CN104499714B - 基于bim平台及测量机器人的机电安装工程施工方法 - Google Patents

基于bim平台及测量机器人的机电安装工程施工方法 Download PDF

Info

Publication number
CN104499714B
CN104499714B CN201410639944.3A CN201410639944A CN104499714B CN 104499714 B CN104499714 B CN 104499714B CN 201410639944 A CN201410639944 A CN 201410639944A CN 104499714 B CN104499714 B CN 104499714B
Authority
CN
China
Prior art keywords
construction
electrical
measurement
robot measurement
dimensional data
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410639944.3A
Other languages
English (en)
Other versions
CN104499714A (zh
Inventor
彭青
钟剑
唐铁军
任慧军
蒋保胜
邓亚宏
伍学智
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Construction Engineering Co Ltd of China Construction Third Engineering Division
Original Assignee
Second Construction Engineering Co Ltd of China Construction Third Engineering Division
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Construction Engineering Co Ltd of China Construction Third Engineering Division filed Critical Second Construction Engineering Co Ltd of China Construction Third Engineering Division
Priority to CN201410639944.3A priority Critical patent/CN104499714B/zh
Publication of CN104499714A publication Critical patent/CN104499714A/zh
Application granted granted Critical
Publication of CN104499714B publication Critical patent/CN104499714B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

本发明涉及基于BIM平台及测量机器人的机电安装工程施工方法,包括机电综合管线BIM模型、测量机器人,其主要特征包括:1、优化设计成果,将现场建筑结构的实际尺寸情况以三维数据的形式反馈到机电综合管线BIM模型中,从而优化施工设计,减少施工错误。2、通过测量机器人利用机电综合管线BIM模型中的三维数据信息进行现场机电管线和设备安装精确高效的定位放样,优化施工流程、提高施工效率,同时保证优良的施工质量。3、利用测量机器人采集施工现场数据,通过实测数据与设计数据的对比,可以实现辅助施工验收,确保施工成果的质量水平达到设计要求。

