CN104153400A - Soft soil foundation cast-in-place pile head waterproof and construction method thereof - Google Patents
Soft soil foundation cast-in-place pile head waterproof and construction method thereof Download PDFInfo
- Publication number
- CN104153400A CN104153400A CN201410415983.5A CN201410415983A CN104153400A CN 104153400 A CN104153400 A CN 104153400A CN 201410415983 A CN201410415983 A CN 201410415983A CN 104153400 A CN104153400 A CN 104153400A
- Authority
- CN
- China
- Prior art keywords
- waterproof
- pile
- pile head
- layer
- polyurethane
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims abstract description 57
- 239000002689 soil Substances 0.000 title abstract 3
- 239000010410 layer Substances 0.000 claims abstract description 39
- 239000000463 material Substances 0.000 claims abstract description 36
- 239000004570 mortar (masonry) Substances 0.000 claims abstract description 34
- 229920002635 polyurethane Polymers 0.000 claims abstract description 29
- 239000004814 polyurethane Substances 0.000 claims abstract description 29
- 238000000034 method Methods 0.000 claims abstract description 28
- 238000007789 sealing Methods 0.000 claims abstract description 22
- 238000000576 coating method Methods 0.000 claims abstract description 20
- 239000011248 coating agent Substances 0.000 claims abstract description 17
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 14
- 239000011083 cement mortar Substances 0.000 claims abstract description 13
- 239000000853 adhesive Substances 0.000 claims abstract description 10
- 230000001680 brushing effect Effects 0.000 claims abstract description 7
- 239000003795 chemical substances by application Substances 0.000 claims abstract description 6
- 239000004575 stone Substances 0.000 claims abstract description 5
- 239000011241 protective layer Substances 0.000 claims abstract description 4
- 238000004078 waterproofing Methods 0.000 claims description 39
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 26
- 150000001875 compounds Chemical class 0.000 claims description 15
- 235000011194 food seasoning agent Nutrition 0.000 claims description 12
- 229920000742 Cotton Polymers 0.000 claims description 6
- 238000004140 cleaning Methods 0.000 claims description 6
- 238000007689 inspection Methods 0.000 claims description 6
- 230000011218 segmentation Effects 0.000 claims description 6
- 241000316770 Deschampsia cespitosa var. alpina Species 0.000 claims description 3
- 238000009412 basement excavation Methods 0.000 claims description 3
- 239000004568 cement Substances 0.000 claims description 3
- 239000013039 cover film Substances 0.000 claims description 3
- 239000006071 cream Substances 0.000 claims description 3
- 230000007547 defect Effects 0.000 claims description 3
- 238000010410 dusting Methods 0.000 claims description 3
- 210000002615 epidermis Anatomy 0.000 claims description 3
- 239000004744 fabric Substances 0.000 claims description 3
- 238000007667 floating Methods 0.000 claims description 3
- 238000012423 maintenance Methods 0.000 claims description 3
- 239000000758 substrate Substances 0.000 claims description 3
- 239000011449 brick Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 229940126545 compound 53 Drugs 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000003673 groundwater Substances 0.000 description 1
- 230000002265 prevention Effects 0.000 description 1
- FDBYIYFVSAHJLY-UHFFFAOYSA-N resmetirom Chemical compound N1C(=O)C(C(C)C)=CC(OC=2C(=CC(=CC=2Cl)N2C(NC(=O)C(C#N)=N2)=O)Cl)=N1 FDBYIYFVSAHJLY-UHFFFAOYSA-N 0.000 description 1
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
The invention relates to a soft soil foundation cast-in-place pile head waterproof, which comprises a polyurethane waterproof coating, a waterproof coiled material, sealing paste and waterproof mortar, wherein polyurethane waterproof coating reinforcing layers are arranged on the periphery, the top and the periphery of the pile head; double-sided self-adhesive waterproof coiled materials reach the root of the pile head; sealing the periphery of the pile head with sealing paste; and (4) making waterproof mortar on the periphery and the top of the pile head protruding out of the bedding surface. Also discloses a soft soil foundation cast-in-place pile head waterproof construction method, which comprises the following construction procedures: constructing a foundation concrete cushion; rounding the pile head and leveling the pile body to the pile top; making a cement mortar leveling layer on the surface of the cushion layer; brushing a base layer treating agent on the cement mortar leveling layer; the pile head is used as a polyurethane waterproof coating reinforcing layer; double-sided self-adhesive waterproof coiled materials reach the root of the pile head; sealing the periphery of the pile head with sealing paste; making waterproof mortar on the pile head; and a fine stone concrete protective layer is formed on the waterproof roll material layer. Through multiple fortifications, leakage points at the pile head are prevented, and the engineering quality is guaranteed.
