CN104278680A - Envelope structure combining five (six) shaft mixing piles with press grouting piles and construction method - Google Patents

Envelope structure combining five (six) shaft mixing piles with press grouting piles and construction method Download PDF

Info

Publication number
CN104278680A
CN104278680A CN201310270606.2A CN201310270606A CN104278680A CN 104278680 A CN104278680 A CN 104278680A CN 201310270606 A CN201310270606 A CN 201310270606A CN 104278680 A CN104278680 A CN 104278680A
Authority
CN
China
Prior art keywords
pile
piles
reinforcing cage
axle
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201310270606.2A
Other languages
Chinese (zh)
Inventor
谢晓东
周玉石
谢益飞
赵伟明
黄立伟
鲍国强
汤武
张群
施问知
邢克伦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai City Ground Ground Design Co Ltd
SHANGHAI CHENGDI CONSTRUCTION CO Ltd
Original Assignee
Shanghai City Ground Ground Design Co Ltd
SHANGHAI CHENGDI CONSTRUCTION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai City Ground Ground Design Co Ltd, SHANGHAI CHENGDI CONSTRUCTION CO Ltd filed Critical Shanghai City Ground Ground Design Co Ltd
Priority to CN201310270606.2A priority Critical patent/CN104278680A/en
Publication of CN104278680A publication Critical patent/CN104278680A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/18Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • E02D5/187Bulkheads or similar walls made solely of concrete in situ the bulkheads or walls being made continuously, e.g. excavating and constructing bulkheads or walls in the same process, without joints
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/36Concrete or concrete-like piles cast in position ; Apparatus for making same making without use of mouldpipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/46Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil

Abstract

The invention relates to an envelope structure combining mixing piles with grouting piles and a construction method. The mixing piles are constructed by adopting the five (six) shaft mixing pile technology, hereafter referred to as an FCW construction method. The grouting piles combined with the mixing piles are formed by inserting reinforcement cages after pressing and grouting concrete in long spiral drill holes. The characteristics of the FCW construction method are combined with the characteristics of the technology of inserting the reinforcement cages after pressing and grouting the concrete in the long spiral drill holes. The construction technology of the whole envelope structure has the advantages of being friendly to the environment, high in effect, low in cost, free of slurry pollution, small in soil-squeezing and effect on the environment and the like.

