CN104213559B - Intertidal zone beam lower carriage steel pipe pile extracts the method for pulling out of equipment - Google Patents

Intertidal zone beam lower carriage steel pipe pile extracts the method for pulling out of equipment Download PDF

Info

Publication number
CN104213559B
CN104213559B CN201410460415.7A CN201410460415A CN104213559B CN 104213559 B CN104213559 B CN 104213559B CN 201410460415 A CN201410460415 A CN 201410460415A CN 104213559 B CN104213559 B CN 104213559B
Authority
CN
China
Prior art keywords
steel pipe
pipe pile
truss
crossbeam
equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201410460415.7A
Other languages
Chinese (zh)
Other versions
CN104213559A (en
Inventor
张大鹏
崔红伟
蔡唐涛
郭保林
李明
栾国华
李军
高捷
靳小波
贾绍强
王冲
张付军
王磊
王东亮
张绪峰
王建军
张连瑞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Linchuan Engineering Technology Consulting Co., Ltd.
CCCC Fourth Highway Engineering Co Ltd
Original Assignee
QINGDAO LINCHUAN ENGINEERING TECHNOLOGY CONSULTING Co Ltd
CCCC Fourth Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by QINGDAO LINCHUAN ENGINEERING TECHNOLOGY CONSULTING Co Ltd, CCCC Fourth Highway Engineering Co Ltd filed Critical QINGDAO LINCHUAN ENGINEERING TECHNOLOGY CONSULTING Co Ltd
Priority to CN201410460415.7A priority Critical patent/CN104213559B/en
Publication of CN104213559A publication Critical patent/CN104213559A/en
Application granted granted Critical
Publication of CN104213559B publication Critical patent/CN104213559B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The invention provides the method for pulling out that a kind of intertidal zone beam lower carriage steel pipe pile extracts equipment.It avoids directly blocking along sea bottom surface and abandoning the way of buried depth part steel pipe pile, avoids waste of material, saving project to drop into, reduces risk of navigating.This intertidal zone beam lower carriage steel pipe pile is extracted equipment and is comprised the truss being set up in beam body end face place, the slide mechanism extended along beam body length direction is set between truss and beam body, adopt elevator to hang below truss and crossbeam is set, truss and crossbeam are in be arrangeding in parallel up and down, crossbeam to be formed with the slotting steel pipe pile be absorbed in beach mud ground by soft rope and links, and its method is: (1), case top surface of the beam install truss; (2) crossbeam and link steel pipe pile, is assembled; (3), start pile pulling; (4), part cutting then continues pile pulling.The present invention possess structural principle clear and definite, implement reliable and practical, job safety, simple operation, efficiency of construction are high, can realize one across pile pulling feature continuous in scope.

