CN104264635A - Construction technology of slag stacking behind concrete faced rock-fill dam - Google Patents

Construction technology of slag stacking behind concrete faced rock-fill dam Download PDF

Info

Publication number
CN104264635A
CN104264635A CN201410485510.2A CN201410485510A CN104264635A CN 104264635 A CN104264635 A CN 104264635A CN 201410485510 A CN201410485510 A CN 201410485510A CN 104264635 A CN104264635 A CN 104264635A
Authority
CN
China
Prior art keywords
dam
slag
behind
drainage
excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410485510.2A
Other languages
Chinese (zh)
Inventor
赵兵
曲景涛
唐国峰
宋德强
何平
徐智桓
夏辉
金辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHINA WATER NORTHEASTERN INVESTIGATION DESIGN AND RESEARCH Co Ltd
Mudanjiang Heilungkiang Pumped Storage Co Ltd
State Grid Xinyuan Group Co Ltd
State Grid Corp of China SGCC
Original Assignee
CHINA WATER NORTHEASTERN INVESTIGATION DESIGN AND RESEARCH Co Ltd
Mudanjiang Heilungkiang Pumped Storage Co Ltd
State Grid Xinyuan Group Co Ltd
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHINA WATER NORTHEASTERN INVESTIGATION DESIGN AND RESEARCH Co Ltd, Mudanjiang Heilungkiang Pumped Storage Co Ltd, State Grid Xinyuan Group Co Ltd, State Grid Corp of China SGCC filed Critical CHINA WATER NORTHEASTERN INVESTIGATION DESIGN AND RESEARCH Co Ltd
Priority to CN201410485510.2A priority Critical patent/CN104264635A/en
Publication of CN104264635A publication Critical patent/CN104264635A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/02Fixed barrages
    • E02B7/04Dams across valleys
    • E02B7/06Earth-fill dams; Rock-fill dams

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Revetment (AREA)

Abstract

面板堆石坝坝后堆渣施工技术,涉及水电水利工程技术领域。它是将弃渣区域设在面板堆石坝后,主要堆放主坝坝基、护岸开挖、石料场开挖的弃渣,以及临时工程开挖的弃渣,弃渣区域顶部及边坡设绿化水保措施,适当高程设马道,坝后堆渣体内设排水棱体及排水廊道,用以排出堆渣体内的渗水和作为主坝的排水通道。渣场布置在坝后,堆渣体直接压覆在下游坝面上,可减少渣场及其连接道路的征地和移民;临近工程开挖区,减少了弃渣运距;可部分利用主坝的排水及其防护措施,减少了渣场工程防护量;堆渣体可作为坝脚压重,增加了坝体的稳定性,尤其是抗震稳定;主坝坝后渣场结构既经济又环保,可广泛用于水电水利工程堆石坝建设。

The slag stacking construction technology behind the face rockfill dam relates to the technical field of hydropower and water conservancy engineering. It sets the spoil area behind the concrete face rockfill dam, and mainly stacks spoils from the main dam foundation, revetment excavation, stone yard excavation, and temporary engineering excavation. The top and side slopes of the spoil area are greened For soil and water conservation measures, set up horse tracks at appropriate elevations, and set drainage prisms and drainage corridors in the slag body behind the dam to discharge seepage water in the slag body and serve as a drainage channel for the main dam. The slag yard is arranged behind the dam, and the slag pile is directly pressed on the downstream dam surface, which can reduce the land acquisition and resettlement of the slag yard and its connecting roads; it is close to the excavation area of the project, which reduces the slag transportation distance; part of the main dam can be used The drainage and protective measures of the slag yard reduce the protection of the slag yard; the slag pile can be used as the weight of the dam foot, which increases the stability of the dam body, especially the anti-seismic stability; the slag yard structure behind the main dam is economical and environmentally friendly. It can be widely used in the construction of rockfill dams in hydropower and water conservancy projects.

Description

面板堆石坝坝后堆渣施工技术Construction technology of slag pile behind face rockfill dam

技术领域 technical field

 本发明涉及水电水利工程技术领域,具体涉及面板坝坝后堆渣施工技术。 The invention relates to the technical field of hydropower and water conservancy engineering, in particular to the slag stacking construction technology behind a face dam.

