CN201459737U - Foundation pit supporting structure - Google Patents

Foundation pit supporting structure Download PDF

Info

Publication number
CN201459737U
CN201459737U CN2009200427764U CN200920042776U CN201459737U CN 201459737 U CN201459737 U CN 201459737U CN 2009200427764 U CN2009200427764 U CN 2009200427764U CN 200920042776 U CN200920042776 U CN 200920042776U CN 201459737 U CN201459737 U CN 201459737U
Authority
CN
China
Prior art keywords
sequence
cast
mixing method
place concrete
cement mixing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2009200427764U
Other languages
Chinese (zh)
Inventor
杨平
程知言
邹宝祥
樊有维
嵇晓雷
胡光云
金雪莲
张婷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Huadong Engineering Design Co., Ltd.
Nanjing Forestry University
Original Assignee
JIANGSU HUADONG CONSTRUCTIONAL FUNDAMENT ENGINEERING Co Ltd
Nanjing Forestry University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU HUADONG CONSTRUCTIONAL FUNDAMENT ENGINEERING Co Ltd, Nanjing Forestry University filed Critical JIANGSU HUADONG CONSTRUCTIONAL FUNDAMENT ENGINEERING Co Ltd
Priority to CN2009200427764U priority Critical patent/CN201459737U/en
Application granted granted Critical
Publication of CN201459737U publication Critical patent/CN201459737U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a foundation pit supporting structure, which consists of soil cement stirring piles in a first sequence n1 to n9 and a concrete filling piles in a second sequence m1 to m9 which are mutually meshed and are arranged in a line, wherein the radius of each soil cement stirring pile is 0.3 to 0.4 meter and a pile interval S is 0.6 to 0.8 meter; the radius of each concrete filling pile is 0.5 to 0.6 meter; a meshing interval L between each soil cement stirring pile in the first sequence and the corresponding concrete filling pile in the second sequence is 0.2 meter; and the length of each pile is 6 to 8 meters. Compared with the conventional supporting structure, the foundation pit supporting structure of the utility model prolongs construction time for meshing, specifically, construction can be carried out on the premise that the soil cement stirring piles in the first sequence and the concrete filling piles in the second sequence are meshed within 48 to 96 hours, so that the problem of water leakage and soil cement leakage of foundation pits resulted from overlong construction pause time caused by natural causes and human errors is avoided, and construction cost is reduced.

