CN104264635A - Construction technology of slag stacking behind concrete faced rock-fill dam - Google Patents

Construction technology of slag stacking behind concrete faced rock-fill dam Download PDF

Info

Publication number
CN104264635A
CN104264635A CN201410485510.2A CN201410485510A CN104264635A CN 104264635 A CN104264635 A CN 104264635A CN 201410485510 A CN201410485510 A CN 201410485510A CN 104264635 A CN104264635 A CN 104264635A
Authority
CN
China
Prior art keywords
dam
slag
behind
waste
excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410485510.2A
Other languages
Chinese (zh)
Inventor
赵兵
曲景涛
唐国峰
宋德强
何平
徐智桓
夏辉
金辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHINA WATER NORTHEASTERN INVESTIGATION DESIGN AND RESEARCH Co Ltd
Mudanjiang Heilungkiang Pumped Storage Co Ltd
State Grid Corp of China SGCC
State Grid Xinyuan Co Ltd
Original Assignee
CHINA WATER NORTHEASTERN INVESTIGATION DESIGN AND RESEARCH Co Ltd
Mudanjiang Heilungkiang Pumped Storage Co Ltd
State Grid Corp of China SGCC
State Grid Xinyuan Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHINA WATER NORTHEASTERN INVESTIGATION DESIGN AND RESEARCH Co Ltd, Mudanjiang Heilungkiang Pumped Storage Co Ltd, State Grid Corp of China SGCC, State Grid Xinyuan Co Ltd filed Critical CHINA WATER NORTHEASTERN INVESTIGATION DESIGN AND RESEARCH Co Ltd
Priority to CN201410485510.2A priority Critical patent/CN104264635A/en
Publication of CN104264635A publication Critical patent/CN104264635A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/02Fixed barrages
    • E02B7/04Dams across valleys
    • E02B7/06Earth-fill dams; Rock-fill dams

Abstract

The invention discloses a construction technology of slag stacking behind a concrete faced rock-fill dam and relates to the technical field of water and electricity hydraulic engineering. According to the construction technology of the slag stacking behind the concrete faced rock-fill dam, a waste slag area is arranged behind the concrete faced rock-fill dam, waste slags from main dam foundation, shore protection excavation, quarry excavation and temporary project excavation, the top and side slops of the waste slag area are provided with greening and water protection measures, a riding track is arranged at an appropriate elevation, and a drainage edge body, a drainage gallery and a drainage channel which is used for draining seepage water inside the slag stacking body and served as a main dam are arranged inside a slag stacking body behind the dam; a slag yard is arranged behind the dam, the slag stacking body directly presses a downstream dam surface, land acquisition and immigrants at the slag yard and a connecting road are reduced; the waste slag area is close to an engineering excavation area and accordingly waste slag haul distance is reduced; drainage and protection measures of the main dam can be partially utilized and accordingly the slag yard engineering protection amount is reduced; the slag stacking body can be served as dam toe weight and accordingly the dam body stability, particularly the anti-seismic is increased; the structure of the slag yard behind the main dam is economic and environmental friendly and can be widely applied to rock-fill dam construction of the water and electricity hydraulic engineering.

Description

Slag construction technology behind rock dam
Technical field
The present invention relates to water power hydraulic engineering technical field, be specifically related to slag construction technology behind face dam dam.
Background technology
The main advantage of rock construction makes full use of local material, and construction is simple, can Appropriate application excavated material, and reduce waste, save and take up an area and investment, environment protecting is good simultaneously.But not every excavation slag charge can as dam embankment material, and the organic component that humus soil contains is unstable, and physical and mechanical property is poor; The above rock mass in general severely-weathered middle part due to weathering serious, intensity is low, and mechanics index of physics is poor, and fragmentation can not be gone up dam and be thrown aside, and these rejected materials all need waste region to hold.Common engineering can select some natural cheuches as slag field usually; so just bring the comparatively far away and series of problems such as water and soil conservation, environmental protection of the expropriation of land immigrant of waste region and linking-up road thereof, waste haul distance; the general slope of natural cheuch is high simultaneously, ditch steep, charge for remittance amount is large; make slag field preventive works amount comparatively large, not only uneconomical but also not environmentally.
Summary of the invention
Technical problem to be solved by this invention is: for the problems referred to above, by slag technology behind rock dam, make full use of dam rear space and stack waste, a kind of expropriation of land and the immigrant that reduce waste region and linking-up road thereof are provided, reduce slag field preventive works amount and waste haul distance, increase dam stabilization simultaneously, beautify dam district environment, not only slag field structure behind economy but also the dam of environmental protection.
Technical solution of the present invention is: slag construction technology behind rock dam, it is after waste region is located at rock, the waste of the main stacking key dam dam foundation, shore protection excavation, building stones field excavation, and the waste of temporary works excavation, top, waste region and side slope establish greening soil erosion management, suitable elevation establishes packway, establishes drainage prism and collector drain behind dam in slag body, in order to discharge the infiltration in slag body and the drainage channel as key dam.
Technique effect of the present invention is: after 1, slag field is arranged in dam, and slag body is directly laminated on the dam facing of downstream, can reduce expropriation of land and the immigrant of slag field and linking-up road thereof; 2, close on engineering excavation district, decrease waste haul distance; 3, partly can utilize draining and the safeguard procedures thereof of key dam, decrease slag field engineering protection amount; 4, slag body can be used as base of dam ballast, adds the stability of dam body, especially stability against earthquake; 5, the domatic earth-covering greening of slag field end face and downstream beautifies Liao Ba district environment, increases the recreation facilities such as square, the development of favourable later stage travel industry; 6, slag field structure not only economy but also environmental protection behind key dam dam, can be widely used in the construction of water power hydraulic engineering loose rock dam.
Accompanying drawing explanation
Fig. 1 is slag field structure floor map behind key dam dam of the present invention;
Fig. 2 is slag field structure generalized section behind key dam dam of the present invention.
Detailed description of the invention
As illustrated in fig. 1 and 2, it is after waste region is located at rock, the waste of the main stacking key dam dam foundation, shore protection excavation, building stones field excavation, and the waste of temporary works excavation, top, waste region and side slope establish greening soil erosion management, suitable elevation establishes packway, drainage prism and collector drain is established in slag body behind dam, in order to discharge the infiltration in slag body and the drainage channel as key dam, both produce reverse water pressure power after can preventing construction period panel, drainage in dam body can be kept unobstructed in the runtime again.
Establish drainage prism in slag body behind dam, both sides drainage prism is located at and closes in the slag body of bank slope, main infiltration of discharging in high-order bit dam body and slag body; Establish main drainage prism between bottom slag body, in main drainage prism, establish collector drain, be the arterial drainage passage of key dam and slag body, produce reverse water pressure power after both can preventing construction period panel, drainage in dam body can be kept unobstructed in the runtime again.
3 draining stainless steel tubes established by panel, stretch into collector drain, (comprise slag body periphery) and be provided with system drain dyke behind dam, discharge both sides massif and dam body surface heavy rain charge for remittance.
After waste region is located at rock, the excavation wastes such as the mainly waste of the stacking key dam dam foundation, shore protection excavation, building stones field excavation, and temporary works, top, waste region and side slope establish greening soil erosion management, establish packway respectively at suitable elevation.Establish drainage prism and collector drain in slag body behind dam, in order to discharge the infiltration in slag body and the drainage channel as key dam, after both can preventing construction period panel, produce reverse water pressure power, drainage in dam body can be kept unobstructed in the runtime again.
Within waste region is positioned at scope line of taking over the land for use behind dam beyond rock dam body behind dam, mainly stack the excavation wastes such as the key dam dam foundation and shore protection excavation, the waste of building stones field excavation and temporary works, top, waste region and side slope establish greening soil erosion management.
Drainage prism is established in slag body behind dam.Both sides drainage prism is located at and closes in the slag body of bank slope, main infiltration of arranging in high-order bit dam body and slag body; Establish main draining and rib body between bottom slag body, in main drainage prism, establish collector drain, be the arterial drainage passage of key dam and slag body, produce reverse water pressure power after both can preventing construction period panel, drainage in dam body can be kept unobstructed in the runtime again.3 draining stainless steel tubes established by panel, stretch into collector drain, (comprise slag body periphery) and be provided with system drain dyke behind dam, discharge both sides massif and dam body surface heavy rain charge for remittance.
Embodiment 1:
Further illustrate by reference to the accompanying drawings for the major works that have employed technical solution of the present invention below: Mudanjiang pumped storage power plant upper storage reservoir key dam, behind dam, waste region is taken over the land for use within scope line after being positioned at upper storage reservoir key dam dam, behind key dam dam on bank slope, in upper storage reservoir key dam foundation excavation line.After main waste region is located at rock, the excavation wastes such as the waste that the main stacking key dam dam foundation and shore protection excavation, building stones field are excavated and temporary works, waste amount is about 264 × 10 4m 3, waste region top platform elevation is 640.00m, top width 112m, and downstream side slope is than for 1:3.0, if greening soil erosion management (three-dimensional plant net, in join shrub grass seeds), maximum height is about 62m, establishes the wide packway of 3m respectively at 580m, 600m, 620m elevation.
Slag body Nei She tri-road drainage prism behind dam.Both sides drainage prism is basic at earthy completely decomposed layer top, drainage prism section: bottom width 3m, thickness 3m, main infiltration of arranging in high-order bit dam body and slag body; In the middle of bottom slag, the bottom width of drainage prism is 5m, inside set collector drain as the arterial drainage passage of key dam, collector drain is gateway opening steel bar concrete, and internal diameter is that 2m × 2.5m(is wide × high), wall thickness is 1.0m, drain hole (array pitch 2m is established on basis, spacing 3m, hole depth 1.5m), Quan Dongxian pre-buried φ 100mmPE gutter, spacing 0.5m, array pitch 1.0m; Establish reverse osmosis draining steel pipe (3 φ 25cm, pass in collector drain) after panel, produce reverse water pressure power after both can preventing construction period panel, drainage in dam body can be kept unobstructed in the runtime again.(comprise slag body periphery) behind dam and be provided with system drain dyke, discharge both sides massif and dam body surface heavy rain charge for remittance.
By adopting technical scheme of the present invention, obtain following effect:
(1) this engineering site is seated in prestige Tiger Mountain forest park Chai He forestry bureau forest farm, after slag field is arranged in rock dam, and slag field capacity 2,640,000 m 3, to avoid selecting away from the natural cheuch of Ba Qu as slag field, a large amount of slag field can be reduced and linking-up road occupies cultivated land and forest land area, reduce immigrant;
(2) partly can utilize draining and the safeguard procedures thereof of loose rock dam, decrease the gear row safeguard procedures of slag field, decrease slag field protection amount engineering;
(3) be close to the engineering excavation districts such as loose rock dam, decrease waste haul distance, save great amount of investment;
(4) slag body can be used as base of dam ballast, adds the stability of dam body;
(5) the domatic earth-covering greening of slag field end face and downstream beautifies Liao Ba district environment;
(6) slag field fees paid for taking rural land, engineering measure expense and waste freight charges nearly ten million are saved, not only economy but also environmental protection.

Claims (3)

1. slag construction technology behind rock dam, it is characterized in that, it is after waste region is located at rock, the waste of the main stacking key dam dam foundation, shore protection excavation, building stones field excavation, and the waste of temporary works excavation, top, waste region and side slope establish greening soil erosion management, and suitable elevation establishes packway, drainage prism and collector drain is established in slag body, in order to discharge the infiltration in slag body and the drainage channel as key dam behind dam.
2. slag construction technology behind rock dam as claimed in claim 1, it is characterized in that, establish drainage prism behind dam in slag body, both sides drainage prism is located at and closes in the slag body of bank slope, establish main drainage prism between bottom slag body, in main drainage prism, establish collector drain.
3. slag construction technology behind rock dam as claimed in claim 1, it is characterized in that, draining stainless steel tube established by panel, stretches into collector drain, arranges system drain dyke behind dam.
CN201410485510.2A 2014-09-23 2014-09-23 Construction technology of slag stacking behind concrete faced rock-fill dam Pending CN104264635A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410485510.2A CN104264635A (en) 2014-09-23 2014-09-23 Construction technology of slag stacking behind concrete faced rock-fill dam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410485510.2A CN104264635A (en) 2014-09-23 2014-09-23 Construction technology of slag stacking behind concrete faced rock-fill dam

Publications (1)

Publication Number Publication Date
CN104264635A true CN104264635A (en) 2015-01-07

Family

ID=52156199

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410485510.2A Pending CN104264635A (en) 2014-09-23 2014-09-23 Construction technology of slag stacking behind concrete faced rock-fill dam

Country Status (1)

Country Link
CN (1) CN104264635A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104695386A (en) * 2015-04-09 2015-06-10 中国电建集团成都勘测设计研究院有限公司 Blocking and discharge structure and method for ditch water treatment
CN105970882A (en) * 2016-04-19 2016-09-28 长江勘测规划设计研究有限责任公司 Structure solving reverse osmosis water problem of dam body in construction process of concrete-faced rockfill dam and construction method thereof
CN107165129A (en) * 2017-07-19 2017-09-15 中国电建集团成都勘测设计研究院有限公司 Canyon Area high dam hydroelectric project slag ditch-water flow guide system
CN110468785A (en) * 2019-09-12 2019-11-19 中国电建集团中南勘测设计研究院有限公司 A kind of slag structure and slag method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102296572A (en) * 2011-06-23 2011-12-28 中国水电顾问集团华东勘测设计研究院 Earth and rockfill dam body seepage monitoring structure provided with abandoned dreg site behind dam and construction method thereof
CN102797241A (en) * 2012-08-30 2012-11-28 合肥工业大学 Resin panel earth-rock fill dam and panel construction method
KR101273819B1 (en) * 2011-07-13 2013-06-11 한국수자원공사 water tightness evaluation method of core zone of rockfill dam
CN203096697U (en) * 2013-03-01 2013-07-31 中国水电顾问集团北京勘测设计研究院 Ballast field structure at earth and rockfill dam toe

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102296572A (en) * 2011-06-23 2011-12-28 中国水电顾问集团华东勘测设计研究院 Earth and rockfill dam body seepage monitoring structure provided with abandoned dreg site behind dam and construction method thereof
KR101273819B1 (en) * 2011-07-13 2013-06-11 한국수자원공사 water tightness evaluation method of core zone of rockfill dam
CN102797241A (en) * 2012-08-30 2012-11-28 合肥工业大学 Resin panel earth-rock fill dam and panel construction method
CN203096697U (en) * 2013-03-01 2013-07-31 中国水电顾问集团北京勘测设计研究院 Ballast field structure at earth and rockfill dam toe

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104695386A (en) * 2015-04-09 2015-06-10 中国电建集团成都勘测设计研究院有限公司 Blocking and discharge structure and method for ditch water treatment
CN105970882A (en) * 2016-04-19 2016-09-28 长江勘测规划设计研究有限责任公司 Structure solving reverse osmosis water problem of dam body in construction process of concrete-faced rockfill dam and construction method thereof
CN105970882B (en) * 2016-04-19 2017-12-29 长江勘测规划设计研究有限责任公司 Solve the structure and its building method of face dam construction time dam body reverse osmosis water problems
CN107165129A (en) * 2017-07-19 2017-09-15 中国电建集团成都勘测设计研究院有限公司 Canyon Area high dam hydroelectric project slag ditch-water flow guide system
CN110468785A (en) * 2019-09-12 2019-11-19 中国电建集团中南勘测设计研究院有限公司 A kind of slag structure and slag method

Similar Documents

Publication Publication Date Title
CN203603105U (en) Wall plate type ecological retaining wall bank protection structure
CN106759825A (en) A kind of construction method of sponge urban green space water storage system
CN103953008B (en) A kind of modified mixed dam being applicable to Tailings Dam
CN202718138U (en) Self-locking type ecological retaining wall structure
CN104480974B (en) Reverse seepage drain system suitable for upstream type tailings pond and upstream type tailings pond
CN106801424A (en) A kind of cofferdam construction method
CN210827501U (en) Greening structure of stock ground rock slope
CN106368227A (en) Water erosion prevention system and method for ecology of slope of abandoned rear-earth mine land
CN104264635A (en) Construction technology of slag stacking behind concrete faced rock-fill dam
CN104695386A (en) Blocking and discharge structure and method for ditch water treatment
CN106087953A (en) A kind of drainage and construction method preventing and treating large-scale spoil ground, mountain area mud-rock flow
CN101748734A (en) Foundation pit side slope sandy soil drainage method
CN202081409U (en) Initial dam structure of ash storage field built of ash and slag
CN102425175B (en) Reinforcement protective structure of large spoil disposal area in mountainous area
CN203530924U (en) Green and ecological revetment retaining wall structure of river channel
CN109371919A (en) The native stone water-retaining structure of seepage prevention of core wall
CN205936632U (en) Tunnel lining structure can be maintained to disconnect -type
CN203096697U (en) Ballast field structure at earth and rockfill dam toe
CN106836243A (en) A kind of sponge greenery patches of suitable mountain topography and its building method
CN203625928U (en) Integrated cutting retaining wall
CN215122670U (en) Semiarid refuse dump side slope vegetation restoration structure of high-efficient rainfall of utilizing
CN105672242A (en) Consolidating and water draining system and method for coal cinder yard of coal-fired power plant
CN103046536B (en) A kind of refuse dump integral harness measure being suitable for soft foundation
CN206245319U (en) A kind of anti-rare earth slash side slope water erosion system
CN109403356B (en) Side slope supporting structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20150107