The content of utility model
The purpose of this utility model is intended to overcome the problem that two cast-in-place concrete piles surpass after 20 hours, the interlock poor quality causes foundation ditch infiltration leakage mud and cast-in-place concrete pile to be wasted, thus the foundation pit supporting construction that provides a kind of cement mixing method and the mutual interlock of cast-in-place concrete pile, in-line to arrange.
The purpose of this utility model is to be achieved through the following technical solutions:
Can see the utility model---a kind of overall picture of foundation pit supporting construction substantially clearly from Fig. 1.A kind of foundation pit supporting construction, it is characterized in that it is by the cast-in-place concrete pile (2) of the cement mixing method (1) of the first sequence n1-n9 and the second sequence m1-m8 interlock and foundation pit supporting construction that the in-line that forms is arranged mutually, the radius R 1=0.3-0.4m of cement mixing method (1) wherein, pile spacing (4) S=0.6-0.8m, the radius R 2=0.5-0.6m of cast-in-place concrete pile (2), mutual interlock is apart from (3) L=0.2m between the cement mixing method of the first sequence n1-n9 (1) and the second sequence m1-m8 cast-in-place concrete pile (2), a long 6-8m that is of cement mixing method (1) and cast-in-place concrete pile (2).Realize that construction sequence of the present utility model is as follows:
1, the single shaft soil-cement stirring is moved on the 1st position of the first sequence cement mixing method 1, the code name of the 1st cement mixing method 1 is n
1, radius R
1, make the round center of the 1st cement mixing method 1 of central tube centrally aligned of single shaft soil-cement stirring;
2, one stir sinking, start the motor of single shaft soil-cement stirring, loosen wire rope, while the stirring-head of single shaft soil-cement stirring lower end stirs, when treating that stirring-head sinks down into the projected depth of cement mixing method 1, the single shaft soil-cement stirring is extracted into cement paste in the hopper;
3, two stir rising, the water spray mud while stirring, after stirring-head sinks down into the projected depth of cement mixing method 1, open single shaft soil-cement stirring pump for mortar transmission, from the spout of stirring-head cement paste is pressed into the soil, water spray mud limit, limit promotes the design stake top degree of depth of stirring-head to cement mixing method 1, and pressure 0.4-0.6MPa, hoisting velocity 0.8-1m/min, rod rotation speed 40-45 commentaries on classics/min are starched in sending of assurance single shaft soil-cement stirring, finish the 1st cement mixing method 1 of first sequence, code name n
1
4, the bearing of trend according to foundation pit supporting construction moves the single shaft soil-cement stirring, makes the round center of the 2nd cement mixing method 1 of central tube centrally aligned of single shaft soil-cement stirring, the code name n of the 2nd cement mixing method 1
2, radius R
1, and make 2 cement mixing methods, 1 spacing 4 be S=2R
2-2L, R
2Be the radius of several root cast-in-place concrete piles 1 of second sequence construction, L is the interlock distance 3 between the first sequence cement mixing method 1 and the second sequence cast-in-place concrete pile 2, L=0.2m;
5, repeating step 2,3, finish the 2nd cement mixing method 1 of first sequence, code name n
2
6, repeating step 4,2,3, finish cement mixing method 1 n of first sequence successively
3, n
4, n
5, n
6, n
7, n
8, n
9
7, after after the 1st cement mixing method 1 construction end of first sequence 48 hours, rotary drilling rig
8, rotary drilling rig cycle is poured over cubic metre of earth car or ground with the native sand material in the drill bit; Boring is finished, and carries out the clear hole first time; Put into reinforcing cage, carry out the clear hole second time; Concrete perfusion is finished the 1st cast-in-place concrete pile 2 of second sequence, code name m
1, radius R
2, the cast-in-place concrete pile 2 that guarantees the cement mixing method 1 of first sequence and second sequence has the interlock distance of L;
9, rotary drilling rig is moved on the position of the 2nd cast-in-place concrete pile 2 of second sequence, the rotary drilling rig drill bit lands gently, and rotation is spudded in, to the projected depth of cast-in-place concrete pile 2;
10, repeating step 8, finish the 2nd cast-in-place concrete pile 2 of second sequence, code name m
2, radius R
2, cast-in-place concrete pile 2 interlocks that guarantee the cement mixing method 1 of first sequence and second sequence are apart from L;
11, repeating step 9,10, under the prerequisite of the shortest 48-96 hour internal gearing, finish cast-in-place concrete pile 2 m of second sequence between the cast-in-place concrete pile 2 of the cement mixing method 1 that guarantees first sequence and second sequence
3, m
4, m
5, m
6, m
7, m
8
The utility model beneficial effect
1, do not need existing single shaft soil-cement stirring and rotary drilling rig are carried out technological improvement.