Description

A kind of foundation pit supporting construction
Technical field
The utility model is the supporting and protection structure of foundation ditch, and specifically it is the foundation pit supporting construction of arranging with cement mixing method and the mutual interlock of cast-in-place concrete pile, in-line.
Background technology
For the smooth construction that guarantees foundation ditch and the safety of surrounding building, between foundation ditch and foundation pit side-wall, supporting and protection structure is set usually, foundation pit supporting construction has various ways, and the effect of foundation pit supporting construction is to stop the outer underground water and soil of foundation ditch to flow in the foundation ditch.Foundation pit supporting construction is a kind of temporary structure, and under the prerequisite that guarantees foundation ditch safety, the supporting and protection structure expense is the smaller the better.The interlock stake supporting and protection structure that in-line is arranged is a kind of economic foundation pit supporting construction form, because interlock stake supporting and protection structure can prevent the seepage flow of underground water to foundation ditch, can stop soil flowing in foundation ditch again.
Interlock stake supporting and protection structure adopts the snap-fit arrangement between the cast-in-place concrete pile usually, and its construction sequence is as follows: several root radiuses of first sequence of constructing at interval on the position between foundation ditch and the foundation pit side-wall are R 1Cast-in-place concrete pile, cast-in-place concrete pile interval S=2R 2-2L (R 2Be the radius of several root cast-in-place concrete piles of second sequence construction, L is the interlock distance between first sequence and the second sequence cast-in-place concrete pile); Construction second sequence, radius are R between the cast-in-place concrete pile of first sequence construction then 2Cast-in-place concrete pile, the interlock that guarantees to have between first sequence and the second sequence cast-in-place concrete pile L is apart from (L 〉=150mm).Because hardening of concrete speed is fast, in order to guarantee the interlock effect between the cast-in-place concrete pile, the engineering time interval of requirement between the first sequence cast-in-place concrete pile and the second sequence cast-in-place concrete pile is the longest can not be above 20 hours, otherwise the interlock effect is bad, cause the foundation ditch infiltration to leak mud, influence the foundation ditch safe construction.In engineering practice; regular meeting meets nature and the artificial origin causes two sequence concrete spouting pile driving construction dead times above 20 hours; not only influenced the interlock quality between the cast-in-place concrete pile; reduce antiseepage resistance mud effect; and can cause the waste of the first sequence cast-in-place concrete pile of having constructed, cause the rising of foundation pit supporting construction cost.
Therefore, needing to solve two cast-in-place concrete piles surpasses after 20 hours, because the rising that mud and foundation pit supporting construction cost are leaked in the foundation ditch that the interlock poor quality brings infiltration surpasses 20 hours, causes interlock poor quality's foundation pit supporting construction but present incapability still solves two cast-in-place concrete piles.
The content of utility model
The purpose of this utility model is intended to overcome the problem that two cast-in-place concrete piles surpass after 20 hours, the interlock poor quality causes foundation ditch infiltration leakage mud and cast-in-place concrete pile to be wasted, thus the foundation pit supporting construction that provides a kind of cement mixing method and the mutual interlock of cast-in-place concrete pile, in-line to arrange.
The purpose of this utility model is to be achieved through the following technical solutions:
Can see the utility model---a kind of overall picture of foundation pit supporting construction substantially clearly from Fig. 1.A kind of foundation pit supporting construction, it is characterized in that it is by the cast-in-place concrete pile (2) of the cement mixing method (1) of the first sequence n1-n9 and the second sequence m1-m8 interlock and foundation pit supporting construction that the in-line that forms is arranged mutually, the radius R 1=0.3-0.4m of cement mixing method (1) wherein, pile spacing (4) S=0.6-0.8m, the radius R 2=0.5-0.6m of cast-in-place concrete pile (2), mutual interlock is apart from (3) L=0.2m between the cement mixing method of the first sequence n1-n9 (1) and the second sequence m1-m8 cast-in-place concrete pile (2), a long 6-8m that is of cement mixing method (1) and cast-in-place concrete pile (2).Realize that construction sequence of the present utility model is as follows:
