CN104195919A - Gravel waste sidewalk construction process - Google Patents

Gravel waste sidewalk construction process Download PDF

Info

Publication number
CN104195919A
CN104195919A CN201410426950.0A CN201410426950A CN104195919A CN 104195919 A CN104195919 A CN 104195919A CN 201410426950 A CN201410426950 A CN 201410426950A CN 104195919 A CN104195919 A CN 104195919A
Authority
CN
China
Prior art keywords
construction process
finished particle
sand
steel bar
paving
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410426950.0A
Other languages
Chinese (zh)
Other versions
CN104195919B (en
Inventor
曾德明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhu Longhu Construction Engineering Co ltd
Original Assignee
CHENGDU RONGDE CONSTRUCTION LABOR Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHENGDU RONGDE CONSTRUCTION LABOR Co Ltd filed Critical CHENGDU RONGDE CONSTRUCTION LABOR Co Ltd
Priority to CN201410426950.0A priority Critical patent/CN104195919B/en
Publication of CN104195919A publication Critical patent/CN104195919A/en
Application granted granted Critical
Publication of CN104195919B publication Critical patent/CN104195919B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

The invention discloses a gravel waste sidewalk construction process. The gravel waste sidewalk construction process comprises the following steps: (1) screening and sorting, (2) crushing construction waste into finished particles being less than 10cm; (3) paving steel bars with groove-shaped sections on the tamped foundation and then putting the finished particles between the two steel bars in a filling manner, wherein the height of each steel bar is greater than 15cm, a through hole is formed in each steel bar and a layer of geotechnical cloth is paved in the groove of the steel bar; (4) after finishing the paving of the finished particles, paving more than one layer of geotechnical cloth between the two adjacent steel bars and fixing the end parts of the geotechnical cloth to the steel bars; (5) after finishing the paving of the geotechnical cloth, paving a layer of sand by 10cm-20cm on the geotechnical cloth, and paving face bricks on the sand by use of concrete after finishing the paving of the fine sand. The gravel waste sidewalk construction process has the advantages of material cost saving, environmental protection, quick drainage, the reduction of unevenness possibility due to different subsidence degrees of lower layers of the face bricks, and the like.

Description

Sandstone waste material sidewalk construction process
?
Technical field
The present invention relates to a kind of road surfacing method, what be specifically related to is sandstone waste material sidewalk construction process.
Background technology
Sidewalk (side walk; Foot way) refer in road the part of specializing in walk of being separated with road kerb or guardrail and other similar facilities.In city, sidewalk is very general, Pang Junyou sidewalk, general street.Between the sidewalk that some is local and motorway across meadow or trees.
In city, claim again the street of continuous architectural complex, refer to road kerb from marking roadway boundary line, kerb (flowing water stone) to building line and exceed roadway part, specialize in walk, forbid illegally occupying, also forbid that vehicle sails into, but it is current on sidewalk that walk one's bicycle on sidewalk walking or disabled person shake wheel-chair, should treat by pedestrian.Exit, lane or unit exit be sidewalk truncation part, though be the common current area of pedestrian and vehicle, must be considered as is the sidewalk being truncated, and vehicle has been passed through pedestrian while passing through herein, must slow down or Stop and give way, to guarantee safety.
The working procedure of sidewalk surface construction mainly comprises measures unwrapping wire, based process, tile work and on-the-spot cleaning.Described based process: be that table soil or the foreign material of ground are removed, then with being aided with manual amendment after machinery leveling compacting.Wherein, the existing process of deployment of this tile work is as follows:
(1) adopt lime fly ash gravel compound to be laid on ground as bottom, the thick 20cm of substructure;
(2) pave bed course, bed course adopts M7.5 cement mortar, and thickness is 2cm, while paving, keeps flat gently, with rubber hammer, beats stable levelling, but must not damage corner;
(3) face brick is paved Qian Xianjiang basic unit leveling, with both sides road kerb top, be as the criterion and hang longitudinally and horizontal altitude traverse, first segmentation floating screed, after fill a vacancy and mat formation, check at any time position and elevation;
(4) finally lay face brick.
Because adopting the preserving period of above-mentioned face brick to be generally no less than 7 days, should forbid during this period the walking about and collide of pedestrian, vehicle etc., and then cause construction period longer.
And after having constructed, if while running into continuously rainy or rainstorm weather, rainwater is seepage fast, and then is stacked into face brick lower floor, causes drainage effect bad.And because long-term rain soaks, easily cause face brick lower floor depression degree everywhere different, and then cause face brick uneven, and then cause pedestrian very inconvenient when walking.
And because rainwater is deposited in face brick lower floor, and the uneven row of tile surface that differs and cause due to face brick lower floor depression degree everywhere, while easily causing walking, ponding splash is to pedestrian's leg.
Summary of the invention
After the object of the invention is to solve existing People's Bank of China road surface face brick and laying ponding can not discharge fast, the problem of the uneven impact walking of brick quality after a period of time, provide a kind of can Quick drainage, reduce the face brick lower floor different sandstone waste material sidewalk construction process that causes uneven situation to occur of depression degree everywhere.
For solving above-mentioned shortcoming, technical scheme of the present invention is as follows:
Sandstone waste material sidewalk construction process, comprises the following steps:
(1) sieve, select processing: utilize screening plant that fineness modulus is less than to 3.7 the grains of sand and sieve out from building debris; Metal in building debris, wooden unit and plastics are picked out;
(2) break process: put into construction waste crusher by selecting rear remaining building debris in step (2), and be ground into the finished particle that is less than 10cm, and then process through step (1);
(3) after ground compacting, the steel bar that is groove shape with cross section is laid on ground, and then is filled between two steel bars with the finished particle that is less than 10cm; Wherein the height of steel bar is greater than 15cm, and on steel bar, is provided with through hole and in the groove of this steel bar, lays one deck geotextiles, and the laying depth of finished particle is not less than 20cm;
(4), after finished particle has been laid, between adjacent two steel bars, lay geotextiles more than one deck, and the end of geotextiles is fixed on steel bar;
(5) after geotextile laying completes, then the grains of sand that sieve out in step (1) and step (2) are routed in geotextiles, then on grains of sand top, lay face brick with mixed earth.
The present invention adopts the paving mode of the upper strata grains of sand, lower floor's finished particle, effectively improves the seepage speed of ponding; The laying of geotextiles between the upper strata grains of sand and lower floor's finished particle, effectively avoids the grains of sand along with rainwater flows in lower floor's finished particle, guarantees the seepage effect of ponding.
Meanwhile, the laying of this geotextiles not only effectively to isolating between the grains of sand and finished particle and then guaranteeing seepage effect, and can also be reinforced finished particle top layer when lower floor's finished particle has part depression, effectively reduces the effect of depression.
And the grains of sand that the present invention adopts and finished particle are all to make after the building debris processing adopting, and can alleviate the environment stress that building waste brings, time and the cost saving building waste transportation simultaneously and process, effect is very remarkable.
In described step (1), adopt magnetic method that ironwork is picked out from remaining building debris; And then the building debris after selecting is put into salt solution, and by salt buoyancy of water, the wooden unit in building debris and plastics are picked out, finally by artificial method, other metal products are picked out from building debris again.
By above-mentioned screening technique, can not only filter out substantially ironwork, plastic products and the woodwork in building waste, and can to the material of large particle diameter, carry out abundant fragmentation substantially, save the broken time.
Because the space of contact surface between finished particle and ground is larger, the pressure that the position ground that causes contacting between finished particle ground bears is larger, thereby easily causes the region depression degree at frequent walking position larger.In order to address the above problem, the present invention is also equipped with the blinding that a layer thickness is 5~10cm between described ground and finished particle, and this blinding obtains by the finished particle fragmentation in step (2), and the particle after fragmentation is less than 3cm.
When raining continuously or raining in torrents, rainwater infiltrates face brick lower floor, is stacked into the gap between the grains of sand and finished particle, when ground can not receive the water of infiltration completely, can road pavement impact, thereby, in the roadside on People's Bank of China road surface, be provided with the aqueduct being communicated with finished particle place.Due to the setting of aqueduct, effectively discharge and be deposited in the ponding in finished particle, when not affecting this place, People's Bank of China road surface ecological, effectively guaranteed the discharge of ponding, effect is very remarkable.
As a kind of preferred, described grains of sand laying depth is 10cm~20cm; Distance between described adjacent two steel bars is 2m~4m.
The present invention compared with prior art, has the following advantages and beneficial effect:
Drainage effect of the present invention is good, avoids ponding; Simultaneously can effectively reduce the sinking degree on face brick top layer, so can effectively avoid pedestrian to walk time ponding splash to it.
The specific embodiment
Below in conjunction with embodiment, the present invention is described in further detail, but embodiments of the present invention are not limited to this.
Embodiment
Sandstone waste material sidewalk construction process, is characterized in that, mainly following steps, consists of:
(1) screening is processed: utilize screening plant that fineness modulus is less than to 3.7 the grains of sand and sieve out from building debris.
Select separation: adopt magnetic method that ironwork is picked out from remaining building debris; And then the building debris after selecting is put into salt solution, and by salt buoyancy of water, the wooden unit in building debris and plastics are picked out, finally by artificial method, other metal products are picked out from building debris again.
Wherein, the metal product of the picking out recovery double teeming of can classifying, as aluminium alloys, copper, color steel, ironwork, stainless steel etc., after this step sieves out, is transported to garbage reclamation station, by recycle bin by its recycling.And plastic products in this step are also the same with metal product, are transported to recycle bin and recycle.
The woodwork reclaiming in this step can be recycled as metal product is the same with plastic products, or directly broken on the spot, after building, is buried in substrate at the bottom of flower stylobate, can be used as the fertilizer of plant in colored platform after its corruption.
(2) break process: put into construction waste crusher by selecting rear remaining building debris in step (2), and be ground into the finished particle that granularity is less than 10cm; Then finished particle being passed through again to step (1) processes.
The method can be separated being buried in ironwork in block building debris etc. from building debris, again by screening process with select separated after, effectively the grains of sand and finished particle are distinguished again.
(3) after ground compacting, the steel bar that is groove shape with cross section is laid on ground, and then is filled between two steel bars with finished particle; Wherein the height of steel bar is greater than 15cm, and on steel bar, is provided with through hole and in the groove of this steel bar, lays one deck geotextiles, and the size of finished particle is less than 10cm, and the laying depth of finished particle is greater than 20cm.
In order to alleviate the pressure to ground causing when finished particle is directly routed on ground, between this finished particle and ground, be also equipped with the blinding that one deck size is less than 3cm, the blinding thickness of this laying is 5~10cm.
In the present embodiment, finished particle is preferably the cobble of 6cm left and right, and the thickness of laying is preferably 20cm left and right.The size of blinding is preferably 2cm left and right, and the thickness of this blinding is preferably 7cm.
(4), after finished particle has been laid, between adjacent two steel bars, lay geotextiles more than one deck, and the end of geotextiles is fixed on steel bar.
In the present embodiment, geotextiles is preferably non-woven geotextile, lay the number of plies and be two-layer more than.
(5) after geotextile laying completes, then in geotextiles, lay the grains of sand that one deck 10cm~20cm is thick, after fine sand has been laid, then with mixed earth, on grains of sand top, lay face brick.In the present embodiment, this grains of sand thickness is preferably 15cm.
In order effectively to draw unnecessary rainwater, the roadside on described People's Bank of China road surface is provided with the aqueduct being communicated with finished particle place.
Above-described embodiment is only the preferred embodiments of the present invention, and not limiting the scope of the invention, adopts design principle of the present invention in every case, and carries out non-creativeness work on this basis and the variation made, within all should belonging to protection scope of the present invention.

Claims (5)

1. sandstone waste material sidewalk construction process, is characterized in that, comprises the following steps:
(1) sieve, select processing: utilize screening plant that fineness modulus is less than to 3.7 the grains of sand and sieve out from building debris; Metal in building debris, wooden unit and plastics are picked out;
(2) break process: put into construction waste crusher by selecting rear remaining building debris in step (2), and be ground into the finished particle that is less than 10cm, and then process through step (1);
(3) after ground compacting, the steel bar that is groove shape with cross section is laid on ground, and then is filled between two steel bars with the finished particle that is less than 10cm; Wherein the height of steel bar is greater than 15cm, and on steel bar, is provided with through hole and in the groove of this steel bar, lays one deck geotextiles, and the laying depth of finished particle is not less than 20cm;
(4), after finished particle has been laid, between adjacent two steel bars, lay geotextiles more than one deck, and the end of geotextiles is fixed on steel bar;
(5) after geotextile laying completes, then the grains of sand that sieve out in step (1) and step (2) are routed in geotextiles, then on grains of sand top, lay face brick with mixed earth.
2. sandstone waste material according to claim 1 sidewalk construction process, is characterized in that, adopts magnetic method that ironwork is picked out from remaining building debris in described step (1); And then the building debris after selecting is put into salt solution, and by salt buoyancy of water, the wooden unit in building debris and plastics are picked out, finally by artificial method, other metal products are picked out from building debris again.
3. sandstone waste material according to claim 2 sidewalk construction process, it is characterized in that, between ground and finished particle, be also equipped with the blinding that a layer thickness is 5~10cm, this blinding obtains by the finished particle fragmentation in step (2), and the particle after fragmentation is less than 3cm.
4. sandstone waste material according to claim 3 sidewalk construction process, is characterized in that, the roadside on described People's Bank of China road surface is provided with the aqueduct being communicated with finished particle place.
5. according to the sandstone waste material sidewalk construction process described in claim 1~4 any one, it is characterized in that, described grains of sand laying depth is 10cm~20cm; Distance between described adjacent two steel bars is 2m~4m.
CN201410426950.0A 2014-08-27 2014-08-27 Sandstone waste material sidewalk construction process Expired - Fee Related CN104195919B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410426950.0A CN104195919B (en) 2014-08-27 2014-08-27 Sandstone waste material sidewalk construction process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410426950.0A CN104195919B (en) 2014-08-27 2014-08-27 Sandstone waste material sidewalk construction process

Publications (2)

Publication Number Publication Date
CN104195919A true CN104195919A (en) 2014-12-10
CN104195919B CN104195919B (en) 2016-03-09

Family

ID=52081272

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410426950.0A Expired - Fee Related CN104195919B (en) 2014-08-27 2014-08-27 Sandstone waste material sidewalk construction process

Country Status (1)

Country Link
CN (1) CN104195919B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1480264A (en) * 2003-07-08 2004-03-10 健 王 Method for treating inorganic solid waste and application
CN1558030A (en) * 2004-02-04 2004-12-29 同济大学 Method for making civil work engineering structure layer using domestic incinerator slag
KR100830986B1 (en) * 2007-12-21 2008-05-20 주식회사 태영알이씨 The flex road elasticity pavement for a bicycle and the method for executing the flex road elasticity pavement
CN101265685A (en) * 2007-06-24 2008-09-17 沧州市市政工程公司 Method for regenerating waste solid for use in road foundation

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1480264A (en) * 2003-07-08 2004-03-10 健 王 Method for treating inorganic solid waste and application
CN1558030A (en) * 2004-02-04 2004-12-29 同济大学 Method for making civil work engineering structure layer using domestic incinerator slag
CN101265685A (en) * 2007-06-24 2008-09-17 沧州市市政工程公司 Method for regenerating waste solid for use in road foundation
KR100830986B1 (en) * 2007-12-21 2008-05-20 주식회사 태영알이씨 The flex road elasticity pavement for a bicycle and the method for executing the flex road elasticity pavement

Also Published As

Publication number Publication date
CN104195919B (en) 2016-03-09

Similar Documents

Publication Publication Date Title
CN102140771B (en) Construction method for processing saline soil roadbed by separation layer
CN104878678A (en) Construction method for water-permeable and water-retaining water-permeable pavement structure
CN108316089A (en) It is a kind of that road surface method is repaired using plain concrete and reinforced concrete
CN104452510B (en) Immediate construction method of rural road
CN106120524A (en) A kind of road construction method
CN102051848B (en) HMA/CC (Hot-Mix Asphalt)/(Cement Concrete) composite type pavement structure and constructing method thereof
KR101270531B1 (en) blocked the temporary storage space of rain water using recycled aggregate
CN205893857U (en) Road surface maintenance transverse drainage system
CN104195918A (en) Method for paving face bricks on pavement of pedestrian walkway
KR101436316B1 (en) Color elastic permeable concrete pavement composition and its method that is improved on anti-freeze process, the radiant heat reduction, and nonslip surface by sustainable porosity
CN104164822A (en) Process for paving pedestrian pavement by utilizing building debris
CN209211198U (en) A kind of urban environmental protection road surface
CN210529400U (en) Solidified building residue soil road structure
CN208917622U (en) A kind of regenerative pervious pavement structure
CN104195919B (en) Sandstone waste material sidewalk construction process
CN106431149A (en) Precast concrete pavement slab and mounting method thereof
CN207552833U (en) A kind of elevated bridge basal perimeter ground road structure
CN203834313U (en) Impound strap for highway pavement
CN208701457U (en) Pavement bricks, the pavement using pavement bricks and engineering road
CN211849540U (en) Building rubbish breaks room soil and handles weak foundation structure
CN211713556U (en) Energy-concerving and environment-protective cement regeneration asphalt concrete pavement structure
CN216864701U (en) Environment-friendly thin-layer colored sand cast-in-place pavement
CN208055793U (en) A kind of structure using plain concrete and reinforced concrete repairing road
CN104195917A (en) Process for paving latticed pavement of pedestrian walkway
CN206219927U (en) A kind of highway filled-up ground

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20160125

Address after: Xindu District of Chengdu City, Sichuan province 610000 Lee Road No. 1 (the city 3G KIC Plaza Building 13 layer 10, 2)

Applicant after: CHENGDU LAIBAO PETROLEUM EQUIPMENT Co.,Ltd.

Address before: 610000 Chengdu City, Chenghua District Province, No. two North Ring Road, No. four, No. 1, with a layer of No. 2, No. 104

Applicant before: CHENGDU RONGDE CONSTRUCTION LABOR SERVICE Co.,Ltd.

C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
CB03 Change of inventor or designer information

Inventor after: Liu Jinlong

Inventor before: Zeng Deming

COR Change of bibliographic data
TR01 Transfer of patent right

Effective date of registration: 20161026

Address after: 241000, Anhui City, Wuhu province Longhu District Street business city C-1

Patentee after: Wuhu Longhu Construction Engineering Co.,Ltd.

Address before: Xindu District of Chengdu City, Sichuan province 610000 Lee Road No. 1 (the city 3G KIC Plaza Building 13 layer 10, 2)

Patentee before: CHENGDU LAIBAO PETROLEUM EQUIPMENT Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160309

Termination date: 20210827