JPH10168879A - Pulling method for steel sheet pile - Google Patents

Pulling method for steel sheet pile

Info

Publication number
JPH10168879A
JPH10168879A JP33002596A JP33002596A JPH10168879A JP H10168879 A JPH10168879 A JP H10168879A JP 33002596 A JP33002596 A JP 33002596A JP 33002596 A JP33002596 A JP 33002596A JP H10168879 A JPH10168879 A JP H10168879A
Authority
JP
Japan
Prior art keywords
sheet pile
steel pipe
pipe sheet
ground
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP33002596A
Other languages
Japanese (ja)
Inventor
Miyuki Harashige
重 幸 原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP33002596A priority Critical patent/JPH10168879A/en
Publication of JPH10168879A publication Critical patent/JPH10168879A/en
Pending legal-status Critical Current

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a pulling method for a steel sheet pile by which the danger of collapsing the ground can be eliminated, and also the place of use of not limited due to its vibration and noise. SOLUTION: After the completion of constructing an underground structure, a steel pipe sheet pile 1 is pulled out by the following method. First, the soil improvement 2 is performed for the back of the steel pipe sheet pile 1, and back filling is bone for the inside of the works. After the reaction ground for pulling a steel pipe sheet pile 1 is improved, a guide wall 6 for muddy water replacement work and a jack is constricted. Next, after soil in the steel pipe sheet pipe 1 is discharged by an auger screw, mud replacement is performed for the periphery of the steel pipe sheet pile by a superhigh pressure injection pump to sever the relation with the ground. A pulling device (Japan Patent Laid-Open No. 3-126437) is installed on the guide wall 6 to pull out the steel pipe sheet pile 14. Thus, the steel pipe sheet pile 1 is pulled out, and then back foiling is done for the pull-out trace and grout is injected.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、市街地等で使用可
能な鋼管矢板の引抜き方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of drawing a steel pipe sheet pile usable in an urban area or the like.

【0002】[0002]

【従来の技術】土止めや水止めの目的で施工前に地盤に
打ち込まれた矢板は、施工後引抜かれるが、従来におい
ては、杭打ち機のバイブロハンマーを用い、このバイブ
ロハンマーのチャックで鋼管杭等の上端を直接つかむ
か、あるいは鋼管杭等の上端に鉄板を溶接し、これをつ
かんで引き抜いていた。しかし、前述の方法を用いる
と、バイブロハンマーのチャックを介して杭に振動を与
えるため、杭が変形、切断したり、また、その振動、騒
音等のため使用場所が制限される問題があった。
2. Description of the Related Art Sheet piles that have been driven into the ground prior to construction for the purpose of embankment and water stoppage are pulled out after construction. Conventionally, however, a vibratory hammer of a pile driver has been used, and a steel pipe has been attached with a chuck of the vibro hammer. The upper end of a pile or the like was directly grasped, or an iron plate was welded to the upper end of a steel pipe pile or the like, and this was grasped and pulled out. However, when the above-mentioned method is used, the pile is deformed and cut because the pile is vibrated through the chuck of the vibro hammer, and the place of use is limited due to the vibration and noise. .

【0003】そこで、本願出願人は前記問題点を解決す
べく、振動を利用しない鋼管杭等の引抜き装置を開発
し、平成3年特許願126437号に先行技術として開
示している。
In order to solve the above-mentioned problems, the present applicant has developed a drawing device for steel pipe piles or the like which does not utilize vibration, and disclosed it in Japanese Patent Application No. 26437/1991 as prior art.

【0004】[0004]

【発明が解決しようとする課題】前記鋼管杭等の引抜き
装置の利用により、振動による騒音等は軽減され、使用
できる場所は、従来のバイブロハンマーの利用に比較し
て広がった。しかし、市街地における仮設杭等を引抜き
撤去する場合においては、振動、騒音被害のみならず地
盤によっては地盤崩壊の恐れがあり、迅速な対応が望ま
れていた。
The use of the pulling device for steel pipe piles and the like reduces noise due to vibration and the like, and the place where the device can be used has been widened as compared with the use of a conventional vibro hammer. However, when pulling out and removing temporary piles and the like in an urban area, not only vibration and noise damage but also the possibility of ground collapse depending on the ground has been desired, and prompt measures have been desired.

【0005】そこで本発明は、前述のような問題点を解
消すべくなされたもので、前記引抜き装置(図6参照)
を用い、使用場所を制限しない無振動・無騒音で迅速か
つ安全な鋼管矢板の引抜き方法を提供することを目的と
し、開発したものである。
The present invention has been made in order to solve the above-mentioned problems, and the present invention has been made to solve the above-described draw-out device (see FIG. 6).
The purpose of the present invention is to provide a method for quickly and safely removing a sheet pile from a vibration-free, noise-free steel pipe that does not limit the place of use.

【0006】[0006]

【課題を解決するための手段】上記目的を達成するた
め、本発明では鋼管矢板の引抜き装置として、本願出願
人が先に開示した引抜き装置を用いることにした(特開
平6年10350号参照)。その装置は次のような構成
である。ジャッキが接続される柱状本体の下端に、引抜
方向に突出する取付軸を設けると共に、この取付軸に接
続金具を引抜方向に移動可能に設け、前記取付軸の下端
につかみ爪をその先端つかみ面が杭打面に対して進退可
能に軸着し、このつかみ爪の先端部と前記接続金具とを
連結リンクを介して連結し、柱状本体を上下動させるこ
とによりつかみ爪を開閉し、柱状本体を把持して杭を引
き上げるように構成した。
In order to achieve the above-mentioned object, in the present invention, a drawing device disclosed by the applicant of the present invention is used as a drawing device for steel pipe sheet piles (see Japanese Patent Application Laid-Open No. 10350/1994). . The device has the following configuration. At the lower end of the columnar main body to which the jack is connected, a mounting shaft protruding in the pulling direction is provided, and a connection fitting is provided on the mounting shaft so as to be movable in the pulling direction. Is attached to the pile driving surface so as to be able to advance and retreat, the tip of the gripping claw and the connection metal fitting are connected via a connecting link, and the columnar body is moved up and down to open and close the gripping claw, and And the pile was lifted up.

