CN104195919B - Sandstone waste material sidewalk construction process - Google Patents

Sandstone waste material sidewalk construction process Download PDF

Info

Publication number
CN104195919B
CN104195919B CN201410426950.0A CN201410426950A CN104195919B CN 104195919 B CN104195919 B CN 104195919B CN 201410426950 A CN201410426950 A CN 201410426950A CN 104195919 B CN104195919 B CN 104195919B
Authority
CN
China
Prior art keywords
finished particle
steel bar
geotextiles
laid
sand
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201410426950.0A
Other languages
Chinese (zh)
Other versions
CN104195919A (en
Inventor
曾德明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhu Longhu Construction Engineering Co ltd
Original Assignee
Chengdu Laibao Petroleum Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Laibao Petroleum Equipment Co Ltd filed Critical Chengdu Laibao Petroleum Equipment Co Ltd
Priority to CN201410426950.0A priority Critical patent/CN104195919B/en
Publication of CN104195919A publication Critical patent/CN104195919A/en
Application granted granted Critical
Publication of CN104195919B publication Critical patent/CN104195919B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

Disclosed by the invention is sandstone waste material sidewalk construction process.The present invention includes (1) to sieve, select process; (2) building debris is ground into the finished particle being less than 10cm; (3) after consolidation, be laid on ground with the steel bar that cross section is groove-like, and then be filled between two steel bars with finished particle; Wherein the height of steel bar is greater than 15cm, and steel bar is provided with through hole and lays one deck geotextiles in the groove of this steel bar; (4) after finished particle has been laid, between adjacent two steel bars, the geotextiles of more than one deck is laid, and by the end winding support of geotextiles on steel bar; (5) after geotextile laying completes, then in geotextiles, lay the thick grains of sand of one deck 10cm ~ 20cm, after fine sand has been laid, then lay face brick with concrete on grains of sand top.The present invention has can save material cost, protection of the environment, and Quick drainage, reducing face brick lower floor, depression degree is different everywhere causes the advantages such as rough situation generation.

Description

Sandstone waste material sidewalk construction process
Technical field
The present invention relates to a kind of road surfacing method, what be specifically related to is sandstone waste material sidewalk construction process.
Background technology
Sidewalk (sidewalk; Footway) refer in road by the part specializing in walk that road kerb or guardrail and other similar facilities are separated.In city, sidewalk is very general, Pang Junyou sidewalk, general street.Across meadow or trees between the sidewalk in some place and motorway.
In city also known as the street of continuous architectural complex, refer to and exceed roadway sections to building line from the road kerb marking roadway boundary line, kerb (flowing water stone), specialize in walk, forbid illegally occupying, also forbid that vehicle sails into, but it is current on pavement that walk one's bicycle walking or disabled person on pavement shake wheel-chair, should treat by pedestrian.Exit, lane or unit exit are by sidewalk truncation part, though be the area that pedestrian and vehicle pass through jointly, must be considered as is the sidewalk be truncated, and vehicle has passed through pedestrian when passing through herein, must slow down or Stop and give way, to ensure safety.
The working procedure of sidewalk surface construction mainly comprises surveying setting-out, based process, tile work and on-the-spot cleaning.Described based process: be that the table of ground soil or foreign material are removed, be then aided with manual amendment with after Mechanical Planarization compacting.Wherein, the existing process of deployment of this tile work is as follows:
(1) lime fly ash gravel compound is adopted to be laid on ground as bottom, the thick 20cm of substructure;
(2) pave bed course, bed course adopts M7.5 cement mortar, and thickness is 2cm, keeps flat gently when paving, and beats and stablizes levelling, but must not damage corner with rubber hammer;
(3) basic unit first flattens before paving by face brick, with road kerb top, both sides be as the criterion hang longitudinally with horizontal altitude traverse, first segmentation floating screed, after fill a vacancy and mat formation, check position and elevation at any time;
(4) finally face brick is laid.
Because adopting the preserving period of above-mentioned face brick to be generally no less than 7 days, the walking about and colliding of pedestrian, vehicle etc. should be forbidden during this period, and then cause construction period longer.
And after having constructed, if run into rain continuously or rainstorm weather time, rainwater cannot seepage fast, and then is stacked into face brick lower floor, causes drainage effect bad.And because long-term rain soaks, easily cause face brick lower floor depression degree everywhere different, and then cause face brick uneven, and then cause pedestrian very inconvenient when walking.
And be deposited in face brick lower floor due to rainwater, and to differ the uneven row of tile surface caused due to face brick lower floor depression degree everywhere, when easily causing walking, ponding splash is on pedestrian's leg.
Summary of the invention
The object of the invention is to solve existing People's Bank of China road surface face brick lay after ponding can not discharge fast, the problem of brick uneven impact walking quality after a period of time, provide a kind of can Quick drainage, reduce the face brick lower floor different sandstone waste material sidewalk construction process causing uneven situation to occur of depression degree everywhere.
For solving above-mentioned shortcoming, technical scheme of the present invention is as follows:
Sandstone waste material sidewalk construction process, comprises the following steps:
(1) sieve, select process: the grains of sand utilizing screening plant fineness modulus to be less than 3.7 sieve out from building debris; Metal in building debris, wooden unit and plastics are picked out;
(2) break process: put into construction waste crusher by selecting rear remaining building debris in step (1), and be ground into the finished particle being less than 10cm, and then process through step (1);
(3) after consolidation, be laid on ground with the steel bar that cross section is groove-like, and then be filled between two steel bars with the finished particle being less than 10cm; Wherein the height of steel bar is greater than 15cm, and steel bar is provided with through hole and lays one deck geotextiles in the groove of this steel bar, and the laying depth of finished particle is not less than 20cm;
(4) after finished particle has been laid, between adjacent two steel bars, the geotextiles of more than one deck is laid, and by the end winding support of geotextiles on steel bar;
(5) after geotextile laying completes, then the grains of sand sieved out in step (1) and step (2) are routed in geotextiles, then lay face brick with concrete on grains of sand top.
The present invention adopts the paving mode of the upper strata grains of sand, lower floor's finished particle, effectively improves the leak rate of ponding; The laying of geotextiles between the upper strata grains of sand and lower floor's finished particle, effectively avoids the grains of sand to flow in lower floor's finished particle along with rainwater, ensures the seepage effect of ponding.
Meanwhile, the laying of this geotextiles, not only effective in isolating between the grains of sand and finished particle and then ensureing seepage effect, and can also reinforce finished particle top layer when lower floor's finished particle has part depression, effectively reduce the effect of depression.
And the present invention adopt the grains of sand and finished particle be all adopt building debris processing after make, the environment stress that building waste brings can be alleviated, simultaneously save building waste transport and process time and cost, effect is very remarkable.
Magnetic method is adopted to be picked out from remaining building debris by ironwork in described step (1); And then the building debris after selecting is put into salt solution, by salt buoyancy of water, the wooden unit in building debris and plastics are picked out, finally by artificial method, other metal products are picked out from building debris again.
Ironwork, plastic products and the woodwork in building waste can not only be filtered out by above-mentioned screening technique substantially, and abundant fragmentation can be carried out to the material of Large stone substantially, save the broken time.
Because the space of contact surface between finished particle and ground is comparatively large, the pressure causing the position ground of the Contact of finished particle ground to bear is comparatively large, thus easily causes the region yields degree at often walking position larger.In order to solve the problem, the present invention is also equipped with the blinding that a layer thickness is 5 ~ 10cm between described ground and finished particle, and this blinding is obtained by the finished particle fragmentation in step (2), and the particle after fragmentation is less than 3cm.
When to rain continuously or when raining in torrents, rainwater infiltrates face brick lower floor, is stacked into the gap between the grains of sand and finished particle, when ground can not receive the water of infiltration completely, road pavement can impact, thus, be communicated with the aqueduct of the position, roadside being positioned at People's Bank of China road surface at finished particle place.Due to the setting of aqueduct, effectively discharge the ponding be deposited in finished particle, while the ecology not affecting this road surface place of People's Bank of China, effectively ensure that the discharge of ponding, effect is very remarkable.
Preferred as one, described grains of sand laying depth is 10cm ~ 20cm; Distance between described adjacent two steel bars is 2m ~ 4m.
The present invention compared with prior art, has the following advantages and beneficial effect:
Drainage effect of the present invention is good, avoids ponding; Effectively can reduce the sinking degree on face brick top layer simultaneously, so when can effectively avoid pedestrian to walk ponding splash to it.
Detailed description of the invention
Below in conjunction with embodiment, the present invention is described in further detail, but embodiments of the present invention are not limited thereto.
Embodiment
Sandstone waste material sidewalk construction process, is characterized in that, form primarily of following steps:
(1) screening process: the grains of sand utilizing screening plant fineness modulus to be less than 3.7 sieve out from building debris.
Select separation: adopt magnetic method to be picked out from remaining building debris by ironwork; And then the building debris after selecting is put into salt solution, by salt buoyancy of water, the wooden unit in building debris and plastics are picked out, finally by artificial method, other metal products are picked out from building debris again.
Wherein, the metal product picked out can be classified recovery double teeming, as aluminium alloys, copper, color steel, ironwork, stainless steel etc., after this step sieves out, is transported to garbage reclamation station, by recycle bin by its recycling.And plastic products in this step are also the same with metal product, are transported to recycle bin and recycle.
The woodwork reclaimed in this step can be recycled as metal product is the same with plastic products, or directly broken on the spot, after building, is buried in the substrate at the bottom of flower stylobate, when can be used as the fertilizer of plant in colored platform after its corruption.
(2) break process: put into construction waste crusher by selecting rear remaining building debris in step (1), and the finished particle being ground into that granularity is less than 10cm; Then finished particle is processed through step (1) again.
The ironwork etc. be buried in block building debris can be separated by the method from building debris, again by screening process with select and be separated after, effectively the grains of sand and finished particle are distinguished again.
(3) after consolidation, be laid on ground with the steel bar that cross section is groove-like, and then be filled between two steel bars with finished particle; Wherein the height of steel bar is greater than 15cm, and steel bar is provided with through hole and lays one deck geotextiles in the groove of this steel bar, and the size of finished particle is less than 10cm, and the laying depth of finished particle is greater than 20cm.
In order to alleviate the pressure to ground caused when finished particle is directly routed on ground, be also equipped with the blinding that one deck size is less than 3cm between this finished particle and ground, the blinding thickness of this laying is 5 ~ 10cm.
In the present embodiment, finished particle is preferably the cobble of about 6cm, and the thickness of laying is preferably about 20cm.The size of blinding is preferably about 2cm, and the thickness of this blinding is preferably 7cm.
(4) after finished particle has been laid, between adjacent two steel bars, the geotextiles of more than one deck is laid, and by the end winding support of geotextiles on steel bar.
In the present embodiment, geotextiles is preferably non-woven geotextile, lay the number of plies be two-layer more than.
(5) after geotextile laying completes, then in geotextiles, lay the thick grains of sand of one deck 10cm ~ 20cm, after fine sand has been laid, then lay face brick with concrete on grains of sand top.In the present embodiment, this grains of sand thickness is preferably 15cm.
In order to effectively draw unnecessary rainwater, the roadside on described People's Bank of China road surface is provided with the aqueduct be communicated with finished particle place.
Above-described embodiment is only the preferred embodiments of the present invention, not limiting the scope of the invention, as long as adopt design principle of the present invention, and the change carried out non-creativeness work on this basis and make, all should belong within protection scope of the present invention.

Claims (5)

1. sandstone waste material sidewalk construction process, is characterized in that, comprise the following steps:
(1) sieve, select process: the grains of sand utilizing screening plant fineness modulus to be less than 3.7 sieve out from building debris; Metal in building debris, wooden unit and plastics are picked out;
(2) break process: put into construction waste crusher by selecting rear remaining building debris in step (1), and be ground into the finished particle being less than 10cm, and then process through step (1);
(3) after consolidation, be laid on ground with the steel bar that cross section is groove-like, and then be filled between two steel bars with the finished particle being less than 10cm; Wherein the height of steel bar is greater than 15cm, and steel bar is provided with through hole and lays one deck geotextiles in the groove of this steel bar, and the laying depth of finished particle is not less than 20cm;
(4) after finished particle has been laid, between adjacent two steel bars, the geotextiles of more than one deck is laid, and by the end winding support of geotextiles on steel bar;
(5) after geotextile laying completes, then the grains of sand sieved out in step (1) and step (2) are routed in geotextiles, then lay face brick with concrete on grains of sand top.
2. sandstone waste material sidewalk according to claim 1 construction process, is characterized in that, adopts magnetic method to be picked out from remaining building debris by ironwork in described step (1); And then the building debris after selecting is put into salt solution, by salt buoyancy of water, the wooden unit in building debris and plastics are picked out, finally by artificial method, other metal products are picked out from building debris again.
3. sandstone waste material sidewalk according to claim 2 construction process, it is characterized in that, also be equipped with the blinding that a layer thickness is 5 ~ 10cm between ground and finished particle, this blinding is obtained by the finished particle fragmentation in step (2), and the particle after fragmentation is less than 3cm.
4. sandstone waste material sidewalk according to claim 3 construction process, it is characterized in that, described finished particle place is communicated with the aqueduct of the position, roadside being positioned at People's Bank of China road surface.
5. the sandstone waste material sidewalk construction process according to any one of Claims 1 to 4, it is characterized in that, described grains of sand laying depth is 10cm ~ 20cm; Distance between described adjacent two steel bars is 2m ~ 4m.
CN201410426950.0A 2014-08-27 2014-08-27 Sandstone waste material sidewalk construction process Expired - Fee Related CN104195919B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410426950.0A CN104195919B (en) 2014-08-27 2014-08-27 Sandstone waste material sidewalk construction process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410426950.0A CN104195919B (en) 2014-08-27 2014-08-27 Sandstone waste material sidewalk construction process

Publications (2)

Publication Number Publication Date
CN104195919A CN104195919A (en) 2014-12-10
CN104195919B true CN104195919B (en) 2016-03-09

Family

ID=52081272

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410426950.0A Expired - Fee Related CN104195919B (en) 2014-08-27 2014-08-27 Sandstone waste material sidewalk construction process

Country Status (1)

Country Link
CN (1) CN104195919B (en)

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1186134C (en) * 2003-07-08 2005-01-26 王健 Method for treating inorganic solid waste and application
CN100458014C (en) * 2004-02-04 2009-02-04 同济大学 Method for making civil work engineering structure layer using domestic incinerator slag
CN101265685A (en) * 2007-06-24 2008-09-17 沧州市市政工程公司 Method for regenerating waste solid for use in road foundation
KR100830986B1 (en) * 2007-12-21 2008-05-20 주식회사 태영알이씨 The flex road elasticity pavement for a bicycle and the method for executing the flex road elasticity pavement

Also Published As

Publication number Publication date
CN104195919A (en) 2014-12-10

Similar Documents

Publication Publication Date Title
CN104878678A (en) Construction method for water-permeable and water-retaining water-permeable pavement structure
CN106120501A (en) Existing barricade section roadbed is spelled width and is increased structure and construction method
CN108316089A (en) It is a kind of that road surface method is repaired using plain concrete and reinforced concrete
CN104452510B (en) Immediate construction method of rural road
CN111042293A (en) Construction process of road central green belt seepage-proofing drainage structure
CN102051848B (en) HMA/CC (Hot-Mix Asphalt)/(Cement Concrete) composite type pavement structure and constructing method thereof
KR101270531B1 (en) blocked the temporary storage space of rain water using recycled aggregate
CN205893857U (en) Road surface maintenance transverse drainage system
CN107700299A (en) A kind of elevated bridge lower floor road structure and its construction method
CN104195918A (en) Method for paving face bricks on pavement of pedestrian walkway
KR101436316B1 (en) Color elastic permeable concrete pavement composition and its method that is improved on anti-freeze process, the radiant heat reduction, and nonslip surface by sustainable porosity
CN104195919B (en) Sandstone waste material sidewalk construction process
CN104164822A (en) Process for paving pedestrian pavement by utilizing building debris
CN209211198U (en) A kind of urban environmental protection road surface
CN106431149A (en) Precast concrete pavement slab and mounting method thereof
US20120269573A1 (en) Systems and Methods for Diverting Sub-surface Water
CN207552833U (en) A kind of elevated bridge basal perimeter ground road structure
KR20110100805A (en) Pavement road including a plurality of water-permeable layers and water-bearing layers and pavement method of the road
CN211713556U (en) Energy-concerving and environment-protective cement regeneration asphalt concrete pavement structure
CN208701457U (en) Pavement bricks, the pavement using pavement bricks and engineering road
CN203834313U (en) Impound strap for highway pavement
KR100966473B1 (en) Structure of invisible waterway and construction method thereof including punctured pipes
CN203795269U (en) Blind drainage ditch for highway pavement
CN216864701U (en) Environment-friendly thin-layer colored sand cast-in-place pavement
CN104195917A (en) Process for paving latticed pavement of pedestrian walkway

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20160125

Address after: Xindu District of Chengdu City, Sichuan province 610000 Lee Road No. 1 (the city 3G KIC Plaza Building 13 layer 10, 2)

Applicant after: CHENGDU LAIBAO PETROLEUM EQUIPMENT Co.,Ltd.

Address before: 610000 Chengdu City, Chenghua District Province, No. two North Ring Road, No. four, No. 1, with a layer of No. 2, No. 104

Applicant before: CHENGDU RONGDE CONSTRUCTION LABOR SERVICE Co.,Ltd.

C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
CB03 Change of inventor or designer information

Inventor after: Liu Jinlong

Inventor before: Zeng Deming

COR Change of bibliographic data
TR01 Transfer of patent right

Effective date of registration: 20161026

Address after: 241000, Anhui City, Wuhu province Longhu District Street business city C-1

Patentee after: Wuhu Longhu Construction Engineering Co.,Ltd.

Address before: Xindu District of Chengdu City, Sichuan province 610000 Lee Road No. 1 (the city 3G KIC Plaza Building 13 layer 10, 2)

Patentee before: CHENGDU LAIBAO PETROLEUM EQUIPMENT Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160309

Termination date: 20210827

CF01 Termination of patent right due to non-payment of annual fee