preferred embodiment, fixed throttle 5 uses shaped steel and sheet metal to be welded, and it is arranged on axial flow Between ventilation blower 4 and jet blower 3, and between gripper shoe 15 and top, hole.Movable air door 2 uses Electric steel-coil gate or multilamellar canvas air curtain, it is arranged on outside gantry support 1 and ventilates near axial flow The side of machine 4 air outlet;When using electric steel-coil gate as movable air door 2, it is additionally provided with and it The steel chute of coupling, for the lifting of electric steel-coil gate.
Concrete, as depicted in figs. 1 and 2, the present invention includes gantry support 1, movable air door 2,1~2 Platform jet blower 3, propeller fan 4, fixed throttle 5.Large power shaft flow blow 4 is arranged on The center upper portion of gantry support 1, and make ventilation smoke exhaust direction towards outside hole, by 1~2 jet blower 3 It is arranged on the both sides of the upper axis flow blow 4 of gantry support 1, and makes the air supply direction of jet blower 3 Towards the scope of operation, during installation, the axis of large power shaft flow blow 4 and jet blower 3 all should be with tunnel axle Line is parallel;Fixed throttle 5 uses channel-section steel to form with Plate Welding, and is weldingly fixed on gantry support 1 Between top and propeller fan 4, jet blower 3, movable air door 2 uses and customizes from specialized factory The electric steel-coil gate of thickening, be arranged on propeller fan 4 air outlet side, be positioned in whole device Bottom, and join steel chute for shutter door lifting.Gantry support 1 of the present invention uses height H type I-steel 12, channel-section steel, double flute steel, Plate Welding form, at four support posts of gantry support 1 Bottom, has installed 1 rated load weight 8~10t, the stroke hydraulic jack more than 1.0m respectively, with Realize the lifting of gantry support 1.
The operation principle of the present invention is divided into two kinds of situations: the first situation, as shown in Figure 5 and Figure 6, when After long tunnel scope of operation blasting procedure terminates, substantial amounts of explosion poisonous and harmful gas will be assembled near the scope of operation Body and flue dust, now, in shotfiring safety region, first pass through motor long-distance control cabinet 11 and motor basis Ground switch board 8, the movable air door 2 on rapid Descent apparatus, as far as possible by toxic and harmful and flue dust Intercept in the space between device and the scope of operation, then by motor long-distance control cabinet 11 and motor the machine Switch board 9, the jet blower 3 in starter, make toxic and harmful and flue dust flow to rapidly device Near, finally by the big merit on motor long-distance control cabinet 11 and motor this locality switch board 10 starter The propeller fan 4 of rate, through the flexible air duct 16 of major diameter rapidly by device near poisonous and harmful gas Body and flue dust pump drainage are to outside hole, thus reach quick ventilation smoke exhaust purpose;The second situation, such as Fig. 7 and Shown in Fig. 8, after quick ventilation smoke exhaust has worked, the movable air door 2 on device is risen, makes to execute Construction equipment, personnel pass through below device, are engaged in the construction of other operation, other operation construction period, penetrate Flow fan 3 and powerful propeller fan 4 keep duty, on the one hand provide at a high speed to the scope of operation Fresh distinguished and admirable, reduce ground temperature, improve working environment, the dirty wind row that on the other hand will produce in work progress Outside hole.
Wherein, the powerful propeller fan 4 of reasonable selection sets to hole separate ventilation smoke evacuation as on device Standby, it is fixed on the upper end of gantry support 1 by bolt, direction of discharging fume when propeller fan 4 is installed Outside hole.It is close to propeller fan 4 air inlet and is welded with the protection network that one employing bar-mat reinforcement is made 17, constitute double protection with the protection network of propeller fan 4 self, indivedual little slungshots during to avoid explosion Pound damage air inlet;Air outlet is firmly connected with supporting flexible air duct 16, and flexible air duct 16 hangs along top, hole Hang straight and extend to outside hole, discharging fume to hole separate ventilation.Air duct is adopted when the corner that corner is bigger Using rigidity air duct, in this preferred embodiment, employing angle steel and Plate Welding make.
The air outlet of jet blower 3 is welded the protection network 17 using bar-mat reinforcement to make together, with jet Blower fan self-protection net constitutes double protection.During work, jet blower 3 injects the fresh wind of high speed to the scope of operation Stream, the fresh distinguished and admirable one side of high speed serves dilution scope of operation blasting fume or dirty wind, reduces scope of operation temperature Effect, on the other hand accelerates blasting fume or dirty distinguished and admirable to powerful propeller fan 4, beneficially axial flow Ventilation blower 4 is quickly by outside its pump drainage to hole.
When carrying out the selection of movable air door 2, it is vertical wall for tunnel section abutment wall, such as gateway opening Shape, rectangle and square, use electric steel-coil gate as movable air door 2, and meet according to below device Height that equipment is current and width dimensions, select or customize electric steel-coil gate model;For tunnel section For the section of other form, use multilamellar canvas air curtain as movable air door 2.Movable air door 2 is only quick-fried Close during needing quick ventilation smoke exhaust after Po, namely fall, and other operation construction period opens, also Being exactly to rise, to meet construction equipment, personnel pass through needs.
Present invention moving method in actual applications, as shown in Figure 9 and Figure 10, moves at device Before, first big diameter blouing tube 16 is taken apart from the air outlet of propeller fan 4, is hung on tunnel top, The external circuit of motor this locality switch board 8,9,10 is disconnected;The support being made up of shaped steel is placed on In 15~20t Wagons of lorries, truck is started the underface to ventilation and exhaust device, passes through Manipulation hydraulic control system 7, shrinks the hydraulic cylinder 6 on ventilation and exhaust device, makes ventilation and exhaust device drop Fall on type support, and ensure that the support post distance from bottom ground of device is not less than 25cm, to ventilation After smoke extractor is made suitably to reinforce, the most at the uniform velocity start truck, make ventilation and exhaust device to the scope of operation Direction is moved to new position, then by manipulation hydraulic control system 7, jacking hydraulic cylinder 6, makes ventilation Cigarette device lifting is in place, outputs truck, extend and firmly connect the flexible air duct 16 of major diameter with And the external circuit of motor this locality switch board 8,9,10, ventilation can be proceeded in a new location Cigarette works.