Description
Technical field
The present invention relates to a kind of soft foundation pouring pile head waterproof and construction method thereof, is the realm of building construction.
Background technology
The building foundation waterproof problem of complicated geological environment is the tackling key problem emphasis of technical field of buildings always, the present invention is that engineering pile pile crown waterproofing node way taking soft foundation environment is as research object, with the actual problem running into of engineering in conjunction with existing job specfication, atlas, the scientific and technical innovation of carrying out as object to improve engineering foundation waterproof quality.
Summary of the invention
For achieving the above object, the invention discloses a kind of soft foundation pouring pile head waterproof, the technical scheme adopting is: pile crown waterproof comprises polyurethane waterproof coating, waterproof roll, sealing compound and waterproofing mortar, does polyurethane waterproof coating enhancement Layer at pile crown surrounding, top and periphery; Double-sided self-adhesive waterproof coiled materials is to pile crown root; Pile crown surrounding seals by sealing compound; Pile crown protrudes bedding plane surrounding and waterproofing mortar is made at top.
Further, described polyurethane waterproof coating enhancement Layer is that 2 ㎜ are thick, expands to periphery 500 ㎜ scopes; Described double-sided self-adhesive waterproof coiled materials is that 4 ㎜ are thick, affixes to pile crown root; Described waterproofing mortar is thick is 20 ㎜, and proportioning is 1:2.5.
The invention also discloses a kind of soft foundation pouring pile head waterproof construction method, comprise following working procedure: the first step, base concrete cushion construction; Second step, builds one deck pea gravel concreten by pile crown surrounding and top, looks for round pile body levelling stake top; The 3rd step, making cement mortar levelling layer on bedding plane; The 4th step is brushed base treatment agent one time on cement mortar screeding layer; The 5th step, pile crown surrounding, top and periphery do polyurethane waterproof coating enhancement Layer; The 6th step, double-sided self-adhesive waterproof coiled materials is to pile crown root; The 7th step, pile crown surrounding seals by sealing compound; The 8th step, pile crown protrudes bedding plane surrounding and waterproofing mortar is made together in top; The 9th step, does pea gravel concreten topping on waterproof roll layer.
Further, in the first step, the construction process of base concrete bed course is: substrate equating after excavation of foundation pit → put architecture basics sideline adds 300 ㎜ control lines → install bed course limit mould → follow closely in foundation ditch absolute altitude control height reinforcing rod, 4 meters of spacing in length and breadth → according to construction flowing water section, C20 blinding concrete is built in segmentation, thickness is not less than 150 ㎜, before bracing wire is closed flat concrete surface → final set on absolute altitude control reinforcing rod, receive light processing → cover film, water seasoning.
Further, in second step, the pile body that exposes outside base concrete bed course is looked for to circle, the levelling of stake end face.Construction process is: pile concrete epidermis picks cutter, the loose stone in stake top and reject → do circular mode with three-ply board ribbing hoop, adds 30 ㎜ hassock pieces → get rid of the cotton felt water seasoning of the pea gravel concreten that reinforcing bar subscript goes out the high grade of absolute altitude control line → build → cover outward at pile crown between Mo Nei and pile body.