【0007】そして、前記した構成の引抜き装置を用
い、地下構造物の施工完了後、次のような工程からなる
引抜き方法で、鋼管矢板を引抜くようにした。 (第1工程)鋼管矢板の背後の地盤改良をする。 (第2工程)施工における仮設設備を撤去し、内部を埋
め戻す。 (第3工程)鋼管矢板の地上周辺部を地盤改良し、引抜
き用の反力地盤を形成する。 (第4工程)前記反力地盤の改良を施した鋼管矢板の地
上周辺部に、泥水置換作業およびジャッキ用のガイドウ
ォールを構築する。 (第5工程)オーガースクリューで鋼管矢板内部の土を
排出する。 (第6工程)鋼管矢板と周囲の地盤とを縁切りするた
め、超高圧噴射ポンプで泥水置換する。 (第7工程)前記ガイドウォール上に反力台、パワーケ
ーシングジャッキを備えた前記引抜き装置を設置し、該
引抜き装置にて鋼管矢板を引抜く。 (第8工程)前記引抜き完了後、前記鋼管矢板の引抜き
跡に埋め戻しを行い、地盤沈下防止対策としてグラウト
注入を行う。
[0007] Then, after the construction of the underground structure is completed, the steel pipe sheet pile is drawn out by the drawing method comprising the following steps, using the drawing device having the above-described configuration. (First step) The ground behind the steel sheet pile is improved. (Second step) Temporary equipment during construction is removed and the inside is backfilled. (Third step) The ground around the steel pipe sheet pile is ground-improved to form a reaction force ground for drawing. (Fourth Step) A guide wall for a muddy water replacement work and a jack is constructed around the ground of the steel pipe sheet pile having the improved reaction ground. (Fifth step) The soil inside the steel sheet pile is discharged with an auger screw. (Sixth step) In order to cut off the steel pipe sheet pile and the surrounding ground, muddy water is replaced by an ultra-high pressure injection pump. (Seventh step) The drawing device provided with a reaction table and a power casing jack is installed on the guide wall, and the steel sheet pile is drawn out by the drawing device. (Eighth step) After the drawing is completed, backfill is performed on the drawing trace of the steel pipe sheet pile, and grout is injected as a measure to prevent ground subsidence.

【0008】[0008]

【発明の実施の形態】次に添付図面に基づき、本発明の
具体的な一実施例を説明する。図1は共同溝設置工事の
完了後、鋼管矢板の背後を地盤改良した状態を示す概略
図、図2は共同溝内部を埋め戻した後、反力地盤改良を
行い、ガイドウォールを構築した状態を示す概略図、図
3はオーガースクリューで鋼管矢板内の土を排出する状
態を示す概略図、図4は超高圧噴射ポンプで泥水置換を
行なう状態を示す概略図、図5はガイドウォール上に、
引抜き装置Aを設置した状態を示す概略図、図6は鋼管
矢板の引抜き跡にグラウト注入を行う状態を示す概略図
である。また、図7は引抜き装置Aの一実施形態を示す
縦断断面図であり、左面(a)はチャックが閉じた状
態、右面(b)はチャックが開いた状態である。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS A specific embodiment of the present invention will be described below with reference to the accompanying drawings. FIG. 1 is a schematic view showing a state in which the ground behind the steel pipe sheet pile has been improved after the completion of the joint groove installation work, and FIG. 2 is a state in which the ground has been constructed by backfilling the inside of the common groove and making a ground reaction force improvement. FIG. 3 is a schematic view showing a state in which soil in a steel pipe sheet pile is discharged by an auger screw, FIG. 4 is a schematic view showing a state in which muddy water is replaced by an ultra-high pressure injection pump, and FIG. ,
FIG. 6 is a schematic diagram showing a state where the drawing device A is installed, and FIG. 6 is a schematic diagram showing a state where grout is injected into a drawing trace of a steel pipe sheet pile. FIG. 7 is a longitudinal sectional view showing one embodiment of the drawing device A, wherein the left side (a) shows a state where the chuck is closed, and the right side (b) shows a state where the chuck is opened.

【0009】まず、図面により、市街地等での共同溝設
置工事の完了後に行う鋼管矢板の引抜き方法について説
明する。図1において1は打設された鋼管矢板であり、
図3に示すごとく、複数本の鋼管矢板1が並列に並んで
いる。さらに、前記複数本の鋼管矢板1は、各々がジャ
ンクション7によって連結されている。前記ジャンクシ
ョン7は各鋼管矢板1に溶接固着されており、隣合うジ
ャンクション7同士で係合している。本実施例において
は断面円形状の鋼管矢板について説明するが、前記引抜
き装置(平成3年特許願126437号にかかる引抜装
置であり、以下本願実施例において引抜装置Aという)
が利用できる形状であれば、かかる矢板の形状が多角形
もしくは断面の一部で途切れていてもよく、特に限定は
されない。
First, a drawing method of a steel pipe sheet pile to be performed after completion of a joint groove installation work in an urban area or the like will be described with reference to the drawings. In FIG. 1, reference numeral 1 denotes a cast steel sheet pile,
As shown in FIG. 3, a plurality of steel pipe sheet piles 1 are arranged in parallel. Further, each of the plurality of steel pipe sheet piles 1 is connected by a junction 7. The junctions 7 are fixedly welded to the respective steel pipe sheet piles 1, and the adjacent junctions 7 are engaged with each other. In this embodiment, a steel pipe sheet pile having a circular cross section will be described, but the drawing device (a drawing device according to Japanese Patent Application No. 126437, hereinafter referred to as a drawing device A in the present application).
As long as the shape can be used, the shape of the sheet pile may be a polygon or a part of a cross section, and is not particularly limited.

【0010】まず図1の如く、共同溝設置工事完了後に
鋼管矢板1の背後に地盤改良2を施す(第1工程)。本
願発明における前記地盤改良の目的は、後述する泥水置
換を施した時の地盤崩壊の防止、及び反力地盤改良を行
う時の基礎固めにある。
First, as shown in FIG. 1, after the joint groove installation work is completed, ground improvement 2 is performed behind the steel pipe sheet pile 1 (first step). The purpose of the ground improvement in the present invention is to prevent ground collapse when muddy water replacement described later is performed and to solidify the foundation when performing reaction force ground improvement.

【0011】次に図2の如く、前記共同溝工事内部の支
保工5を撤去した後、前記工事内部を埋戻す(第2工
程)。なお埋戻し後の地盤は、後述する泥水置換の時に
地盤崩壊が発生しない地盤とする必要がある。前記埋戻
しの後、鋼管矢板1の地上周辺部に反力地盤改良3を施
し(第3工程)、重量物を設置した時または鋼管矢板1
を引抜く時の反力等に耐えうる土壌とする。そして、前
記反力地盤改良3を施した後に、ガイドウォール6を構
築し、機械の接近等による表土の崩れを防止する(第4
工程)。また、前記地盤改良2および前記反力地盤改良
3は、各々の目的を有効に達成すべく、地盤の状態、土
質に応じた工法を採用すればよい。
Next, as shown in FIG. 2, after removing the support 5 inside the common groove work, the inside of the work is backfilled (second step). In addition, the ground after backfilling needs to be ground in which ground collapse does not occur at the time of muddy water replacement described later. After the backfilling, a ground reaction improvement 3 is applied to the periphery of the steel pipe sheet pile 1 above the ground (third step), and when a heavy object is installed or the steel pipe sheet pile 1
The soil should be able to withstand the reaction force when pulling out. Then, after the reaction force ground improvement 3 is performed, the guide wall 6 is constructed to prevent collapse of the topsoil due to approach of a machine or the like (fourth embodiment).
Process). The ground improvement 2 and the reaction ground improvement 3 may employ a construction method according to the state of the ground and the soil quality in order to effectively achieve each purpose.

【0012】さらに、図3にて示すようにオーガースク
リュー8にて鋼管矢板1内部の土を排出する(第5工
程)。次に、図4の如く鋼管矢板1の周囲を地盤と縁切
りするため、超高圧噴射ポンプ10を利用して泥水置換
を行う。泥水置換の方法は、例えば泥水プラントにより
生成した泥水を高圧に圧縮し、ロータリーボーリングマ
シンのロッド部分に取り付けられたウォータージェット
管を介して、もしくは前記ロッド自体を介して前記ロッ
ドの地中先端部分から前記圧縮した泥水を噴出すること
により行なわれる。
Further, as shown in FIG. 3, the soil inside the steel pipe sheet pile 1 is discharged by the auger screw 8 (fifth step). Next, as shown in FIG. 4, in order to cut off the periphery of the steel pipe sheet pile 1 from the ground, muddy water is replaced using an ultra-high pressure injection pump 10. The method of muddy water replacement is, for example, compressing muddy water generated by a muddy water plant to a high pressure, and through a water jet pipe attached to a rod portion of a rotary boring machine, or through the rod itself, the underground tip portion of the rod This is carried out by ejecting the compressed mud from above.

【0013】また前記泥水置換の方法は、ロータリーボ
ーリングマシンの利用に限定されるものではなく、前記
ロッド部分にオーガースクリューを利用し、かかるオー
ガスクリューの先端部分から泥水を噴出する構成とする
こともできる。さらに、前記泥水置換の目的は、前記鋼
管矢板の引き抜きの際に抵抗を軽減し、引抜きを迅速に
行なう事を目的としている為、かかる目的を達成できれ
ば、泥水の利用に限定されない。
[0013] Further, the method for replacing muddy water is not limited to the use of a rotary boring machine, but may be configured such that an auger screw is used for the rod portion and muddy water is ejected from the tip of the auger screw. it can. Further, since the purpose of the muddy water replacement is to reduce the resistance at the time of pulling out the steel pipe sheet pile and to perform the pulling out quickly, the use of muddy water is not limited as long as this purpose can be achieved.

【0014】図4中の9は圧縮された泥水を地中に送り
こむ装置としてCJG(クラムジェットグラウト)マシ
ンを利用した例である。但し、圧縮された泥水を地中に
送りこめる機能を有する装置であれば、前記CJGマシ
ン9に限定されない。また、泥水置換の目的が鋼管矢板
1を引抜く場合の抵抗の軽減にあるため、泥水置換の方
法は、前記の方法および泥水の利用に限らず、前記泥水
置換の目的を有効に達成しうる方法であれば、他の工法
であっても良い(第6工程)。
Reference numeral 9 in FIG. 4 shows an example in which a CJG (clam jet grout) machine is used as a device for sending compressed muddy water into the ground. However, the device is not limited to the CJG machine 9 as long as it has a function of sending compressed muddy water into the ground. In addition, since the purpose of the muddy water replacement is to reduce the resistance when the steel pipe sheet pile 1 is pulled out, the method of the muddy water replacement is not limited to the method and the use of the muddy water, and the purpose of the muddy water replacement can be effectively achieved. If it is a method, another construction method may be used (sixth step).

【0015】前記泥水置換の後、図5の如く引抜き装置
Aを利用して鋼管矢板1を引抜く(第7工程)。前記引
抜き装置Aを利用するために、まずガイドウォール6上
に反力台Cを設置し、かかる反力台Cの上にパワーケー
シングジャッキBを固定する。前記パワーケーシングジ
ャッキBは、例えば同期して駆動される4本のジャッキ
B2と、当該ジャッキB2の可動体に接続され、開閉し
て柱状本体(ヤットコ)を抱持しうる一対の抱持体B1
からなり、柱状本体A1を抱持して上昇し、抱持を解除
して下降し、柱状本体A1を尺取式に上昇できるように
構成されている。
After the replacement of the muddy water, the steel pipe sheet pile 1 is pulled out using the drawing device A as shown in FIG. 5 (seventh step). In order to use the drawing device A, first, a reaction table C is installed on the guide wall 6 and the power casing jack B is fixed on the reaction table C. The power casing jack B is connected to, for example, four jacks B2 driven synchronously and a movable body of the jack B2, and a pair of holding members B1 that can be opened and closed to hold the columnar body (Yatco).
It is configured such that the columnar body A1 can be raised by holding the columnar body A1, released by holding the columnar body A1, and can be lifted up in a tapered manner.

【0016】前記柱状本体(ヤットコ)A1は打設され
た前記鋼管矢板1に継ぎ足すことが可能な形状をなして
おり、この柱状本体A1の先端部にチャックを取付けた
ものが引抜装置Aであり、当該引抜き装置A及びパワー
ケーシングジャッキBを利用して鋼管矢板1を引き抜
く。
The columnar main body (Yatco) A1 has a shape capable of being added to the cast steel pipe sheet pile 1, and the columnar main body A1 having a chuck attached to the tip thereof is a drawing device A. Then, the steel pipe sheet pile 1 is pulled out using the drawing device A and the power casing jack B.

【0017】引抜き装置Aを利用した鋼管矢板1の引抜
きの具体的な手順を以下に説明する。(図5参照) 前記ガイドウォール6上に反力台Cを設置する。 前記反力台C上にパワーケーシングジャッキBを設
置すると共に、前記鋼管矢板1の上端に引抜き装置Aを
連結し、抱持体B1で柱状本体A1を抱持する。 パワーケーシングジャッキBにより鋼管矢板1を尺
取り式に引抜く。 引抜かれた鋼管矢板1の上部を切断除去する。 充填土で埋め戻し、ジャンクションが外れるまで前
記〜を繰り返す。 ジャンクションが外れたらボウズ引き抜きを行う。
The specific procedure for drawing the steel pipe sheet pile 1 using the drawing device A will be described below. (See FIG. 5) A reaction table C is set on the guide wall 6. A power casing jack B is installed on the reaction table C, a drawing device A is connected to an upper end of the steel pipe sheet pile 1, and a columnar main body A1 is held by a holding body B1. The steel pipe sheet pile 1 is pulled out with a power casing jack B in a length-measuring manner. The upper part of the drawn steel pipe sheet pile 1 is cut and removed. Backfill with filled soil and repeat ~ until the junction is disengaged. When the junction comes off, pull out the bow.

【0018】次に、前記引き抜き装置Aについて説明す
る。図5、図7に示すように、引抜き装置Aは、主とし
て柱状本体(ヤットコ)A1、取付軸A2、接続金具A
3、つかみ爪A5、連結リンクA4から構成される。柱
状本体A1は、例えば円筒形の筒体であり、上部に一対
の吊り下げ用金具14を設けてクレーンにて吊り上げ可
能とし、下部にはチャックを接続するための取付用基板
15を取付ける。この柱状本体A1は前記の通り、前記
パワーケーシングジャッキBの抱持体B1により抱持さ
れて引き上げられる部分であり、これに耐えうる強度を
持ち、また前記パワーケーシングジャッキBが尺取式の
引き上げを行いうる長さとする。
Next, the drawing device A will be described. As shown in FIGS. 5 and 7, the pulling-out device A mainly includes a columnar main body (Yatco) A1, a mounting shaft A2, and a connection fitting A.
3. It is composed of a gripper A5 and a link A4. The columnar main body A1 is, for example, a cylindrical body, and is provided with a pair of hanging metal fittings 14 at an upper portion so that the columnar main body A1 can be lifted by a crane. At a lower portion, a mounting substrate 15 for connecting a chuck is mounted. As described above, the pillar-shaped main body A1 is a portion that is held and lifted by the holding body B1 of the power casing jack B, has strength enough to withstand this, and the power casing jack B is a scale-up type lifter. Is long enough to perform

【0019】取付軸A2は、取付用基板15の取付孔1
6に上方から挿入してそのフランジ17により係り止め
し、鋼管矢板1の上端部内に突出するようにする。接続
金具A3は、鋼管矢板1の上端に載置される接続基板1
8と、鋼管矢板1の上端部外面を覆うリング状のガイド
板19から構成し、接続基板18の中央に穿設した挿通
孔20に取付軸A2を挿通することにより、取付用基板
15の下方において柱状本体A1対して引抜方向に相対
移動可能とする。なお、ガイド板19は二つのくさび状
部材から構成し、これを重ね合わせてボルトで結合する
ようにしてもよい。(図6参照)
The mounting shaft A2 is provided in the mounting hole 1 of the mounting substrate 15.
6 is inserted from above and engaged with the flange 17 so as to project into the upper end of the steel pipe sheet pile 1. The connection fitting A3 is a connection board 1 mounted on the upper end of the steel pipe sheet pile 1.
8 and a ring-shaped guide plate 19 that covers the outer surface of the upper end portion of the steel pipe sheet pile 1. The mounting shaft A2 is inserted through an insertion hole 20 formed in the center of the connection substrate 18 so that the lower part of the mounting substrate 15 In the drawing, relative to the columnar main body A1 in the pulling-out direction. The guide plate 19 may be composed of two wedge-shaped members, which may be overlapped and connected by bolts. (See Fig. 6)

【0020】そして、つかみ爪A5は、鋼管矢板1の内
面に当接可能な平面視円弧状のつかみ面23を有する爪
部材21と、この爪部材は上部先端に取付けられる一対
の支持レバー22から構成され、支持レバー22の基部
を取付軸A2の先端部に水平ピン28を介して取付ける
ことにより、つかみ面23が鋼管矢板1の内面に対して
進退するよう構成する。連結リンクA4は、接続基板1
8とつかみ爪A5の上部先端部とを連結すると共に、両
端をそれぞれ接続基板18の下面に支持レバー22の上
部にピン24を介して取付けることにより揺動し、取付
軸A2の上下動により、つかみ爪A5の上部先端部が上
下動するのを阻止しつつ鋼管矢板1の内面に対して揺動
進退させる部材である。
The gripping claw A5 is formed by a claw member 21 having a gripping surface 23 having an arc shape in a plan view that can abut on the inner surface of the steel sheet pile 1 and a pair of support levers 22 attached to the upper end. The gripping surface 23 is configured to advance and retreat with respect to the inner surface of the steel pipe sheet pile 1 by attaching the base of the support lever 22 to the distal end of the attachment shaft A2 via the horizontal pin 28. The connection link A4 is connected to the connection board 1
8 and the upper end of the gripping claw A5 are connected to each other, and both ends are attached to the lower surface of the connection board 18 via the pins 24 above the support lever 22, respectively. It is a member that swings forward and backward with respect to the inner surface of the steel sheet pile 1 while preventing the upper end of the gripping claw A5 from moving up and down.

【0021】これらつかみ爪A5と連結リンクA4の長
さや角度は、取付軸A2が接続金具A3に対して上昇す
ると、つかみ面23が鋼管矢板1の内面に押圧され、逆
に下降すると、つかみ面23が鋼管矢板1の内面から所
定距離だけ離れるように設定しておく。また、取付用基
板15と接続基板18の側面には、重なり合う連結片2
5、26をそれぞれ突設し、これら連結片25、26を
固定ピン27で連結することにより、取付用基板15と
接続基板18を当接させた状態で固定し、つかみ爪A5
のつかみ面23が鋼管矢板1の内面から離れる開状態に
保持できるようにする。なお、つかみ爪A5は、取付軸
A2の両側に一対で配設し、鋼管矢板1の内面全体にわ
たってつかめるようにする。また、つかみ面23には例
えば引抜き方向に平行な歯を多数刻設しておく。
The lengths and angles of the gripping claws A5 and the connecting links A4 are such that when the mounting shaft A2 rises with respect to the connection fitting A3, the gripping surface 23 is pressed against the inner surface of the steel sheet pile 1 and, conversely, when the gripping surface A3 descends. 23 is set so as to be separated from the inner surface of the steel pipe sheet pile 1 by a predetermined distance. In addition, the connecting pieces 2 overlapping each other are provided on the side surfaces of the mounting board 15 and the connection board 18.
5 and 26 are respectively protruded, and these connecting pieces 25 and 26 are connected by fixing pins 27 so that the mounting board 15 and the connecting board 18 are fixed in contact with each other.
Of the steel pipe sheet pile 1 can be held in an open state away from the inner surface thereof. The gripping claws A5 are provided as a pair on both sides of the mounting shaft A2 so that they can be gripped over the entire inner surface of the steel sheet pile 1. In addition, for example, a large number of teeth parallel to the pulling-out direction are engraved on the gripping surface 23.

【0022】以上のような構成において前記引抜き装置
Aは以下のように作動する。 固定ピン27で連結片25、26を連結することに
より、一対のつかみ爪A5のつかみ面23が前記鋼管矢
板内面から退避する開状態に保持し、前記柱上本体A1
を吊り、下部のつかみ爪A5等のチャック部分を鋼管矢
板1の上端部に嵌装する。この際、接続金具A3のリン
グ状ガイド板19が案内となってつかみ爪A5が鋼管矢
板1内に円滑に挿入される。 固定ピン27を抜き、パワーケーシングジャッキB
で柱状本体A1を例えば50mmほど持ち上げると、接
続金具A3に対して取付軸A2が上昇し、連結リンクA
4の作用によりつかみ爪A5のつかみ面23が鋼管矢板
1の内面に向かって進出し、鋼管矢板1の内面を押圧し
て鋼管矢板1を内側から絞め付ける。
In the above configuration, the drawing device A operates as follows. By connecting the connecting pieces 25 and 26 with the fixing pins 27, the gripping surfaces 23 of the pair of gripping claws A5 are held in an open state in which the gripping surfaces 23 are retracted from the inner surface of the steel pipe sheet pile, and the column main body A1 is held.
And a lower chuck portion such as a gripper A5 is fitted to the upper end of the steel sheet pile 1. At this time, the ring-shaped guide plate 19 of the connection fitting A3 serves as a guide, and the gripping claw A5 is smoothly inserted into the steel pipe sheet pile 1. Pull out the fixing pin 27 and set the power casing jack B
When the columnar main body A1 is lifted by, for example, about 50 mm, the mounting shaft A2 rises with respect to the connection fitting A3, and the connecting link A
By the action of 4, the gripping surface 23 of the gripping claw A5 advances toward the inner surface of the steel pipe sheet pile 1 and presses the inner surface of the steel pipe sheet pile 1 to squeeze the steel pipe sheet pile 1 from the inside.

【0023】 柱状本体A1と鋼管矢板1が一体化
し、柱状本体A1をパワーケーシングジャッキBで持ち
上げれば、鋼管矢板1が引き抜かれる。 柱状本体A1の抱持、ジャッキB2の1ストローク
分の上昇、抱持の解除、ジャッキB2の1ストローク分
の下降を順次繰り返し、鋼管矢板1が所定高さまで引き
抜かれると、柱状本体A1をジャッキB2により鋼管矢
板1に対して下降させれば、つかみ爪A5が開状態とな
る。 固定ピン27により連結片25、26を連結する
と、つかみ爪A5が開状態で固定される。 クレーンにて柱状本体A1を吊り、鋼管矢板1の上
端から取り除く。
When the columnar main body A1 and the steel pipe sheet pile 1 are integrated and the columnar main body A1 is lifted by the power casing jack B, the steel pipe sheet pile 1 is pulled out. When the holding of the columnar body A1, the lifting of the jack B2 for one stroke, the release of the holding, and the lowering of the jack B2 for one stroke are sequentially repeated, when the steel pipe sheet pile 1 is pulled out to a predetermined height, the columnar body A1 is moved to the jack B2. When it is lowered with respect to the steel sheet pile 1, the gripping claws A5 are opened. When the connecting pieces 25 and 26 are connected by the fixing pin 27, the grip claw A5 is fixed in an open state. The columnar main body A1 is suspended by a crane and removed from the upper end of the steel sheet pile 1.

【0024】さらに前記鋼管矢板1の引抜きが終了し、
前記ガイドウォール6を撤去した後、図6に示す如くボ
ーリングマシン12のロッド13を介して、引抜き跡部
にグラウト注入を行う(第8工程)。前記グラウトの注
入には、公知のグラウト工法を利用するようにした。
Further, the drawing of the steel pipe sheet pile 1 is completed,
After the guide wall 6 is removed, grout is injected into the drawing trace portion via the rod 13 of the boring machine 12 as shown in FIG. 6 (eighth step). A known grouting method was used for the grout injection.

【0025】[0025]

【発明の効果】以上詳述したように、地下構造物の施工
完了後の鋼管矢板の引抜きに前記引抜き装置を利用する
事により、特に騒音問題等が発生し易い市街地等で、安
全かつ迅速に鋼管矢板の引抜きを実施できる。そして、
地盤改良および反力地盤改良を施しているので、地盤崩
壊の恐れが無く、また泥水置換および鋼管矢板内部の土
をオーガースクリューにて排土するので、鋼管矢板引抜
きの際に生ずる摩擦抵抗を軽減できる。
As described in detail above, the use of the above-mentioned drawing apparatus for drawing out the steel pipe sheet piles after the completion of the construction of the underground structure enables safe and quick operation particularly in an urban area where noise problems are likely to occur. The steel pipe sheet pile can be pulled out. And
The ground improvement and reaction ground improvement have been performed, so there is no danger of ground collapse, and the muddy water is replaced and the soil inside the steel pipe sheet pile is discharged with an auger screw, reducing frictional resistance generated when pulling steel pipe sheet pile. it can.

【図面の簡単な説明】[Brief description of the drawings]

【図1】共同溝設置工事完了後、鋼管矢板の背後を地盤
改良した状態を示す概略図
FIG. 1 is a schematic diagram showing a state in which the ground behind a steel pipe sheet pile has been improved after the completion of installation work of a common gutter.

【図2】共同溝内部を埋戻した後、反力地盤改良を行い
ガイドウォールを構築した状態を示す概略図
FIG. 2 is a schematic view showing a state in which a guide wall has been constructed by backfilling the interior of the common groove and then improving the reaction ground.

【図3】オーガースクリューで鋼管矢板内の土を排出す
る状態を示す概略図
FIG. 3 is a schematic view showing a state in which soil in a steel pipe sheet pile is discharged by an auger screw.

【図4】超高圧噴射ポンプで泥水置換を行なう状態を示
す概略図
FIG. 4 is a schematic diagram showing a state in which muddy water is replaced by an ultra-high pressure injection pump.

【図5】ガイドウォール上に、引抜き装置Aを設置した
状態を示す概略図
FIG. 5 is a schematic diagram showing a state in which a drawing device A is installed on a guide wall.

【図6】鋼管矢板の引抜き跡にグラウト注入を行う状態
を示す概略図
FIG. 6 is a schematic view showing a state in which grout is injected into a drawing trace of a steel sheet pile.

【図7】引抜き装置Aの一実施形態を示す縦断断面図FIG. 7 is a longitudinal sectional view showing one embodiment of a drawing device A;

【符号の説明】[Explanation of symbols]

1:鋼管矢板 2:地盤改良 3:反力地盤改良 4:泥水置換部分 5:支保工 6:ガイドウォール 7:ジャンクション 8:オーガースクリュー 9:CJGマシン A:引抜き装置A A1:柱状本体 A2:取付軸 A3:接続金具 A4:連結リンク A5:つかみ爪 B:パワーケーシングジャッキ C:反力台 10:超高圧噴射ポンプ 11:泥水プラント 12:ボーリングマシン 13:ロッド 14:吊り下げ用金具 15:取付用基板 16:取付孔 17:フランジ 18:接続基板 19:ガイド板 20:挿通孔 21:爪部材 22:支持レバー 23:つかみ面 24:ピン 25,26:連結片 27:固定ピン 28:水平ピン 1: Steel pipe sheet pile 2: Ground improvement 3: Reaction ground improvement 4: Muddy water replacement part 5: Shoring work 6: Guide wall 7: Junction 8: Auger screw 9: CJG machine A: Drawing device A A1: Column body A2: Mounting Shaft A3: Connection fitting A4: Connection link A5: Gripping claw B: Power casing jack C: Reaction table 10: Ultra-high pressure injection pump 11: Muddy water plant 12: Boring machine 13: Rod 14: Hanging fitting 15: Mounting Substrate 16: Mounting hole 17: Flange 18: Connection board 19: Guide plate 20: Insertion hole 21: Claw member 22: Support lever 23: Gripping surface 24: Pin 25, 26: Connection piece 27: Fixing pin 28: Horizontal pin

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】ジャッキが接続される柱状本体の下端に、
引抜方向に突出する取付軸を設けると共に、この取付軸
に接続金具を引抜方向に移動可能に設け、前記取付軸の
下端につかみ爪をその先端つかみ面が杭打面に対して進
退可能に軸着し、このつかみ爪の先端部と前記接続金具
とを連結リンクを介して連結し、柱状本体を上下動させ
ることによりつかみ爪を開閉し、柱状本体を把持して杭
を引き上げるように構成した引抜き装置による鋼管矢板
の引抜き方法であって、地下構造物の施工完了後、次の
第1工程〜第8工程の各工程により行うことを特徴とす
る鋼管矢板の引抜き方法。 (第1工程)鋼管矢板の背後の地中地盤を改良する。 (第2工程)施工における仮設設備を撤去し、内部を埋
め戻す。 (第3工程)鋼管矢板の地上周辺部を地盤改良し、引抜
き用の反力地盤を形成する。 (第4工程)前記反力地盤の改良を施した鋼管矢板の地
上周辺部に、泥水置換作業およびジャッキ用のガイドウ
ォールを構築する。 (第5工程)オーガースクリューで鋼管矢板内部の土を
排出する。 (第6工程)鋼管矢板と周囲の地盤とを縁切りするた
め、超高圧噴射ポンプで泥水置換する。 (第7工程)前記ガイドウォール上に反力台、パワーケ
ーシングジャッキを備えた前記引抜き装置を設置し、該
引抜き装置にて鋼管矢板を引抜く。 (第8工程)前記引抜き完了後、前記鋼管矢板の引抜き
跡に埋め戻しを行い、地盤沈下防止対策としてグラウト
注入を行う。
(1) At the lower end of a columnar body to which a jack is connected,
A mounting shaft protruding in the pull-out direction is provided, and a connection fitting is provided on the mounting shaft so as to be movable in the pull-out direction. The gripping claw was connected to the tip of the gripping claw and the connection fitting via a connection link, and the columnar body was moved up and down to open and close the gripping claw. A method for drawing a steel pipe sheet pile by a drawing apparatus, wherein the method is performed by the following first to eighth steps after completion of construction of an underground structure. (First step) The underground ground behind the steel sheet pile is improved. (Second step) Temporary equipment during construction is removed and the inside is backfilled. (Third step) The ground around the steel pipe sheet pile is ground-improved to form a reaction force ground for drawing. (Fourth Step) A guide wall for a muddy water replacement work and a jack is constructed around the ground of the steel pipe sheet pile having the improved reaction ground. (Fifth step) The soil inside the steel sheet pile is discharged with an auger screw. (Sixth step) In order to cut off the steel pipe sheet pile and the surrounding ground, muddy water is replaced by an ultra-high pressure injection pump. (Seventh step) The drawing device provided with a reaction table and a power casing jack is installed on the guide wall, and the steel sheet pile is drawn out by the drawing device. (Eighth step) After the drawing is completed, backfill is performed on the drawing trace of the steel pipe sheet pile, and grout is injected as a measure to prevent ground subsidence.
JP33002596A 1996-12-10 1996-12-10 Pulling method for steel sheet pile Pending JPH10168879A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP33002596A JPH10168879A (en) 1996-12-10 1996-12-10 Pulling method for steel sheet pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP33002596A JPH10168879A (en) 1996-12-10 1996-12-10 Pulling method for steel sheet pile

Publications (1)

Publication Number Publication Date
JPH10168879A true JPH10168879A (en) 1998-06-23

Family

ID=18227943

Family Applications (1)

Application Number Title Priority Date Filing Date
JP33002596A Pending JPH10168879A (en) 1996-12-10 1996-12-10 Pulling method for steel sheet pile

Country Status (1)

Country Link
JP (1) JPH10168879A (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010065501A (en) * 2008-09-12 2010-03-25 Ohbayashi Corp Pile pulling-out method
CN103911996A (en) * 2014-04-01 2014-07-09 中铁六局集团有限公司 Construction method for pulling out steel sheet piles close to existing buildings
CN104213559A (en) * 2013-03-26 2014-12-17 青岛林川工程技术咨询有限公司 Pull-out method for pull-out equipment of bracket steel pipe pile under girder in beach area
CN104612155A (en) * 2015-02-04 2015-05-13 绥棱县宏运养鱼场 Removing device of well pipe of abandoned water well
CN104790397A (en) * 2015-05-05 2015-07-22 张继红 Sleeve method damaged pile treatment and construction method and construction device using same
CN105908744A (en) * 2015-02-09 2016-08-31 张继红 Pore pressure counterforce construction method, construction device and soil clearing device
CN106193042A (en) * 2016-07-20 2016-12-07 中建八局第三建设有限公司 Next-door neighbour's underground structure sandy soil layer is gone along with sb. to guard him obstacle pile sweep-out method at ground wall
CN106677183A (en) * 2016-11-30 2017-05-17 中铁十六局集团第三工程有限公司 Bridge abutment prestressed pipe pile pulling-out method and matched device thereof
CN108894224A (en) * 2018-08-03 2018-11-27 中冶沈勘工程技术有限公司 A kind of method for pulling out of static pressure pipe pile
CN110306540A (en) * 2019-06-26 2019-10-08 广州穗岩土木科技股份有限公司 A kind of construction method of full circle swinging casing pile foundation pore-forming
CN113737796A (en) * 2021-09-07 2021-12-03 江苏兴宇建设集团有限公司 Construction method for high-pressure water flushing assisted pile driving and pile pulling synchronous grouting of steel plate pile

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010065501A (en) * 2008-09-12 2010-03-25 Ohbayashi Corp Pile pulling-out method
CN104213559A (en) * 2013-03-26 2014-12-17 青岛林川工程技术咨询有限公司 Pull-out method for pull-out equipment of bracket steel pipe pile under girder in beach area
CN104213559B (en) * 2013-03-26 2015-12-09 青岛林川工程技术咨询有限公司 Intertidal zone beam lower carriage steel pipe pile extracts the method for pulling out of equipment
CN103911996B (en) * 2014-04-01 2015-08-19 中铁六局集团有限公司 Close on existing building steel sheet pile and pull out construction method
CN103911996A (en) * 2014-04-01 2014-07-09 中铁六局集团有限公司 Construction method for pulling out steel sheet piles close to existing buildings
CN104612155A (en) * 2015-02-04 2015-05-13 绥棱县宏运养鱼场 Removing device of well pipe of abandoned water well
CN105908744A (en) * 2015-02-09 2016-08-31 张继红 Pore pressure counterforce construction method, construction device and soil clearing device
CN104790397A (en) * 2015-05-05 2015-07-22 张继红 Sleeve method damaged pile treatment and construction method and construction device using same
CN106193042A (en) * 2016-07-20 2016-12-07 中建八局第三建设有限公司 Next-door neighbour's underground structure sandy soil layer is gone along with sb. to guard him obstacle pile sweep-out method at ground wall
CN106677183A (en) * 2016-11-30 2017-05-17 中铁十六局集团第三工程有限公司 Bridge abutment prestressed pipe pile pulling-out method and matched device thereof
CN106677183B (en) * 2016-11-30 2019-11-22 中铁十六局集团第三工程有限公司 A kind of abutment pile for prestressed pipe method for pulling out and its corollary equipment
CN108894224A (en) * 2018-08-03 2018-11-27 中冶沈勘工程技术有限公司 A kind of method for pulling out of static pressure pipe pile
CN110306540A (en) * 2019-06-26 2019-10-08 广州穗岩土木科技股份有限公司 A kind of construction method of full circle swinging casing pile foundation pore-forming
CN113737796A (en) * 2021-09-07 2021-12-03 江苏兴宇建设集团有限公司 Construction method for high-pressure water flushing assisted pile driving and pile pulling synchronous grouting of steel plate pile

Similar Documents

Publication Publication Date Title
JPH10168879A (en) Pulling method for steel sheet pile
JP6103575B2 (en) Cast-in-place pile construction device and cast-in-place pile construction method
CA2070417A1 (en) Method for the mounting of underground pipelines
KR20010073338A (en) File foundation work and equipment
JP6319942B2 (en) Steel pipe sheet pile press-in method and pipes
JP2820247B2 (en) Pile pull-out method and device
JP3204616B2 (en) Steel pipe press-fitting method in narrow space area with sky restriction
JP2006016756A (en) Extraction method for existing pile
JP4719041B2 (en) Pile press-in method and pile press-out machine
JPH0610350A (en) Device for extracting steel pipe pile
JP7481947B2 (en) Casing removal device and removal method
CN219430743U (en) Tubular pile repairing device
JP2000154541A (en) Pulling-out device for existing pile
JPH08120676A (en) Earth retaining timbering detaching method and device therefor
KR102532616B1 (en) PHC file withdrawal method using the high pressure water spraying
KR102532617B1 (en) PHC file withdrawal method using the crack prevention device insertion and high frequency vibration
JPH10102974A (en) Method for constructing vertical shaft
JP3080840B2 (en) How to remove underground pipes
JP2581551B2 (en) Pile press-in assist device
JP2002030881A (en) Casing for shaft
JPH07127060A (en) Pile pressing-in machine and pile pressing-in and drawing-out construction method
JPH06129181A (en) Tunnel boring construction method and tunnel construction support device
JP3587756B2 (en) Tunnel backfill apparatus and tunnel backfill method
JP3393545B2 (en) Method of connecting buried pipe in excavation propulsion device and propulsion device
JP2964406B1 (en) Driving protection device for protective fence post