CN110549082A - installation method of tank equipment in plant for preventing metal ions from polluting - Google Patents

installation method of tank equipment in plant for preventing metal ions from polluting Download PDF

Info

Publication number
CN110549082A
CN110549082A CN201810555801.2A CN201810555801A CN110549082A CN 110549082 A CN110549082 A CN 110549082A CN 201810555801 A CN201810555801 A CN 201810555801A CN 110549082 A CN110549082 A CN 110549082A
Authority
CN
China
Prior art keywords
equipment
pipeline
tank
center line
metal ions
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810555801.2A
Other languages
Chinese (zh)
Inventor
冯永锁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Tiangong Group Corp Ltd
Original Assignee
MCC Tiangong Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Tiangong Group Corp Ltd filed Critical MCC Tiangong Group Corp Ltd
Priority to CN201810555801.2A priority Critical patent/CN110549082A/en
Publication of CN110549082A publication Critical patent/CN110549082A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23PMETAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
    • B23P19/00Machines for simply fitting together or separating metal parts or objects, or metal and non-metal parts, whether or not involving some deformation; Tools or devices therefor so far as not provided for in other classes

Abstract

An installation method for preventing metal ions from polluting tank equipment in a factory building comprises the following steps: firstly, confirming a central line of tank equipment; confirming the central line of the pipeline; measuring data; erecting a total station at a position where the axis of a plant control network, the center of an equipment circle and the center of a fixed pipeline can be measured simultaneously, determining the center line of a pipe orifice of an equipment body and the center line of the fixed pipeline by using the erected total station, enabling the center line of the pipe orifice of the equipment body and the center line of the fixed pipeline to be on the same center line, and then measuring data; adjusting and fixing the central line of the pipeline; checking and measuring; hoisting the tank equipment to the installation position; seventhly, after the tank type equipment is installed in place, the cleaned movable pipelines are connected, so that the whole pipeline and the equipment form a system. The invention can ensure the cleanliness of equipment and pipelines, effectively control metal ion pollution, and has small adjustment value, high adjustment precision and no pollution accumulation. Meanwhile, the invention has the advantages of high construction speed and high efficiency.