Description

基于BIM平台及测量机器人的机电安装工程施工方法
技术领域
本发明涉及一种基于BIM平台及测量机器人的机电安装工程施工方法。
背景技术
根据目前建筑机电安装工程施工空间非常有限,分布复杂,施工精度要求高的特点。
传统的机电安装施工技术中存在一些关键问题难以解决。1、由于建筑结构空间的复杂性,以及结构施工过程中存在的误差,使机电深化设计人员无法准确把握现场实际情况,造成图纸所画无法在现场施工,导致大量人力物力的浪费。2、传统的机电管线安装施工测量工作方法粗糙,操作麻烦,工作效率低,空间局限性较大,尤其是施工精度不够,导致施工质量不能够满足设计要求。3、传统的机电安装验收对管线水平度、直线度等信息检查不够完善,利用测量机器人指导综合管线现场施工能够有效完善验收过程,提高施工质量。4、在弧形管线等敷设线路复杂的机电安装领域,传统施工方法效率很低,无法满足工期要求。
目前建筑机电安装工程施工空间非常有限,分布复杂,施工精度要求高的特点,
发明内容
本发明的目的结合现阶段建筑信息建模BIM技术发展条件,突破传统机电综合管线施工过程中的施工测量精度不高、施工流程复杂、施工效率低、验收手段有限等缺点,而提供一种基于BIM平台及测量机器人的机电安装工程施工方法,该方法主要从机电管线深化设计阶段,综合管线敷设施工阶段,施工验收阶段进行实施。在深化设计阶段:基于测量机器人与机电综合管线BIM模型的结合,将现场测量机器人测绘所得到的结构信息与机电综合管线BIM模型中的数据对比,考量现场施工环境与设计的机电综合管线BIM模型之间的偏差,为机电安装深化设计、施工工艺选择等提供依据;在施工阶段,基于测量机器人高效精确的放样定位功能,将机电综合管线BIM模型中的设计坐标与尺寸以相应的数据格式导入测量机器人,结合施工现场轴线网、控制点及标高控制线,实现精确的施工放样,推动机电安装施工工作;在施工验收阶段,基于测量机器人精确的数据采集功能,在施工完成后对现场实物进行实测实量,通过将实测数据与深化设计的机电综合管线BIM模型三维数据进行对比来检查安装质量与是否符合要求。
本发明的技术方案为:
一种基于BIM平台及测量机器人的机电安装工程施工方法,其特征在于按以下步骤进行:
(1)建立机电综合管线BIM模型:利用REVIT软件,在建筑信息建模BIM基础上,根据原始机电设计目标、结合现有机电各专业施工技术规范要求,避免管线碰撞,有效利用有限建筑空间,建立精细实用的机电综合管线BIM模型;
(2)利用测量机器人对机电施工现场建筑结构复核测量,将复核测量机电施工建筑结构的实际尺寸情况以三维数据的形式反馈到建立的机电综合管线BIM模型中,进行比对,考量实际测量值与设计值之间差值对现场施工的影响,当现场结构误差的影响导致现有建立的机电综合管线BIM模型无法满足施工要求时,及时与结构施工单位协调,改正现场结构施工错误;若误差由于建立的机电综合管线BIM模型没有全面考虑现场结构具体特点导致碰撞,则及时对建立的机电综合管线BIM模型进行调整优化;
(3)根据优化后的机电综合管线BIM模型的三维数据信息形成测量放样三维数据,并将测量放样三维数据导入测量机器人的放样管理器中,测量机器人进行现场施工放样;
(4)根据放样结果完成机电施工,并利用测量机器人对施工成果进行施工验收。
本发明进一步利用测量机器人对施工成果进行实测实量,辅助验收,将验收实测三维数据与优化后的机电综合管线BIM模型的三维数据对比;若实测值与设计值的差值不满足施工验收规范要求时为不合格,现场进行施工整改,若差值满足施工验收规范要求则为合格,以此判定验收是否合格。
步骤(2)的现场建筑结构复核测量的主要测量点位为现场预留洞标高及位置、梁底标高和巨柱倾斜度情况,这些都是影响机电管线分布的关键部位。