Description

Intertidal zone beam lower carriage steel pipe pile extracts the method for pulling out of equipment
Technical field
The invention belongs to technical field of bridge construction, what be applicable to intertidal zone beam lower carriage steel pipe pile extracts work, and particularly a kind of intertidal zone beam lower carriage steel pipe pile extracts the method for pulling out of equipment.
Background technology
Mobile formwork, steel pipe pile support, full hall scaffold are the conventional supporting way of cast-in-situ box girder template.Mobile formwork initial investment is huge, and the object of construction production little for cast-in-situ box girder quantity seldom adopts mobile formwork scheme; Full hall scaffold is applicable to the little land construction of headroom at the bottom of beam mostly; And Coastal Area due to bearing capacity of foundation soil more weak, then usually adopt steel pipe pile support scheme.
After bridge substructure completes, immediately below case beam, squeeze into the steel pipe pile of some, then lay crossbeam and case beam base plate template and frange plate template at steel pipe pile end face.Box beam concrete builds the initial stage, and the deadweight of case beam, template, template crossbeam etc. is all born by steel pipe pile, and steel pipe pile needs enough diameters, length and quantity.Need to remove beam lower supporter after case beam is poured, because between support and case beam base plate, space is very little, steel pipe pile is difficult to remove.Under normal circumstances, when seawater low tide, being blocked by steel pipe pile along ooze end face and reuse, the part be embedded under mud can forever be discarded.Steel pipe pile abandoneds a large amount of is thus in ooze, and the project that so both adds drops into, wastes resource, becomes again marine potential safety hazard of navigating in the future.
Summary of the invention
The object of the invention is to there are the problems referred to above for existing technology, propose and be a kind ofly in Coastal Area the pile pulling technology using steel pipe pile support for bridge construction, and its be implement reliable and practical, job safety, the intertidal zone beam lower carriage steel pipe pile of simple operation extracts the method for pulling out of equipment.
Object of the present invention realizes by following technical proposal: intertidal zone beam lower carriage steel pipe pile extracts equipment, comprise the truss being set up in beam body end face place, the slide mechanism extended along beam body length direction is set between described truss and beam body, adopt elevator to hang below described truss and crossbeam is set, described truss and crossbeam are in be arrangeding in parallel up and down, and described crossbeam to be formed with the slotting steel pipe pile be absorbed in beach mud ground by soft rope and links.
The length direction that this intertidal zone beam lower carriage steel pipe pile extracts truss in equipment is vertical with the length direction of case beam, by being slidably connected of slide mechanism, truss can be walked along the translation of case beam length direction.Crossbeam is cylindrical, and its length direction is parallel with truss.Truss controls the beam lifting action below it by elevator mode, and keeps level at lifting process middle cross beam, and then is driven by the rising of crossbeam, and the steel pipe pile linked with it is extracted by beach mud ground.
Extract in equipment at above-mentioned intertidal zone beam lower carriage steel pipe pile, symmetrically hang down and establish two root posts in described truss bottom side, described slide mechanism is specially the parallel sliding track being symmetrically installed in beam body end face, and described column forms slip clamping by its bottom is corresponding with above-mentioned parallel sliding track.Two root posts are symmetrical set the position, both ends at truss, provide the firm support to truss thus; Parallel sliding track is specially two and parallels extended rail, and truss is by the slip clamping of column bottom, and the translation that can complete sync equalizing along parallel sliding track is advanced.
Extract in equipment at above-mentioned intertidal zone beam lower carriage steel pipe pile, between the both sides of described every root post and truss, all symmetrically set firmly hound.Truss body, column and hound form the triangle with rock-steady structure, are beneficial to the stability and fastness that strengthen truss thus.
Extract in equipment at above-mentioned intertidal zone beam lower carriage steel pipe pile, the both ends of described truss symmetrically set firmly hoist engine, the both ends of described crossbeam symmetrically set firmly hanger, and next face-off is presented in the position of described hoist engine and hanger, and hoist engine is hung by wire rope and connects corresponding hanger.
Extract in equipment at above-mentioned intertidal zone beam lower carriage steel pipe pile, described crossbeam sets up ribs in hanger position.
Extract in equipment at above-mentioned intertidal zone beam lower carriage steel pipe pile, the two ends of described soft rope all have closed loop, and described one end closed loop is socketed on above-mentioned crossbeam, and other end closed loop is socketed on above-mentioned steel pipe pile.
Above-mentioned intertidal zone beam lower carriage steel pipe pile extracts the method for pulling out of equipment, at pile foundation, cushion cap and pier stud successively casting complete, and implements after box girder pre-stressed stretch-draw, it is characterized in that, comprise the following steps:
(1), erection of truss in case top surface of the beam, and the column of truss firmly slides and is connected on parallel sliding track, so that truss can be walked along the length direction of case beam;
(2), crossbeam is transported to immediately below truss, and be synchronously positioned at the below of case beam, the closed loop of soft rope one end is inserted in by the end of crossbeam, the sagging wire rope of hoist engine on truss two ends, the hanger at the corresponding bind crossbeam two ends place of wire rope, cut away the steel pipe pile that a section is exposed the beach water surface, the closed loop of the soft rope other end is worn by steel pipe pile top and traps, and make it be socketed position as far as possible to move down;
(3), the hoist engine rolling wire rope opened on truss two ends, rising with constant speed in crossbeam two ends, and then is synchronously extracted by steel pipe pile;
(4), in steel pipe pile rising withdrawal process, if its top is touched or is about to touch the bottom surface of case beam, then cut away the upper part of steel pipe pile, pull up space to provide, then implement again to extract operation to the remaining part of steel pipe pile.
In the method for pulling out of above-mentioned intertidal zone beam lower carriage steel pipe pile extracting apparatus, after this is all extracted across the steel pipe pile in scope, the wire rope unclamping bind hanger unloads lower transverse beam, slippage truss and transport crossbeam to next step into row repeat pile pulling operation.
In this intertidal zone beam lower carriage steel pipe pile method for pulling out, when seawater high water mark, use ship to be transported to by crossbeam and require that position is assembled, and realize pile pulling operation; All should extract across the steel pipe pile in scope, when seawater high water mark, crossbeam to be transferred to ship and removal, and then be transferred to next and realize operation across repetition step.
Compared with prior art, the method for pulling out that this intertidal zone beam lower carriage steel pipe pile extracts equipment is in Coastal Area the pile pulling technology using steel pipe pile support especially for bridge construction, and it possess structural principle clear and definite, implement reliable and practical, job safety, simple operation, efficiency of construction are high, can realize one across features such as continuous pile pullings in scope.
Accompanying drawing explanation
Fig. 1 is the structural representation that this intertidal zone beam lower carriage steel pipe pile extracts equipment.
Fig. 2 is the partial enlargement structural representation that this intertidal zone beam lower carriage steel pipe pile extracts equipment.
In figure, 1, pile foundation; 2, cushion cap; 3, pier stud; 4, case beam; 5, steel pipe pile; 6, soft rope; 7, crossbeam; 8, hanger; 9, parallel sliding track; 10, truss; 11, wire rope; 12, column; 13, hound; 14, hoist engine; 15, ribs.
Detailed description of the invention
Be below specific embodiments of the invention and by reference to the accompanying drawings, technical scheme of the present invention is further described, but the present invention be not limited to these embodiments.
As depicted in figs. 1 and 2, this intertidal zone beam lower carriage steel pipe pile is extracted equipment and is comprised the truss 10 being set up in beam body end face place, and the slide mechanism that truss 10 slippage is walked is set between truss 10 and beam body, adopt elevator to hang below truss 10 and arrange crossbeam 7, crossbeam 7 to be formed with the slotting steel pipe pile 5 be absorbed in beach mud ground by soft rope 6 and links.
Beam body has stacked pile foundation 1, cushion cap 2, pier stud 3 and case beam 4 from the bottom to top successively.
The length direction of truss 10 is vertical with the length direction of case beam 4, and symmetrically hang down and establish two root posts 12 in truss 10 bottom side, and two root posts 12 are specifically installed in the position, both ends of truss 10.All symmetrically set firmly hound 13 between the both sides of every root post 12 and truss 10, truss 10 body, column 12 form the triangle with rock-steady structure with hound 13 thus, are beneficial to the stability and fastness that strengthen truss 10 support.
Slide mechanism is the parallel sliding track 9 being symmetrically installed in case beam 4 end face, this parallel sliding track 9 is specially two and parallels extended rail, chute is offered in column 12 bottom of truss 10, and being slidably connected of forming that corresponding card establishes by chute and rail, realize the translation that truss 10 completes sync equalizing along parallel sliding track 9 to advance, namely truss 10 can be walked along the translation of case beam 4 length direction.
Crossbeam 7 is cylindrical, and after hanging, its length direction parallels with truss 10 length direction, and namely both are in be arrangeding in parallel up and down.The both ends of truss 10 symmetrically set firmly hoist engine 14, and the both ends of crossbeam 7 symmetrically set firmly hanger 8, and set up ribs 15 in hanger 8 position.Two hoist engines 14 and two hanger 8 positions stand facing each other one by one up and down, and by the corresponding hanger 8 of wire rope 11 bind that hoist engine 14 is sagging, to realize the hanging of crossbeam 7.
The two ends of soft rope 6 all have closed loop, and its one end closed loop adapter sleeve is connected on crossbeam 7, on the steel pipe pile 5 extracted needed for other end closed loop adapter sleeve is connected to.
As follows according to its operational method of structure of the said equipment: pile foundation 1, cushion cap 2 and pier stud 3 casting complete successively, with pile driver, steel pipe pile 5 is squeezed in beach mud ground immediately below case beam 4, wherein steel pipe pile 5 diameter, length and quantity should be conducted oneself with dignity according to case beam 4 and the deadweight of template system is determined, after case beam 4 prestressed stretch-draw, just pile pulling step can be carried out.
(1), truss 10 is set up in case beam 4 end face, and the column 12 of truss 10 firmly slides and is connected on parallel sliding track 9, so that truss 10 can be walked along the length direction of case beam 4;
(2), when seawater high water mark, ship is used to be transported to immediately below truss 10 by crossbeam 7, and be synchronously positioned at the below of case beam 4, the closed loop of soft rope 6 one end is inserted in by the end of crossbeam 7, the sagging wire rope 11 of hoist engine 14 on truss 10 two ends, the hanger 8 at wire rope 11 corresponding bind crossbeam 7 two ends place, cuts away the steel pipe pile 5 that a section is exposed the beach water surface, the closed loop of soft rope 6 other end is worn by steel pipe pile 5 top trap, and make it be socketed position as far as possible to move down;
(3), the hoist engine 14 rolling wire rope 11 opened on truss 10 two ends, rising with constant speed in crossbeam 7 two ends, and then is synchronously extracted by steel pipe pile 5;
(4), at steel pipe pile 5 rise in withdrawal process, if its top is touched or is about to touch the bottom surface of case beam 4, then cut away the upper part of steel pipe pile 5, pull up space to provide, then implement again to extract operation to the remaining part of steel pipe pile 5.
Namely truss 10 controls below it by elevator mode crossbeam 7 lifting action, and keeps level at lifting process middle cross beam 7, and then is driven by the rising of crossbeam 7, and the steel pipe pile 5 linked with it is extracted by beach mud ground.
After this is all extracted across the steel pipe pile 5 in scope, when seawater high water mark, crossbeam 7 is transferred on ship, and the wire rope 11 unclamping bind hanger 8 unloads lower transverse beam 7, slippage truss 10 and transport crossbeam 7 to next step into row repeat pile pulling operation.
Specific embodiment described herein is only to the explanation for example of the present invention's spirit.Those skilled in the art can make various amendment or supplement or adopt similar mode to substitute to described specific embodiment, but can't depart from spirit of the present invention or surmount the scope that appended claims defines.
Although more employ pile foundation 1 herein; Cushion cap 2; Pier stud 3; Case beam 4; Steel pipe pile 5; Soft rope 6; Crossbeam 7; Hanger 8; Parallel sliding track 9; Truss 10; Wire rope 11; Column 12; Hound 13; Hoist engine 14; Term such as ribs 15 grade, but do not get rid of the possibility using other term.These terms are used to be only used to describe and explain essence of the present invention more easily; The restriction that they are construed to any one additional is all contrary with spirit of the present invention.