Description

The space enclosing structure that a kind of five (six) axle agitation piles combine with guncreting pile and construction method
Technical field
The present invention relates to a kind of continuous multi-shaft cement mixing wall and insert the space enclosing structure that combines of reinforcing cage castinplace pile (abbreviation guncreting pile) and construction method thereof with after long auger guncreting, be mainly used in civilian and industrial infrastructure construction build in bracing of foundation pit sealing and braced cuts.
Background technology
The concrete filling pile construction method of current routine has the castinplace pile etc. of the castinplace pile of dry operation pore-forming, the castinplace pile of mud off pore-forming, the castinplace pile of casing pipe hole forming and explosive expansion pore-forming
The construction process of bored concrete pile flow process of dry operation pore-forming: sediment → hole quality at the bottom of land clearing → surveying setting-out fixed pile → pile-forming machine perching → boring extracting soil pore-forming → cleaning hole is inspected for acceptance → install reinforcing cage → pouring hole inner concrete.
The castinplace pile of mud off pore-forming utilizes mud off, during boring by circulating mud by the native slag tap under bit cutting outer and pore-forming, then install reinforcing cage, underwater concreting and pile.
Casing pipe hole forming castinplace pile utilizes impact pile driving method or vibrosinking, and by with valve type pile shoe or sink in soil with the steel sleeve of precast concrete shoe, then limit is pulled out cover tube edge concrete perfusion and formed.If when being furnished with reinforcing bar, then before fluid concrete, first hang cage of reinforcement.Utilize hammer piling equipment immersed tube, tube drawing, be called hammer hidden pipe caisson pile; Utilize the vibration sinking tube of vibrator, tube drawing, be called vibrator pipe sinking cast-in-place pile.
Conventional construction process of bored concrete pile is all first put reinforcing cage usually, then concreting.There is waste concrete, environment pollution, shortcoming that cost is higher in current Concrete Grouting Pale, construction period aspect is also to be improved simultaneously, construction machinery intelligence degree is not high, is many times reinforcedly all experience according to field personnel and determines, and well can not carry out monitoring management.
Summary of the invention
Agitation pile involved in the present invention is novel five (six) axle Soil-cement Walls (hereinafter referred to as FCW engineering method), this engineering method uses novel intellectuality five (six) axle ram machine construction, once at most can pile five (six) root, without displacement soil, to some extent solve the deficiency of above-mentioned several agitation pile technique, have efficient, without the feature of displacement, intelligent, environmental protection.
The present invention is achieved through the following technical solutions:
The space enclosing structure that a kind of five (six) axle agitation piles combine with reinforcing cage castinplace pile slotting after long auger guncreting, five (six) described axle agitation piles adopt ground, cities five axle Soil-cement Wall construction technologies (hereinafter referred to as FCW engineering method); Castinplace pile inserts reinforcing cage castinplace pile after adopting long auger guncreting.
The construction method of described one five (six) axle Soil-cement Wall, its construction method comprises the following steps:
(1) setting-out, open channels, device is in place, and five (six) axle cement-soil mixing pile devices are moved to position to be onstructed;
(2) start backstage cement paste stirring system, then cement paste is delivered to slurry storage bucket;
(3) open integrated computer, allow computer control the data pre-set: every meter of decrease speed, every meter of whitewashing amount, stake end design elevation, total whitewashing amount and total mixing time;
(4) head that turns on the power drives Multifunctional drill, while stirring water-spray type slurry, rotates forward absolute altitude at the bottom of sinking whitewashing 70% to design wall.
(5) stir again in absolute altitude 0.5 ~ 1 meter of interval at the bottom of wall.
(6) brill is carried on reversion whitewashing limit, limit, and reversion whitewashing 30% to wall top mark is high;
(7) get final product pile one on the other, form gravity dam as required;
(8) one groups of constructions terminate, and move to second group and continue construction.
Insert reinforcing cage castinplace pile after described long auger guncreting, its construction method comprises the following steps:
(1) smooth location, the setting-out of stake position;
(2) Installation and Debugging rig, lays steel pile casting (as needs);
(3) debug concrete pump, pump line is installed;
(4) driller insertion;
(5) boring to projected depth stops creeping into;
(6) limit infusion Superfluid state concrete limit promotes drilling rod;
(7) propose drilling rod, remove drilling tool;
(8) reinforcing cage, vibrating hammer is lifted by crane;
(9) the lower slotting reinforcing cage of Vibration on Start-up hammer is to design elevation;
(10) Stake head handling;
(11) one groups of constructions terminate, and move to second group and continue construction.
Five (six) described axle agitation piles and the combining form of castinplace pile can be the form be arranged side by side or the form that both are connected in snap-in manner, also can be the forms that castinplace pile is embedded between many row's agitation piles.
The invention has the advantages that:
1, castinplace pile of the present invention bores under adopting auger stem and carries soil, and promote auger stem and pour into Superfluid state concrete by the hollow part of drilling rod simultaneously, more traditional construction technology, shortens the engineering time, and efficiency of construction is higher;
2, traditional handicraft whitewashing amount and drilling down and up, does not install flow instrument and depth sensing instrument, and construction is complete by rule of thumb.Existing equipment has installed corresponding computer sensing instrument, reaches requirement that is directly perceived, effective, automation, ensure that quality.
3, the present invention can one-step pore-creating, not only ensure that construction quality but also shorten the construction period;
4, in stake, arrangement of reinforcement adopts high tensile reinforcement, and horizontal direction anti-bending strength is also better, gives full play to high tensile reinforcement tension, both concrete anti-compressions advantage, more economical in cost.
5, agitation pile adopts novel five axle construction technology constructions, and increase than traditional handicraft pile quantity, efficiency of construction is significantly improved, and without displacement soil, pollution-free generation.
6, agitation pile adopts novel five axle construction technology constructions, and the cost of engineering water-stop curtain aspect can save about 20%.
7, agitation pile adopts novel five axle construction technologies constructions, and the plant equipment of employing contains Intellectualized monitoring equipment, and workmanship is guaranteed, and solving that cement in mixing pile construction technique uses cannot the shortcoming of accurate-metering.
Accompanying drawing explanation
Fig. 1 is that Superfluid state concrete post-set reinforcing cage castinplace pile and five axle agitation piles combine with campshed form;
Fig. 2 is that Superfluid state concrete post-set reinforcing cage castinplace pile is engaged mutually with five axle agitation piles;
Fig. 3 is that Superfluid state concrete post-set reinforcing cage castinplace pile is embedded in many rows five axle agitation piles;
Fig. 4 is the construction sequence chart of Superfluid state concrete post-set reinforcing cage castinplace pile;
Fig. 5 is that Superfluid state concrete post-set reinforcing cage castinplace pile and five axle agitation pile campsheds are constructed sequence.
Detailed description of the invention
Go along with sb. to guard him form below in conjunction with the drawings and specific embodiments to one of the present invention to be described in detail.The present embodiment is implemented premised on technical solution of the present invention, give detailed embodiment and concrete operating process, but protection scope of the present invention is not limited to following embodiment.
Embodiment:
As shown in Figure 3, a kind of adopt above-mentioned construction method to construct Superfluid state concrete post-set reinforcing cage castinplace pile and the vertical space enclosing structure of the combined campshed of five axle agitation piles, comprise multiple castinplace pile and agitation pile,
Described castinplace pile is Superfluid state concrete post-set reinforcing cage castinplace pile, the i.e. stake of A sequence, and its construction process is:
Smooth location → stake position setting-out → Installation and Debugging rig (installation steel pile casting) → debugging concrete pump, pump line → driller insertion → lifting reinforcing cage is installed, vibrating hammer → hole to projected depth stops creeping into → infusion Superfluid state concrete limit, limit promotes drilling rod → propositions drilling rod, removes drilling tool → Vibration on Start-up hammer into shape under slotting reinforcing cage to design elevation → pile → Stake head handling → stake top safeguard measure.
After A sequence pile driving construction completes, carry out the construction of B sequence stake, i.e. the construction of five axle agitation piles, adopt joint form, Specific construction flow process is as follows:
(1) setting-out; Open channels; Device is in place, and five axle Soil-cement Wall plant equipment are moved to position to be onstructed.
(2) start backstage automatic water mud stirring system, then cement paste is delivered to slurry storage bucket.
(3) open integrated computer, become wall critical data by computer monitoring; Every meter of decrease speed, hoisting velocity, every Rice & peanut milk amount, wall end design elevation, verticality, total whitewashing amount and total mixing time.Effective control quality of wall.
(4) head that turns on the power drives Multifunctional drill, while stirring water-spray type slurry, rotates forward absolute altitude at the bottom of sinking whitewashing 70% to design wall.
(5) stir again in absolute altitude 0.5 ~ 1 meter of interval at the bottom of wall.
(6) brill is carried on reversion whitewashing limit, limit, and reversion whitewashing 30% to wall top mark is high.
(7) one groups are terminated, and move on to second group and continue construction.

Claims (4)

1. (six) axle agitation piles and the space enclosing structure of inserting reinforcing cage castinplace pile after long auger guncreting and combining, it is characterized in that, five (six) described axle agitation piles adopt ground, city five axle Soil-cement Wall construction technologies (hereinafter referred to as FCW engineering method); Castinplace pile inserts reinforcing cage castinplace pile after adopting long auger guncreting.
2. the construction method of five (six) axle Soil-cement Walls according to claim 1, it is characterized in that, described construction method comprises the following steps:
(1) setting-out, open channels, device is in place, and five (six) axle cement-soil mixing pile devices are moved to position to be onstructed;
(2) start backstage cement paste stirring system, then cement paste is delivered to slurry storage bucket;
(3) open integrated computer, allow computer control the data pre-set: every meter of decrease speed, every meter of whitewashing amount, stake end design elevation, total whitewashing amount and total mixing time;
(4) head that turns on the power drives Multifunctional drill, while stirring water-spray type slurry, rotates forward absolute altitude at the bottom of sinking whitewashing 70% to design wall.
(5) stir again in absolute altitude 0.5 ~ 1 meter of interval at the bottom of wall.
(6) brill is carried on reversion whitewashing limit, limit, and reversion whitewashing 30% to wall top mark is high;
(7) get final product pile one on the other, form gravity dam as required;
(8) one groups of constructions terminate, and move to second group and continue construction.
3. insert reinforcing cage castinplace pile after long auger guncreting according to claim 1, it is characterized in that, described construction method comprises the following steps:
(1) smooth location, the setting-out of stake position;
(2) Installation and Debugging rig, lays steel pile casting (as needs);
(3) debug concrete pump, pump line is installed;
(4) driller insertion;
(5) boring to projected depth stops creeping into;
(6) limit infusion Superfluid state concrete limit promotes drilling rod;
(7) propose drilling rod, remove drilling tool;
(8) reinforcing cage, vibrating hammer is lifted by crane;
(9) the lower slotting reinforcing cage of Vibration on Start-up hammer is to design elevation;
(10) Stake head handling;
(11) one groups of constructions terminate, and move to second group and continue construction.
4. a kind of five (six) axle agitation piles according to claim 1 insert the space enclosing structure that combines of reinforcing cage castinplace pile with after long auger guncreting, it is characterized in that, five (six) described axle agitation piles and the combining form of castinplace pile can be the form be arranged side by side or the form that both are connected in snap-in manner, also can be the forms that castinplace pile is embedded between many row's agitation piles.
CN201310270606.2A 2013-07-01 2013-07-01 Envelope structure combining five (six) shaft mixing piles with press grouting piles and construction method Pending CN104278680A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310270606.2A CN104278680A (en) 2013-07-01 2013-07-01 Envelope structure combining five (six) shaft mixing piles with press grouting piles and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310270606.2A CN104278680A (en) 2013-07-01 2013-07-01 Envelope structure combining five (six) shaft mixing piles with press grouting piles and construction method

Publications (1)

Publication Number Publication Date
CN104278680A true CN104278680A (en) 2015-01-14

Family

ID=52253988

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310270606.2A Pending CN104278680A (en) 2013-07-01 2013-07-01 Envelope structure combining five (six) shaft mixing piles with press grouting piles and construction method

Country Status (1)

Country Link
CN (1) CN104278680A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105714832A (en) * 2016-02-29 2016-06-29 济南轨道交通集团有限公司 Deep-foundation-pit large-sized precast building envelope and construction method
CN109306700A (en) * 2018-11-09 2019-02-05 上海长凯岩土工程有限公司 Support water stop integration building enclosure and its construction method
CN110485413A (en) * 2019-07-31 2019-11-22 中国铁建港航局集团有限公司 One kind closing on subway overpass pile foundation combined type protection fast pore-creating method
CN113832960A (en) * 2021-09-30 2021-12-24 中国二十冶集团有限公司 Construction method of soft soil foundation bored pile

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2617821Y (en) * 2003-04-29 2004-05-26 天津市水利科学研究所 Deep jet stirred pile with rigid core
CN1676761A (en) * 2005-04-18 2005-10-05 祁春伟 Long-spiral post-joint-bar bored concrete pile construction method
CN101509254A (en) * 2009-03-09 2009-08-19 天津市建工工程总承包有限公司 Steel reinforced concrete filling pile and cement stirring pile meshing engagement type foundation pit support construction method
CN201459737U (en) * 2009-06-25 2010-05-12 南京林业大学 Foundation pit supporting structure
JP2011012443A (en) * 2009-07-01 2011-01-20 Ohbayashi Corp Construction method for soil cement structure and the soil cement structure
CN102535450A (en) * 2012-01-17 2012-07-04 上海城地建设发展有限公司 Five-axis cement-soil mixing pile device and construction method
CN102628266A (en) * 2011-12-30 2012-08-08 中铁二局股份有限公司 Construction method of long spiral cast-in-situ bored pile

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2617821Y (en) * 2003-04-29 2004-05-26 天津市水利科学研究所 Deep jet stirred pile with rigid core
CN1676761A (en) * 2005-04-18 2005-10-05 祁春伟 Long-spiral post-joint-bar bored concrete pile construction method
CN101509254A (en) * 2009-03-09 2009-08-19 天津市建工工程总承包有限公司 Steel reinforced concrete filling pile and cement stirring pile meshing engagement type foundation pit support construction method
CN201459737U (en) * 2009-06-25 2010-05-12 南京林业大学 Foundation pit supporting structure
JP2011012443A (en) * 2009-07-01 2011-01-20 Ohbayashi Corp Construction method for soil cement structure and the soil cement structure
CN102628266A (en) * 2011-12-30 2012-08-08 中铁二局股份有限公司 Construction method of long spiral cast-in-situ bored pile
CN102535450A (en) * 2012-01-17 2012-07-04 上海城地建设发展有限公司 Five-axis cement-soil mixing pile device and construction method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105714832A (en) * 2016-02-29 2016-06-29 济南轨道交通集团有限公司 Deep-foundation-pit large-sized precast building envelope and construction method
CN109306700A (en) * 2018-11-09 2019-02-05 上海长凯岩土工程有限公司 Support water stop integration building enclosure and its construction method
CN110485413A (en) * 2019-07-31 2019-11-22 中国铁建港航局集团有限公司 One kind closing on subway overpass pile foundation combined type protection fast pore-creating method
CN110485413B (en) * 2019-07-31 2021-01-05 中国铁建港航局集团有限公司 Combined type protection rapid hole forming method for pile foundation of viaduct adjacent to subway
CN113832960A (en) * 2021-09-30 2021-12-24 中国二十冶集团有限公司 Construction method of soft soil foundation bored pile

Similar Documents

Publication Publication Date Title
CN103924586B (en) Multi section drill grouting pile construction method
CN106400782B (en) A kind of construction method for going along with sb. to guard him hole-drilling interlocking pile using rotary drilling rig construction foundation pit
CN108360972A (en) A kind of rotary drilling rig is combined with percussive drill carries out bored pile construction method
CN104947690B (en) Grooving construction method for embedding underground continuous wall into rock
CN107524142A (en) A kind of holing with slurry wall protection cast-in-place pile construction method
CN101560767A (en) Method for connecting slotted sections in underground construction of diaphragm wall
CN102286984A (en) Water-stop curtain and construction method thereof
CN107059877A (en) Basis and its construction method of the bottom with chain knife during a kind of construction
CN104963346A (en) Support construction method for deep foundation pit in complex geological condition
CN107386285A (en) A kind of novel steel tube pile foundation rock borehole anchorage method
CN106930276A (en) The deep hole blasting of rotary digging bored concrete pile and the construction method of conduit rotary digging removing obstacles
CN104278680A (en) Envelope structure combining five (six) shaft mixing piles with press grouting piles and construction method
CN105649094B (en) A kind of deep water foundation bearing platform construction three wall steel cofferdams and its construction method
CN105155519A (en) Rotary-excavating under-reamed bored pile constructing method
CN201762702U (en) Drilling bitten pile
CN104278679A (en) Envelope structure combining five (six) shaft mixing piles with precast tubular piles and construction method
CN104250970A (en) Novel visual intelligent super-fluid cast-in-place concrete pile device and construction method
CN106592605A (en) Construction method of foundation pit bracing with tri-axial stirring piles overlapped with reinforced concrete cast-in-place piles to be driven
CN102409972B (en) Multi-bit convolution punching/tamping engineering groover
CN106930278A (en) A kind of method that compromise joint pipe is used for support pile occlusion
CN104563100A (en) Cement mixing pile later embedding press-grouting pile support structure and construction method
CN205444192U (en) Bridge stake is towards pile driving construction system
CN110306539A (en) A kind of pile base construction method using all steel cylinder-wall
CN109930624A (en) A kind of embedding petrographic province blower foundation of offshore wind farm and construction method
CN203487527U (en) Novel visual intelligent extra-liquid concrete cast-in-place pile device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20150114

WD01 Invention patent application deemed withdrawn after publication