Claims (10)

1. a distance tunnel construction phase quick ventilation and exhaust device, it is characterised in that include that gantry is propped up Frame (1), is separately positioned on fixed throttle (5) and the movable wind of its side of gantry support (1) upper end Door (2), is arranged on the propeller fan of the upper end of gantry support (1) through fixed throttle (5) And jet blower (3), and movable air door (2), propeller fan (4) and jet blower (4) (3) electric machine control system;Fixed throttle (5) with launch after movable air door (2) match use The most distinguished and the most admirable in cut off in tunnel;The air intake vent of propeller fan (4) and going out of jet blower (3) Air port is arranged on the fixed throttle (5) side near the scope of operation, and the air outlet of propeller fan (4) is even Connecing flexible air duct (16), the air outlet of flexible air duct (16) extends to outside tunnel.
A kind of distance tunnel construction phase quick ventilation and exhaust device the most according to claim 1, its Being characterised by, gantry support (1) includes support platform and support post, and support platform is framework knot Structure, lower end is at least symmetrical arranged four support posts, and upper end is coated with the gripper shoe being fixedly installed (15);Between the support post that the same sidewall of adjacent tunnel is arranged and inside the frame structure of support platform Triangular support configurations is formed by bracing piece (13);At the bottom of the support post that the same sidewall of adjacent tunnel is arranged End is fixed on the connecting plate (14) be arrangeding in parallel with canal axes jointly.
A kind of distance tunnel construction phase quick ventilation and exhaust device the most according to claim 2, its It is characterised by, supports the hydraulic cylinder being respectively arranged to altitude mixture control on pillar, support post and connecting plate (14) cylinder body and the piston rod of hydraulic cylinder (6) are connected respectively;The hydraulic control system (7) of hydraulic cylinder It is arranged on gantry support (1), is used for controlling the linkage operation of each hydraulic cylinder (6) or individually making Industry.
A kind of distance tunnel construction phase quick ventilation and exhaust device the most according to claim 1, its Being characterised by, electric machine control system includes the motor this locality switch board being arranged on gantry support (1) (8,9,10), and it is arranged on the motor long-distance control cabinet (11) of home beyond blast area;Electricity Machine this locality switch board (8,9,10) and motor long-distance control cabinet (11) are logical by wirelessly or non-wirelessly connecting News.
A kind of distance tunnel construction phase quick ventilation and exhaust device the most according to claim 1, its Being characterised by, movable air door (2) is arranged on the side of propeller fan (4) air outlet, uses multilamellar Flexible air curtain or be provided with the shutter door of chute.
A kind of distance tunnel construction phase quick ventilation and exhaust device the most according to claim 1, its Being characterised by, propeller fan (4) is arranged on gantry support (1) upper center, jet blower (3) both sides of propeller fan (4) it are symmetricly set on;The air intake vent of propeller fan (4) and penetrating The air outlet of flow fan (3) is respectively arranged with protection network (17).
A kind of distance tunnel construction phase quick ventilation and exhaust device the most according to claim 1, its Being characterised by, flexible air duct (16) is arranged along the hanging of tunnel top, and it is corner turning round more than 15 degree Time arrange rigidity air duct transition connect.