Claims (7)

1. intertidal zone beam lower carriage steel pipe pile extracts the method for pulling out of equipment, this is extracted equipment and is positioned at Liang Tishang, described beam body has stacked pile foundation from the bottom to top successively, cushion cap, pier stud and case beam, equipment comprises the truss being set up in beam body end face place, the slide mechanism extended along beam body length direction is set between described truss and beam body, described slide mechanism is the parallel sliding track being symmetrically installed in beam body end face, adopt elevator to hang below described truss and crossbeam is set, described truss and crossbeam are in be arrangeding in parallel up and down, described crossbeam to be formed with the slotting steel pipe pile be absorbed in beach mud ground by soft rope and links, the method is in pile foundation, cushion cap and pier stud casting complete successively, and implement after box girder pre-stressed stretch-draw, it is characterized in that, comprise the following steps:
(1), erection of truss in case top surface of the beam, and the column of truss firmly slides and is connected on parallel sliding track, so that truss can be walked along the length direction of case beam;
(2), crossbeam is transported to immediately below truss, and be synchronously positioned at the below of case beam, the closed loop of soft rope one end is inserted in by the end of crossbeam, the sagging wire rope of hoist engine on truss two ends, the hanger at the corresponding bind crossbeam two ends place of wire rope, cut away the steel pipe pile that a section is exposed the beach water surface, the closed loop of the soft rope other end is worn by steel pipe pile top and traps, and make it be socketed position as far as possible to move down;
(3), the hoist engine rolling wire rope opened on truss two ends, rising with constant speed in crossbeam two ends, and then is synchronously extracted by steel pipe pile;
(4), in steel pipe pile rising withdrawal process, if its top is touched or is about to touch the bottom surface of case beam, then cut away the upper part of steel pipe pile, pull up space to provide, then implement again to extract operation to the remaining part of steel pipe pile.
2. intertidal zone beam lower carriage steel pipe pile according to claim 1 extracts the method for pulling out of equipment, it is characterized in that, after this is all extracted across the steel pipe pile in scope, the wire rope unclamping bind hanger unloads lower transverse beam, slippage truss and transport crossbeam to next step into row repeat pile pulling operation.
3. intertidal zone beam lower carriage steel pipe pile according to claim 1 extracts the method for pulling out of equipment, it is characterized in that, symmetrically hangs down and establish two root posts in described truss bottom side, and described column forms slip clamping by its bottom is corresponding with above-mentioned parallel sliding track.
4. intertidal zone beam lower carriage steel pipe pile according to claim 3 extracts the method for pulling out of equipment, it is characterized in that, all symmetrically sets firmly hound between the both sides of described every root post and truss.
5. intertidal zone beam lower carriage steel pipe pile according to claim 1 extracts the method for pulling out of equipment, it is characterized in that, the both ends of described truss symmetrically set firmly hoist engine, the both ends of described crossbeam symmetrically set firmly hanger, next face-off is presented in the position of described hoist engine and hanger, and hoist engine is hung by wire rope and connects corresponding hanger.
6. intertidal zone beam lower carriage steel pipe pile according to claim 5 extracts the method for pulling out of equipment, and it is characterized in that, described crossbeam sets up ribs in hanger position.
7. intertidal zone beam lower carriage steel pipe pile according to claim 1 extracts the method for pulling out of equipment, it is characterized in that, the two ends of described soft rope all have closed loop, and described one end closed loop is socketed on above-mentioned crossbeam, and other end closed loop is socketed on above-mentioned steel pipe pile.
CN201410460415.7A 2013-03-26 2013-03-26 Intertidal zone beam lower carriage steel pipe pile extracts the method for pulling out of equipment Expired - Fee Related CN104213559B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410460415.7A CN104213559B (en) 2013-03-26 2013-03-26 Intertidal zone beam lower carriage steel pipe pile extracts the method for pulling out of equipment

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201410460415.7A CN104213559B (en) 2013-03-26 2013-03-26 Intertidal zone beam lower carriage steel pipe pile extracts the method for pulling out of equipment
CN201310098693.8A CN103174141B (en) 2013-03-26 2013-03-26 Intertidal zone beam lower supporting frame steel pipe pile pulling-out device

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201310098693.8A Division CN103174141B (en) 2013-03-26 2013-03-26 Intertidal zone beam lower supporting frame steel pipe pile pulling-out device

Publications (2)

Publication Number Publication Date
CN104213559A CN104213559A (en) 2014-12-17
CN104213559B true CN104213559B (en) 2015-12-09

Family

ID=48634296

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201410460415.7A Expired - Fee Related CN104213559B (en) 2013-03-26 2013-03-26 Intertidal zone beam lower carriage steel pipe pile extracts the method for pulling out of equipment
CN201310098693.8A Expired - Fee Related CN103174141B (en) 2013-03-26 2013-03-26 Intertidal zone beam lower supporting frame steel pipe pile pulling-out device

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN201310098693.8A Expired - Fee Related CN103174141B (en) 2013-03-26 2013-03-26 Intertidal zone beam lower supporting frame steel pipe pile pulling-out device

Country Status (1)

Country Link
CN (2) CN104213559B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108360521B (en) * 2018-03-15 2021-07-06 中国石油大学(华东) Method for dismounting offshore platform pile foundation by twisting and pulling up
CN108894226A (en) * 2018-09-28 2018-11-27 中国冶集团有限公司 Pile pulling device under a kind of bridge
CN109972621B (en) * 2019-04-22 2024-03-26 中建三局基础设施建设投资有限公司 Pile pulling device for steel pipe pile in small-clearance shallow water area and construction method of pile pulling device
CN110306553B (en) * 2019-04-28 2021-06-29 中国一冶集团有限公司 Underwater steel pile dismantling device and method
CN115075247A (en) * 2022-05-24 2022-09-20 保利长大工程有限公司 Pulling-out method for steel pipe pile of cross-river channel box girder bracket

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10168879A (en) * 1996-12-10 1998-06-23 Taisei Corp Pulling method for steel sheet pile
JPH10306443A (en) * 1997-04-30 1998-11-17 Nishimatsu Constr Co Ltd Pile pull-out jig and pile pull-out method using jig
CN2348010Y (en) * 1998-05-15 1999-11-10 江苏金猴机械集团公司研究所 Pile pulling mechanism
CN101858083A (en) * 2010-06-22 2010-10-13 天津第三市政公路工程有限公司 Low spatial pile pulling construction method and device of steel pipe pile in water

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3697576B2 (en) * 2001-02-28 2005-09-21 Jfeスチール株式会社 Remaining pile drawing device and remaining pile drawing method
CN102296610B (en) * 2011-05-19 2013-05-08 中天建设集团有限公司 Device for removing square pile and construction method thereof
CN203129146U (en) * 2013-03-26 2013-08-14 山东高速青岛公路有限公司 Extraction device for under-beam supporting bracket steel pipe pile in beach area

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10168879A (en) * 1996-12-10 1998-06-23 Taisei Corp Pulling method for steel sheet pile
JPH10306443A (en) * 1997-04-30 1998-11-17 Nishimatsu Constr Co Ltd Pile pull-out jig and pile pull-out method using jig
CN2348010Y (en) * 1998-05-15 1999-11-10 江苏金猴机械集团公司研究所 Pile pulling mechanism
CN101858083A (en) * 2010-06-22 2010-10-13 天津第三市政公路工程有限公司 Low spatial pile pulling construction method and device of steel pipe pile in water

Also Published As

Publication number Publication date
CN103174141B (en) 2015-06-03
CN103174141A (en) 2013-06-26
CN104213559A (en) 2014-12-17

Similar Documents

Publication Publication Date Title
CN104213559B (en) Intertidal zone beam lower carriage steel pipe pile extracts the method for pulling out of equipment
CN201502061U (en) Recoverable prestressing anchor rope with double anchor heads
CN102650118B (en) Construction device and method for erecting prefabricated beam by slip method
CN104500075B (en) Rope saw cuts the construction method of underground obstacle
CN106049281A (en) Deep-water construction method of bridge at water pebble soil and argillaceous sandstone areas and auxiliary working platform
CN204266134U (en) Heavy duty longspan steel truss girder walking type pushing device
CN101838988B (en) Comprehensive construction method for extracting anchor cable
CN101705687B (en) Deep foundation pit reinforced concrete waist rail detaching device and construction method
CN101851922A (en) Method for eliminating underground anchor rope/rod by using all casing drill
CN203684099U (en) Floating drag anchoring positioning system of high-pier large-span steel truss girder bridge
CN205529936U (en) Hang basket displacement device
CN202672149U (en) Height controller for underwater concrete grouting pile
CN107227862A (en) The gliding construction method of building
CN215052994U (en) Extraction and recovery device for steel pipe pile under bridge
CN203129146U (en) Extraction device for under-beam supporting bracket steel pipe pile in beach area
CN206143823U (en) Loess coombe district bridge substructure effect identification system
CN204738299U (en) Device for quickly forming slag collecting platform on high and steep slope
CN105089058A (en) Method and device for quickly forming slag collecting platform on high and steep slope
CN103306293A (en) Reinforcement structure and construction method for water-rich landslide
CN203922510U (en) A kind of simple and easy cable machine that is arranged in slope
CN204475350U (en) Bored pile construction system under high-voltage line
CN204898696U (en) Telescopic steel cofferdam
CN203924072U (en) The retaining wall supporting and protection structure of the super dark hand excavated pile of a kind of super large
CN211898417U (en) Construction structure based on cutter-suction type ground is wall local to replace campshed and is strutted
CN105672150B (en) Sand-sliding slope cutting reinforcement protection structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
CB03 Change of inventor or designer information

Inventor after: Zhang Dapeng

Inventor after: Jia Shaoqiang

Inventor after: Wang Chong

Inventor after: Zhang Fujun

Inventor after: Wang Lei

Inventor after: Wang Dongliang

Inventor after: Zhang Xufeng

Inventor after: Wang Jianjun

Inventor after: Zhang Lianrui

Inventor after: Cui Hongwei

Inventor after: Cai Tangtao

Inventor after: Guo Baolin

Inventor after: Li Ming

Inventor after: Luan Guohua

Inventor after: Li Jun

Inventor after: Gao Jie

Inventor after: Jin Xiaobo

Inventor before: Guo Baolin

COR Change of bibliographic data
TA01 Transfer of patent application right

Effective date of registration: 20151111

Address after: 266520 Qingdao economic and Technological Development Zone, Shandong, No. 182 Jinshatan Road

Applicant after: Qingdao Linchuan Engineering Technology Consulting Co., Ltd.

Applicant after: CCCC Fourth Highway Engineering Co., Ltd.

Address before: 266520 Qingdao economic and Technological Development Zone, Shandong, No. 182 Jinshatan Road

Applicant before: Qingdao Linchuan Engineering Technology Consulting Co., Ltd.

C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20151209

Termination date: 20160326