1, the single shaft soil-cement stirring is moved on the 1st position of the first sequence cement mixing method 1, the code name of the 1st cement mixing method 1 is n 1, radius R 1, make the round center of the 1st cement mixing method 1 of central tube centrally aligned of single shaft soil-cement stirring;
2, one stir sinking, start the motor of single shaft soil-cement stirring, loosen wire rope, while the stirring-head of single shaft soil-cement stirring lower end stirs, when treating that stirring-head sinks down into the projected depth of cement mixing method 1, the single shaft soil-cement stirring is extracted into cement paste in the hopper;
3, two stir rising, the water spray mud while stirring, after stirring-head sinks down into the projected depth of cement mixing method 1, open single shaft soil-cement stirring pump for mortar transmission, from the spout of stirring-head cement paste is pressed into the soil, water spray mud limit, limit promotes the design stake top degree of depth of stirring-head to cement mixing method 1, and pressure 0.4-0.6MPa, hoisting velocity 0.8-1m/min, rod rotation speed 40-45 commentaries on classics/min are starched in sending of assurance single shaft soil-cement stirring, finish the 1st cement mixing method 1 of first sequence, code name n 1
4, the bearing of trend according to foundation pit supporting construction moves the single shaft soil-cement stirring, makes the round center of the 2nd cement mixing method 1 of central tube centrally aligned of single shaft soil-cement stirring, the code name n of the 2nd cement mixing method 1 2, radius R 1, and make 2 cement mixing methods, 1 spacing 4 be S=2R 2-2L, R 2Be the radius of several root cast-in-place concrete piles 1 of second sequence construction, L is the interlock distance 3 between the first sequence cement mixing method 1 and the second sequence cast-in-place concrete pile 2, L=0.2m;
5, repeating step 2,3, finish the 2nd cement mixing method 1 of first sequence, code name n 2
6, repeating step 4,2,3, finish cement mixing method 1 n of first sequence successively 3, n 4, n 5, n 6, n 7, n 8, n 9
7, after after the 1st cement mixing method 1 construction end of first sequence 48 hours, rotary drilling rig
8, rotary drilling rig cycle is poured over cubic metre of earth car or ground with the native sand material in the drill bit; Boring is finished, and carries out the clear hole first time; Put into reinforcing cage, carry out the clear hole second time; Concrete perfusion is finished the 1st cast-in-place concrete pile 2 of second sequence, code name m 1, radius R 2, the cast-in-place concrete pile 2 that guarantees the cement mixing method 1 of first sequence and second sequence has the interlock distance of L;
9, rotary drilling rig is moved on the position of the 2nd cast-in-place concrete pile 2 of second sequence, the rotary drilling rig drill bit lands gently, and rotation is spudded in, to the projected depth of cast-in-place concrete pile 2;
10, repeating step 8, finish the 2nd cast-in-place concrete pile 2 of second sequence, code name m 2, radius R 2, cast-in-place concrete pile 2 interlocks that guarantee the cement mixing method 1 of first sequence and second sequence are apart from L;
11, repeating step 9,10, under the prerequisite of the shortest 48-96 hour internal gearing, finish cast-in-place concrete pile 2 m of second sequence between the cast-in-place concrete pile 2 of the cement mixing method 1 that guarantees first sequence and second sequence 3, m 4, m 5, m 6, m 7, m 8
The utility model beneficial effect
1, do not need existing single shaft soil-cement stirring and rotary drilling rig are carried out technological improvement.
2, prolonged the engineering time of interlock, if between the cast-in-place concrete pile of the cement mixing method that guarantees first sequence and second sequence after the shortest 48 hours, under the prerequisite of 96 hours internal gearings of maximum, just can construct.
3, owing to prolonged the interlock engineering time, the rising of having avoided nature and artificial origin to cause the long foundation ditch infiltration that brings of construction dead time to leak mud and foundation pit supporting construction cost.
4, in the construction practice,, just can carry out the flowing water construction incessantly if construction is arranged rationally.
Description of drawings
Fig. 1 is the floor map of the foundation pit supporting construction arranged of in-line that the mutual interlock of single shaft cement mixing method and cast-in-place concrete pile constitutes.
Reference numeral: 1-single shaft cement mixing method; The 2-cast-in-place concrete pile; 3-interlock distance; 4-cement mixing method spacing; N1-n9 is the cement mixing method of first sequence, and m1-m8 is the cast-in-place concrete pile of second sequence, and L-is the interlock distance, the pilespacing of S-cement mixing method.
The specific embodiment
Embodiment 1
The dark 6m of Zhongshan Road, Nanjing, Jiangsu Province engineering basement foundation ditch, foundation ditch one length of side 10.2m.Ground, place is silty clay to below ground 4m, and 4m is following to be silt, and below ground 1.5m is a phreatic surface.For stoping the outer underground water and soil of foundation ditch to flow in the foundation ditch, guarantee foundation pit construction and foundation ditch surrounding building safety, need between foundation ditch and foundation pit side-wall, supporting and protection structure be set.Supporting and protection structure adopts the form of 9 cement mixing methods 1 and 8 cast-in-place concrete pile 2 interlocks, wherein cement mixing method 1 radius R 1=0.3m, cement mixing method 1 long H=6m, cast-in-place concrete pile 2 radius Rs 2=0.5m, cast-in-place concrete pile 2 long H=6m, interlock is apart from 3L=0.2m, and cement mixing method 1 spacing 4 is S=2R 2-2L=0.6m.At the bottom of the stake of cement mixing method 1 and cast-in-place concrete pile 2 was foundation ditch an end, the stake top was ground.1 cement mixing method 1 of constructing needs 8 hours, and 1 cast-in-place concrete pile 2 of constructing needs 9 hours, and the foundation pit supporting construction pattern construction sequence that then cement mixing method 1 and cast-in-place concrete pile 2 interlocks, in-line are arranged is as follows.
1, SJB-1 single shaft soil-cement stirring is moved on the 1st position of the first sequence cement mixing method 1 the code name n of the 1st cement mixing method 1 1, radius R 1=0.3m makes the round center of the 1st cement mixing method 1 of central tube centrally aligned of SJB-1 single shaft soil-cement stirring;
2, one stir sinking, start the motor of SJB-1 single shaft soil-cement stirring, loosen wire rope, the stirring-head of dual spindle soil-cement stirring lower end is while stirring, when treating that stirring-head sinks down into the 6m degree of depth of cement mixing method 1, SJB-1 single shaft soil-cement stirring is extracted into cement paste in the hopper;
3, two stir rising, the water spray mud while stirring, after stirring-head sinks down into cement mixing method 1 projected depth 6m, open the dual spindle soil-cement stirring pump for mortar transmission, from the spout of stirring-head cement paste is pressed into the soil, water spray mud limit, limit promotes stirring-head to ground, and pressure 0.4MPa, hoisting velocity 0.8m/min, rod rotation speed 45 commentaries on classics/min are starched in sending of assurance dual spindle soil-cement stirring, finish the 1st cement mixing method 1 of first sequence, code name n 1
4, the bearing of trend according to interlock stake supporting and protection structure moves SJB-1 single shaft soil-cement stirring, makes the round center of the 2nd cement mixing method 1 of central tube centrally aligned of SJB-1 single shaft soil-cement stirring, the code name n of the 2nd cement mixing method 1 2, radius R 1=0.3m, and make cement mixing method 1 spacing 4 be S=2R 2-2L=0.6m, R 2=0.5m is the radius of 8 cast-in-place concrete piles 1 of second sequence construction, and L is the interlock distance 3 between the first sequence cement mixing method 1 and the second sequence cast-in-place concrete pile 2, L=0.2m;
5, repeating step 2,3, finish the 2nd cement mixing method 1 of first sequence, code name n 2
6, repeating step 4,2,3, finish cement mixing method 1 n of first sequence successively 3, n 4, n 5, n 6, n 7, n 8, n 9
7, after the 6th cement mixing method 1 construction of first sequence finishes, the 1st cement mixing method 1 construction of first sequence finishes 48 hours, and the SLR-1 rotary drilling rig is moved to the 1st cast-in-place concrete pile 2 of second sequence, code name m 1The position on, SLR-1 rotary drilling rig drill bit lands gently, the rotation, spud in, to the projected depth of cast-in-place concrete pile 2, H=6m;
8, SLR-1 rotary drilling rig cycle is poured over cubic metre of earth car or ground with the native sand material in the drill bit; Boring is finished, and carries out the clear hole first time; Put into reinforcing cage, carry out the clear hole second time; Concrete perfusion is finished the 1st cast-in-place concrete pile 2 of second sequence, code name m 1, radius R 2=0.5m, the cast-in-place concrete pile 2 that guarantees the cement mixing method 1 of first sequence and second sequence has the interlock distance of L=0.2m;
9, the SLR-1 rotary drilling rig is moved on the position of the 2nd cast-in-place concrete pile 2 of second sequence, SLR-1 rotary drilling rig drill bit lands gently, and rotation is spudded in, to the projected depth of cast-in-place concrete pile 2, H=6m;
10, repeating step 8, finish the 1st cast-in-place concrete pile 2 of second sequence, code name m 2, radius R 2, cast-in-place concrete pile 2 interlocks that guarantee the cement mixing method 1 of first sequence and second sequence are apart from L=0.2m;
11, repeating step 9,10, between the cast-in-place concrete pile 2 of the cement mixing method 1 that guarantees first sequence and second sequence after the shortest 48 hours, under the prerequisite of 96 hours internal gearings of maximum, finish the cast-in-place concrete pile 2m of second sequence 3, m 4, m 5, m 6, m 7, m 8
Embodiment 2
The dark 8m of Nanjing, Jiangsu Province Changjiang Road engineering basement foundation ditch, foundation ditch one length of side 13.6m.Ground, place is clay to below ground 6m, and 4m is following to be silty clay, and below ground 1m is a phreatic surface.For stoping the outer underground water and soil of foundation ditch to flow in the foundation ditch, guarantee foundation pit construction and foundation ditch surrounding building safety, need between foundation ditch and foundation pit side-wall, supporting and protection structure be set.Supporting and protection structure adopts the form of 9 cement mixing methods 1 and 8 cast-in-place concrete pile 2 interlocks, wherein cement mixing method 1 radius R 1=0.4m, cement mixing method 1 long H=8m, cast-in-place concrete pile 2 radius Rs 2=0.6m, cast-in-place concrete pile 2 long H=8m, interlock is apart from 3L=0.2m, and cement mixing method 1 spacing 4 is S=2R 2-2L=0.8m.At the bottom of the stake of cement mixing method 1 and cast-in-place concrete pile 2 was foundation ditch an end, the stake top was ground.Because clay and silty clay hardness are little, 1 cement mixing method 1 of constructing needs 8 hours, 1 cast-in-place concrete pile 2 of constructing needs 9 hours, and the foundation pit supporting construction pattern construction sequence that then cement mixing method 1 and cast-in-place concrete pile 2 interlocks, in-line are arranged is as follows.
1, SJB-1 single shaft soil-cement stirring is moved on the 1st position of the first sequence cement mixing method 1 the code name n of the 1st cement mixing method 1 1, radius R 1=0.4m makes the round center of the 1st cement mixing method 1 of central tube centrally aligned of SJB-1 single shaft soil-cement stirring;
2, one stir sinking, start the motor of SJB-1 single shaft soil-cement stirring, loosen wire rope, the stirring-head of dual spindle soil-cement stirring lower end is while stirring, when treating that stirring-head sinks down into the 8m degree of depth of cement mixing method 1, SJB-1 single shaft soil-cement stirring is extracted into cement paste in the hopper;
3, two stir rising, the water spray mud while stirring, after stirring-head sinks down into cement mixing method 1 projected depth 8m, open the dual spindle soil-cement stirring pump for mortar transmission, from the spout of stirring-head cement paste is pressed into the soil, limit water spray mud limit promotes stirring-head till the ground, and what guarantee dual spindle soil-cement stirring send slurry pressure 0.5MPa, hoisting velocity 1m/min, rod rotation speed 40 commentaries on classics/min, finish the 1st cement mixing method 1 of first sequence, code name n 1
4, the bearing of trend according to interlock stake supporting and protection structure moves SJB-1 single shaft soil-cement stirring, makes the round center of the 2nd cement mixing method 1 of central tube centrally aligned of SJB-1 single shaft soil-cement stirring, the code name n of the 2nd cement mixing method 1 2, radius R 1=0.4m, and make cement mixing method 1 spacing 4 be S=2R 2-2L=0.8m, R 2=0.6m is the radius of 8 cast-in-place concrete piles 1 of second sequence construction, and L is the interlock distance 3 between the first sequence cement mixing method 1 and the second sequence cast-in-place concrete pile 2, L=0.2m;
5, repeating step 2,3, finish the 2nd cement mixing method 1 of first sequence, code name n 2
6, repeating step 4,2,3, finish the cement mixing method 1n of first sequence successively 3, n 4, n 5, n 6, n 7, n 8, n 9
7, after the 6th cement mixing method 1 construction of first sequence finishes, the 1st cement mixing method 1 construction of first sequence finishes 48 hours, and the SLR-1 rotary drilling rig is moved to the 1st cast-in-place concrete pile 2 of second sequence, code name m 1The position on, SLR-1 rotary drilling rig drill bit lands gently, the rotation, spud in, to projected depth 8m;
8, SLR-1 rotary drilling rig cycle is poured over cubic metre of earth car or ground with the native sand material in the drill bit; Boring is finished, and carries out the clear hole first time; Put into reinforcing cage, carry out the clear hole second time; Concrete perfusion is finished the 1st cast-in-place concrete pile 2 of second sequence, code name m 1, radius R 2=0.6m, the cast-in-place concrete pile 2 that guarantees the cement mixing method 1 of first sequence and second sequence has the interlock distance of L=0.2m;
9, the SLR-1 rotary drilling rig is moved on the position of the 2nd cast-in-place concrete pile 2 of second sequence, SLR-1 rotary drilling rig drill bit lands gently, and rotation is spudded in, to projected depth 8m;
10, repeating step 8, finish the 1st cast-in-place concrete pile 2 of second sequence, code name m 2, radius R 2=0.6m, cast-in-place concrete pile 2 interlocks that guarantee the cement mixing method 1 of first sequence and second sequence are apart from L=0.2m;
11, repeating step 9,10, between the cast-in-place concrete pile 2 of the cement mixing method 1 that guarantees first sequence and second sequence after the shortest 48 hours, under the prerequisite of 96 hours internal gearings of maximum, finish the cast-in-place concrete pile 2m of second sequence 3, m 4, m 5, m 6, m 7, m 8