Further, in the 3rd step cement mortar screeding layer construction, according to mat surface planeness and defect situation, concrete cushion is carried out to leveling, mainly concrete mats aspect out-of-flatness of having peeling, dusting, pin nest, crack and flowing water section separated place etc., and lead the foot of a wall portion, the cloudy male trowel circular arc of the well that catchments; Construction process is: cutter cleaning → fault location sprinkle water moistening, trickle mud → the smear thick 1:2 cement mortar screeding of 20 ㎜ → lead the foot of a wall portion, the 50 ㎜ circular arc → compacting maintenances of the cloudy male trowel diameter of the well that catchments are picked in fault location surface.
Further, in the 5th step, pile crown surrounding, top and periphery 500 ㎜ scopes are done the thick polyurethane waterproof coating enhancement Layer of 2 ㎜; Construction process is: the cleaning of concrete mats aspect, clear away the foreign material → 500 ㎜ place setting-outs outside pile body limit such as floating ash, control polyurethane boundary of works area → point three times brushing polyurethane waterproof coatings, the time interval with last all over hand by sticky being advisable not, pile crown gets rid of reinforcing bar place outward and wants emphasis brushing → inspection to have or not omission → be coated with and brush one times polyurethane → evenly shed one deck peastone in stake top bit, constructs in order to stake top waterproofing mortar.
Further, in the 6th step, the thick waterproof roll of large paving of base concrete bed course 4 ㎜, until engineering pile edge at one's side; Construction process is: base mat aspect cleans out → put paving line at base mat aspect bullet, 1 meter of coiled material fabric width, lap width is that 80mm paving line spacing is 920mm → lead the foot of a wall portion, the negative and positive place of the well that catchments carries out extra play → inspect for acceptance → along the large face waterproof roll of the sticky paving of paving, it between coiled material and bed course, is empty paving, it between coiled material, is self-adhesion overlap joint, the careful compacting of lap-joint → coiled material is met engineering pile place, along pile body circular arc cutting coiled material, make waterproof roll prop up pile body, coiled material and pile body spacing are not more than 20mm → coiled material and pile body periphery polyurethane enhancement Layer will cement.
Further, in the 7th step, between waterproof roll and pile body, use the shutoff of Special seal cream; Construction process is: waterproof roll and pile body junction are cleaned out → have or not omission along the gap → compacting sealing compound → inspection between pile body border sealing compound shutoff waterproof roll and pile body.
Further, in the 8th step, pile crown protrudes concrete mats aspect surrounding and 20 ㎜ 1:2.5 waterproofing mortars are made at top; Construction process is: by match ratio mixing waterproofing mortar → waterproofing mortar construction is cleaned out → carried out in waterproofing mortar construction place, and smear and flatten → cover cotton felt water seasoning.
Further, in the 9th step, on waterproof roll layer, do the thick C20 pea gravel concreten of 50 ㎜ topping; Construction process is: waterproofing mortar layer check and accept complete and clean out → copy and survey basis end absolute altitude with level gauge, on waterproofing course, make the segmentation of protective layer thickness control ash cake → according to construction flowing water section and build waterproofing protection layer concrete → receipts face and smear flatten → water seasoning.
Beneficial effect of the present invention is as follows:
The present invention compares with traditional basic pile crown waterproofing node way, polyurethane, waterproof roll, sealing compound, 4 kinds of waterproofing courses of waterproofing mortar have been made respectively at pile crown place, there is rigid waterproofing also to have flexible water, in pile crown joints complexity, distortion more greatly, under the medium unfavorable conditions of influence on groundwater environment, can have good applicability for a long time.By multi-way prevention, prevent that breakthrough from appearring in pile crown place, to ensure workmanship.
Brief description of the drawings
Fig. 1 is soft foundation pouring pile head water proof structure figure;
In figure, 1-pile crown, 2-concrete cushion, 3-agent structure base plate, 4-concrete cover, 51-waterproof coating, 52-waterproof roll, 53-sealing compound, 54-waterproofing mortar.
Detailed description of the invention
Below in conjunction with accompanying drawing, the present invention is described in further detail.
A kind of soft foundation pouring pile head waterproof, pile crown waterproof comprises polyurethane waterproof coating 51, waterproof roll 52, sealing compound 53 and waterproofing mortar 54, doing polyurethane waterproof coating enhancement Layer at pile crown 1 surrounding, top and periphery is that 2 ㎜ are thick, expands to periphery 500 ㎜ scopes; Double-sided self-adhesive waterproof coiled materials is that 4 ㎜ are thick, and paving is to pile crown root; Pile crown surrounding seals by sealing compound; Pile crown protrudes bedding plane surrounding and waterproofing mortar is made at top, and waterproofing mortar is thick is 20 ㎜, and proportioning is 1:2.5.
The invention also discloses a kind of soft foundation pouring pile head waterproof construction method, comprise following working procedure:
The first step, base concrete bed course 2 is constructed.Construction process is: substrate equating after excavation of foundation pit → put architecture basics sideline+300 ㎜ control line (consider that brick loose tool build by laying bricks or stones) → install bed course limit mould → follow closely in foundation ditch absolute altitude control height reinforcing rod, 4 meters of spacing in length and breadth → according to construction flowing water section, C20 blinding concrete is built in segmentation, thickness is not less than 150 ㎜, before bracing wire is closed flat concrete surface → final set on absolute altitude control reinforcing rod, receive light processing → cover film, water seasoning.
Second step, one deck pea gravel concreten is built at pile crown 1 surrounding and the top that just expose outside base concrete bed course, looks for round pile body levelling stake top.Construction process is: pile concrete epidermis picks cutter, the loose stone in stake top and reject → do circular mode with three-ply board ribbing hoop, adds 30 ㎜ hassock pieces → get rid of the cotton felt water seasoning of the pea gravel concreten that reinforcing bar subscript goes out the high grade of absolute altitude control line → build → cover outward at pile crown between Mo Nei and pile body.
The 3rd step, making cement mortar levelling layer 6 on bedding plane, according to mat surface planeness and defect situation, concrete cushion 2 is carried out to leveling, mainly concrete cushion 2 faces out-of-flatness of having peeling, dusting, pin nest, crack and flowing water section separated place etc., and lead the foot of a wall portion, the cloudy male trowel circular arc of the well that catchments.Construction process is: cutter cleaning → fault location sprinkle water moistening, trickle mud → the smear thick 1:2 cement mortar screeding of 20 ㎜ → lead the foot of a wall portion, the 50 ㎜ circular arc → compacting maintenances of the cloudy male trowel diameter of the well that catchments are picked in fault location surface.
The 4th step is brushed base treatment agent one time on cement mortar screeding layer 6.
The 5th step, pile crown surrounding, top and periphery 500 ㎜ scopes are done thick polyurethane waterproof coating 51 enhancement Layers of 2 ㎜.Construction process is: 4 cleanings of concrete cushion, clear away the foreign material → 500 ㎜ place setting-outs outside pile body limit such as floating ash, control polyurethane boundary of works area → point three times brushing polyurethane waterproof coatings, the time interval with last all over hand by sticky being advisable not, pile crown gets rid of reinforcing bar place outward and wants emphasis brushing → inspection to have or not omission → be coated with and brush one times polyurethane → evenly shed one deck peastone in stake top bit, constructs in order to stake top waterproofing mortar.
The 6th step, the thick double-sided self-adhesive waterproof coiled materials 52 of large face paving 4 ㎜ of base concrete bed course 2, until engineering pile edge at one's side; Construction process is: base mat aspect cleans out → put paving line at base mat aspect bullet, 1 meter of coiled material fabric width, lap width is that 80mm paving line spacing is 920mm → lead the foot of a wall portion, the negative and positive place of the well that catchments carries out extra play → inspect for acceptance → along the large face waterproof roll of the sticky paving of paving, it between coiled material and bed course, is empty paving, it between coiled material, is self-adhesion overlap joint, the careful compacting of lap-joint → coiled material is met engineering pile place, along pile body circular arc cutting coiled material, make waterproof roll prop up pile body, coiled material and pile body spacing are not more than 20mm → coiled material and pile body periphery polyurethane enhancement Layer will cement.
The 7th step, uses 53 shutoff of Special seal cream between waterproof roll 52 and pile body; Construction process is: waterproof roll 52 and pile body junction are cleaned out → have or not omission along the gap → compacting sealing compound → inspection between pile body border sealing compound shutoff waterproof roll and pile body.
The 8th step, pile crown protrudes 2 surroundings of concrete cushion and top and makees 20 ㎜ 1:2.5 waterproofing mortar 54 one; Construction process is: by match ratio mixing waterproofing mortar → waterproofing mortar construction is cleaned out → carried out in waterproofing mortar 54 constructions place, and smear and flatten → cover cotton felt water seasoning.
The 9th step, does the thick C20 pea gravel concreten of 50 ㎜ topping 4 on 52 layers of waterproof rolls; Construction process is: waterproofing mortar layer check and accept complete and clean out → copy and survey basis end absolute altitude with level gauge, on waterproofing course, make the segmentation of protective layer thickness control ash cake → according to construction flowing water section and build waterproofing protection layer concrete → receipts face and smear flatten → water seasoning.
After soft foundation pouring pile head waterproof construction, just can carry out the construction of agent structure base plate 3.
Claims (10)
1. a soft foundation pouring pile head waterproof, comprise polyurethane waterproof coating (51), waterproof roll (52), sealing compound (53) and waterproofing mortar (54), it is characterized in that, do polyurethane waterproof coating enhancement Layer at pile crown (1) surrounding, top and periphery; Double-sided self-adhesive waterproof coiled materials is to pile crown root; Pile crown surrounding seals by sealing compound; Pile crown protrudes bedding plane surrounding and waterproofing mortar is made at top;
Described polyurethane waterproof coating enhancement Layer is that 2 ㎜ are thick, expands to periphery 500 ㎜ scopes; Described double-sided self-adhesive waterproof coiled materials is that 4 ㎜ are thick, affixes to pile crown root; Described waterproofing mortar is thick is 20 ㎜, and proportioning is 1:2.5.
2. a soft foundation pouring pile head waterproof construction method, is characterized in that, comprises following working procedure:
The first step, base concrete bed course (2) construction;
Second step, builds one deck pea gravel concreten by pile crown (1) surrounding and top, looks for round pile body levelling stake top;
The 3rd step, making cement mortar levelling layer (6) on bedding plane;
The 4th step, above brushes base treatment agent one time at cement mortar screeding layer (6);
The 5th step, pile crown surrounding, top and periphery do polyurethane waterproof coating (51) enhancement Layer;
The 6th step, double-sided self-adhesive waterproof coiled materials (52) is to pile crown root;
The 7th step, pile crown is sealing compound (53) sealing for surrounding;
The 8th step, pile crown protrudes bedding plane surrounding and waterproofing mortar (54) is made together in top;
The 9th step, does pea gravel concreten topping (4) on waterproof roll (52) layer.
3. waterproof construction method according to claim 2, it is characterized in that, in the first step, the construction process of base concrete bed course (2) is: substrate equating after excavation of foundation pit → put architecture basics sideline adds 300 ㎜ control lines → install bed course limit mould → follow closely in foundation ditch absolute altitude control height reinforcing rod, 4 meters of spacing in length and breadth → according to construction flowing water section, C20 blinding concrete is built in segmentation, thickness is not less than 150 ㎜, before bracing wire is closed flat concrete surface → final set on absolute altitude control reinforcing rod, receive light processing → cover film, water seasoning.
4. waterproof construction method according to claim 2, is characterized in that, in second step, the pile body that exposes outside base concrete bed course is looked for to circle, the levelling of stake end face; Construction process is: pile concrete epidermis picks cutter, the loose stone in stake top and reject → do circular mode with three-ply board ribbing hoop, adds 30 ㎜ hassock pieces → get rid of the cotton felt water seasoning of the pea gravel concreten that reinforcing bar subscript goes out the high grade of absolute altitude control line → build → cover outward at pile crown between Mo Nei and pile body.
5. waterproof construction method according to claim 2, it is characterized in that, in the 3rd step cement mortar screeding layer (6) construction, according to mat surface planeness and defect situation, concrete cushion (2) is carried out to leveling, mainly concrete cushion (2) face out-of-flatness of having peeling, dusting, pin nest, crack and flowing water section separated place etc., and lead the foot of a wall portion, the cloudy male trowel circular arc of the well that catchments; Construction process is: cutter cleaning → fault location sprinkle water moistening, trickle mud → the smear thick 1:2 cement mortar screeding of 20 ㎜ → lead the foot of a wall portion, the 50 ㎜ circular arc → compacting maintenances of the cloudy male trowel diameter of the well that catchments are picked in fault location surface.
6. waterproof construction method according to claim 2, is characterized in that, in the 5th step, pile crown surrounding, top and periphery 500 ㎜ scopes are done the thick polyurethane waterproof coating of 2 ㎜ (51) enhancement Layer; Construction process is: the cleaning of concrete cushion (4) face, clear away the foreign material → 500 ㎜ place setting-outs outside pile body limit such as floating ash, control polyurethane boundary of works area → point three times brushing polyurethane waterproof coatings, the time interval with last all over hand by sticky being advisable not, pile crown gets rid of reinforcing bar place outward and wants emphasis brushing → inspection to have or not omission → be coated with and brush one times polyurethane → evenly shed one deck peastone in stake top bit, constructs in order to stake top waterproofing mortar.
7. waterproof construction method according to claim 2, is characterized in that, in the 6th step, the large face paving thick waterproof roll of 4 ㎜ (52) of base concrete bed course (2), until engineering pile edge at one's side; Construction process is: base mat aspect cleans out → put paving line at base mat aspect bullet, 1 meter of coiled material fabric width, lap width is that 80mm paving line spacing is 920mm → lead the foot of a wall portion, the negative and positive place of the well that catchments carries out extra play → inspect for acceptance → along the large face waterproof roll of the sticky paving of paving, it between coiled material and bed course, is empty paving, it between coiled material, is self-adhesion overlap joint, the careful compacting of lap-joint → coiled material is met engineering pile place, along pile body circular arc cutting coiled material, make waterproof roll prop up pile body, coiled material and pile body spacing are not more than 20mm → coiled material and pile body periphery polyurethane enhancement Layer will cement.
8. waterproof construction method according to claim 2, is characterized in that, in the 7th step, uses Special seal cream (53) shutoff between waterproof roll (52) and pile body; Construction process is: waterproof roll (52) and pile body junction are cleaned out → have or not omission along the gap → compacting sealing compound → inspection between pile body border sealing compound shutoff waterproof roll and pile body.
9. waterproof construction method according to claim 2, is characterized in that, in the 8th step, pile crown protrudes concrete cushion (2) face surrounding and 20 ㎜ 1:2.5 waterproofing mortars (54) are made at top; Construction process is: by match ratio mixing waterproofing mortar → waterproofing mortar construction is cleaned out → carried out in waterproofing mortar (54) construction place, and smear and flatten → cover cotton felt water seasoning.
10. waterproof construction method according to claim 2, is characterized in that, in the 9th step, on waterproof roll (52) layer, does 50 ㎜ thick C20 pea gravel concreten topping (4); Construction process is: waterproofing mortar layer check and accept complete and clean out → copy and survey basis end absolute altitude with level gauge, making protective layer thickness control ash cake on waterproof roll (52) layer → build pea gravel concreten topping (4) → receipts face according to the flowing water section segmentation of constructing to smear and flatten → water seasoning.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410415983.5A CN104153400B (en) | 2014-08-22 | 2014-08-22 | Construction method for preventing soft soil foundation cast-in-place pile head from being waterproof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410415983.5A CN104153400B (en) | 2014-08-22 | 2014-08-22 | Construction method for preventing soft soil foundation cast-in-place pile head from being waterproof |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104153400A true CN104153400A (en) | 2014-11-19 |
CN104153400B CN104153400B (en) | 2016-03-09 |
Family
ID=51879014
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410415983.5A Expired - Fee Related CN104153400B (en) | 2014-08-22 | 2014-08-22 | Construction method for preventing soft soil foundation cast-in-place pile head from being waterproof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104153400B (en) |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104727335A (en) * | 2015-02-13 | 2015-06-24 | 常熟建工建设集团有限公司 | Fast foundation constructing method |
CN104947809A (en) * | 2015-06-29 | 2015-09-30 | 广西金雨伞防水装饰有限公司 | Full-seal waterproof system of concrete construction project |
CN104975617A (en) * | 2015-07-15 | 2015-10-14 | 郑贤方 | Waterproof construction method of basement foundation cast-in-place pile head |
CN105178452A (en) * | 2015-06-29 | 2015-12-23 | 广西金雨伞防水装饰有限公司 | Full-seal waterproof construction method |
CN105951893A (en) * | 2016-06-27 | 2016-09-21 | 中铁第四勘察设计院集团有限公司 | Uplift pile head node waterproof structure and construction method thereof |
CN106759308A (en) * | 2016-11-30 | 2017-05-31 | 中国冶集团有限公司 | A kind of precast hollow pile head waterproof construction method |
CN111456108A (en) * | 2020-04-11 | 2020-07-28 | 广东建兴基础工程有限公司 | Waterproof structure of foundation bearing platform and construction method thereof |
CN112081146A (en) * | 2020-09-03 | 2020-12-15 | 江苏凯伦建材股份有限公司 | Construction method of polymer self-adhesive film waterproof coiled material capable of being constructed in rainy season |
CN112411564A (en) * | 2020-11-06 | 2021-02-26 | 天津市市政工程设计研究院 | Waterproof structure with latticed columns penetrating through bottom plate and construction method of waterproof structure |
CN112815153A (en) * | 2021-01-04 | 2021-05-18 | 江苏凯伦建材股份有限公司 | Waterproof treatment method for root of through-wall or floor pipeline |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08226134A (en) * | 1991-09-27 | 1996-09-03 | Maeda Corp | Construction method for basement water-barrier wall |
CN202718147U (en) * | 2012-07-19 | 2013-02-06 | 朱奎 | Waterproof structure of pile head |
CN202809660U (en) * | 2012-07-31 | 2013-03-20 | 中天建设集团有限公司天津分公司 | Waterproof structure for pile head of engineering pile |
CN203256816U (en) * | 2013-04-08 | 2013-10-30 | 中国建筑第七工程局有限公司 | Pile foundation bottom plate pile head waterproof structure |
CN103572786A (en) * | 2013-11-19 | 2014-02-12 | 中铁十六局集团北京工程有限公司 | Pile head joint waterproof processing device and construction method thereof |
-
2014
- 2014-08-22 CN CN201410415983.5A patent/CN104153400B/en not_active Expired - Fee Related
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08226134A (en) * | 1991-09-27 | 1996-09-03 | Maeda Corp | Construction method for basement water-barrier wall |
CN202718147U (en) * | 2012-07-19 | 2013-02-06 | 朱奎 | Waterproof structure of pile head |
CN202809660U (en) * | 2012-07-31 | 2013-03-20 | 中天建设集团有限公司天津分公司 | Waterproof structure for pile head of engineering pile |
CN203256816U (en) * | 2013-04-08 | 2013-10-30 | 中国建筑第七工程局有限公司 | Pile foundation bottom plate pile head waterproof structure |
CN103572786A (en) * | 2013-11-19 | 2014-02-12 | 中铁十六局集团北京工程有限公司 | Pile head joint waterproof processing device and construction method thereof |
Cited By (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104727335A (en) * | 2015-02-13 | 2015-06-24 | 常熟建工建设集团有限公司 | Fast foundation constructing method |
CN105178452B (en) * | 2015-06-29 | 2018-07-31 | 广西金雨伞防水装饰有限公司 | Hermetically sealed waterproof construction method |
CN104947809A (en) * | 2015-06-29 | 2015-09-30 | 广西金雨伞防水装饰有限公司 | Full-seal waterproof system of concrete construction project |
CN105178452A (en) * | 2015-06-29 | 2015-12-23 | 广西金雨伞防水装饰有限公司 | Full-seal waterproof construction method |
CN104975617A (en) * | 2015-07-15 | 2015-10-14 | 郑贤方 | Waterproof construction method of basement foundation cast-in-place pile head |
CN104975617B (en) * | 2015-07-15 | 2017-01-25 | 郑贤方 | Waterproof construction method of basement foundation cast-in-place pile head |
CN105951893A (en) * | 2016-06-27 | 2016-09-21 | 中铁第四勘察设计院集团有限公司 | Uplift pile head node waterproof structure and construction method thereof |
CN106759308A (en) * | 2016-11-30 | 2017-05-31 | 中国冶集团有限公司 | A kind of precast hollow pile head waterproof construction method |
CN106759308B (en) * | 2016-11-30 | 2019-04-23 | 中国一冶集团有限公司 | A kind of precast hollow pile head waterproof construction method |
CN111456108A (en) * | 2020-04-11 | 2020-07-28 | 广东建兴基础工程有限公司 | Waterproof structure of foundation bearing platform and construction method thereof |
CN111456108B (en) * | 2020-04-11 | 2021-09-14 | 广东建兴基础工程有限公司 | Waterproof structure of foundation bearing platform and construction method thereof |
CN112081146A (en) * | 2020-09-03 | 2020-12-15 | 江苏凯伦建材股份有限公司 | Construction method of polymer self-adhesive film waterproof coiled material capable of being constructed in rainy season |
CN112411564A (en) * | 2020-11-06 | 2021-02-26 | 天津市市政工程设计研究院 | Waterproof structure with latticed columns penetrating through bottom plate and construction method of waterproof structure |
CN112815153A (en) * | 2021-01-04 | 2021-05-18 | 江苏凯伦建材股份有限公司 | Waterproof treatment method for root of through-wall or floor pipeline |
Also Published As
Publication number | Publication date |
---|---|
CN104153400B (en) | 2016-03-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104153400B (en) | Construction method for preventing soft soil foundation cast-in-place pile head from being waterproof | |
CN207987983U (en) | A kind of waterproof construction being used for underground engineering main body construction seam and post-cast strip | |
CN101565997A (en) | Construction method for large-area irregular floor tile | |
CN102776897B (en) | Wash apron anti-settling anti-cracking construction method and structure | |
CN202809660U (en) | Waterproof structure for pile head of engineering pile | |
CN202559540U (en) | Waterproof plugging structure for outer wall split bolt hole | |
CN204492025U (en) | The waterproof construction of the contour deformation joint of roofing | |
CN107816138A (en) | A kind of construction technology of subsided rest room | |
CN109184253A (en) | A kind of method for repairing and mending of exterior wall leakage | |
CN108755983A (en) | A kind of waterproof technology | |
CN105201025B (en) | Basement waterproofing construction and its construction method | |
CN106284998A (en) | Plastering on inner walls completely spreads fiberglass gridding cloth construction method | |
CN204982908U (en) | Elevartor shaft deep basal pit seepage prevention structure | |
CN207775948U (en) | Pulling-Resistant Anchor Rod root waterproofing node structure | |
CN107152012A (en) | Sluice construction technique | |
CN103572786B (en) | A kind of pile crown node waterproof treating apparatus and construction method thereof | |
CN110185277A (en) | The restorative procedure of existing building external wall seepage point | |
CN105178364B (en) | Underground building light precipitation well point post-cast strip anti-seepage construction method | |
CN112942432A (en) | Construction method of anti-leakage brick inspection well | |
CN108385614A (en) | A kind of concrete facing board construction method of anti-floating towing force | |
CN206616676U (en) | A kind of toilet floor drain position waterproof construction | |
CN101586367B (en) | Method for preventing decorative surfaces of ceramic tiles in shower room from leaking water | |
CN109881794A (en) | A kind of swimming pool waterproof construction | |
CN110439016A (en) | A kind of pile foundation waterproof construction method | |
CN115807450A (en) | Pile-wall integrated drainage-prevention combined basement exterior wall waterproof construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20160309 Termination date: 20160822 |