背景技术 Background technique

面板堆石坝建设的主要优势是充分利用当地材料,施工简单,能够合理利用开挖料,减少弃渣,节省占地及投资,同时环保效果好。但不是所有的开挖渣料都能作为坝体填筑料,腐殖土含有的有机成份不稳定,物理力学性能较差;一般强风化中部以上岩体由于风化严重,强度低,物理力学指标差,破碎不能上坝而被弃置,这些弃料都需要弃渣区域容纳。一般工程通常会选择一些天然沟谷作为渣场,这样就带来了弃渣区域及其连接道路的征地移民、弃渣运距较远及水土保持、环境保护等一系列问题,同时天然沟谷一般坡高、沟陡、汇水量大,使得渣场防护工程量较大,既不经济又不环保。 The main advantages of the construction of face rockfill dams are the full use of local materials, simple construction, reasonable use of excavated materials, reduction of spoils, savings in land occupation and investment, and good environmental protection effects. However, not all excavation slag can be used as dam filling materials. The organic components contained in humus soil are unstable, and the physical and mechanical properties are poor; generally, due to severe weathering, the rock mass above the middle part has low strength and physical and mechanical indicators. If it is broken, it cannot go to the dam and is discarded. These waste materials need to be accommodated in the waste slag area. Generally, some natural valleys are selected as slag dumps in general engineering, which brings a series of problems such as land acquisition and resettlement in the spoil area and its connecting roads, long distance of spoil transportation, water and soil conservation, and environmental protection. High, steep ditches, and large water catchment volumes make the slag field protection work a lot, which is neither economical nor environmentally friendly.

发明内容 Contents of the invention

本发明所要解决的技术问题是:针对上述问题,通过面板堆石坝坝后堆渣技术,充分利用坝后空间堆放弃渣,提供一种可减少弃渣区域及其连接道路的征地和移民,减少渣场防护工程量以及弃渣运距,同时增加坝体稳定、美化坝区环境,既经济又环保的坝后渣场结构。 The technical problem to be solved by the present invention is: in view of the above problems, through the slag stacking technology behind the face rockfill dam, make full use of the space behind the dam to pile up the slag, provide a land acquisition and resettlement that can reduce the slag area and its connecting roads, Reduce the amount of slag field protection works and waste slag transportation distance, increase the stability of the dam body, beautify the environment of the dam area, and create an economical and environmentally friendly slag field structure behind the dam.

本发明的技术解决方案是:面板堆石坝坝后堆渣施工技术,它是将弃渣区域设在面板堆石坝后,主要堆放主坝坝基、护岸开挖、石料场开挖的弃渣,以及临时工程开挖的弃渣,弃渣区域顶部及边坡设绿化水保措施,适当高程设马道,坝后堆渣体内设排水棱体及排水廊道,用以排出堆渣体内的渗水和做为主坝的排水通道。 The technical solution of the present invention is: the slag stacking construction technology behind the face rockfill dam, which is to set the spoil area behind the face rockfill dam, and mainly pile up the spoil of the main dam foundation, bank revetment excavation, and stone yard excavation , as well as the spoil excavated by the temporary project, greening and water conservation measures shall be set up on the top and side slope of the spoil area, horse roads shall be set at appropriate elevations, and drainage prisms and drainage corridors shall be set in the slag dump behind the dam to discharge seepage in the slag dump and as a drainage channel for the main dam.

本发明的技术效果是:1、渣场布置在坝后,堆渣体直接压覆在下游坝面上,可减少渣场及其连接道路的征地和移民;2、临近工程开挖区,减少了弃渣运距;3、可部分利用主坝的排水及其防护措施,减少了渣场工程防护量;4、堆渣体可作为坝脚压重,增加了坝体的稳定性,尤其是抗震稳定;5、渣场顶面及下游坡面覆土绿化美化了坝区环境,增加广场等游乐设施,有利后期旅游产业的发展;6、主坝坝后渣场结构既经济又环保,可广泛用于水电水利工程堆石坝建设。 The technical effects of the present invention are: 1. The slag field is arranged behind the dam, and the slag body is directly pressed on the downstream dam surface, which can reduce the land acquisition and resettlement of the slag field and its connecting roads; 2. It is close to the excavation area of the project, reducing 3. The drainage of the main dam and its protection measures can be partially utilized, which reduces the protection amount of the slag field project; 4. The slag body can be used as the weight of the dam foot, which increases the stability of the dam body, especially Seismic and stable; 5. The top surface of the slag yard and the downstream slope are greened to beautify the environment of the dam area, adding recreational facilities such as squares, which is conducive to the development of the tourism industry in the later stage; 6. The structure of the slag yard behind the main dam is economical and environmentally friendly, and can be widely used It is used in the construction of rockfill dams in hydropower and water conservancy projects.