Claims (1)

1. foundation pit supporting construction, it is characterized in that it is by the cast-in-place concrete pile (2) of the cement mixing method (1) of the first sequence n1-n9 and the second sequence m1-m8 interlock and foundation pit supporting construction that the in-line that forms is arranged mutually, the radius R 1=0.3-0.4m of cement mixing method (1) wherein, pile spacing (4) S=0.6-0.8m, the radius R 2=0.5-0.6m of cast-in-place concrete pile (2), mutual interlock is apart from (3) L=0.2m between the cement mixing method of the first sequence n1-n9 (1) and the second sequence m1-m8 cast-in-place concrete pile (2), a long 6-8m that is of cement mixing method (1) and cast-in-place concrete pile (2).
CN2009200427764U 2009-06-25 2009-06-25 Foundation pit supporting structure Expired - Lifetime CN201459737U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009200427764U CN201459737U (en) 2009-06-25 2009-06-25 Foundation pit supporting structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009200427764U CN201459737U (en) 2009-06-25 2009-06-25 Foundation pit supporting structure

Publications (1)

Publication Number Publication Date
CN201459737U true CN201459737U (en) 2010-05-12

Family

ID=42387090

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009200427764U Expired - Lifetime CN201459737U (en) 2009-06-25 2009-06-25 Foundation pit supporting structure

Country Status (1)