Description

Installation method of tank equipment in plant for preventing metal ions from polluting
the technical field is as follows:
The invention belongs to the field of installation and maintenance of metal ion pollution prevention plant equipment, and particularly relates to an installation method of tank equipment in a metal ion pollution prevention plant.
background art:
in the installation of plant equipment for preventing metal ions from polluting, the content of the metal ions in the air directly influences the quality of the produced product, so that the installation process of the equipment directly influences the cleanliness of the equipment in the installation and maintenance processes of the equipment.
Because the content of metal ions in the air is too high, the numerical value of the metal ions in the pipeline is too high, and secondary pollution of the equipment is easily caused in the process of connecting the equipment and the pipeline. Although the traditional installation method (the method of positioning the equipment and then installing the pipeline) is small in adjustment amount and low in construction difficulty, the equipment is easy to pollute after being installed, and when pollution is accumulated to the equipment, the difficulty of cleaning and protecting the equipment is multiplied.
The invention content is as follows:
The invention aims to overcome the defects in the prior art and provide the installation method for preventing the tank equipment in the plant from being polluted by the metal ions, which has small adjustment value and high adjustment precision and can ensure the cleanliness of the equipment and the pipeline.
As conceived above, the technical scheme of the invention is as follows: a method for installing tank equipment in a plant to prevent metal ions from polluting is characterized by comprising the following steps: the method comprises the following steps:
Firstly, confirming a center line of tank equipment: firstly, determining the position coordinates of the central point of tank equipment by using a total station;
confirming the center line of the pipeline: measuring the position coordinates of the central line of the fixed pipeline by using a total station according to the drawing size by taking the equipment center point as a reference;
measuring data; erecting a total station at a position where the axis of a plant control network, the center of an equipment circle and the center of a fixed pipeline can be measured simultaneously, determining the center line of a pipe orifice of an equipment body and the center line of the fixed pipeline by using the erected total station, enabling the center line of the pipe orifice of the equipment body and the center line of the fixed pipeline to be on the same center line, and then measuring data;
Adjusting and fixing the central line of the pipeline; measuring the central lines of a plurality of fixed pipelines in sequence, and analyzing and determining the adjustment direction quantity of each fixed pipeline according to the measured data, so that the pipeline bracket of each fixed pipeline is adjusted to ensure that the central line of the pipe orifice of the equipment body and the central line of each fixed pipeline are on the same central line;
checking and measuring; after all pipelines are adjusted, carrying out recheck measurement and recording measurement data;
hoisting tank equipment to the installation position, and determining the installation position of the equipment by using a total station;
seventhly, installing a movable pipeline; after the tank equipment is installed in place, the cleaned movable pipelines are connected, so that the whole pipeline and the equipment form a system.
The operation standard of the first step is as follows: when the position of the center point of the tank equipment is determined, the central axis of the plant control network is used as a reference, and the measurement precision reaches within +/-0.2 mm.
The operation standard of the step II is as follows: the measurement precision reaches within +/-0.2 mm.
The operation standard of the step IV is as follows: the measurement precision reaches within +/-0.2 mm.
The invention adopts the method of installing the equipment after the equipment, firstly, a fixed pipeline at the periphery of the equipment is installed, firstly, the central point of the equipment is positioned, the elevation and the center of the pipeline are positioned by using a total station with the central point as a reference, the fixed pipeline is positioned by using a fixed bracket, then, an equipment body is installed, the position of the equipment body is positioned by using the total station, and finally, a movable pipeline is installed. The invention can ensure the cleanliness of equipment and pipelines, effectively control metal ion pollution, and has small adjustment value, high adjustment precision and no pollution accumulation. Meanwhile, the invention has the advantages of high construction speed and high efficiency.
description of the drawings:
FIG. 1 is a schematic front view of a process apparatus;
FIG. 2 is a schematic top view of a processing tool;
FIG. 3 is a schematic front view of a process tool measurement;
FIG. 4 is a schematic top view of process equipment measurement.
in the figure: 1-an equipment body; 2-a movable pipeline; -a stationary pipe; 4-a movable pipe; 5-fixing the pipeline; 6-movable pipeline; 7-fixing a pipeline; 8-a movable pipe; 9-fixing a pipeline; 10-a movable pipe; 11-fixed pipe; 12-a movable pipe; 13-fixing the pipeline; 14-total station.
the specific implementation mode is as follows:
As shown in fig. 1-4: an installation method for preventing metal ions from polluting tank equipment in a factory building comprises the following steps:
1. Confirming the center line of tank equipment; because the central line of the fixed pipeline is superposed with the central line of the tank equipment, before the pipeline and the equipment are installed, the position coordinates of the central point of the tank equipment are determined by using a total station. The operation standard is as follows: the center point position of the tank type equipment is determined by taking a central axis of a plant control net as a reference. The measured data is real and reliable. The measurement accuracy is within +/-0.2 mm, so that the relative position of the equipment and the pipeline during connection and the position deviation of the flange during connection are ensured.
2. confirming the center line of the pipeline: and measuring the position coordinates of the central line of the fixed pipeline by using a total station according to the drawing size by taking the equipment center point as a reference. The operation standard is as follows: the method comprises the steps of determining the center line of a fixed pipeline by taking the position of the center point of a tank type device as a reference. The measurement accuracy is within +/-0.2 mm, so that the relative position of the equipment and the pipeline during connection and the position deviation of the flange during connection are ensured.
3. Measuring data; the method includes the steps that the total station is erected at the position where the axis of a plant control network, the center of an equipment circle and the center of a fixed pipeline can be measured simultaneously. The erected total station is used for determining the center line of the pipe orifice of the equipment body and the center line of the fixed pipeline, so that the center line of the pipe orifice of the equipment body and the center line of the fixed pipeline are on the same center line. And measuring data.
4. adjusting the central line of the fixed pipeline; measuring the central lines of a plurality of fixed pipelines in sequence, and analyzing and determining the adjustment direction quantity of each fixed pipeline according to the measured data, thereby adjusting the pipeline bracket of the fixed pipeline to ensure that the central line of the pipe orifice of the equipment body and the central line of the fixed pipeline are in the same central line. The operation standard is as follows: the pipeline support is fixed after the pipeline central line is adjusted and fixed, and the position of the adjusted pipeline is prevented from deviating. The measurement accuracy is within +/-0.2 mm, so that the relative position of the equipment and the pipeline during connection and the position deviation of the flange during connection are ensured.
5. rechecking and measuring; after all pipelines are adjusted, rechecking measurement is carried out, and the measured data is recorded, so that the data of all the pipelines and the position data of the equipment meet the equipment hoisting requirement.
6. Hoisting tank equipment; after all pipelines are adjusted, after the reexamination and measurement are completed, the tank type equipment is hoisted to the installation position, the installation position of the equipment is determined by using a total station, and the data of all the pipelines and the position data of the equipment are ensured to meet the equipment acceptance requirements.
7. Installing a movable pipeline; after the tank equipment is installed in place, the process pipeline is cleaned firstly, and the equipment is cleaned after the pipeline reaches the acceptance standard. And after all cleaning is finished and the inspection and acceptance standards are met, connecting the cleaned movable pipelines. The whole pipeline and the equipment form a system and reach the acceptance standard.