附图说明 Description of drawings

图1为本发明主坝坝后渣场结构平面示意图; Fig. 1 is a schematic plan view of the slag field structure behind the main dam of the present invention;

图2是本发明主坝坝后渣场结构剖面示意图。 Fig. 2 is a schematic cross-sectional view of the structure of the slag field behind the main dam of the present invention.

具体实施方式 Detailed ways

如图1和2所示,它是将弃渣区域设在面板堆石坝后,主要堆放主坝坝基、护岸开挖、石料场开挖的弃渣,以及临时工程开挖的弃渣,弃渣区域顶部及边坡设绿化水保措施,适当高程设马道,坝后堆渣体内设排水棱体及排水廊道,用以排出堆渣体内的渗水和作为主坝的排水通道,既可防止施工期面板后产生反向水压力,又可在运行期保持坝体排水通畅。 As shown in Figures 1 and 2, the spoil area is set behind the face rockfill dam, and the spoils from the main dam foundation, revetment excavation, stone yard excavation, and temporary engineering excavation are mainly piled up. Greening and water conservation measures shall be provided on the top and side slope of the slag area, horse roads shall be set at appropriate elevations, and drainage prisms and drainage corridors shall be arranged in the slag pile behind the dam to discharge water seepage in the slag pile and serve as a drainage channel for the main dam, which can prevent During the construction period, the reverse water pressure is generated behind the panel, and the drainage of the dam body can be kept smooth during the operation period.

坝后堆渣体内设排水棱体,两侧排水棱体设在临近岸坡的堆渣体内,主要排出高部位坝体及堆渣体内的渗水;堆渣体底部间设主排水棱体,主排水棱体内设排水廊道,为主坝及堆渣体的主要排水通道,既可防止施工期面板后产生反向水压力,又可在运行期保持坝体排水通畅。 Drainage prisms are arranged in the slag body behind the dam, and the drainage prisms on both sides are arranged in the slag body near the bank slope, mainly to discharge the seepage water in the high parts of the dam body and the slag body; the main drainage prisms are arranged between the bottom of the slag body, and the main Drainage corridors are set in the drainage prism, which are the main drainage channels for the main dam and slag, which can not only prevent reverse water pressure behind the panel during the construction period, but also maintain smooth drainage of the dam during the operation period.

面板设3根排水不锈钢管,伸入排水廊道,坝后(包括堆渣体周边)设置了系统截排水沟,排出两侧山体及坝体表面暴雨汇水。 Three drainage stainless steel pipes are installed on the panel, which extend into the drainage corridor, and a system cut-off drainage ditch is set behind the dam (including around the slag pile) to discharge the rainstorm catchment water from the mountains on both sides and the surface of the dam body.

弃渣区域设在面板堆石坝后,主要堆放主坝坝基、护岸开挖、石料场开挖的弃渣,以及临时工程等开挖弃渣,弃渣区域顶部及边坡设绿化水保措施,在适当高程分别设马道。坝后堆渣体内设排水棱体及排水廊道,用以排出堆渣体内的渗水和作为主坝的排水通道,既可防止施工期面板后产生反向水压力,又可在运行期保持坝体排水通畅。 The spoil area is set behind the concrete face rockfill dam, mainly stacking spoils from the excavation of the main dam foundation, revetment excavation, stone yard, and temporary works. , and set up horse trails at appropriate elevations. Drainage prisms and drainage corridors are set in the slag body behind the dam to discharge water seepage in the slag body and serve as a drainage channel for the main dam, which can prevent reverse water pressure behind the face plate during the construction period and maintain the dam during the operation period. Body drainage is smooth.

坝后弃渣区域位于面板堆石坝坝体以外坝后征地范围线以内,主要堆放主坝坝基和护岸开挖、石料场开挖的弃渣以及临时工程等开挖弃渣,弃渣区域顶部及边坡设绿化水保措施。 The spoil area behind the dam is located outside the dam body of the concrete face rockfill dam and within the scope of land acquisition behind the dam. It is mainly piled with excavated spoil from the excavation of the main dam foundation and revetment, the excavation of the stone yard, and temporary works. The top of the spoil area is Greening and water conservation measures shall be set up on the side slope.

    坝后堆渣体内设排水棱体。两侧排水棱体设在临近岸坡的堆渣体内,主要排高部位坝体及堆渣体内的渗水;堆渣体底部间设主排水及棱体,主排水棱体内设排水廊道,为主坝及堆渣体的主要排水通道,既可防止施工期面板后产生反向水压力,又可在运行期保持坝体排水通畅。面板设3根排水不锈钢管,伸入排水廊道,坝后(包括堆渣体周边)设置了系统截排水沟,排出两侧山体及坝体表面暴雨汇水。 A drainage prism is arranged in the slag pile behind the dam. Drainage prisms on both sides are set in the slag body near the bank slope, and mainly drain water seepage from the dam body and slag body at the height; main drainage and prisms are set between the bottom of the slag body, and drainage corridors are set in the main drainage prism for The main drainage channel of the main dam and the slag body can not only prevent the reverse water pressure behind the face plate during the construction period, but also keep the drainage of the dam body smooth during the operation period. Three drainage stainless steel pipes are installed on the panel, which extend into the drainage corridor, and a system cut-off drainage ditch is set behind the dam (including around the slag pile) to discharge the rainstorm catchment water from the mountains on both sides and the surface of the dam body.

实施实例1: Implementation example 1:

    下面以采用了本发明技术方案的大型工程为例结合附图进一步说明:牡丹江抽水蓄能电站上水库主坝,坝后弃渣区域位于上水库主坝坝后征地范围线之内,主坝坝后岸坡上,上水库主坝基础开挖线内。主弃渣区域设在面板堆石坝后,主要堆放主坝坝基和护岸开挖、石料场开挖的弃渣以及临时工程等开挖弃渣,弃渣量约为264×104m3,弃渣区域顶部平台高程为640.00m,顶宽112m,下游边坡比为1:3.0,设绿化水保措施(三维植物网、内配灌木草种),最大高度约62m,在580m、600m、620m高程分别设3m宽马道。 Below take the large-scale project that has adopted the technical scheme of the present invention as example in conjunction with accompanying drawing to further illustrate: the main dam of the upper reservoir of the Mudanjiang pumped storage power station, the spoil area behind the dam is located within the range line of land expropriation behind the main dam of the upper reservoir, and the main dam On the rear bank slope, within the excavation line of the main dam foundation of the upper reservoir. The main spoil area is located behind the concrete face rockfill dam, where the main dam foundation and revetment excavation, the spoil from the excavation of the stone yard and the excavation spoil of temporary works are mainly piled up. The spoil volume is about 264×10 4 m 3 , The elevation of the top platform in the spoil area is 640.00m, the top width is 112m, and the downstream side-slope ratio is 1:3.0. Greening and water conservation measures (three-dimensional plant nets, internal shrubs and grass species) are set up. The maximum height is about 62m. 3m wide bridleways are set at the elevation of 620m.

 坝后堆渣体内设三道排水棱体。两侧排水棱体基础在土状全风化层顶部,排水棱体断面:底宽3m,厚度3m,主要排高部位坝体及堆渣体内的渗水;堆渣底部中间排水棱体的底宽为5m,内设排水廊道为主坝的主要排水通道,排水廊道为城门洞型钢筋混凝土,内径为2m×2.5m(宽×高),壁厚为1.0m,基础设排水孔(排距2m,间距3m,孔深1.5m),全洞线预埋φ100mmPE排水管,间距0.5m,排距1.0m;面板后设反渗排水钢管(3φ25cm,通入排水廊道中),既可防止施工期面板后产生反向水压力,又可在运行期保持坝体排水通畅。坝后(包括堆渣体周边)设置了系统截排水沟,排出两侧山体及坝体表面暴雨汇水。 There are three drainage prisms in the slag pile behind the dam. The foundation of the drainage prism on both sides is on the top of the soil-like fully weathered layer. The cross-section of the drainage prism: the bottom width is 3m, and the thickness is 3m. 5m, and the main drainage channel of the main dam is provided with a drainage corridor. The drainage corridor is reinforced concrete with a gate hole type, the inner diameter is 2m×2.5m (width×height), and the wall thickness is 1.0m. Drainage holes (row spacing 2m, spacing 3m, hole depth 1.5m), the entire tunnel line pre-buried φ100mmPE drainage pipes, spacing 0.5m, row spacing 1.0m; reverse osmosis drainage steel pipes (3φ25cm, leading into the drainage corridor) are installed behind the panel, which can prevent construction The reverse water pressure will be generated behind the panel during the period, and the drainage of the dam body will be kept smooth during the operation period. Behind the dam (including the surrounding area of the slag pile) a system intercepting drainage ditch is set up to discharge the rainwater catchment from the mountains on both sides and the surface of the dam body.

     通过采用本发明的技术方案,获得了如下效果: By adopting the technical solution of the present invention, the following effects are obtained:

(1) 本工程场址坐落在威虎山森林公园柴河林业局林场内,渣场布置在面板堆石坝坝后,渣场容量264万m3,避免选择远离坝区的天然沟谷作为渣场,可减少大量渣场及其连接道路占用耕地和林地面积,减少移民; (1) The project site is located in the forest farm of Chaihe Forestry Bureau in Weihushan Forest Park. The slag dump is arranged behind the face rockfill dam. It can reduce the area of arable land and forest land occupied by a large number of slag yards and their connecting roads, and reduce immigration;

(2) 可部分利用堆石坝的排水及其防护措施,减少了渣场的挡排防护措施,减少了渣场防护量工程; (2) The drainage of the rockfill dam and its protection measures can be partially utilized, reducing the protection measures for the slag yard and the protection amount of the slag yard;

(3) 紧临堆石坝等工程开挖区,减少了弃渣运距,节省大量投资; (3) It is close to the excavation area of rockfill dams and other projects, which reduces the distance of waste slag transportation and saves a lot of investment;

(4) 堆渣体可作为坝脚压重,增加了坝体的稳定性; (4) The slag body can be used as the weight of the dam foot, which increases the stability of the dam body;

(5) 渣场顶面及下游坡面覆土绿化美化了坝区环境; (5) The greening of the top surface of the slag yard and the downstream slope surface beautifies the environment of the dam area;

(6) 节省渣场征地费、工程措施费及弃渣运费近千万,既经济又环保。 (6) Save nearly ten million in land acquisition fees, engineering measures fees and waste slag transportation costs for slag yards, which is both economical and environmentally friendly.

Claims (3)

1. slag construction technology behind rock dam, it is characterized in that, it is after waste region is located at rock, the waste of the main stacking key dam dam foundation, shore protection excavation, building stones field excavation, and the waste of temporary works excavation, top, waste region and side slope establish greening soil erosion management, and suitable elevation establishes packway, drainage prism and collector drain is established in slag body, in order to discharge the infiltration in slag body and the drainage channel as key dam behind dam.
2. slag construction technology behind rock dam as claimed in claim 1, it is characterized in that, establish drainage prism behind dam in slag body, both sides drainage prism is located at and closes in the slag body of bank slope, establish main drainage prism between bottom slag body, in main drainage prism, establish collector drain.
3. slag construction technology behind rock dam as claimed in claim 1, it is characterized in that, draining stainless steel tube established by panel, stretches into collector drain, arranges system drain dyke behind dam.
CN201410485510.2A 2014-09-23 2014-09-23 Construction technology of slag stacking behind concrete faced rock-fill dam Pending CN104264635A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410485510.2A CN104264635A (en) 2014-09-23 2014-09-23 Construction technology of slag stacking behind concrete faced rock-fill dam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410485510.2A CN104264635A (en) 2014-09-23 2014-09-23 Construction technology of slag stacking behind concrete faced rock-fill dam

Publications (1)

Publication Number Publication Date
CN104264635A true CN104264635A (en) 2015-01-07

Family

ID=52156199

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410485510.2A Pending CN104264635A (en) 2014-09-23 2014-09-23 Construction technology of slag stacking behind concrete faced rock-fill dam

Country Status (1)

Country Link
CN (1) CN104264635A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104695386A (en) * 2015-04-09 2015-06-10 中国电建集团成都勘测设计研究院有限公司 Blocking and discharge structure and method for ditch water treatment
CN105970882A (en) * 2016-04-19 2016-09-28 长江勘测规划设计研究有限责任公司 Structure solving reverse osmosis water problem of dam body in construction process of concrete-faced rockfill dam and construction method thereof
CN107165129A (en) * 2017-07-19 2017-09-15 中国电建集团成都勘测设计研究院有限公司 Canyon Area high dam hydroelectric project slag ditch-water flow guide system
CN110468785A (en) * 2019-09-12 2019-11-19 中国电建集团中南勘测设计研究院有限公司 A kind of slag structure and slag method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102296572A (en) * 2011-06-23 2011-12-28 中国水电顾问集团华东勘测设计研究院 Earth and rockfill dam body seepage monitoring structure provided with abandoned dreg site behind dam and construction method thereof
CN102797241A (en) * 2012-08-30 2012-11-28 合肥工业大学 Resin panel earth-rock fill dam and panel construction method
KR101273819B1 (en) * 2011-07-13 2013-06-11 한국수자원공사 water tightness evaluation method of core zone of rockfill dam
CN203096697U (en) * 2013-03-01 2013-07-31 中国水电顾问集团北京勘测设计研究院 Ballast field structure at earth and rockfill dam toe

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102296572A (en) * 2011-06-23 2011-12-28 中国水电顾问集团华东勘测设计研究院 Earth and rockfill dam body seepage monitoring structure provided with abandoned dreg site behind dam and construction method thereof
KR101273819B1 (en) * 2011-07-13 2013-06-11 한국수자원공사 water tightness evaluation method of core zone of rockfill dam
CN102797241A (en) * 2012-08-30 2012-11-28 合肥工业大学 Resin panel earth-rock fill dam and panel construction method
CN203096697U (en) * 2013-03-01 2013-07-31 中国水电顾问集团北京勘测设计研究院 Ballast field structure at earth and rockfill dam toe

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104695386A (en) * 2015-04-09 2015-06-10 中国电建集团成都勘测设计研究院有限公司 Blocking and discharge structure and method for ditch water treatment
CN105970882A (en) * 2016-04-19 2016-09-28 长江勘测规划设计研究有限责任公司 Structure solving reverse osmosis water problem of dam body in construction process of concrete-faced rockfill dam and construction method thereof
CN105970882B (en) * 2016-04-19 2017-12-29 长江勘测规划设计研究有限责任公司 Solve the structure and its building method of face dam construction time dam body reverse osmosis water problems
CN107165129A (en) * 2017-07-19 2017-09-15 中国电建集团成都勘测设计研究院有限公司 Canyon Area high dam hydroelectric project slag ditch-water flow guide system
CN110468785A (en) * 2019-09-12 2019-11-19 中国电建集团中南勘测设计研究院有限公司 A kind of slag structure and slag method

Similar Documents

Publication Publication Date Title
CN104131575B (en) A kind of karst height grows the leak stopping water discharge method of the stratum dam foundation
CN201943173U (en) Sinking groove type permeable gutter inlet facility system
CN103603320B (en) A LID type rainwater ditch and its design calculation method
CN105178125B (en) A kind of lake region High-filled emkankment is blown sand embankments construction method and embankment structure
CN109371918B (en) Dam structure with permanent combination of multifunctional drainage box culvert and construction method thereof
CN104653195B (en) A kind of coombe landforms tunnel portal structure and its construction method
CN107237388A (en) Waterproof ground rainwater leads the system of oozing
WO2022095494A1 (en) Dry desilting method for riverway
CN104264635A (en) Construction technology of slag stacking behind concrete faced rock-fill dam
CN205242205U (en) a road drain
CN207228038U (en) The countermeasure system of large-scale Dumping Sites in a kind of debris flow gully
CN106703053A (en) Construction method for reinforced soil drainage composite revetment structure
CN203096697U (en) Ballast field structure at earth and rockfill dam toe
CN106836243B (en) A kind of sponge greenery patches of suitable mountain topography and its building method
CN104652595B (en) Half support water storage type greenery patches structure of a kind of urban flood defence and utilization of flood resources
CN209429056U (en) The native stone water-retaining structure of seepage prevention of core wall
CN203834439U (en) Temporarily built site along river or gully
CN203625739U (en) Embankment made of red sandstone filler
CN205062744U (en) Half gravity type two -stage view anti -flood wall on half cantilever
CN107558587A (en) One kind omits water system in printing slowly after first catchmenting
CN206768634U (en) Shed hole structure for Unevenly-pressured shallow tunnel
CN208563267U (en) A kind of earth and rockfill dam pressure slope body discharge structure
CN106049508A (en) Pit-pond type depression earthwork and stonework filling structure and construction method
CN105064264A (en) Super-large-scale water conservancy project and construction technology thereof
CN207160056U9 (en) A warehouse support structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20150107