Country Link
CN (1) CN201459737U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103882870A (en) * 2014-03-24 2014-06-25 上海强劲地基工程股份有限公司 Cement mixing pile and concrete pile meshing supporting structure and construction method
CN104278680A (en) * 2013-07-01 2015-01-14 上海城地建设股份有限公司 Envelope structure combining five (six) shaft mixing piles with press grouting piles and construction method
CN104278679A (en) * 2013-07-01 2015-01-14 上海城地建设股份有限公司 Envelope structure combining five (six) shaft mixing piles with precast tubular piles and construction method
CN104480947A (en) * 2014-11-24 2015-04-01 江西中恒岩土工程技术有限公司 Construction method of prestress cast-in-place pile and soil cement pile engagement support
CN104563095A (en) * 2014-12-18 2015-04-29 上海建工二建集团有限公司 Novel enclosure system of soft-hard occlusion piles and construction method
CN104594359A (en) * 2014-11-24 2015-05-06 江西中恒岩土工程技术有限公司 Multi-row structural steel lap joint supporting construction method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104278680A (en) * 2013-07-01 2015-01-14 上海城地建设股份有限公司 Envelope structure combining five (six) shaft mixing piles with press grouting piles and construction method
CN104278679A (en) * 2013-07-01 2015-01-14 上海城地建设股份有限公司 Envelope structure combining five (six) shaft mixing piles with precast tubular piles and construction method
CN103882870A (en) * 2014-03-24 2014-06-25 上海强劲地基工程股份有限公司 Cement mixing pile and concrete pile meshing supporting structure and construction method
CN104480947A (en) * 2014-11-24 2015-04-01 江西中恒岩土工程技术有限公司 Construction method of prestress cast-in-place pile and soil cement pile engagement support
CN104594359A (en) * 2014-11-24 2015-05-06 江西中恒岩土工程技术有限公司 Multi-row structural steel lap joint supporting construction method
CN104563095A (en) * 2014-12-18 2015-04-29 上海建工二建集团有限公司 Novel enclosure system of soft-hard occlusion piles and construction method

Similar Documents

Publication Publication Date Title
CN101591914B (en) Construction method for foundation pit supporting structure occluded by filling piles and stirring piles
CN1193141C (en) Combined grouting construction process of reinforcing foundation
CN201459737U (en) Foundation pit supporting structure
CN110924383A (en) Construction method of pressurized cast-in-place pile based on reinforced fibers and metakaolin
CN102286984A (en) Water-stop curtain and construction method thereof
CN104612179B (en) Through the construction method of the diaphram wall of super thick silty sand ground
CN101205721A (en) Method for surrounding water by combination of steel cofferdam and heavy-pressure rotary-spraying pile in deep-water low-pile cap construction
CN100510281C (en) Semi-inverse construction method of super large diameter, ultra-burial depth storage pond
CN107513994A (en) One kind segmentation becomes supporting rotary digging stake and its construction method without leave
CN101812843A (en) Centre grouted poured post-grouting pile construction methods, and grouter and grout injector used thereby
CN102628267A (en) Casing-less, long-spiral concrete secant pile construction method
CN202194149U (en) Water-proof curtain
CN103806433A (en) Foundation backfill reinforcement method
CN106812149A (en) A kind of construction method of pile foundation
CN102011591A (en) Grouting process for working surface of deep well
CN107268608A (en) Building waste earth-boring stake forming hole method
CN104314071A (en) Construction method of underground diaphragm wall by employing rotary drilling rig
CN201762702U (en) Drilling bitten pile
CN104988914A (en) Cast-in-situ bored pile breakage processing method under water area environment
CN105484277A (en) Component for tubular well precipitation construction in elevator foundation pit or sump and construction method
CN102235008B (en) Engineering pile deviation preventing structure of soft soil foundation and pretreatment method
CN105525605A (en) Basement backfill area reinforcing method
CN204608773U (en) Pile work drilling machine coordinated type breast wall apparatus
CN113445516A (en) Drilling and pouring type cement soil pile and construction method thereof
CN101481913A (en) Construction method of rock-socketed underground continuous wall punching slot section

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: JIANGSU EAST CHINA ENGINEERING DESIGN CO., LTD.

Free format text: FORMER OWNER: JIANGSU HUADONG CONSTRUCTIONAL FUNDAMENT ENGINEERING CO., LTD.

Effective date: 20130407

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20130407

Address after: Longpan road Xuanwu District of Nanjing city Jiangsu province 210037 Xinzhuang No. 9

Patentee after: Nanjing Forestry University

Patentee after: Jiangsu Huadong Engineering Design Co., Ltd.

Address before: Nanjing City, Jiangsu province 210037 Longpan Road No. 159

Patentee before: Nanjing Forestry University

Patentee before: Jiangsu Huadong Constructional Fundament Engineering Co., Ltd.

CX01 Expiry of patent term

Granted publication date: 20100512

CX01 Expiry of patent term