2, prolonged the engineering time of interlock, if between the cast-in-place concrete pile of the cement mixing method that guarantees first sequence and second sequence after the shortest 48 hours, under the prerequisite of 96 hours internal gearings of maximum, just can construct.
3, owing to prolonged the interlock engineering time, the rising of having avoided nature and artificial origin to cause the long foundation ditch infiltration that brings of construction dead time to leak mud and foundation pit supporting construction cost.
4, in the construction practice,, just can carry out the flowing water construction incessantly if construction is arranged rationally.
The specific embodiment
Embodiment 1
The dark 6m of Zhongshan Road, Nanjing, Jiangsu Province engineering basement foundation ditch, foundation ditch one length of side 10.2m.Ground, place is silty clay to below ground 4m, and 4m is following to be silt, and below ground 1.5m is a phreatic surface.For stoping the outer underground water and soil of foundation ditch to flow in the foundation ditch, guarantee foundation pit construction and foundation ditch surrounding building safety, need between foundation ditch and foundation pit side-wall, supporting and protection structure be set.Supporting and protection structure adopts the form of 9 cement mixing methods 1 and 8 cast-in-place concrete pile 2 interlocks, wherein cement mixing method 1 radius R
1=0.3m, cement mixing method 1 long H=6m, cast-in-place concrete pile 2 radius Rs
2=0.5m, cast-in-place concrete pile 2 long H=6m, interlock is apart from 3L=0.2m, and cement mixing method 1 spacing 4 is S=2R
2-2L=0.6m.At the bottom of the stake of cement mixing method 1 and cast-in-place concrete pile 2 was foundation ditch an end, the stake top was ground.1 cement mixing method 1 of constructing needs 8 hours, and 1 cast-in-place concrete pile 2 of constructing needs 9 hours, and the foundation pit supporting construction pattern construction sequence that then cement mixing method 1 and cast-in-place concrete pile 2 interlocks, in-line are arranged is as follows.
1, SJB-1 single shaft soil-cement stirring is moved on the 1st position of the first sequence cement mixing method 1 the code name n of the 1st cement mixing method 1
1, radius R
1=0.3m makes the round center of the 1st cement mixing method 1 of central tube centrally aligned of SJB-1 single shaft soil-cement stirring;
2, one stir sinking, start the motor of SJB-1 single shaft soil-cement stirring, loosen wire rope, the stirring-head of dual spindle soil-cement stirring lower end is while stirring, when treating that stirring-head sinks down into the 6m degree of depth of cement mixing method 1, SJB-1 single shaft soil-cement stirring is extracted into cement paste in the hopper;
3, two stir rising, the water spray mud while stirring, after stirring-head sinks down into cement mixing method 1 projected depth 6m, open the dual spindle soil-cement stirring pump for mortar transmission, from the spout of stirring-head cement paste is pressed into the soil, water spray mud limit, limit promotes stirring-head to ground, and pressure 0.4MPa, hoisting velocity 0.8m/min, rod rotation speed 45 commentaries on classics/min are starched in sending of assurance dual spindle soil-cement stirring, finish the 1st cement mixing method 1 of first sequence, code name n
1
4, the bearing of trend according to interlock stake supporting and protection structure moves SJB-1 single shaft soil-cement stirring, makes the round center of the 2nd cement mixing method 1 of central tube centrally aligned of SJB-1 single shaft soil-cement stirring, the code name n of the 2nd cement mixing method 1
2, radius R
1=0.3m, and make cement mixing method 1 spacing 4 be S=2R
2-2L=0.6m, R
2=0.5m is the radius of 8 cast-in-place concrete piles 1 of second sequence construction, and L is the interlock distance 3 between the first sequence cement mixing method 1 and the second sequence cast-in-place concrete pile 2, L=0.2m;
5, repeating step 2,3, finish the 2nd cement mixing method 1 of first sequence, code name n
2
6, repeating step 4,2,3, finish cement mixing method 1 n of first sequence successively
3, n
4, n
5, n
6, n
7, n
8, n
9
7, after the 6th cement mixing method 1 construction of first sequence finishes, the 1st cement mixing method 1 construction of first sequence finishes 48 hours, and the SLR-1 rotary drilling rig is moved to the 1st cast-in-place concrete pile 2 of second sequence, code name m
1The position on, SLR-1 rotary drilling rig drill bit lands gently, the rotation, spud in, to the projected depth of cast-in-place concrete pile 2, H=6m;
8, SLR-1 rotary drilling rig cycle is poured over cubic metre of earth car or ground with the native sand material in the drill bit; Boring is finished, and carries out the clear hole first time; Put into reinforcing cage, carry out the clear hole second time; Concrete perfusion is finished the 1st cast-in-place concrete pile 2 of second sequence, code name m
1, radius R
2=0.5m, the cast-in-place concrete pile 2 that guarantees the cement mixing method 1 of first sequence and second sequence has the interlock distance of L=0.2m;
9, the SLR-1 rotary drilling rig is moved on the position of the 2nd cast-in-place concrete pile 2 of second sequence, SLR-1 rotary drilling rig drill bit lands gently, and rotation is spudded in, to the projected depth of cast-in-place concrete pile 2, H=6m;
10, repeating step 8, finish the 1st cast-in-place concrete pile 2 of second sequence, code name m
2, radius R
2, cast-in-place concrete pile 2 interlocks that guarantee the cement mixing method 1 of first sequence and second sequence are apart from L=0.2m;
11, repeating step 9,10, between the cast-in-place concrete pile 2 of the cement mixing method 1 that guarantees first sequence and second sequence after the shortest 48 hours, under the prerequisite of 96 hours internal gearings of maximum, finish the cast-in-place concrete pile 2m of second sequence
3, m
4, m
5, m
6, m
7, m
8
Embodiment 2
The dark 8m of Nanjing, Jiangsu Province Changjiang Road engineering basement foundation ditch, foundation ditch one length of side 13.6m.Ground, place is clay to below ground 6m, and 4m is following to be silty clay, and below ground 1m is a phreatic surface.For stoping the outer underground water and soil of foundation ditch to flow in the foundation ditch, guarantee foundation pit construction and foundation ditch surrounding building safety, need between foundation ditch and foundation pit side-wall, supporting and protection structure be set.Supporting and protection structure adopts the form of 9 cement mixing methods 1 and 8 cast-in-place concrete pile 2 interlocks, wherein cement mixing method 1 radius R
1=0.4m, cement mixing method 1 long H=8m, cast-in-place concrete pile 2 radius Rs
2=0.6m, cast-in-place concrete pile 2 long H=8m, interlock is apart from 3L=0.2m, and cement mixing method 1 spacing 4 is S=2R
2-2L=0.8m.At the bottom of the stake of cement mixing method 1 and cast-in-place concrete pile 2 was foundation ditch an end, the stake top was ground.Because clay and silty clay hardness are little, 1 cement mixing method 1 of constructing needs 8 hours, 1 cast-in-place concrete pile 2 of constructing needs 9 hours, and the foundation pit supporting construction pattern construction sequence that then cement mixing method 1 and cast-in-place concrete pile 2 interlocks, in-line are arranged is as follows.