步骤(3)的具体步骤为:机电施工过程中管线布设、支吊架预埋点位坐标、机电设备安装轴线和净高的数据均来自于优化后的机电综合管线BIM模型的三维数据;首先,以机电综合管线BIM模型为基础,利用REVIT软件绘制设计管线支架分布图为放样三维数据提供依据也就是施工设计图;然后,根据支架分布图结合现场施工操作要求进行放样点位选取,放样点主要包括管线支架安装点位以及辅助管线吊装点位;接着,将选取的放样点位以三维坐标形式导出储存,在选取放样点前应确保施工坐标系与图纸坐标一致,能通过轴线网实现二者间的相互转化,根据点位特征分类整理放样三维数据;最后,将点位坐标三维数据及施工设计图以放样文件的形式载入测量机器人的放样管理器,测量机器人进行现场施工放样。
本发明在深化设计阶段:基于测量机器人与机电综合管线BIM模型的结合,将现场测绘所得到的结构信息与机电综合管线BIM模型中的数据对比,考量现场施工环境与设计机电综合管线BIM模型之间的偏差,为机电安装深化设计、施工工艺选择等提供依据。在施工阶段,基于测量机器人高效精确的放样定位功能,将机电综合管线BIM模型中的设计坐标与尺寸以特定的数据格式导入测量机器人,结合施工现场轴线网、控制点及标高控制线,实现精确的施工放样,推动机电安装施工工作。在施工验收阶段,基于测量机器人精确的数据采集功能,在施工完成后对现场实物进行实测实量,通过将实测数据与设计数据进行对比来检查安装质量与是否符合要求。
附图说明
图1为本发明的施工工艺流程图。
具体实施方式
结合附图及具体实施例对本发明作进一步详细的说明:
如图1所示,1、仪器准备,为了实现该技术的应用我们选用的设备是Tablet与Trimble RTS773机器人全站仪系统。
设备名称 Trimble RTS773
无线wifi通讯最大距离 700m
水平角测角精度 3″
竖直角测角精度 2″
标准测量精度(棱镜模式) ±2mm+2ppm
最大测距(棱镜模式) 3000m
最小测距 1.5m
2、建立机电综合管线BIM模型:利用REVIT软件,在建筑信息建模BIM基础上,根据原始机电设计目标、结合现有机电各专业施工技术规范要求,避免管线碰撞,有效利用有限建筑空间,建立精细实用的机电综合管线BIM模型。
3、复核建筑结构,优化机电安装工程深化设计
1)复核建筑结构,即根据机电设计具体要求和建筑结构特点到现场进行测量,采集相关部位的三维坐标。结构复核的主要测量点位包括现场预留洞标高及位置、梁底标高、巨柱倾斜度情况等影响机电管线分布的关键部位。
2)将实测实量数据与现有设计的机电综合管线BIM模型数据对比,考量实际测量值与设计值之间差值对现场施工的影响。
3)将数据对比结果以报告的形式反馈给设计部门,提出调整优化机电综合管线BIM模型或者进行结构修整的处理意见,确保设计成果的可靠性。
4、用机器人全站仪结合优化后的机电综合管线BIM模型进行施工放线
1)数据准备,施工过程中为实现精确设计施工,机电安装过程中管线布设,支吊架预埋点位坐标,机电设备安装轴线,净高等测量数据均来自于经过深化设计的机电综合管线BIM模型。首先,以设计图纸为基础,利用CAD或REVIT软件绘制设计管线支架分布图,为放样数据提供依据。然后,根据支架分布图结合现场施工操作要求进行放样点位选取,其主要包括管线支架安装点位以及辅助管线吊装点位。接着,将选取的放样点位以三维坐标形式导出储存,在选取放样点前应确保施工坐标系与图纸坐标一致,可通过轴线网实现二者间的相互转化,根据点位特征分类整理放样数据。最后,将点位坐标数据及施工设计图以放样文件的形式载入放样管理器。
2)利用测量机器人进行管线施工放样,首先,根据现场控制点,通过后方交会的方法进行仪器设站设置(确保后视角在30°至135°之间),该方法可以确保施测精度在±3mm,同时实现在建筑平面内任意满足控制点通视要求的位置设站。完成机器人全站仪的设站之后,根据导入放样管理器中的设计图纸进行机电管线放样。其中一名测量人员操作仪器,另一名施工人员进行放样点位标注。即可完成所有机电管线的放样工作,高效准确。最后,根据不同专业的管线对放样点位进行分类标记,点位标记必须清晰准确,并及时保存测量数据。
4、全站仪辅助施工验收,首先,通过天宝机器人全站仪高效的数据采集功能,测量现场施工成果三维信息。然后,根据实测实量信息与设计模型中的信息对比分析来检查管线、设备的安装施工质量。

Claims (2)

1.一种基于BIM平台及测量机器人的机电安装工程施工方法,其特征在于按以下步骤进行:
(1)建立机电综合管线BIM模型:利用REVIT软件,在建筑信息建模BIM基础上,根据原始机电设计目标、结合现有机电各专业施工技术规范要求,避免管线碰撞,有效利用有限建筑空间,建立精细实用的机电综合管线BIM模型;
(2)利用测量机器人对机电施工现场建筑结构复核测量,现场建筑结构复核测量的主要测量点位为现场预留洞标高及位置、梁底标高和巨柱倾斜度情况,将复核测量机电施工现场建筑结构的实际尺寸情况以三维数据的形式反馈到建立的机电综合管线BIM模型中,进行比对,考量实际测量值与设计值之间差值对现场施工的影响,当现场结构误差的影响导致现有建立的机电综合管线BIM模型无法满足施工要求时,及时与结构施工单位协调,改正现场结构施工错误;若由于建立的机电综合管线BIM模型没有全面考虑现场结构具体特点而导致碰撞,则及时对建立的机电综合管线BIM模型进行调整优化;
(3)根据优化后的机电综合管线BIM模型的三维数据信息形成测量放样三维数据,并将测量放样三维数据导入测量机器人的放样管理器中,测量机器人进行现场施工放样;具体为:机电施工过程中管线布设、支吊架预埋点位坐标、机电设备安装轴线和净高的数据均来自于优化后的机电综合管线BIM模型的三维数据;首先,以机电综合管线BIM模型为基础,利用REVIT软件绘制设计管线支架分布图为放样三维数据提供依据,也就是施工设计图;然后,根据支架分布图结合现场施工操作要求进行放样点位选取,放样点主要包括管线支架安装点位以及辅助管线吊装点位;接着,将选取的放样点位以三维坐标形式导出储存,在选取放样点前应确保施工坐标系与图纸坐标一致,能通过轴线网实现二者间的相互转化,根据点位特征分类整理放样三维数据;最后,将点位坐标三维数据及施工设计图以放样文件的形式载入测量机器人的放样管理器,通过测量机器人进行现场施工放样;
(4)根据放样结果完成机电施工,并利用测量机器人对施工成果进行施工验收。
2.根据权利要求1所述的基于BIM平台及测量机器人的机电安装工程施工方法,其特征在于:步骤(4)利用测量机器人对施工成果进行实测实量,辅助验收,将验收实测三维数据与优化后的机电综合管线BIM模型的三维数据对比;判定验收是否合格;若实测值与设计值的差值不满足施工验收规范要求时为不合格,现场进行施工整改,若差值满足施工验收规范要求为合格。
CN201410639944.3A 2014-11-13 2014-11-13 基于bim平台及测量机器人的机电安装工程施工方法 Active CN104499714B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410639944.3A CN104499714B (zh) 2014-11-13 2014-11-13 基于bim平台及测量机器人的机电安装工程施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410639944.3A CN104499714B (zh) 2014-11-13 2014-11-13 基于bim平台及测量机器人的机电安装工程施工方法

Publications (2)

Publication Number Publication Date
CN104499714A CN104499714A (zh) 2015-04-08
CN104499714B true CN104499714B (zh) 2017-03-15

Family

ID=52941155

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410639944.3A Active CN104499714B (zh) 2014-11-13 2014-11-13 基于bim平台及测量机器人的机电安装工程施工方法

Country Status (1)

Country Link
CN (1) CN104499714B (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109537896A (zh) * 2018-11-22 2019-03-29 中铁上海工程局集团有限公司 一种基于bim的施工场地电箱智能化布置方法及系统

Families Citing this family (40)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104899378A (zh) * 2015-06-10 2015-09-09 上海大学 基于bim和三维测量的高层钢结构数字化安装方法
CN105089216A (zh) * 2015-09-11 2015-11-25 深圳市深装总装饰股份有限公司 旋转楼梯石材饰面三维定位装饰施工方法
CN105808835B (zh) * 2016-03-04 2018-12-25 上海宝冶集团有限公司 基于bim的机电系统管线装配方法
CN105888317B (zh) * 2016-04-19 2018-07-27 中建三局第二建设工程有限责任公司 中央制冷机房模块化预制及装配化施工方法
CN107451706A (zh) * 2016-06-01 2017-12-08 无锡市工业设备安装有限公司 一种用于机电安装的工业化安装方式
CN106013798A (zh) * 2016-06-12 2016-10-12 江苏宜安建设有限公司 一种基于bim的标准层施工方法
CN107784137A (zh) * 2016-08-26 2018-03-09 上海宝冶集团有限公司 基于bim技术的机电综合支吊架设计方法
CN106354943A (zh) * 2016-08-31 2017-01-25 赖正伦 一种工程模块化制造系统及其制造方法
CN106709660B (zh) * 2016-12-29 2021-11-19 天津市建筑设计院 基于bim的建筑设计方法
CN106777831B (zh) * 2017-02-10 2020-07-21 深圳瑞和建筑装饰股份有限公司 一种基于bim的施工和装修方法
CN106968370B (zh) * 2017-02-21 2018-03-23 中建七局建筑装饰工程有限公司 一种球类幕墙的快速放线、定位及下料方法
CN108151717A (zh) * 2017-11-15 2018-06-12 四川建筑职业技术学院 一种基于bim系统的全自动放样方法
CN108363860A (zh) * 2018-02-07 2018-08-03 中交公局第二工程有限公司 一种基于bim技术的三维异形桥梁模板拼装测设方法
CN108468427A (zh) * 2018-03-22 2018-08-31 中建四局安装工程有限公司 防止建筑施工中因线管破坏造成线管不通的方法
CN108827253B (zh) * 2018-03-29 2020-11-03 上海宝冶集团有限公司 雪车雪橇赛道的管道支架的安装及定位测量方法
CN108647384A (zh) * 2018-04-03 2018-10-12 中国建筑第八工程局有限公司 机电管线及设备安装测量定位的方法
CN108827255B (zh) * 2018-04-20 2020-10-23 中铁九局集团第二工程有限公司 一种基于bim的钢混组合结构索塔的索鞍测量方法
CN108763821A (zh) * 2018-06-15 2018-11-06 中国机械工业机械工程有限公司 一种城市轨道交通高架车站机电设备安装方法
CN109063973B (zh) * 2018-07-10 2022-03-18 赵华 基于人工智能的建设工程建造方法
CN109033592B (zh) * 2018-07-13 2023-06-30 深圳市郑中设计股份有限公司 一种异形饰面板的bim放样方法
CN109614723B (zh) * 2018-12-14 2023-04-28 中建二局第一建筑工程有限公司 一种基于bim技术的综合施工方法
CN109737929A (zh) * 2018-12-26 2019-05-10 国网浙江省电力有限公司建设分公司 一种输电线路工程特高钢管塔分段验收方法
CN109740246A (zh) * 2018-12-29 2019-05-10 江苏龙腾数字建造技术研究院有限公司 一种基于bim的精装修深化设计优化方法
CN109826108B (zh) * 2019-01-15 2020-08-11 东南大学 一种基于放样机器人的桥梁顶推自动监控方法
CN110216672A (zh) * 2019-05-17 2019-09-10 广东博智林机器人有限公司 信息交互方法、服务器及建筑机器人
CN110362030A (zh) * 2019-06-14 2019-10-22 中国一冶集团有限公司 基于bim技术的建筑项目管线净空检测装置
CN110864625A (zh) * 2019-11-18 2020-03-06 上海建工四建集团有限公司 施工现场设备安装定位与检测的方法及系统
CN111007881B (zh) * 2019-11-25 2023-04-11 重庆建工机电安装工程有限公司 基于bim的轨道交通机电安装工程系统及方法
CN111070387B (zh) * 2019-12-31 2021-07-20 中铁大桥局集团有限公司 预制梁体模板自动精密调整装置、方法及系统
CN111127656B (zh) * 2020-01-09 2020-11-24 中建一局集团第二建筑有限公司 一种基于bim模型的异形屋顶放样施工方法
CN111475877A (zh) * 2020-03-06 2020-07-31 青岛腾远设计事务所有限公司 一种基于bim技术测算空间净高的方法、装置及终端
CN112231815A (zh) * 2020-10-22 2021-01-15 中铁四局集团第四工程有限公司 一种基于bim与测量机器人的桥梁工程施工自动化测量系统及方法
CN112668910A (zh) * 2020-12-31 2021-04-16 深圳市昊源建设监理有限公司 一种建筑监理用全过程建设工程智能管控方法及系统
CN113111827A (zh) * 2021-04-22 2021-07-13 北京房江湖科技有限公司 施工监控方法、装置、电子设备和存储介质
CN113312692A (zh) * 2021-05-19 2021-08-27 江苏中匀安装集团有限公司 一种基于bim的公共建筑机电安装工程施工方法
CN113435757B (zh) * 2021-06-30 2022-05-03 中建华帆建筑设计院有限公司 基于bim的建筑砌筑的设计及施工方法
CN115112104A (zh) * 2021-08-17 2022-09-27 上海环创安装工程集团有限公司 一种建筑施工现场测绘放样方法
CN113702902A (zh) * 2021-09-02 2021-11-26 中建八局第二建设有限公司 一种基于bim的可视化穿线引导装置及引导方法
CN114295110A (zh) * 2021-12-20 2022-04-08 南京国豪装饰安装工程股份有限公司 一种基于bim机器人的放线施工方法
CN114428993B (zh) * 2022-04-06 2022-06-21 山东高速德建建筑科技股份有限公司 基于bim的管线综合排布方法和系统

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090072385A (ko) * 2007-12-28 2009-07-02 주식회사 두올테크 건설 프로젝트 통합의사결정 지원 시스템 및 방법
CN103093061B (zh) * 2013-02-07 2015-09-09 中铁二十二局集团电气化工程有限公司 一种地铁机电工程综合管线碰撞优化方法
CN103198195A (zh) * 2013-04-16 2013-07-10 上海上安机电设计事务所有限公司 一种基于bim的建筑工程模型碰撞检测方法
CN103247004B (zh) * 2013-04-28 2015-09-16 中建安装工程有限公司 一种基于机电集成bim模型的信息管理方法与系统
CN103530826B (zh) * 2013-09-06 2017-02-15 上海大学 基于bim的盾构法隧道施工管理方法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
BIM 技术在武汉某项目机电设计中的研究及应用;裴以军,彭友元,陈爱东 ,牛俊乔 ,蔡春良 ,孙亮;《施工技术》;20111110;第40卷(第352期);正文第94页右栏倒数第4行至第96页右栏第11行 *
基于BIM 的自动化测量在陈翔路地道工程中的应用;陈威,秦雯,陈森,叶梅,黄铭丰;《土木建筑工程信息技术》;20130215;第5卷(第1期);正文第73页右栏第1行至第74页左栏最后1行以及表1、图4 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109537896A (zh) * 2018-11-22 2019-03-29 中铁上海工程局集团有限公司 一种基于bim的施工场地电箱智能化布置方法及系统
CN109537896B (zh) * 2018-11-22 2021-04-30 中铁上海工程局集团有限公司 一种基于bim的施工场地电箱智能化布置方法及系统

Also Published As

Publication number Publication date
CN104499714A (zh) 2015-04-08

Similar Documents

Publication Publication Date Title
CN104499714B (zh) 基于bim平台及测量机器人的机电安装工程施工方法
CN105888317B (zh) 中央制冷机房模块化预制及装配化施工方法
CN107402001B (zh) 基于3d扫描的超高层建筑施工偏差数字化检验系统及方法
CN109033592B (zh) 一种异形饰面板的bim放样方法
CN111627099B (zh) 基于三维扫描技术的钢结构非接触式实测实量方法和系统
CN107093206A (zh) 利用3d激光扫描技术快速bim建模的方法
CN111062081A (zh) 一种基于bim技术的地下连续墙施工方法
CN111191307B (zh) 一种基于bim+gis技术的土方工程虚拟施工方法
CN111578916B (zh) 基于bim技术在装饰工程中智能放线施工方法
CN112282847B (zh) 一种煤矿井下巷道形变监测方法
CN108871266A (zh) 一种基于中间法三角高程方法的自动化沉降监测方法
CN103591944B (zh) 一种弧形建筑测量施工方法
CN107192381A (zh) 一种任意无序空间结构的测量放样方法
CN111125821A (zh) 基于bim+gis地基与基础分部工程分析及选型方法
CN109635340B (zh) 一种基于倾斜摄影和bim的矿山加工系统设计方法
CN107270814A (zh) 一种预制装配式风洞高精度安装控制方法
CN110489896B (zh) 一种基于多源数据融合技术的临建工程选址及设计方法
CN112989532A (zh) 基于bim的地铁车站市政管线改迁施工方法
CN112884647A (zh) 一种基于bim点云技术指导埋件施工定位方法
CN109826248A (zh) 3D Laser Scanner应用于基坑变形监测的方法
CN113221221A (zh) 一种基于bim技术的预制梁上预应力管道定位方法
CN111691691A (zh) 箱体弯扭构件与鼓节点安装测量定位方法
US9803977B2 (en) Apparatus and method for bridge assembly
CN106203796B (zh) 一种基于工程电子图纸原位标注的实测实量方法
CN113374282B (zh) 采用假定坐标系控制预埋螺栓的方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant