CN104314096A - Steel pipe pole pile type foundation construction method for using epoxy coal pitch finish paint to prevent corrosion - Google Patents

Steel pipe pole pile type foundation construction method for using epoxy coal pitch finish paint to prevent corrosion Download PDF

Info

Publication number
CN104314096A
CN104314096A CN201410635775.6A CN201410635775A CN104314096A CN 104314096 A CN104314096 A CN 104314096A CN 201410635775 A CN201410635775 A CN 201410635775A CN 104314096 A CN104314096 A CN 104314096A
Authority
CN
China
Prior art keywords
steel pipe
pipe pole
pile
type foundation
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410635775.6A
Other languages
Chinese (zh)
Inventor
张磊
阚伟
鲁广辉
薄其伟
顾毅
许权
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANDONG LIYUAN TOWER MANUFACTURING Co Ltd
State Grid Corp of China SGCC
Zaozhuang Power Supply Co of State Grid Shandong Electric Power Co Ltd
Original Assignee
SHANDONG LIYUAN TOWER MANUFACTURING Co Ltd
State Grid Corp of China SGCC
Zaozhuang Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANDONG LIYUAN TOWER MANUFACTURING Co Ltd, State Grid Corp of China SGCC, Zaozhuang Power Supply Co of State Grid Shandong Electric Power Co Ltd filed Critical SHANDONG LIYUAN TOWER MANUFACTURING Co Ltd
Priority to CN201410635775.6A priority Critical patent/CN104314096A/en
Publication of CN104314096A publication Critical patent/CN104314096A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • E02D27/16Foundations formed of separate piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/28Prefabricated piles made of steel or other metals
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/02Placing by driving

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a steel pipe pole pile type foundation construction method for using epoxy coal pitch finish paint to prevent corrosion. The steel pipe pole pile type foundation construction method for using the epoxy coal pitch finish paint to prevent the corrosion includes steps: using a hand tool to remove rust of a steel pipe pole pile, and brushing zinc-rich primer and the epoxy coal pitch finish paint onto the surface of the steel pipe pole pile; maintaining the steel pipe pole pile above 10 degree centigrade for 7-10 days before using the steel pipe pole pile; selecting a pile position, placing the steel pipe pole pile on the selected pile position, and using a pile driver to drive the steel pipe pole pile into the ground. The steel pipe pole pile type foundation construction method for using the epoxy coal pitch finish paint to prevent the corrosion can replace a traditional large area excavation concrete foundation with a steel pipe pole pile type foundation, combines the characteristics of the pile type foundation of being small in occupied area, convenient and fast to construct, short in work period, free of weather restrictions and the like, uses the epoxy coal pitch finish paint to prevent the corrosion, and thereby is low in cost and reliable in performance, and reduces cost by 60% by being compared with a hot galvanizing corrosion prevention method.

Description

Adopt the construction method of epoxy coalification bituminous sheaths paint corrosion-resistant steel pipe pole pile type foundation
Technical field
The present invention relates to pile foundation technology construction field, specifically adopt the construction method of epoxy coalification bituminous sheaths paint corrosion-resistant steel pipe pole pile type foundation.
Background technology
Method for constructing foundation pile refers to the construction method of single pile in pile foundation construction process, and current method for constructing foundation pile mainly contains three kinds: paddle type mill, static pressure type and flush type.Paddle type mill and static pressure type refer to be squeezed into preformed pile or to be pressed into the construction method in stratum, and flush type refers to cast-in-place concrete stake in stratum at the construction field (site).
Because paddle type mill and static pressure type adopt physical method to be squeezed into by preformed pile or to be pressed into the construction method in stratum, so there is the possibility damaged preformed pile, the integrality of preformed pile pile body can be affected, the infringement of macroscopic view or microcosmic can be produced to pile body, above-mentioned situation can cause the concrete strength of preformed pile not give full play to, namely material property can not give full play to, and while pile body performance reduces, causes the waste of non-renewable resources; Because paddle type mill and static pressure type can produce soil compaction effect in work progress, easily have an impact to peripheral facilities, cause and can not select preformed pile in a lot of engineering in urban district, the noise simultaneously in paddle type mill work progress and oil smoke can pollute surrounding enviroment.Flush type, because scene needs boring, then fluid concrete stake, so the quality control of concrete pile get up more difficult, pile quality is unstable, and bearing capacity of single pile is low, and the non-renewable raw material resources such as concrete, steel consumption is large, discharge a large amount of mud, these mud pollute the environment simultaneously.
In order to meet bearing capacity and controlling distortion requirement, prior art often adopts profound pile foundation, paddle type mill or static pressure type tube pile construction often can not meet the performance requirement such as resistance to plucking and horizontal force resistant, many high levels, super highrise building and roadbed etc. have the basis of dynamic load requirement substantially to adopt bored pile, but bored pile cost is high, quality is unstable, antiseptic effect is poor, weather effect is large, and mud emission contaminated environment, do not meet the idea of development of low-carbon environment-friendly.
Summary of the invention
The object of the present invention is to provide the construction method adopting epoxy coalification bituminous sheaths paint corrosion-resistant steel pipe pole pile type foundation, to solve the problem proposed in above-mentioned background technology.
For achieving the above object, the invention provides following technical scheme:
Adopt the construction method of epoxy coalification bituminous sheaths paint corrosion-resistant steel pipe pole pile type foundation, concrete steps comprise:
1) steel pipe pole stake is adopted to the foreign material of the metal surface of hand-operated tools removing steel pipe pole stake; After rust cleaning, at steel pipe pole stake surface brush zinc rich primer, before zinc rich primer solidification, be wound around glass wool cloth, then at steel pipe pole stake surface brush epoxy coalification bituminous sheaths paint; More than 10 DEG C can come into operation for maintenance 7-10 days;
2) select fixed pile, steel pipe pole stake be placed on selected stake position and utilize pile driver to throw the end, ground into.
As the further scheme of the present invention: step 1) in foreign material comprise loosening oxide skin and become rusty with floating, the credit rating after steel pipe pole stake surface derusting is St3.
Compared with prior art, the invention has the beneficial effects as follows: the present invention can substitute traditional dig on a wide area concrete foundation, gathered pile type foundation floor space little, construct convenient, the duration is short, not by the feature such as weather restriction, anticorrosion employing epoxy nigritite is anticorrosion, with low cost, dependable performance cost is compared with the anticorrosion reduction by 60% of galvanizing.
Detailed description of the invention
Below in conjunction with the embodiment of the present invention, be clearly and completely described the technical scheme in the embodiment of the present invention, obviously, described embodiment is only the present invention's part embodiment, instead of whole embodiments.Based on the embodiment in the present invention, those of ordinary skill in the art, not making the every other embodiment obtained under creative work prerequisite, belong to the scope of protection of the invention.
In the embodiment of the present invention, adopt the construction method of epoxy coalification bituminous sheaths paint corrosion-resistant steel pipe pole pile type foundation, concrete steps comprise:
1) hand-operated tools rust cleaning is adopted to steel pipe pole stake, use the foreign material such as oxide skin, floating rust that the metal surface of electronic rotation wire brush removing steel pipe pole stake loosens; Credit rating after steel pipe pole stake surface derusting is St3; After rust cleaning, at steel pipe pole stake surface brush zinc rich primer, before zinc rich primer solidification, be wound around glass wool cloth, then at steel pipe pole stake surface brush epoxy coalification bituminous sheaths paint; More than 10 DEG C can come into operation for maintenance 7-10 days;
2) select fixed pile, steel pipe pole stake is placed on selected stake position and utilizes pile driver to throw the end, ground into.
The present invention can substitute traditional dig on a wide area concrete foundation, gathered that pile type foundation floor space is little, construction make victory, duration short, not by features such as weather restrictions, anticorrosion employing epoxy nigritite is anticorrosion, with low cost, dependable performance cost is compared with the anticorrosion reduction by 60% of galvanizing.
To those skilled in the art, obviously the invention is not restricted to the details of above-mentioned one exemplary embodiment, and when not deviating from spirit of the present invention or essential characteristic, the present invention can be realized in other specific forms.Therefore, no matter from which point, all should embodiment be regarded as exemplary, and be nonrestrictive, scope of the present invention is limited by claims instead of above-mentioned explanation, and all changes be therefore intended in the implication of the equivalency by dropping on claim and scope are included in the present invention.
In addition, be to be understood that, although this manual is described according to embodiment, but not each embodiment only comprises an independently technical scheme, this narrating mode of manual is only for clarity sake, those skilled in the art should by manual integrally, and the technical scheme in each embodiment also through appropriately combined, can form other embodiments that it will be appreciated by those skilled in the art that.

Claims (2)

1. adopt the construction method of epoxy coalification bituminous sheaths paint corrosion-resistant steel pipe pole pile type foundation, it is characterized in that, concrete steps comprise:
1) steel pipe pole stake is adopted to the foreign material of the metal surface of hand-operated tools removing steel pipe pole stake; After rust cleaning, at steel pipe pole stake surface brush zinc rich primer, before zinc rich primer solidification, be wound around glass wool cloth, then at steel pipe pole stake surface brush epoxy coalification bituminous sheaths paint; More than 10 DEG C can come into operation for maintenance 7-10 days;
2) select fixed pile, steel pipe pole stake is placed on selected stake position and utilizes pile driver to throw the end, ground into.
2. the construction method of employing epoxy coalification bituminous sheaths paint corrosion-resistant steel pipe pole pile type foundation according to claim 1, it is characterized in that, described step 1) in foreign material comprise loosening oxide skin and become rusty with floating, the credit rating after steel pipe pole stake surface derusting is St3.
CN201410635775.6A 2014-11-01 2014-11-01 Steel pipe pole pile type foundation construction method for using epoxy coal pitch finish paint to prevent corrosion Pending CN104314096A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410635775.6A CN104314096A (en) 2014-11-01 2014-11-01 Steel pipe pole pile type foundation construction method for using epoxy coal pitch finish paint to prevent corrosion

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410635775.6A CN104314096A (en) 2014-11-01 2014-11-01 Steel pipe pole pile type foundation construction method for using epoxy coal pitch finish paint to prevent corrosion

Publications (1)

Publication Number Publication Date
CN104314096A true CN104314096A (en) 2015-01-28

Family

ID=52369398

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410635775.6A Pending CN104314096A (en) 2014-11-01 2014-11-01 Steel pipe pole pile type foundation construction method for using epoxy coal pitch finish paint to prevent corrosion

Country Status (1)

Country Link
CN (1) CN104314096A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2534938B2 (en) * 1991-04-05 1996-09-18 新日本製鐵株式会社 Polyurethane coated structure
CN200968467Y (en) * 2006-07-20 2007-10-31 廊坊开发区首都航天波纹管厂 Full buried anti-corrosive external pressure thermal insulation type corrugated pipe expansion-joint
CN200999346Y (en) * 2006-09-15 2008-01-02 刘海峰 Fully steel-made universal reinforced type pole tower pile
CN201381509Y (en) * 2008-10-29 2010-01-13 中国科学院金属研究所 Ocean protective steel pile
CN103523411A (en) * 2013-10-24 2014-01-22 成军 Horizontal buried oil storage tank and installation and construction method of matched device pipeline thereof
CN104005407A (en) * 2014-06-10 2014-08-27 山东中能杆塔有限公司 Partially prestressed concrete structure foundation pile

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2534938B2 (en) * 1991-04-05 1996-09-18 新日本製鐵株式会社 Polyurethane coated structure
CN200968467Y (en) * 2006-07-20 2007-10-31 廊坊开发区首都航天波纹管厂 Full buried anti-corrosive external pressure thermal insulation type corrugated pipe expansion-joint
CN200999346Y (en) * 2006-09-15 2008-01-02 刘海峰 Fully steel-made universal reinforced type pole tower pile
CN201381509Y (en) * 2008-10-29 2010-01-13 中国科学院金属研究所 Ocean protective steel pile
CN103523411A (en) * 2013-10-24 2014-01-22 成军 Horizontal buried oil storage tank and installation and construction method of matched device pipeline thereof
CN104005407A (en) * 2014-06-10 2014-08-27 山东中能杆塔有限公司 Partially prestressed concrete structure foundation pile

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张磊等: "1000MW机组防腐保温专业施工方案", 《山东电机工程学会第七届发电专业学术交流会论文集》, 30 September 2008 (2008-09-30) *

Similar Documents

Publication Publication Date Title
CN1710205A (en) Bituminous pavement top-crack or settlement treating method
WO2010137813A3 (en) Method for forming reclaimed land within seawall and construction equipment thereof
CN105672323A (en) Compound soil nail wall supporting structure system with steel pipe piles and construction method of compound soil nail wall supporting structure system
CN102182399A (en) Construction method and equipment for reverse circulation drill to drill hole, hammer to form hole, expand hole and remove slag
CN204000779U (en) A kind of Arch Dam Abutment slope retaining structure
CN104074183A (en) Drilling and concrete injected root composite pile implanting pile structure and construction method
CN110700038A (en) Underground pipe gallery sponge city municipal road surface with load resistance and drainage function
CN104314096A (en) Steel pipe pole pile type foundation construction method for using epoxy coal pitch finish paint to prevent corrosion
CN101545269A (en) Method for rigid waterproof construction of beam and slab type basement
CN204849806U (en) Steel pipe pole for transmission line
CN204849805U (en) Steel pipe pole is with prefabricated basis of stake formula
CN106592514A (en) Construction method of old city riverway piling wall integrated vertical type retaining wall
CN204456097U (en) A kind of anchor cable reinforcing soil cutting side slope
CN201288325Y (en) High voltage rotary spraying enlarged footing pre-stress pipe pile
CN203625902U (en) Expansion shell type anchorage head and anchor rod with same
CN202881938U (en) Ground anchor peg of solar energy photovoltaic power generation device
CN202139595U (en) Short-pipe-type ecological slope protective structure
CN203022001U (en) Pile-pulling device with vibrating sleeve ring
CN204530357U (en) Cliff side slope plank road
CN204982946U (en) Prevent native sediment device that drops
CN211689738U (en) Underground pipe gallery sponge city municipal road surface with load resistance and drainage function
CN202626979U (en) High-pressure rotary jet grouting stiffening pile construction equipment with rib drilling method
CN203867187U (en) Surface closure for floor water pipe pressure groove
CN202577613U (en) Waterproof wall bolt hole structure
CN206245330U (en) A kind of NEW TYPE OF COMPOSITE support disk pile

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20150128