1, SJB-1 single shaft soil-cement stirring is moved on the 1st position of the first sequence cement mixing method 1 the code name n of the 1st cement mixing method 1
1, radius R
1=0.4m makes the round center of the 1st cement mixing method 1 of central tube centrally aligned of SJB-1 single shaft soil-cement stirring;
2, one stir sinking, start the motor of SJB-1 single shaft soil-cement stirring, loosen wire rope, the stirring-head of dual spindle soil-cement stirring lower end is while stirring, when treating that stirring-head sinks down into the 8m degree of depth of cement mixing method 1, SJB-1 single shaft soil-cement stirring is extracted into cement paste in the hopper;
3, two stir rising, the water spray mud while stirring, after stirring-head sinks down into cement mixing method 1 projected depth 8m, open the dual spindle soil-cement stirring pump for mortar transmission, from the spout of stirring-head cement paste is pressed into the soil, limit water spray mud limit promotes stirring-head till the ground, and what guarantee dual spindle soil-cement stirring send slurry pressure 0.5MPa, hoisting velocity 1m/min, rod rotation speed 40 commentaries on classics/min, finish the 1st cement mixing method 1 of first sequence, code name n
1
4, the bearing of trend according to interlock stake supporting and protection structure moves SJB-1 single shaft soil-cement stirring, makes the round center of the 2nd cement mixing method 1 of central tube centrally aligned of SJB-1 single shaft soil-cement stirring, the code name n of the 2nd cement mixing method 1
2, radius R
1=0.4m, and make cement mixing method 1 spacing 4 be S=2R
2-2L=0.8m, R
2=0.6m is the radius of 8 cast-in-place concrete piles 1 of second sequence construction, and L is the interlock distance 3 between the first sequence cement mixing method 1 and the second sequence cast-in-place concrete pile 2, L=0.2m;
5, repeating step 2,3, finish the 2nd cement mixing method 1 of first sequence, code name n
2
6, repeating step 4,2,3, finish the cement mixing method 1n of first sequence successively
3, n
4, n
5, n
6, n
7, n
8, n
9
7, after the 6th cement mixing method 1 construction of first sequence finishes, the 1st cement mixing method 1 construction of first sequence finishes 48 hours, and the SLR-1 rotary drilling rig is moved to the 1st cast-in-place concrete pile 2 of second sequence, code name m
1The position on, SLR-1 rotary drilling rig drill bit lands gently, the rotation, spud in, to projected depth 8m;
8, SLR-1 rotary drilling rig cycle is poured over cubic metre of earth car or ground with the native sand material in the drill bit; Boring is finished, and carries out the clear hole first time; Put into reinforcing cage, carry out the clear hole second time; Concrete perfusion is finished the 1st cast-in-place concrete pile 2 of second sequence, code name m
1, radius R
2=0.6m, the cast-in-place concrete pile 2 that guarantees the cement mixing method 1 of first sequence and second sequence has the interlock distance of L=0.2m;
9, the SLR-1 rotary drilling rig is moved on the position of the 2nd cast-in-place concrete pile 2 of second sequence, SLR-1 rotary drilling rig drill bit lands gently, and rotation is spudded in, to projected depth 8m;
10, repeating step 8, finish the 1st cast-in-place concrete pile 2 of second sequence, code name m
2, radius R
2=0.6m, cast-in-place concrete pile 2 interlocks that guarantee the cement mixing method 1 of first sequence and second sequence are apart from L=0.2m;
11, repeating step 9,10, between the cast-in-place concrete pile 2 of the cement mixing method 1 that guarantees first sequence and second sequence after the shortest 48 hours, under the prerequisite of 96 hours internal gearings of maximum, finish the cast-in-place concrete pile 2m of second sequence
3, m
4, m
5, m
6, m
7, m
8