Claims (4)

1. A method for installing tank equipment in a plant to prevent metal ions from polluting is characterized by comprising the following steps: the method comprises the following steps:
firstly, confirming a center line of tank equipment: firstly, determining the position coordinates of the central point of tank equipment by using a total station;
Confirming the center line of the pipeline: measuring the position coordinates of the central line of the fixed pipeline by using a total station according to the drawing size by taking the equipment center point as a reference;
measuring data; erecting a total station at a position where the axis of a plant control network, the center of an equipment circle and the center of a fixed pipeline can be measured simultaneously, determining the center line of a pipe orifice of an equipment body and the center line of the fixed pipeline by using the erected total station, enabling the center line of the pipe orifice of the equipment body and the center line of the fixed pipeline to be on the same center line, and then measuring data;
Adjusting and fixing the central line of the pipeline; measuring the central lines of a plurality of fixed pipelines in sequence, and analyzing and determining the adjustment direction quantity of each fixed pipeline according to the measured data, so that the pipeline bracket of each fixed pipeline is adjusted to ensure that the central line of the pipe orifice of the equipment body and the central line of each fixed pipeline are on the same central line;
checking and measuring; after all pipelines are adjusted, carrying out recheck measurement and recording measurement data;
hoisting tank equipment to the installation position, and determining the installation position of the equipment by using a total station;
Seventhly, installing a movable pipeline; after the tank equipment is installed in place, the cleaned movable pipelines are connected, so that the whole pipeline and the equipment form a system.
2. The method for installing the tank-type equipment in the plant to prevent the metal ions from polluting the metal ions according to claim 1, wherein the method comprises the following steps: the operation standard of the first step is as follows: when the position of the center point of the tank equipment is determined, the central axis of the plant control network is used as a reference, and the measurement precision reaches within +/-0.2 mm.
3. The method for installing the tank-type equipment in the plant to prevent the metal ions from polluting the metal ions according to claim 1, wherein the method comprises the following steps: the operation standard of the step II is as follows: the measurement precision reaches within +/-0.2 mm.
4. The method for installing the tank-type equipment in the plant to prevent the metal ions from polluting the metal ions according to claim 1, wherein the method comprises the following steps: the operation standard of the step IV is as follows: the measurement precision reaches within +/-0.2 mm.
CN201810555801.2A 2018-06-01 2018-06-01 installation method of tank equipment in plant for preventing metal ions from polluting Pending CN110549082A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810555801.2A CN110549082A (en) 2018-06-01 2018-06-01 installation method of tank equipment in plant for preventing metal ions from polluting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810555801.2A CN110549082A (en) 2018-06-01 2018-06-01 installation method of tank equipment in plant for preventing metal ions from polluting

Publications (1)

Publication Number Publication Date
CN110549082A true CN110549082A (en) 2019-12-10

Family

ID=68734884

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810555801.2A Pending CN110549082A (en) 2018-06-01 2018-06-01 installation method of tank equipment in plant for preventing metal ions from polluting

Country Status (1)

Country Link
CN (1) CN110549082A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08226819A (en) * 1996-01-12 1996-09-03 Toa Harbor Works Co Ltd Laser beam irradiation method on facing of tunnel
CN101289881A (en) * 2008-05-30 2008-10-22 浙江省一建建设集团有限公司 Special-shaped element mounting construction method
CN102759351A (en) * 2011-04-25 2012-10-31 五冶集团上海有限公司 Measuring and positioning method of installation of large-scale annular equipment foundation bolt sleeves
CN104328799A (en) * 2014-11-17 2015-02-04 中建交通建设集团有限公司 Accurate positioning method for steel pipe column in cover and cut top-down subway station
CN107796376A (en) * 2017-09-29 2018-03-13 中国二十冶集团有限公司 The collimator and total Station measurement and positioning method of annular preheating furnace support roller

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08226819A (en) * 1996-01-12 1996-09-03 Toa Harbor Works Co Ltd Laser beam irradiation method on facing of tunnel
CN101289881A (en) * 2008-05-30 2008-10-22 浙江省一建建设集团有限公司 Special-shaped element mounting construction method
CN102759351A (en) * 2011-04-25 2012-10-31 五冶集团上海有限公司 Measuring and positioning method of installation of large-scale annular equipment foundation bolt sleeves
CN104328799A (en) * 2014-11-17 2015-02-04 中建交通建设集团有限公司 Accurate positioning method for steel pipe column in cover and cut top-down subway station
CN107796376A (en) * 2017-09-29 2018-03-13 中国二十冶集团有限公司 The collimator and total Station measurement and positioning method of annular preheating furnace support roller

Similar Documents

Publication Publication Date Title
CN103087731B (en) A kind of Laser measurement installation method of coke dry quenching furnace furnace shell
CN111104709A (en) BIM-based large-scale refrigeration machine room digital assembly method and system
CN102601567B (en) Method for welding special-shaped flange pipelines and welding tool
CN109707934A (en) A kind of pipeline installation sampler and sampling method
CN211954152U (en) Detection apparatus for ballastless track bearing platform measures frock
CN110549082A (en) installation method of tank equipment in plant for preventing metal ions from polluting
CN213580073U (en) Spray water cooling effect detection system in continuous casting process
CN109724411B (en) Modular assembly method for radiation section of large-scale converter
CN112815898A (en) Method for converting ship three-dimensional data measurement into two-dimensional data measurement based on coordinate system
CN101907201A (en) Construction method for positioning sleeve by automatic leveling plumb method
CN105156829A (en) Urban pipeline valve installing construction technology
CN112249262B (en) Quick positioning method for ship anchor platform
CN114215233B (en) Complex hyperboloid curtain wall structure and positioning construction method thereof
CN114000626B (en) Construction method of hyperbolic aluminum plate curtain wall
CN111774813B (en) Method for manufacturing inner field of folding pipe
CN110639969A (en) Deflection angle positioning tool for medium plate descaling header nozzle and application thereof
CN101852479B (en) Segmental out-of-sequence installation method of pipeline
CN107339932B (en) Method for integrally replacing connecting pipe
CN113886751A (en) Pressure pipeline positioning method based on data fusion
CN106871982B (en) Fuzzy parameter measuring method for measuring fluid flow in generator stator bar
CN112945103A (en) Rapid and automatic detecting method and device for contour dimension of tunnel segment and segment mould
CN203795320U (en) Inner steel die for accurately positioning cable-stayed bridge pylon cable guide pipe
CN110923385A (en) Accurate installation method of bustle pipe
CN110000556B (en) Automatic weld track clamping corrector and correction subassembly
CN202196760U (en) Positioning device for performing right-side dotting for back-side defect of silicon chip

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20191210