CN104278680A - Envelope structure combining five (six) shaft mixing piles with press grouting piles and construction method - Google Patents
Envelope structure combining five (six) shaft mixing piles with press grouting piles and construction method Download PDFInfo
- Publication number
- CN104278680A CN104278680A CN201310270606.2A CN201310270606A CN104278680A CN 104278680 A CN104278680 A CN 104278680A CN 201310270606 A CN201310270606 A CN 201310270606A CN 104278680 A CN104278680 A CN 104278680A
- Authority
- CN
- China
- Prior art keywords
- pile
- piles
- reinforcing cage
- axle
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D19/00—Keeping dry foundation sites or other areas in the ground
- E02D19/06—Restraining of underground water
- E02D19/12—Restraining of underground water by damming or interrupting the passage of underground water
- E02D19/18—Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/18—Bulkheads or similar walls made solely of concrete in situ
- E02D5/187—Bulkheads or similar walls made solely of concrete in situ the bulkheads or walls being made continuously, e.g. excavating and constructing bulkheads or walls in the same process, without joints
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/36—Concrete or concrete-like piles cast in position ; Apparatus for making same making without use of mouldpipes or other moulds
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/46—Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil
Abstract
The invention relates to an envelope structure combining mixing piles with grouting piles and a construction method. The mixing piles are constructed by adopting the five (six) shaft mixing pile technology, hereafter referred to as an FCW construction method. The grouting piles combined with the mixing piles are formed by inserting reinforcement cages after pressing and grouting concrete in long spiral drill holes. The characteristics of the FCW construction method are combined with the characteristics of the technology of inserting the reinforcement cages after pressing and grouting the concrete in the long spiral drill holes. The construction technology of the whole envelope structure has the advantages of being friendly to the environment, high in effect, low in cost, free of slurry pollution, small in soil-squeezing and effect on the environment and the like.
Description
Technical field
The present invention relates to a kind of continuous multi-shaft cement mixing wall and insert the space enclosing structure that combines of reinforcing cage castinplace pile (abbreviation guncreting pile) and construction method thereof with after long auger guncreting, be mainly used in civilian and industrial infrastructure construction build in bracing of foundation pit sealing and braced cuts.
Background technology
The concrete filling pile construction method of current routine has the castinplace pile etc. of the castinplace pile of dry operation pore-forming, the castinplace pile of mud off pore-forming, the castinplace pile of casing pipe hole forming and explosive expansion pore-forming
The construction process of bored concrete pile flow process of dry operation pore-forming: sediment → hole quality at the bottom of land clearing → surveying setting-out fixed pile → pile-forming machine perching → boring extracting soil pore-forming → cleaning hole is inspected for acceptance → install reinforcing cage → pouring hole inner concrete.
The castinplace pile of mud off pore-forming utilizes mud off, during boring by circulating mud by the native slag tap under bit cutting outer and pore-forming, then install reinforcing cage, underwater concreting and pile.
Casing pipe hole forming castinplace pile utilizes impact pile driving method or vibrosinking, and by with valve type pile shoe or sink in soil with the steel sleeve of precast concrete shoe, then limit is pulled out cover tube edge concrete perfusion and formed.If when being furnished with reinforcing bar, then before fluid concrete, first hang cage of reinforcement.Utilize hammer piling equipment immersed tube, tube drawing, be called hammer hidden pipe caisson pile; Utilize the vibration sinking tube of vibrator, tube drawing, be called vibrator pipe sinking cast-in-place pile.
Conventional construction process of bored concrete pile is all first put reinforcing cage usually, then concreting.There is waste concrete, environment pollution, shortcoming that cost is higher in current Concrete Grouting Pale, construction period aspect is also to be improved simultaneously, construction machinery intelligence degree is not high, is many times reinforcedly all experience according to field personnel and determines, and well can not carry out monitoring management.
Summary of the invention
Agitation pile involved in the present invention is novel five (six) axle Soil-cement Walls (hereinafter referred to as FCW engineering method), this engineering method uses novel intellectuality five (six) axle ram machine construction, once at most can pile five (six) root, without displacement soil, to some extent solve the deficiency of above-mentioned several agitation pile technique, have efficient, without the feature of displacement, intelligent, environmental protection.
The present invention is achieved through the following technical solutions:
The space enclosing structure that a kind of five (six) axle agitation piles combine with reinforcing cage castinplace pile slotting after long auger guncreting, five (six) described axle agitation piles adopt ground, cities five axle Soil-cement Wall construction technologies (hereinafter referred to as FCW engineering method); Castinplace pile inserts reinforcing cage castinplace pile after adopting long auger guncreting.
The construction method of described one five (six) axle Soil-cement Wall, its construction method comprises the following steps:
(1) setting-out, open channels, device is in place, and five (six) axle cement-soil mixing pile devices are moved to position to be onstructed;
(2) start backstage cement paste stirring system, then cement paste is delivered to slurry storage bucket;
(3) open integrated computer, allow computer control the data pre-set: every meter of decrease speed, every meter of whitewashing amount, stake end design elevation, total whitewashing amount and total mixing time;
(4) head that turns on the power drives Multifunctional drill, while stirring water-spray type slurry, rotates forward absolute altitude at the bottom of sinking whitewashing 70% to design wall.
(5) stir again in absolute altitude 0.5 ~ 1 meter of interval at the bottom of wall.
(6) brill is carried on reversion whitewashing limit, limit, and reversion whitewashing 30% to wall top mark is high;
(7) get final product pile one on the other, form gravity dam as required;
(8) one groups of constructions terminate, and move to second group and continue construction.
Insert reinforcing cage castinplace pile after described long auger guncreting, its construction method comprises the following steps:
(1) smooth location, the setting-out of stake position;
(2) Installation and Debugging rig, lays steel pile casting (as needs);
(3) debug concrete pump, pump line is installed;
(4) driller insertion;
(5) boring to projected depth stops creeping into;
(6) limit infusion Superfluid state concrete limit promotes drilling rod;
(7) propose drilling rod, remove drilling tool;
(8) reinforcing cage, vibrating hammer is lifted by crane;
(9) the lower slotting reinforcing cage of Vibration on Start-up hammer is to design elevation;
(10) Stake head handling;
(11) one groups of constructions terminate, and move to second group and continue construction.
Five (six) described axle agitation piles and the combining form of castinplace pile can be the form be arranged side by side or the form that both are connected in snap-in manner, also can be the forms that castinplace pile is embedded between many row's agitation piles.
The invention has the advantages that:
1, castinplace pile of the present invention bores under adopting auger stem and carries soil, and promote auger stem and pour into Superfluid state concrete by the hollow part of drilling rod simultaneously, more traditional construction technology, shortens the engineering time, and efficiency of construction is higher;
2, traditional handicraft whitewashing amount and drilling down and up, does not install flow instrument and depth sensing instrument, and construction is complete by rule of thumb.Existing equipment has installed corresponding computer sensing instrument, reaches requirement that is directly perceived, effective, automation, ensure that quality.
3, the present invention can one-step pore-creating, not only ensure that construction quality but also shorten the construction period;
4, in stake, arrangement of reinforcement adopts high tensile reinforcement, and horizontal direction anti-bending strength is also better, gives full play to high tensile reinforcement tension, both concrete anti-compressions advantage, more economical in cost.
5, agitation pile adopts novel five axle construction technology constructions, and increase than traditional handicraft pile quantity, efficiency of construction is significantly improved, and without displacement soil, pollution-free generation.
6, agitation pile adopts novel five axle construction technology constructions, and the cost of engineering water-stop curtain aspect can save about 20%.
7, agitation pile adopts novel five axle construction technologies constructions, and the plant equipment of employing contains Intellectualized monitoring equipment, and workmanship is guaranteed, and solving that cement in mixing pile construction technique uses cannot the shortcoming of accurate-metering.
Accompanying drawing explanation
Fig. 1 is that Superfluid state concrete post-set reinforcing cage castinplace pile and five axle agitation piles combine with campshed form;
Fig. 2 is that Superfluid state concrete post-set reinforcing cage castinplace pile is engaged mutually with five axle agitation piles;
Fig. 3 is that Superfluid state concrete post-set reinforcing cage castinplace pile is embedded in many rows five axle agitation piles;
Fig. 4 is the construction sequence chart of Superfluid state concrete post-set reinforcing cage castinplace pile;
Fig. 5 is that Superfluid state concrete post-set reinforcing cage castinplace pile and five axle agitation pile campsheds are constructed sequence.
Detailed description of the invention
Go along with sb. to guard him form below in conjunction with the drawings and specific embodiments to one of the present invention to be described in detail.The present embodiment is implemented premised on technical solution of the present invention, give detailed embodiment and concrete operating process, but protection scope of the present invention is not limited to following embodiment.
Embodiment:
As shown in Figure 3, a kind of adopt above-mentioned construction method to construct Superfluid state concrete post-set reinforcing cage castinplace pile and the vertical space enclosing structure of the combined campshed of five axle agitation piles, comprise multiple castinplace pile and agitation pile,
Described castinplace pile is Superfluid state concrete post-set reinforcing cage castinplace pile, the i.e. stake of A sequence, and its construction process is:
Smooth location → stake position setting-out → Installation and Debugging rig (installation steel pile casting) → debugging concrete pump, pump line → driller insertion → lifting reinforcing cage is installed, vibrating hammer → hole to projected depth stops creeping into → infusion Superfluid state concrete limit, limit promotes drilling rod → propositions drilling rod, removes drilling tool → Vibration on Start-up hammer into shape under slotting reinforcing cage to design elevation → pile → Stake head handling → stake top safeguard measure.
After A sequence pile driving construction completes, carry out the construction of B sequence stake, i.e. the construction of five axle agitation piles, adopt joint form, Specific construction flow process is as follows:
(1) setting-out; Open channels; Device is in place, and five axle Soil-cement Wall plant equipment are moved to position to be onstructed.
(2) start backstage automatic water mud stirring system, then cement paste is delivered to slurry storage bucket.
(3) open integrated computer, become wall critical data by computer monitoring; Every meter of decrease speed, hoisting velocity, every Rice & peanut milk amount, wall end design elevation, verticality, total whitewashing amount and total mixing time.Effective control quality of wall.
(4) head that turns on the power drives Multifunctional drill, while stirring water-spray type slurry, rotates forward absolute altitude at the bottom of sinking whitewashing 70% to design wall.
(5) stir again in absolute altitude 0.5 ~ 1 meter of interval at the bottom of wall.
(6) brill is carried on reversion whitewashing limit, limit, and reversion whitewashing 30% to wall top mark is high.
(7) one groups are terminated, and move on to second group and continue construction.
Claims (4)
1. (six) axle agitation piles and the space enclosing structure of inserting reinforcing cage castinplace pile after long auger guncreting and combining, it is characterized in that, five (six) described axle agitation piles adopt ground, city five axle Soil-cement Wall construction technologies (hereinafter referred to as FCW engineering method); Castinplace pile inserts reinforcing cage castinplace pile after adopting long auger guncreting.
2. the construction method of five (six) axle Soil-cement Walls according to claim 1, it is characterized in that, described construction method comprises the following steps:
(1) setting-out, open channels, device is in place, and five (six) axle cement-soil mixing pile devices are moved to position to be onstructed;
(2) start backstage cement paste stirring system, then cement paste is delivered to slurry storage bucket;
(3) open integrated computer, allow computer control the data pre-set: every meter of decrease speed, every meter of whitewashing amount, stake end design elevation, total whitewashing amount and total mixing time;
(4) head that turns on the power drives Multifunctional drill, while stirring water-spray type slurry, rotates forward absolute altitude at the bottom of sinking whitewashing 70% to design wall.
(5) stir again in absolute altitude 0.5 ~ 1 meter of interval at the bottom of wall.
(6) brill is carried on reversion whitewashing limit, limit, and reversion whitewashing 30% to wall top mark is high;
(7) get final product pile one on the other, form gravity dam as required;
(8) one groups of constructions terminate, and move to second group and continue construction.
3. insert reinforcing cage castinplace pile after long auger guncreting according to claim 1, it is characterized in that, described construction method comprises the following steps:
(1) smooth location, the setting-out of stake position;
(2) Installation and Debugging rig, lays steel pile casting (as needs);
(3) debug concrete pump, pump line is installed;
(4) driller insertion;
(5) boring to projected depth stops creeping into;
(6) limit infusion Superfluid state concrete limit promotes drilling rod;
(7) propose drilling rod, remove drilling tool;
(8) reinforcing cage, vibrating hammer is lifted by crane;
(9) the lower slotting reinforcing cage of Vibration on Start-up hammer is to design elevation;
(10) Stake head handling;
(11) one groups of constructions terminate, and move to second group and continue construction.
4. a kind of five (six) axle agitation piles according to claim 1 insert the space enclosing structure that combines of reinforcing cage castinplace pile with after long auger guncreting, it is characterized in that, five (six) described axle agitation piles and the combining form of castinplace pile can be the form be arranged side by side or the form that both are connected in snap-in manner, also can be the forms that castinplace pile is embedded between many row's agitation piles.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310270606.2A CN104278680A (en) | 2013-07-01 | 2013-07-01 | Envelope structure combining five (six) shaft mixing piles with press grouting piles and construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310270606.2A CN104278680A (en) | 2013-07-01 | 2013-07-01 | Envelope structure combining five (six) shaft mixing piles with press grouting piles and construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN104278680A true CN104278680A (en) | 2015-01-14 |
Family
ID=52253988
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310270606.2A Pending CN104278680A (en) | 2013-07-01 | 2013-07-01 | Envelope structure combining five (six) shaft mixing piles with press grouting piles and construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104278680A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105714832A (en) * | 2016-02-29 | 2016-06-29 | 济南轨道交通集团有限公司 | Deep-foundation-pit large-sized precast building envelope and construction method |
CN109306700A (en) * | 2018-11-09 | 2019-02-05 | 上海长凯岩土工程有限公司 | Support water stop integration building enclosure and its construction method |
CN110485413A (en) * | 2019-07-31 | 2019-11-22 | 中国铁建港航局集团有限公司 | One kind closing on subway overpass pile foundation combined type protection fast pore-creating method |
CN113832960A (en) * | 2021-09-30 | 2021-12-24 | 中国二十冶集团有限公司 | Construction method of soft soil foundation bored pile |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2617821Y (en) * | 2003-04-29 | 2004-05-26 | 天津市水利科学研究所 | Deep jet stirred pile with rigid core |
CN1676761A (en) * | 2005-04-18 | 2005-10-05 | 祁春伟 | Long-spiral post-joint-bar bored concrete pile construction method |
CN101509254A (en) * | 2009-03-09 | 2009-08-19 | 天津市建工工程总承包有限公司 | Steel reinforced concrete filling pile and cement stirring pile meshing engagement type foundation pit support construction method |
CN201459737U (en) * | 2009-06-25 | 2010-05-12 | 南京林业大学 | Foundation pit supporting structure |
JP2011012443A (en) * | 2009-07-01 | 2011-01-20 | Ohbayashi Corp | Construction method for soil cement structure and the soil cement structure |
CN102535450A (en) * | 2012-01-17 | 2012-07-04 | 上海城地建设发展有限公司 | Five-axis cement-soil mixing pile device and construction method |
CN102628266A (en) * | 2011-12-30 | 2012-08-08 | 中铁二局股份有限公司 | Construction method of long spiral cast-in-situ bored pile |
-
2013
- 2013-07-01 CN CN201310270606.2A patent/CN104278680A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2617821Y (en) * | 2003-04-29 | 2004-05-26 | 天津市水利科学研究所 | Deep jet stirred pile with rigid core |
CN1676761A (en) * | 2005-04-18 | 2005-10-05 | 祁春伟 | Long-spiral post-joint-bar bored concrete pile construction method |
CN101509254A (en) * | 2009-03-09 | 2009-08-19 | 天津市建工工程总承包有限公司 | Steel reinforced concrete filling pile and cement stirring pile meshing engagement type foundation pit support construction method |
CN201459737U (en) * | 2009-06-25 | 2010-05-12 | 南京林业大学 | Foundation pit supporting structure |
JP2011012443A (en) * | 2009-07-01 | 2011-01-20 | Ohbayashi Corp | Construction method for soil cement structure and the soil cement structure |
CN102628266A (en) * | 2011-12-30 | 2012-08-08 | 中铁二局股份有限公司 | Construction method of long spiral cast-in-situ bored pile |
CN102535450A (en) * | 2012-01-17 | 2012-07-04 | 上海城地建设发展有限公司 | Five-axis cement-soil mixing pile device and construction method |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105714832A (en) * | 2016-02-29 | 2016-06-29 | 济南轨道交通集团有限公司 | Deep-foundation-pit large-sized precast building envelope and construction method |
CN109306700A (en) * | 2018-11-09 | 2019-02-05 | 上海长凯岩土工程有限公司 | Support water stop integration building enclosure and its construction method |
CN110485413A (en) * | 2019-07-31 | 2019-11-22 | 中国铁建港航局集团有限公司 | One kind closing on subway overpass pile foundation combined type protection fast pore-creating method |
CN110485413B (en) * | 2019-07-31 | 2021-01-05 | 中国铁建港航局集团有限公司 | Combined type protection rapid hole forming method for pile foundation of viaduct adjacent to subway |
CN113832960A (en) * | 2021-09-30 | 2021-12-24 | 中国二十冶集团有限公司 | Construction method of soft soil foundation bored pile |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103924586B (en) | Multi section drill grouting pile construction method | |
CN106400782B (en) | A kind of construction method for going along with sb. to guard him hole-drilling interlocking pile using rotary drilling rig construction foundation pit | |
CN108360972A (en) | A kind of rotary drilling rig is combined with percussive drill carries out bored pile construction method | |
CN104947690B (en) | Grooving construction method for embedding underground continuous wall into rock | |
CN107524142A (en) | A kind of holing with slurry wall protection cast-in-place pile construction method | |
CN101560767A (en) | Method for connecting slotted sections in underground construction of diaphragm wall | |
CN102286984A (en) | Water-stop curtain and construction method thereof | |
CN107059877A (en) | Basis and its construction method of the bottom with chain knife during a kind of construction | |
CN104963346A (en) | Support construction method for deep foundation pit in complex geological condition | |
CN107386285A (en) | A kind of novel steel tube pile foundation rock borehole anchorage method | |
CN106930276A (en) | The deep hole blasting of rotary digging bored concrete pile and the construction method of conduit rotary digging removing obstacles | |
CN104278680A (en) | Envelope structure combining five (six) shaft mixing piles with press grouting piles and construction method | |
CN105649094B (en) | A kind of deep water foundation bearing platform construction three wall steel cofferdams and its construction method | |
CN105155519A (en) | Rotary-excavating under-reamed bored pile constructing method | |
CN201762702U (en) | Drilling bitten pile | |
CN104278679A (en) | Envelope structure combining five (six) shaft mixing piles with precast tubular piles and construction method | |
CN104250970A (en) | Novel visual intelligent super-fluid cast-in-place concrete pile device and construction method | |
CN106592605A (en) | Construction method of foundation pit bracing with tri-axial stirring piles overlapped with reinforced concrete cast-in-place piles to be driven | |
CN102409972B (en) | Multi-bit convolution punching/tamping engineering groover | |
CN106930278A (en) | A kind of method that compromise joint pipe is used for support pile occlusion | |
CN104563100A (en) | Cement mixing pile later embedding press-grouting pile support structure and construction method | |
CN205444192U (en) | Bridge stake is towards pile driving construction system | |
CN110306539A (en) | A kind of pile base construction method using all steel cylinder-wall | |
CN109930624A (en) | A kind of embedding petrographic province blower foundation of offshore wind farm and construction method | |
CN203487527U (en) | Novel visual intelligent extra-liquid concrete cast-in-place pile device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20150114 |
|
WD01 | Invention patent application deemed withdrawn after publication |