8. a distance tunnel construction phase quick ventilation smoke exhaust method, it is characterised in that use such as right Require the distance tunnel construction phase quick ventilation and exhaust device described in 1, partition is set in tunnel axially Distinguished and admirable air door, forms the pollution space of closing, at air door to tunnel portal between work surface and air door Form safe space;Then the ventilation installation of air door it is utilized through by the pollutant that pollute in space with air-flow Being pumped to outside hole by the air exhaust passage closed, the blast apparatus being simultaneously utilized through air door is empty by safety Between to polluting air blast in space, make pollutant add the entrance of flow speed and direction ventilation installation.
A kind of distance tunnel construction phase quick ventilation smoke exhaust method the most according to claim 8, its Being characterised by, described air door includes superposed standing part and lower removable part, in non-explosion The construction period of operation, it is possible to open movable air door, keep the ventilation installation through standing part and air blast The normal operation of equipment, for working face cooling and carry out blowdown operation in real time.
A kind of distance tunnel construction phase quick ventilation smoke exhaust method the most according to claim 8, It is characterized in that, the position that described air door is arranged is more than or equal to 50 meters from the distance of work surface, and Ventilation critical distance and the air blast critical distance of blast apparatus less than ventilation installation.
CN201410810707.9A 2014-12-22 2014-12-22 A kind of distance tunnel construction phase quick ventilation and exhaust device and method Active CN104500123B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410810707.9A CN104500123B (en) 2014-12-22 2014-12-22 A kind of distance tunnel construction phase quick ventilation and exhaust device and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410810707.9A CN104500123B (en) 2014-12-22 2014-12-22 A kind of distance tunnel construction phase quick ventilation and exhaust device and method

Publications (2)

Publication Number Publication Date
CN104500123A CN104500123A (en) 2015-04-08
CN104500123B true CN104500123B (en) 2016-08-17

Family

ID=52941562

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410810707.9A Active CN104500123B (en) 2014-12-22 2014-12-22 A kind of distance tunnel construction phase quick ventilation and exhaust device and method

Country Status (1)

Country Link
CN (1) CN104500123B (en)

Families Citing this family (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105240298B (en) * 2015-11-17 2018-07-20 中国长江三峡集团公司 The ventilation of Cavity Construction phase dissipates cigarette system installation method
CN109282634B (en) * 2018-10-18 2023-07-21 楚天科技股份有限公司 Air door sling isolating device of tunnel oven
CN109869162A (en) * 2019-04-09 2019-06-11 中国水利水电第四工程局有限公司 A kind of moving platform device for accelerating the cooling of tunnel high temperature section
CN110454209A (en) * 2019-08-09 2019-11-15 苏州中车建设工程有限公司 interval tunnel jet fan installation and maintenance platform and installation and maintenance method
CN111197854A (en) * 2020-02-28 2020-05-26 长安大学 Intelligent air door and installation method and working method thereof
CN112127932B (en) * 2020-08-24 2022-09-20 东南大学 Lateral smoke exhaust auxiliary flow guide control device and method
CN112065491A (en) * 2020-09-21 2020-12-11 中铁十八局集团有限公司 Tunnel construction ventilation method
CN112197390A (en) * 2020-11-13 2021-01-08 黄河勘测规划设计研究院有限公司 High-density hidden-hole pedestrian passageway fire protection system
CN112443346B (en) * 2020-11-25 2022-10-14 成都城投建筑工程有限公司 Frame structure of main line under road
CN112459783B (en) * 2020-12-23 2023-01-17 莱芜莱新铁矿有限责任公司 Safety device for mining under filling body
CN113882890B (en) * 2021-09-30 2023-01-10 鄂尔多斯市伊化矿业资源有限责任公司 Long-distance local ventilation device for rapid tunneling of mine working face ultra-long-distance coal roadway

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101324191A (en) * 2007-06-14 2008-12-17 兖州煤业股份有限公司 Dust removal method and apparatus of common drivage working surface
CN101368483A (en) * 2008-10-14 2009-02-18 中铁一局集团有限公司 Ventilation construction method for pressure regulating distribution chamber in tunnel auxiliary pilot pit
JP4472017B2 (en) * 2009-07-09 2010-06-02 川崎重工業株式会社 Road tunnel ventilation system
CN103306702A (en) * 2013-06-28 2013-09-18 中铁十七局集团第三工程有限公司 Inflatable isolating device for tunnel ventilation construction
CN203412612U (en) * 2013-07-22 2014-01-29 河北铁建工程有限公司 Forced ventilation device for railway tunnels
CN104153805A (en) * 2014-07-31 2014-11-19 上海市城市建设设计研究总院 Intra-tunnel smoke discharge system and method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101324191A (en) * 2007-06-14 2008-12-17 兖州煤业股份有限公司 Dust removal method and apparatus of common drivage working surface
CN101368483A (en) * 2008-10-14 2009-02-18 中铁一局集团有限公司 Ventilation construction method for pressure regulating distribution chamber in tunnel auxiliary pilot pit
JP4472017B2 (en) * 2009-07-09 2010-06-02 川崎重工業株式会社 Road tunnel ventilation system
CN103306702A (en) * 2013-06-28 2013-09-18 中铁十七局集团第三工程有限公司 Inflatable isolating device for tunnel ventilation construction
CN203412612U (en) * 2013-07-22 2014-01-29 河北铁建工程有限公司 Forced ventilation device for railway tunnels
CN104153805A (en) * 2014-07-31 2014-11-19 上海市城市建设设计研究总院 Intra-tunnel smoke discharge system and method

Also Published As

Publication number Publication date
CN104500123A (en) 2015-04-08

Similar Documents

Publication Publication Date Title
CN104500123B (en) A kind of distance tunnel construction phase quick ventilation and exhaust device and method
CN109723484B (en) Closed pressure drainage combined ventilation system and ventilation method for tunnel construction by drilling and blasting method
CN204691809U (en) A kind of long distance tunnel construction phase quick ventilation and exhaust device
BR112014032362B1 (en) mobile installation for aspiration and treatment of gases and / or dust and / or gas mixtures
CN110485752A (en) A kind of skyscraper tears building method open and tears building machine open
CN106480249B (en) A kind of blast furnace iron notch top suction dust-extraction unit
CN206676621U (en) A kind of air zoning moves dry spray booth
CN209443579U (en) A kind of steel construction greenhouse for contaminated soil remediation
JP2019214853A (en) Shatter-proof demolition method for waste incineration plant
CN202645572U (en) Slagging-off machine with slurry spraying manipulator and dust controlling and removing functions
CN108796159B (en) Modular detachable blast furnace cast house combined dust removal device
CN204238968U (en) The tunnel structure of natural ventilation
CN111058609A (en) Construction and protection integrated portable operation platform and method
CN103016043B (en) Inflatable smoke exhaust and dust removal isolating hood for tunnel shaft construction
CN107227972A (en) A kind of automatic sprayer
CN204923917U (en) Portable dust collector in line frequency furnace stokehold
CN107725095A (en) Grotto low and intermediate level radioac disposal site accident emergency radioactivity non-proliferation system
CN104074362A (en) Small-sized multifunctional concrete jet pump
CN207004564U (en) A kind of automatic sprayer
CN206956070U (en) Inhale dust arrester in a kind of blast furnace iron notch top
CN208040431U (en) A kind of device preventing subway engineering ventilation smoke exhaust air flow shortcircuit
CN113006550A (en) Emergency battery emergency treatment room system for battery workshop
CN206464718U (en) A kind of exhaust device for welding fume in steel box-girder casing
Apel Designing the ventilation system for the McArthur River Mine—World largest uranium deposit
CN104041360A (en) Method and device for weakening tornado

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant