CN104328799B - A kind of sheltered reverse excavation subway station steel pipe column accurate positioning method - Google Patents

A kind of sheltered reverse excavation subway station steel pipe column accurate positioning method Download PDF

Info

Publication number
CN104328799B
CN104328799B CN201410648052.XA CN201410648052A CN104328799B CN 104328799 B CN104328799 B CN 104328799B CN 201410648052 A CN201410648052 A CN 201410648052A CN 104328799 B CN104328799 B CN 104328799B
Authority
CN
China
Prior art keywords
pipe column
steel pipe
steel
steady arm
location
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410648052.XA
Other languages
Chinese (zh)
Other versions
CN104328799A (en
Inventor
朱军军
白冰
郝本峰
炊鹏飞
郭宏智
丁海明
刘伟
冉道平
景兆骥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Communications Engineering Group Co Ltd
Original Assignee
China Construction Communications Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Communications Engineering Group Co Ltd filed Critical China Construction Communications Engineering Group Co Ltd
Priority to CN201410648052.XA priority Critical patent/CN104328799B/en
Publication of CN104328799A publication Critical patent/CN104328799A/en
Application granted granted Critical
Publication of CN104328799B publication Critical patent/CN104328799B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The present invention relates to a kind of sheltered reverse excavation subway station steel pipe column accurate positioning method, mainly comprise the following steps: (1), steel pipe column pile foundation construction location survey, (2), borer drill rod verticality checking measurements, (3), the installation of steel pipe column steady arm and location survey, (4) erection of steel pipe column is located.This method adopts the non-prism electronic total station associating high-precision laser plumb aligner of measuring technique advanced person, is analyzed, and takes the technical measures such as normalization method, solve the problems such as steel pipe column construction location and perpendicularity correction locating tab assembly reliably by measuring error transmission.Required surveying instrument equipment can recycle for a long time, and power consumption is extremely few, and operation field produces without rubbish, and have economy, environmental protection and energy-conservation feature, social benefit is good.

Description

A kind of sheltered reverse excavation subway station steel pipe column accurate positioning method
Technical field
The invention belongs to building structure construction field, be specifically related to the positioning construction method of subway station steel pipe column.
Background technology
Steel pipe column, with the performance of its excellence, is widely used in the subway station engineering of digging method construction.Steel pipe column construction location is as one of heavy difficult point in sheltered reverse excavation station construction, and its construction surface is narrow, and environment is poor, and positioning accuracy request is high.The location of steel pipe column, end opening adopts steady arm to locate usually, localization method suitable for reading mainly contains: (1) flower basket bolt is located, the interim hook of welding on the steel bushing of steel pipe column top and corresponding absolute altitude, be connected suitable for reading for steel pipe column with steel bushing with 3 ~ 4 steam boat ratchets, located by adjustment flower basket bolt length.(2) shaped steel well cabinet frame is fixed, and shaped steel welds micro actuator adjustment location.(3) between and dado structure suitable for reading at steel pipe column, 4 little lifting jack are installed, by lifting jack, adjustment steel pipe column center suitable for reading.(4) adopt the leading screw symmetry location after four improvement, leading screw band card one end is supported on the ring flange of steel pipe column top, and band holder one end is supported on dado structure.
Summary of the invention
The object of the invention is: realize the high-precision setting-out requirement of steady arm, guarantee the accurately in place of steel pipe column elevation.
To achieve these goals, technical scheme of the present invention is to provide a kind of sheltered reverse excavation subway station steel pipe column accurate positioning method, comprise the following steps: (1), steel pipe column pile foundation location survey, (2), rig squareness measurement, (3), the location survey of steel pipe column steady arm, (4) erection of steel pipe column location, wherein (3) step specifically comprises: steady arm elevation location, steady arm plane positioning; (4) step specifically comprises: steel pipe column is vertically located, steel pipe column elevation is checked.
Concrete steps are:
(1), steel pipe column pile foundation location survey
Absolute altitude at the bottom of the design plane coordinate at the steel pipe column pile foundation center calculated with drawing and stake, the on-the-spot planimetric position adopting total powerstation-pole coordinates lofting mode to release central pile center, and involve 2 orthogonal lead-in wires by pile center's point, carry out and draw stake, so that often check a heart position in piling construction process;
(2), rig squareness measurement
O place erection total powerstation at an arbitrary position, until drilling rod unsettled static after, total powerstation is under non-prism NP pattern, measure the horizontal range D of instrument to drilling rod center, then bottom survey record drilling rod and the horizontal direction value of top ad-hoc location and zenith distance, thus calculate the projected length of drilling rod at level and vertical direction, and according to the verticality computing formula of the rig derived , calculate rig verticality, if verticality is partially within the scope of permissible value, then piling of can constructing;
(3), the location survey of steel pipe column steady arm
The while that what steel pipe column adopted being upper and lower two ends, localization method is fixed, and pipe column lower end location depends on autonavigator, flower basket bolt fine setting location, upper end;
(3.1) steady arm elevation location
The elevation location of steady arm adopts and hangs steel ruler laying off, and on the ground, steel tape is just being hung on the position near steel pile casting wall, and spirit-leveling instrument is erected at leveling point A and steel pile casting relative intermediate position, to reduce i angle error.Backsight reads the reading a of levelling pole, and forward sight reads the ground reading R of steel ruler on, consider the factors such as the long correction of the chi of steel ruler and temperature correction, the following formula A of computing formula:
(formula A)
After hanging up properly steel ruler at every turn, set up No. 2 spirit-leveling instruments respectively, read on a and R, under calculating R, if the difference under the R calculated for twice is within ± 2mm, then average, then under steel ruler reading R, mark a horizontal line by the survey work of down-hole with surveyor's staff on steel pile casting inwall, we are according to actual conditions here, steel ruler is hung up properly respectively corresponding 4 of steel pile casting tube wall cross axis direction, steel pile casting inwall does horizontal lines mark, mutually to check, controls steady arm installed height mark;
(3.2) steady arm plane positioning
Steady arm plane positioning adopts the downward cultellation method of laser, and concrete cultellation process is as follows:
1) steel plate workbench is placed on steel pile casting place suitable for reading, adopts total powerstation polar method, by the setting-out of the planar central of steady arm point within the scope of the batten on steel plate workbench, and carry out mark;
2) with gauge point on batten for alignment, steel plate workbench sets up wooden tripod and prism, and then adopt naturalization laying off, accurate setting-out goes out a design coordinate of heart point P;
3) prism is removed from pedestal, then laser plummet is placed on pedestal, batten on steel plate workbench is removed, central point is just thrown in down-hole by the cultellation reserved opening on steel plate by laser plummet, for avoiding plumb aligner cultellation visor not vertical error, three directions are changed during each cultellation, if when point position all falls within same point, be namely a heart, otherwise three direction point A, B, C can be produced and form a triangle, now, getting leg-of-mutton circumscribed circle centre point O, is namely a heart, finally, be welded and fixed steady arm, casting concrete;
(4) erection of steel pipe column location
After device concrete to be positioned reaches design strength, carry out the lifting of steel pipe column, bottom steel pipe column, directly embed steady arm, or bottom it, be welded with spacer ferrule embedding steady arm, its pipe end is firmly seated on steady arm cross location-plate, by the bottom of absolute altitude measuring column with the degree of agreement of steady arm;
(4.1) steel pipe column is vertically located
Locate owing to adopting steady arm bottom steel pipe column, top adopts flower basket bolt fine setting, for ensureing the verticality of steel pipe column, only need adopt method shown in (1) step, field lofting goes out steel pipe column center point, and sets up laser plummet on the point of center, open laser target to, make steel pipe column upper and lower center point in same laser beam by adjustment flower basket bolt, then determine steel pipe column and vertically locate errorless;
(4.2) steel pipe column elevation is checked
Adopt the top mark hanging steel ruler method measurement steel pipe column high, compare with design load, check the degree of agreement with steady arm at the bottom of post;
During measurement, spirit-leveling instrument is erected at leveling point A and steel pile casting relative intermediate position, and to reduce i angle error, the reading a of backsight levelling pole and the upper chi reading R of steel tape measured by spirit-leveling instrument on, then read the lower chi reading R corresponding with steel pipe column top planes align place under.If consider the factors such as the long correction of the chi of steel ruler and temperature correction, steel pipe column top absolute altitude computing formula is as follows:
(formula B)
Its construction way is: by total station survey, the drilling rod verticality correcting rig, guarantee the construction quality in pile hole construction pile hole; Utilize elevation survey method, ground elevation is delivered to down-hole, control the design height of steady arm bottom steel pipe column; Then with total powerstation and laser plummet associating setting-out cultellation location, orient the planar central point of steady arm in down-hole, casting concrete fixed locator, reach after design strength until concrete, hang steel pipe column, again go out steel pipe column top planes central point with total powerstation and laser plummet associating setting-out cultellation, two fixing with gaily decorated basket spiral shell, build rim of a cup concrete and steel pipe column inner concrete successively, complete the construction at steel pipe column position.
This method adopts the non-prism electronic total station associating high-precision laser plumb aligner of measuring technique advanced person, analyzed by measuring error transmission, and take the technical measures such as normalization method, solve the problems such as steel pipe column construction location and perpendicularity correction locating tab assembly reliably, and in metro station steel pipe column work progress, obtain successful Application, for similar engineering provides referential engineering survey experience.
Accompanying drawing explanation
Fig. 1 is central pile centralized positioning schematic diagram;
Fig. 2 is steady arm schematic side view;
Fig. 3 is steady arm schematic top plan view;
Fig. 4 is that steady arm elevation location hangs steel ruler laying off schematic diagram;
Fig. 5 is steady arm plane positioning workbench schematic diagram;
Fig. 6 is the accurate setting-out schematic diagram of normalization method;
Fig. 7 is total powerstation lofting positioner central point schematic diagram;
Fig. 8 is flower basket bolt location, steel pipe column upper end schematic diagram;
Fig. 9 is laser plumbing method setting-out steel pipe column top central point schematic diagram;
Figure 10 measures steel pipe column top absolute altitude schematic diagram for hanging steel ruler method.
In figure: 1, the stake heart; 2, position line; 3, stake position; 4, timber; 5, diameter 700 steel pipe column; 6, steel pipe column suspension column ring flat-plate; 7, cross steel plate dowel; 8, adjustable junction steel plate; 9, pre-buried installation foot; 10, steel sleeve; 11, drilled pile sideline; 12, reinforced frame; 13, original state soil layer; 14, steel tape; 15, flower basket bolt; 16, steady arm; 17, concrete; 18, spirit-leveling instrument; 19, levelling pole; 20, plate platform; 21, cultellation reserved opening; 22, steel nail; 23, batten; 24, checkpoint C; 25, frame website B; 26, backsight point A; 27, stake position center point P is designed; 28, setting-out stake position center point P '; 29, laser plummet device; 30, prism; 31, steel pile casting place suitable for reading; 32, total powerstation; 33, reference mark; 34, plumb bob; 35, steady arm anchor rib.
Embodiment
Below in conjunction with concrete case study on implementation, the present invention is described as follows: as a kind of sheltered reverse excavation subway station steel pipe column accurate positioning method of one embodiment of the present of invention, comprise the following steps: (1), steel pipe column pile foundation location survey, (2), rig squareness measurement, (3), the installation of steel pipe column steady arm and location survey, (4) erection of steel pipe column location, wherein (3) step specifically comprises: steady arm elevation location, steady arm plane positioning; (4) step specifically comprises: steel pipe column is vertically located, steel pipe column elevation is checked.Concrete steps are: 1, steel pipe column pile foundation location survey
Absolute altitude at the bottom of the design plane coordinate at the steel pipe column pile foundation center calculated with drawing and stake, the on-the-spot planimetric position adopting total powerstation-pole coordinates lofting mode to release central pile center, and involve 2 orthogonal lead-in wires by pile center's point, carry out and draw stake, so that often check a heart position in piling construction process.
2, rig squareness measurement
O place erection total powerstation at an arbitrary position, until drilling rod unsettled static after, total powerstation is under non-prism NP pattern, measure the horizontal range D of instrument to drilling rod center, then bottom survey record drilling rod and the horizontal direction value of top ad-hoc location and zenith distance, thus calculate the projected length of drilling rod at level and vertical direction, and according to the verticality computing formula of the rig derived , calculate rig verticality, if verticality is partially within the scope of permissible value, then piling of can constructing.
3, the location survey of steel pipe column steady arm
The while that what the intermediate column (steel pipe column) as one of station agent structure adopted being upper and lower two ends, localization method is fixed.Pipe column lower end location depends on autonavigator, flower basket bolt fine setting location, upper end.
3.1 steady arm elevation location
The elevation location of steady arm adopts and hangs steel ruler laying off, and the instrument mainly used has: the plumb bob, surveyor's staff, marking pen etc. of optical level, levelling pole 1 handle, wooden tripod, 50m steel tape (assay approval), 5kg.Data encasement: the elevation H of on-the-spot level reference mark A a, the design altitude H in the steady arm leveling board face of certain steel pipe column b.
As shown in Figure 4: on the ground, steel tape is just being hung on the position near steel pile casting wall, and spirit-leveling instrument is erected at leveling point A and steel pile casting relative intermediate position, to reduce i angle error.Backsight reads the reading a of levelling pole, and forward sight reads the ground reading R of steel ruler on.Consider the factors such as the long correction of the chi of steel ruler and temperature correction, computing formula is as follows:
(formula 1)
After hanging up properly steel ruler, set up No. 2 spirit-leveling instruments respectively at every turn, read a and R on, calculate R underif, the R calculated for twice underdifference within ± 2mm, then average, then by the survey work of down-hole at steel ruler reading R underplace's surveyor's staff marks a horizontal line on steel pile casting inwall.Here we are according to actual conditions, hang up properly steel ruler respectively, do horizontal lines mark according to above-mentioned way at steel pile casting inwall corresponding 4 of steel pile casting tube wall cross axis direction, mutually to check, control steady arm installed height mark.
3.2 steady arm plane positioning
Steady arm plane positioning adopts the downward cultellation method of laser, and the instrument mainly used has: total powerstation, 3, wooden tripod, and 2 groups, prism, prism centering rod 1 overlaps, laser plummet.
Steady arm cultellation process is as follows:
1) steel plate workbench is placed on steel pile casting place suitable for reading (as shown in Figure 5), steel plate workbench is wanted steadily, and when people walks about above, steel plate workbench can not vibrate.Adopt total powerstation polar method, by the setting-out of the planar central of steady arm point within the scope of the batten on steel plate workbench, and carry out mark.
2) with gauge point on batten for alignment, steel plate workbench sets up wooden tripod and prism, then adopt naturalization laying off (as shown in Figure 6), accurate setting-out goes out a design coordinate of heart point P.
3) prism is removed from pedestal, note in this process keeping off dynamic foot rest, then laser plummet is placed on pedestal, the batten on steel plate workbench is removed, central point is just thrown in down-hole by the cultellation reserved opening on steel plate by laser plummet.For avoiding plumb aligner cultellation visor not vertical error, during each cultellation, change three directions, if when point position all falls within same point, be namely a heart.Otherwise can produce three direction point A, B, C and form a triangle, now, getting leg-of-mutton circumscribed circle centre point O, is namely a heart.Finally, be welded and fixed steady arm, casting concrete.
4 erection of steel pipe column location
After device concrete to be positioned reaches design strength, carry out the lifting of steel pipe column.Directly can embed steady arm bottom steel pipe column, steel pipe column can be welded with spacer ferrule and embed steady arm bottom it, and its pipe end is firmly located on steady arm cross location-plate, by the bottom of absolute altitude measuring column with the degree of agreement of steady arm.
4.1 steel pipe columns are vertically located
Locate owing to adopting steady arm bottom steel pipe column, top adopts flower basket bolt fine setting, for ensureing the verticality of steel pipe column, only need adopt method shown in (1) step, field lofting goes out steel pipe column center point, and sets up laser plummet on the point of center, open laser target to, make steel pipe column upper and lower center point in same laser beam by adjustment flower basket bolt, then determine steel pipe column and vertically locate errorless.
4.2 steel pipe column elevations are checked
Adopt the top mark hanging steel ruler method measurement steel pipe column high, compare with design load, check the degree of agreement with steady arm at the bottom of post.
During measurement, spirit-leveling instrument is erected at leveling point A and steel pile casting relative intermediate position, to reduce i angle error.The reading a of backsight levelling pole and the upper chi reading R of steel tape measured by spirit-leveling instrument on, then read the lower chi reading R corresponding with steel pipe column top planes align place under.If consider the factors such as the long correction of the chi of steel ruler and temperature correction, steel pipe column top absolute altitude computing formula is as follows:
(formula 2)
Its construction way is: by total station survey, the drilling rod verticality correcting rig, guarantee the construction quality in pile hole construction pile hole; Utilize elevation survey method, ground elevation is delivered to down-hole, control the design height of steady arm bottom steel pipe column; Then with total powerstation and laser plummet associating setting-out cultellation location, orient the planar central point of steady arm in down-hole, casting concrete fixed locator, reach after design strength until concrete, hang steel pipe column, again go out steel pipe column top planes central point with total powerstation and laser plummet associating setting-out cultellation, fix with flower basket bolt, build rim of a cup concrete and steel pipe column inner concrete successively, complete the construction at steel pipe column position.
Above-described embodiment is only be described the preferred embodiment of the present invention; not scope of the present invention is limited; under not departing from the present invention and designing the prerequisite of spirit; the various distortion that those of ordinary skill in the art make technical scheme of the present invention and improvement, all should fall in protection domain that claims of the present invention determines.

Claims (1)

1. a sheltered reverse excavation subway station steel pipe column accurate positioning method, it is characterized in that: comprise the following steps: (1), steel pipe column pile foundation construction location survey, (2), borer drill rod verticality checking measurements, (3), steel pipe column steady arm location survey, (4) erection of steel pipe column location, wherein (3) step steel pipe column steady arm location survey specifically comprises: steady arm elevation location, steady arm plane positioning; (4) step specifically comprises: steel pipe column is vertically located, steel pipe column elevation is checked;
Wherein concrete steps are:
(1), steel pipe column pile foundation construction location survey;
Absolute altitude at the bottom of the design plane coordinate at the steel pipe column pile foundation center calculated with drawing and stake, the on-the-spot planimetric position adopting total powerstation-Apparatus in polar coordinates lofting mode measuring central pile stake heart, and involve 2 orthogonal lead-in wires by pile center's point, carry out and draw stake, so that often check a heart position in piling construction process;
(2), borer drill rod verticality checking measurements;
O place erection total powerstation at an arbitrary position, until drilling rod unsettled static after, total powerstation is under non-prism NP pattern, measure the horizontal range D of instrument to drilling rod center, then bottom survey record drilling rod and the horizontal direction value of top ad-hoc location and zenith distance, thus drilling rod projected length S is in the horizontal direction calculated levelwith the projected length S of vertical direction vertically, and according to the verticality computing formula of the drilling rod derived , calculate drilling rod verticality, if verticality is partially within the scope of permissible value, then piling of can constructing;
(3), the location survey of steel pipe column steady arm;
What steel pipe column adopted is localization method location, upper and lower two ends, first pipe column lower end location, location, rear upper end, and pipe column lower end location depends on autonavigator, flower basket bolt fine setting location, upper end;
(3.1) steady arm elevation location;
The elevation location of steady arm adopts and hangs steel ruler laying off, and on the ground, steel tape is just being hung on the position near steel pile casting wall, spirit-leveling instrument is erected at leveling point A and steel pile casting relative intermediate position, to reduce i angle error, backsight reads the reading a of levelling pole, and forward sight reads the ground reading R of steel ruler on, consider that the chi of steel ruler is long and correct and temperature correction factor, the following formula A of computing formula;
(formula A) wherein:
H bit is the design altitude in the steady arm leveling board face of certain steel pipe column;
H ait is the elevation of A point;
Δ D lthe chi long correction numerical value of steel ruler;
Δ D tthe temperature correction numerical value of steel ruler;
After hanging up properly steel ruler, set up No. 2 spirit-leveling instruments respectively at every turn, read a and R on, calculate R underif, the R calculated for twice underdifference within ± 2mm, then average, then by the survey work of down-hole at steel ruler reading R underplace's surveyor's staff marks a horizontal line on steel pile casting inwall, here we are according to actual conditions, and hang up properly steel ruler respectively corresponding 4 of steel pile casting tube wall cross axis direction, steel pile casting inwall does horizontal lines mark, mutually to check, control steady arm installed height mark;
(3.2) steady arm plane positioning;
Steady arm plane positioning adopts the downward cultellation method of laser, and concrete cultellation process is as follows;
1) steel plate workbench is placed on steel pile casting place suitable for reading, adopts total powerstation polar method, by the setting-out of the planar central of steady arm point within the scope of the batten on steel plate workbench, and carry out mark;
2) with gauge point on batten for alignment, steel plate workbench sets up wooden tripod and prism, and then adopt naturalization laying off, accurate setting-out goes out a design coordinate of heart point P;
3) prism is removed from pedestal, then laser plummet is placed on pedestal, batten on steel plate workbench is removed, central point is just thrown in down-hole by the cultellation reserved opening on steel plate by laser plummet, for avoiding plumb aligner cultellation visor not vertical error, three directions are changed during each cultellation, if when point position all falls within same point, be namely a heart, otherwise three direction point A, B, C can be produced and form a triangle, now, getting leg-of-mutton circumscribed circle centre point O, is namely a heart, finally, be welded and fixed steady arm, casting concrete;
(4) erection of steel pipe column location;
After device concrete to be positioned reaches design strength, carry out the lifting of steel pipe column, bottom steel pipe column, directly embed steady arm, or bottom it, be welded with spacer ferrule embedding steady arm, its pipe end is firmly seated on steady arm cross location-plate, by the bottom of absolute altitude measuring column with the degree of agreement of steady arm;
(4.1) steel pipe column is vertically located;
Locate owing to adopting steady arm bottom steel pipe column, top adopts flower basket bolt fine setting, for ensureing the verticality of steel pipe column, only need adopt method shown in (1) step, field lofting goes out steel pipe column center point, and sets up laser plummet on the point of center, open laser target to, make steel pipe column upper and lower center point in same laser beam by adjustment flower basket bolt, then determine steel pipe column and vertically locate errorless;
(4.2) steel pipe column elevation is checked;
Adopt the top mark hanging steel ruler method measurement steel pipe column high, compare with design load, check the degree of agreement with steady arm at the bottom of post;
During measurement, spirit-leveling instrument is erected at leveling point A and steel pile casting relative intermediate position, and to reduce i angle error, the reading a of backsight levelling pole and the upper chi reading R of steel tape measured by spirit-leveling instrument on, then read the lower chi reading R corresponding with steel pipe column top planes align place underif consider that the chi of steel ruler is long and correct and temperature correction factor, steel pipe column top absolute altitude computing formula is as follows:
(formula B)
Its construction way is: by total station survey, the drilling rod verticality correcting rig, guarantee the construction quality in pile hole construction pile hole; Utilize elevation survey method, ground elevation is delivered to down-hole, control the design height of steady arm bottom steel pipe column; Then with total powerstation and laser plummet associating setting-out cultellation location, orient the planar central point of steady arm in down-hole, casting concrete fixed locator, reach after design strength until concrete, hang steel pipe column, again go out steel pipe column top planes central point with total powerstation and laser plummet associating setting-out cultellation, fix with flower basket bolt, build rim of a cup concrete and steel pipe column inner concrete successively, complete the construction at steel pipe column position.
CN201410648052.XA 2014-11-17 2014-11-17 A kind of sheltered reverse excavation subway station steel pipe column accurate positioning method Active CN104328799B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410648052.XA CN104328799B (en) 2014-11-17 2014-11-17 A kind of sheltered reverse excavation subway station steel pipe column accurate positioning method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410648052.XA CN104328799B (en) 2014-11-17 2014-11-17 A kind of sheltered reverse excavation subway station steel pipe column accurate positioning method

Publications (2)

Publication Number Publication Date
CN104328799A CN104328799A (en) 2015-02-04
CN104328799B true CN104328799B (en) 2016-04-27

Family

ID=52403599

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410648052.XA Active CN104328799B (en) 2014-11-17 2014-11-17 A kind of sheltered reverse excavation subway station steel pipe column accurate positioning method

Country Status (1)

Country Link
CN (1) CN104328799B (en)

Families Citing this family (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105297731B (en) * 2015-10-09 2017-04-12 中铁二局集团有限公司 Reverse construction method steel stand column positioning device and positioning method
CN105333781A (en) * 2015-11-10 2016-02-17 苏州天沃科技股份有限公司 Gasifier four-burner connection pipe mounting position detection tool
CN106871882B (en) * 2017-04-07 2023-07-25 中国建筑土木建设有限公司 Hole digging pile verticality and flatness laser guiding device and construction method thereof
CN108265764A (en) * 2018-02-02 2018-07-10 北京市政建设集团有限责任公司 A kind of method measured and monitoring measurement prepares
CN108374418A (en) * 2018-03-26 2018-08-07 中铁五局集团有限公司 Steel pipe column precise positioning Fast Installation construction technology in a kind of sheltered reverse excavation
CN108571008A (en) * 2018-04-27 2018-09-25 中国电建市政建设集团有限公司 Lid digs station steel pipe column positioning construction method
CN110549082A (en) * 2018-06-01 2019-12-10 中冶天工集团有限公司 installation method of tank equipment in plant for preventing metal ions from polluting
CN108534631A (en) * 2018-06-20 2018-09-14 中国铁路设计集团有限公司 A kind of Subway Station Platform door surveying setting-out device
CN109579655B (en) * 2019-01-15 2024-04-09 中建七局安装工程有限公司 Stiffening steel pipe plane center positioning device and application method thereof
CN109883296B (en) * 2019-01-29 2024-01-02 中建六局建设发展有限公司 Measuring tool and measuring method for detecting deviation of pile diameter and pile position
CN109868851B (en) * 2019-03-15 2020-10-13 中交第三航务工程局有限公司 Measuring method for controlling verticality of wind power foundation steel pipe pile
CN110231055B (en) * 2019-07-18 2022-09-23 南京市测绘勘察研究院股份有限公司 Calibration method for plummet and zenith instrument
CN110966007B (en) * 2019-12-18 2020-12-25 中国水利水电第五工程局有限公司 Curved arc excavation method for downward bending section of vertical shaft
CN111347240B (en) * 2020-03-30 2021-06-29 中国一冶集团有限公司 Installation and centering tool for converter mouth, vaporization flue and oxygen lance and use method thereof
CN111649643B (en) * 2020-06-05 2021-08-10 武汉理工大学 Intelligent vehicle sensor positioning auxiliary device and method
CN112161611B (en) * 2020-09-07 2022-03-18 中铁大桥局集团第五工程有限公司 In-plant concentricity positioning method for offshore wind power guide frame
CN112112187A (en) * 2020-09-27 2020-12-22 广州市第二市政工程有限公司 Construction method for foundation connection node of steel pipe column of assembled Bailey truss
CN112964150B (en) * 2021-03-20 2022-10-21 山东大学 Space coordinate conversion and fixed point measurement device and working method thereof
CN113529727B (en) * 2021-07-09 2023-02-28 中铁二局第四工程有限公司 Steel pipe column accurate positioning method applied to hole-pile method construction
CN114197525B (en) * 2021-11-29 2023-01-10 中铁二局集团有限公司 Verticality control method for steel pipe column by back-inserting method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101498134A (en) * 2009-03-12 2009-08-05 北京市政建设集团有限责任公司 Automatic positioning equipment for underground cover and cut engineering pipe column lower end
JP4427603B1 (en) * 2009-04-27 2010-03-10 株式会社西部工建 Construction method of building foundation and joint board for building foundation construction
CN101864825A (en) * 2010-06-30 2010-10-20 广东省基础工程公司 Reinforced concrete prefabricated column positioning device and construction method thereof
CN203729330U (en) * 2013-12-26 2014-07-23 中铁四局集团第五工程有限公司 Positioning frame of subway station section steel column formed through cover and cut-top down method
CN203891060U (en) * 2014-05-27 2014-10-22 中铁十九局集团轨道交通工程有限公司 Permanent steel pipe column positioning system of major structure of cover and excavation top-down station

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101498134A (en) * 2009-03-12 2009-08-05 北京市政建设集团有限责任公司 Automatic positioning equipment for underground cover and cut engineering pipe column lower end
JP4427603B1 (en) * 2009-04-27 2010-03-10 株式会社西部工建 Construction method of building foundation and joint board for building foundation construction
CN101864825A (en) * 2010-06-30 2010-10-20 广东省基础工程公司 Reinforced concrete prefabricated column positioning device and construction method thereof
CN203729330U (en) * 2013-12-26 2014-07-23 中铁四局集团第五工程有限公司 Positioning frame of subway station section steel column formed through cover and cut-top down method
CN203891060U (en) * 2014-05-27 2014-10-22 中铁十九局集团轨道交通工程有限公司 Permanent steel pipe column positioning system of major structure of cover and excavation top-down station

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
"地铁车站盖挖逆作法钢管柱施工技术";李彪;《施工技术》;20081231;第37卷;第80-83页 *

Also Published As

Publication number Publication date
CN104328799A (en) 2015-02-04

Similar Documents

Publication Publication Date Title
CN104328799B (en) A kind of sheltered reverse excavation subway station steel pipe column accurate positioning method
CN108253946B (en) Multifunctional vertical measurement and connection measurement integrated three-dimensional coordinate transmission device and method
US5841353A (en) Relating to the determination of verticality in tall buildings and other structures
CN105698776B (en) A kind of two dimension reference vehicular transfer device and its measurement method
CN111174771A (en) Method for measuring verticality of stand column
CN102828470B (en) Method for locating main girder cable sleeve of cable-stayed bridge
CN109470222B (en) Supervision control method for super high-rise building engineering measurement
CN104120656B (en) Method for automatically controlling bridge high pier construction perpendicularity
CN105043343A (en) Method for automated measurement of tunnel vault settlement based on laser displacement sensor
CN113280721B (en) Pile core positioning device and pile core positioning method
CN102433827A (en) Pavement construction lofting method for high-speed loop in skid pad
CN110646159A (en) Construction method for high-precision control and measurement of cast-in-place bare concrete wind tunnel
CN109443327A (en) A kind of distribution method of SURVEYING CONTROL NETWORK
CN105444733A (en) Measuring scale and measuring method for automatically-centralized level gauge
CN205333053U (en) Automatic right formula surveyor's level measurment scale
JP6044360B2 (en) Installation error measuring system for building member, measuring error measuring method for building member, and erection method for struts
CN114152239A (en) Surface layer settlement measuring method and observation device thereof
CN206540548U (en) The total powerstation of function is measured with instrument high precision
CN103016914A (en) Multifunctional forced centering leg bracket
CN210321605U (en) Multifunctional measuring instrument
CN104006798B (en) Pier stud verticality measuring instrument
CN104121897B (en) Satellite positioning surveys bar
CN210221089U (en) A support frame for surveying instrument
CN107990881A (en) A kind of ram machine construction localization method based on robot measurement
CN110030986B (en) Theodolite drill rod measuring device and use method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant