CN104420419A - 一种托盘顶帽变尺寸桥墩施工模板的安装方法 - Google Patents
一种托盘顶帽变尺寸桥墩施工模板的安装方法 Download PDFInfo
- Publication number
- CN104420419A CN104420419A CN201310410615.7A CN201310410615A CN104420419A CN 104420419 A CN104420419 A CN 104420419A CN 201310410615 A CN201310410615 A CN 201310410615A CN 104420419 A CN104420419 A CN 104420419A
- Authority
- CN
- China
- Prior art keywords
- plate
- pier
- pallet
- template
- contact net
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/02—Piers; Abutments ; Protecting same against drifting ice
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
本发明涉及一种托盘顶帽变尺寸桥墩施工模板的安装方法,首先按照接触网变化最大尺寸制定一套模板,模板由一个底板、两个侧板和一个端板组成,底板长度与墩柱顶帽等宽,宽度为接触网悬臂长度,侧板和端板与接触网等高,在侧板外侧面板分别设置2根50mm槽钢,伸出墩顶20cm设置直径35mm对拉拉筋孔;底板、两个侧板和端板之间采用标准件连接,在最大尺寸模板内设置第一L型插板、第二L型插板、第三L型插板和第四L型插板,由此四种L型插板组合拼装来满足接触网不同尺寸。在托盘顶帽处模板采用一种半圆形插板,半圆与墩柱托盘弧度相一致,并设置刃脚。
Description
技术领域
本发明属于铁路桥梁工程施工技术领域,尤其涉及一种托盘顶帽变尺寸桥墩施工模板的安装方法。
背景技术
随着交通运输业的飞速发展,原有的铁路已无法满足使用要求,因此需要大量增设新的线路。临近既有铁路增建二线以及三线桥被广泛应用。受线形及线间距控制常常会调整墩柱托盘尺寸以避免相邻两个墩柱的托盘相交,考虑到投资计划,二线、三线桥接触网设计往往会采用硬横跨体系,故出现多种接触网结构,导致墩柱托盘会出现不同尺寸。而且临近既有铁路增建的二线往往只是一部分线路临近既有铁路,所以不在既有线又出现了新的接触网托盘尺寸,如按照设计图纸逐一生产模板,存在成本费用大,模板种类多样安装复杂,现场不易管理,施工速度慢影响工期。
发明内容
为解决上述技术问题,本发明的目的在于提供一种既能满足触网基础尺寸变化同时也能满足调整托盘顶帽尺寸变化,操作过程及所用设备简单、施工成本低且速度快的托盘顶帽变尺寸桥墩施工模板。
本发明的托盘顶帽变尺寸桥墩施工模板的安装方法,依次包括以下步骤:依次包括以下步骤:首先按照接触网变化最大尺寸制定一套模板,模板由一个底板、两个侧板和一个端板组成,底板长度与墩柱顶帽等宽,宽度为接触网悬臂长度,侧板和端板与接触网等高,在侧板外侧面板分别设置2根50mm槽钢,伸出墩顶20cm设置直径35mm对拉拉筋孔;底板、两个侧板和端板之间采用标准件连接,在最大尺寸模板内设置第一L型插板、第二L型插板、第三L型插板和第四L型插板,由此四种L型插板组合拼装来满足接触网不同尺寸,之所以设计成L型插板,因为L形插板稳定性强,易于固定,L形插板与接触网等高,第三L型插板和第四L型插板是固定在第一墩身托盘拼装模板和第二墩身托盘拼装模板之上,采用标准件连接,墩身托盘第一拼装模板和墩身托盘拼第二装模板可根据接触网不同尺寸拆卸;在托盘顶帽处模板采用一种半圆形插板,半圆与墩柱托盘弧度相一致,并设置刃脚;墩身模板安装牢固后,安装托盘模板,托盘模板断面分别与接触网底板、侧板用标准件连接,预留孔一一对应,每15cm设置一个。
借由上述方案,本发明至少具有以下优点:按顺序分别安装接触网底板,2块侧板,其中托盘模板与侧板与端板、底板的接触面之间均采用标准件连接牢固,这样就构成了接触网结构最大尺寸模板,包含了所有接触网结构类型,标准件预留孔每15cm设置一个,保证住了接触网模板的稳定性。有了最大尺寸接触网模板后,则需要选择第一L型插板、第二L型插板、第三L型插板和第四L型插板及墩身托盘第一拼装模板、墩身托盘第二拼装模板的类型和数量,组合拼装成来满足接触网结构的多样性,这样大大的减少了施工模板的成本,而且插板是设计成L形,安装简单且稳定性好,先安装模板墩身托盘第一拼装模板或墩身托盘第二拼装模板,墩身托盘第一拼装模板、墩身托盘第二拼装模板与托盘模板侧面用标准件连接牢固,在模板上先安装第三L型插板或第四L型插板,然后安装第一L型插板1或第二L型插板,插板各插板接触面均采用标准件连接,且一一对应,间距每15cm设置一个。托盘顶帽处模板设计,采用一种半圆形插板,半圆与墩柱托盘弧度相一致,并设置刃脚,这样既不破坏原来模板又很好的达到了成墩的目的,而且安装加固都比较简单,在浇筑前在模板之间用直径25精轧螺纹对拉牢固,稳定性进一步加强了。
附图说明
图1为本发明提供的变尺寸模板内插板示意图;
图2为本发明提供的变尺寸模板模板结构平面图;
图3为本发明提供的变尺寸模板板结构断面图;
图4为本发明提供的变尺寸模板板结构侧视图;
图5-图8为本实施例中0-46#墩接触网采用硬横跨体系的四种形式;
图9和图10为本实施例中0-46#墩托盘两种变截面形式。
具体实施方式
下面结合附图和具体实施例对本发明提供的一种托盘顶帽变尺寸桥墩施工模板进行详细说明。与已有技术相同的部件采用相同的标号,并省略对其进行的说明。
现以货运通路跨京山铁路特大桥工程为例进行说明:本桥共80个桥墩,其中0-46#墩为临近既有铁路增建二线,与增建三线接触网采用硬横跨体系,而且受线形及线间距控制要调整墩柱托盘尺寸,47-80#墩接触网类型为普通接触网体系,接触网结构类型只有一种,且不受三线线间距影响托盘尺寸不需改变。
0-46#墩接触网采用硬横跨体系共有四种形式如图5-8,其中图5与图6,图7与图8结构相同,位置对称。
0-46#墩托盘变截面形式有两种,分别是从新建三线向内切掉40cm、20cm如图9和图10所示。
如按图纸逐一生产模板,0-46#墩需8套模板,47-80#墩需一套模板,共计9套模板。而且加工比较复杂,工期长,成本巨大。本发明的施工模板只需按照桥墩接触网截面最大尺寸定制一套模板,内设置不同型号的插板组合满足接触网多变要求。托盘按照正规尺寸定制,在托盘内设置半圆形插板。
参见图(1)-(4)所示,本发明的托盘顶帽变尺寸桥墩施工模板的安装方法,依次包括以下步骤:
首先按照接触网变化最大尺寸制定一套模板,模板由一个底板9、两个侧板7和一个端板8组成,底板9长度与墩柱顶帽等宽,宽度为接触网悬臂长度,侧板7和端板8与接触网等高,在侧板7外侧面板分别设置2根50mm槽钢,伸出墩顶20cm设置直径35mm对拉拉筋孔;底板9、两个侧板7和一个端板8之间采用标准件连接,在最大尺寸模板内设置第一L型插板1、第二L型插板2、第三L型插板3和第四L型插板4,由此四种L型插板组合拼装来满足接触网不同尺寸,之所以设计成L型插板,因为L形插板稳定性强,易于固定,L形插板与接触网等高,其中,第三L型插板3和第四L型插板4是固定在墩身托盘第一拼装模板5和墩身托盘第二拼装模板6之上,采用标准件连接,墩身托盘第一拼装模板5和墩身托盘第二拼装模板6可根据接触网不同尺寸拆卸;
在托盘顶帽处模板采用一种半圆形插板10或半圆形插板11,半圆与墩柱托盘弧度相一致,并设置刃脚;
墩身模板安装牢固后,安装托盘模板12,托盘模板12断面分别与接触网底板9、侧板7用标准件连接,预留孔一一对应,每15cm设置一个。
以上所述仅是本发明的优选实施方式,应当指出,对于本技术领域的普通技术人员来说,在不脱离本发明技术原理的前提下,还可以做出若干改进和变型,这些改进和变型也应视为本发明的保护范围。
Claims (1)
1.一种托盘顶帽变尺寸桥墩施工模板的安装方法,其特征在于:依次包括以下步骤:首先按照接触网变化最大尺寸制定一套模板,模板由一个底板、两个侧板和一个端板组成,底板长度与墩柱顶帽等宽,宽度为接触网悬臂长度,侧板和端板与接触网等高,在侧板外侧面板分别设置2根50mm槽钢,伸出墩顶20cm设置直径35mm对拉拉筋孔;底板、两个侧板和端板之间采用标准件连接,在最大尺寸模板内设置第一L型插板、第二L型插板、第三L型插板和第四L型插板,由此四种L型插板组合拼装来满足接触网不同尺寸,之所以设计成L型插板,因为L形插板稳定性强,易于固定,L形插板与接触网等高,第三L型插板和第四L型插板是固定在墩身托盘第一拼装模板和墩身托盘第二拼装模板之上,采用标准件连接,墩身托盘第一拼装模板和墩身托盘第二拼装模板可根据接触网不同尺寸拆卸;在托盘顶帽处模板采用一种半圆形插板,半圆与墩柱托盘弧度相一致,并设置刃脚;墩身模板安装牢固后,安装托盘模板,托盘模板断面分别与接触网底板、侧板用标准件连接,预留孔一一对应,每15cm设置一个。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310410615.7A CN104420419B (zh) | 2013-09-11 | 2013-09-11 | 一种托盘顶帽变尺寸桥墩施工模板的安装方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310410615.7A CN104420419B (zh) | 2013-09-11 | 2013-09-11 | 一种托盘顶帽变尺寸桥墩施工模板的安装方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104420419A true CN104420419A (zh) | 2015-03-18 |
CN104420419B CN104420419B (zh) | 2017-01-04 |
Family
ID=52970482
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310410615.7A Active CN104420419B (zh) | 2013-09-11 | 2013-09-11 | 一种托盘顶帽变尺寸桥墩施工模板的安装方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104420419B (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109306664A (zh) * | 2018-11-05 | 2019-02-05 | 云南建投第三建设有限公司 | 一种变截面薄壁空心墩滑板式内模板 |
US11479929B2 (en) | 2020-08-07 | 2022-10-25 | Peri Se | Formwork system and method |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201031502Y (zh) * | 2007-05-10 | 2008-03-05 | 魏志光 | 可调整长度的模板组合支架横梁 |
KR20100009017A (ko) * | 2008-07-17 | 2010-01-27 | 연세대학교 산학협력단 | 조립형 교량 및 그 시공방법 |
JP2010242315A (ja) * | 2009-04-01 | 2010-10-28 | Sumitomo Mitsui Construction Co Ltd | 橋梁架設方法 |
CN202187548U (zh) * | 2011-07-05 | 2012-04-11 | 天津二十冶建设有限公司 | 一种二次灌浆模板 |
CN202745367U (zh) * | 2012-07-24 | 2013-02-20 | 江苏圣乐机械有限公司 | T梁侧模对拉杆 |
CN103088756A (zh) * | 2013-02-01 | 2013-05-08 | 葛洲坝集团第二工程有限公司 | 钢棒承重搭建盖梁施工平台的方法 |
-
2013
- 2013-09-11 CN CN201310410615.7A patent/CN104420419B/zh active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201031502Y (zh) * | 2007-05-10 | 2008-03-05 | 魏志光 | 可调整长度的模板组合支架横梁 |
KR20100009017A (ko) * | 2008-07-17 | 2010-01-27 | 연세대학교 산학협력단 | 조립형 교량 및 그 시공방법 |
JP2010242315A (ja) * | 2009-04-01 | 2010-10-28 | Sumitomo Mitsui Construction Co Ltd | 橋梁架設方法 |
CN202187548U (zh) * | 2011-07-05 | 2012-04-11 | 天津二十冶建设有限公司 | 一种二次灌浆模板 |
CN202745367U (zh) * | 2012-07-24 | 2013-02-20 | 江苏圣乐机械有限公司 | T梁侧模对拉杆 |
CN103088756A (zh) * | 2013-02-01 | 2013-05-08 | 葛洲坝集团第二工程有限公司 | 钢棒承重搭建盖梁施工平台的方法 |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109306664A (zh) * | 2018-11-05 | 2019-02-05 | 云南建投第三建设有限公司 | 一种变截面薄壁空心墩滑板式内模板 |
US11479929B2 (en) | 2020-08-07 | 2022-10-25 | Peri Se | Formwork system and method |
US11885083B2 (en) | 2020-08-07 | 2024-01-30 | Peri Se | Formwork system and method |
Also Published As
Publication number | Publication date |
---|---|
CN104420419B (zh) | 2017-01-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204386159U (zh) | 一种用于立柱结构的组合模板 | |
CA2926238A1 (en) | Concrete block spacer system | |
CN104420419A (zh) | 一种托盘顶帽变尺寸桥墩施工模板的安装方法 | |
CN205000229U (zh) | 一种具有通用截面尺寸的变跨度节段拼装混凝土箱梁 | |
CN203129355U (zh) | 适用于隔震工程的电梯井隔震系统 | |
CN104032868A (zh) | 一种建筑用模块楼板组装结构及工艺方法 | |
CN204252571U (zh) | 一种混凝土结构的新增梁结构 | |
CN201554032U (zh) | 塔桅式机械设备底架的定位构造及其模具 | |
CN205777493U (zh) | 角钢框工具式柱模板 | |
CN102733285A (zh) | 一种叠合式机场道面结构 | |
CN203394022U (zh) | 一种防漏浆易组装的建筑模板及其柱状组合结构 | |
KR20130117662A (ko) | Psc i형 거더 | |
CN204571123U (zh) | 一种楼梯及其楼梯用连接件 | |
CN104358466A (zh) | 一种模块组合式通信塔 | |
CN105633871A (zh) | 塑胶电缆桥架的直角弯头连接结构及其连接方法 | |
CN203821360U (zh) | 多跨径通用组合式船闸检修门 | |
CN204059392U (zh) | 一种立于钢柱柱头上的塔吊基础 | |
CN204456667U (zh) | 一种建筑用钢筋固定器 | |
CN204152184U (zh) | 一种可调钢支顶 | |
CN204401957U (zh) | 一种便于现场安装的运动地板 | |
CN204676792U (zh) | 一种楼梯及其与楼板或地面的连接结构 | |
CN203297205U (zh) | 带立柱的机械安装座 | |
CN208310176U (zh) | 一种装配式施工用节段拼装模具 | |
CN215442782U (zh) | 一种可拼装的预制楼梯 | |
CN215442781U (zh) | 一种拼装式预制楼梯 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |