CN108755983A - A kind of waterproof technology - Google Patents

A kind of waterproof technology Download PDF

Info

Publication number
CN108755983A
CN108755983A CN201810558716.1A CN201810558716A CN108755983A CN 108755983 A CN108755983 A CN 108755983A CN 201810558716 A CN201810558716 A CN 201810558716A CN 108755983 A CN108755983 A CN 108755983A
Authority
CN
China
Prior art keywords
waterproof
coiled material
layer
construction
bottom plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810558716.1A
Other languages
Chinese (zh)
Other versions
CN108755983B (en
Inventor
张伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Jimmy Passive House Technology Co.,Ltd.
Original Assignee
Hunan Jimmy Waterproof Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan Jimmy Waterproof Technology Co Ltd filed Critical Hunan Jimmy Waterproof Technology Co Ltd
Priority to CN201810558716.1A priority Critical patent/CN108755983B/en
Publication of CN108755983A publication Critical patent/CN108755983A/en
Application granted granted Critical
Publication of CN108755983B publication Critical patent/CN108755983B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • E04B1/665Sheets or foils impervious to water and water vapor

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention discloses a kind of waterproof technologies, including step 1:Blinding layer is cleared up;Step 2:Uncured water-repellent paint integral spray, uniform mechanically spraying or the artificial brushing uncured rubber asphalt waterproof coating of 2mm thickness self-cure types on the blinding layer handled well, the thin portions paintbrush auxiliary construction such as inner corner trim, pipe root, it is required that consistency of thickness, and carry out turning over processing in corresponding pipe root, metope, height is no less than 250mm;Step 3:The thick strengths of 2mm are intersected the two-sided high-polymer self-adhesion waterproof coiled material of film and are laid with;Step 4:Coiled material protective layer is constructed, with dilution concrete 50mm protective layers protection bottom plate or plane;Step 5:It is dry in structure base slab construction to spread 1.5 ㎏/㎡ of penetrant crystalline;After bottom plate or flat concrete pour, when solidifying, but can also be trampled completely not yet, cement penetrant crystalline is equably sprinkling upon on bottom plate with sieve, then press polish.The present invention is suitable for the waterproof of the positions such as elevator, kitchen, toilet, balcony, and waterproof effect is splendid.

Description

A kind of waterproof technology
Technical field
The present invention relates to waterproof manufacture technology field, specially a kind of waterproof technology.
Background technology
The former design scheme of waterproof is designing institute's reference relevant national standard or local standard, is that foundation is set with theoretical condition Meter, does not account for practice of construction condition, such as:Basal plane out-of-flatness, basal plane are not dried, and basal plane is not clean, and structure leak, structure is split Seam, bulk settling, duration practice of construction present situation and later period maintenance difficulty, later period maintenance feasibility etc. such as overwork also less are examined Consider state-of-the-art technology, last word, Market Feedback practice result, theoretically reaching by all means or not violating state related requirements can wait It is influenced caused by practical factor, eventually leads to actual result and theoretical effect deviation.
Currently, it is also that level is uneven that the waterproof of building trade, which did process, ununified method be easy to cause local leakage Brush and waterproof effect are poor.
Invention content
The purpose of the present invention is to provide a kind of waterproof technologies, to solve building trade mentioned above in the background art It is also that level is uneven that waterproof, which did process, ununified method, be easy to cause the problem of part leakage brush and waterproof effect difference.
To achieve the above object, the present invention provides the following technical solutions:A kind of waterproof technology, including, following steps:
Step 1:Blinding layer is cleared up;
B) by inner corner trim and pipe root recessing, the groove opened is blocked with leak stopping king, is rinsed groove well with clear water, is reconciled high-strength Degree leak stopping king fills to groove, and when leak stopping king reaches expansion point, compacting is smoothed out to former height;
B) crack location opens wide 30mm in flooring and ceiling location, deep 10mmV type grooves are rinsed well with clear water, are reconciled High intensity leak stopping king blocks, and when leak stopping king reaches expansion point, compacting is smoothed out to former height;
C) perforation seam is being formed and the crack dripped carries out slip casting, the places 3-4cm and basal plane holding by crack or breakthrough 45 degree of angular bit holes, the diameter of head needle until aperture, depth 10-15cm, cross borehole, and keep pitch of holes 8-12cm;Only Head needle is wanted buried and is tightened, and basal plane 1-1.5cm is exposed, with high-pressure grout injector slip casting until having slurry spilling;Equal slurries drying Afterwards, basal plane slurry, and knock-off slip casting end are removed with perching knife;Seal treatment is carried out to slip casting point with waterproofing and leakage-stopping king, it is rear to carry out Basal plane is levelling;
D) pipeline on waterproof matrix, built-in fitting, Equipment Foundations are buried and are installed before construction of waterproof layer, in pipe The node location coating spraying 500mm wide coatings of root, inner corner trim, Equipment Foundations, the corner at negative and positive angle, plane and facade, which is used, prevents Water sand slurry smears into circular arc, arc radius 50mm;Then the floating ash of base and building waste are cleaned out with broom or hair-dryer, It is rinsed well with giant, airing;
Step 2:Uncured water-repellent paint integral spray, on the blinding layer handled well uniform mechanically spraying or Artificial to brush the uncured rubber asphalt waterproof coating of 2mm thickness self-cure types, the thin portions paintbrush auxiliary construction such as inner corner trim, pipe root is wanted Consistency of thickness is sought, there must not be the defects of leakage is scraped, accumulated, being bubbled, and carries out in corresponding pipe root, metope turning over processing, top is high Degree is no less than 250mm, multipass brushing;
Step 3:The thick strengths of 2mm are intersected the two-sided high-polymer self-adhesion waterproof coiled material of film and are laid with;
A) before being laid with large area waterproof roll, in pipe root, the node of Equipment Foundations, negative and positive angle, Shui Luokou, ventilation The position laying additional waterproofing layer of mouth, drainage gutter, deformation joint, laying width is 500mm;
B) by the pre- drawout of coiled material, stress is discharged, tries to spread according to datum line, it is ensured that coiled material lapping position is in 8-10cm, control The direction of installation of membrane processed and straight beauty;It holds fired heater to heat against coiled material to be spread, pushes away rolling coiled material in time and carry out viscous paving, Gas is discharged and is compacted, must not excessively be heated;Coiled material answers smooth overlap joint size correct after paving, must not distort;If twice are rolled up Material overlapping construction, after first of installation of membrane is good, snap the line construction second coiled material, upper layer and lower layer coiled material cannot be the same as seam, Er Qieshang It descends two layers and the short of the adjacent two width coiled material of same layer overlaps fissure of displacement 1500mm, coiled material answers smooth overlap joint size correct after paving, no It must distort;
C) joint treatment:Layer coiled material bottom surface and lower layer coiled material upper surface pitch coating are fully toasted with grilled gun, are compacted It is sealed with Rubber Modified Asphalt Waterproof Coating, it is ensured that ne-leakage point;
Step 4:Coiled material protective layer is constructed, with dilution concrete 50mm protective layers protection bottom plate or plane;
Step 5:It is dry in structure base slab construction to spread 1.5 ㎏/㎡ of penetrant crystalline;
After bottom plate or flat concrete pour, when solidifying, but can also be trampled completely not yet, cement is oozed with sieve Crystallization is equably sprinkling upon on bottom plate thoroughly, then press polish.
Preferably, the recess width in the step 1 is 30mm, and deep 10mm, shape is V-type.
Preferably, the basal plane in the step 1 is answered smooth, dry, solid, must not there is peeling dusting phenomenon.
Preferably, the coating in the step 1 is the uncured rubber asphalt waterproof coating of 2mm thickness self-cure types.
Compared with prior art, the beneficial effects of the invention are as follows:
The waterproof method of the present invention combine various waterproof materials construction, using with the characteristic and knot that are showed in repair Fruit ensures waterproof project quality, it is ensured that ne-leakage to greatest extent for different construction sites, it is ensured that long-term ne-leakage, and grind Send out a set of materials'use scheme the most reliable, standard construction method.The present invention is suitable for elevator, kitchen, toilet, sun The waterproof of the positions such as platform.
Specific implementation mode
The technical scheme in the embodiments of the invention will be clearly and completely described below, it is clear that described implementation Example is only a part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, this field is common The every other embodiment that technical staff is obtained without making creative work belongs to the model that the present invention protects It encloses.
A kind of waterproof technology, including, following steps:
Step 1:Blinding layer is cleared up;
C) by inner corner trim and pipe root recessing, the groove opened is blocked with leak stopping king, is rinsed groove well with clear water, is reconciled high-strength Degree leak stopping king fills to groove, and when leak stopping king reaches expansion point, compacting is smoothed out to former height;
B) crack location opens wide 30mm in flooring and ceiling location, deep 10mmV type grooves are rinsed well with clear water, are reconciled High intensity leak stopping king blocks, and when leak stopping king reaches expansion point, compacting is smoothed out to former height;
C) perforation seam is being formed and the crack dripped carries out slip casting, the places 3-4cm and basal plane holding by crack or breakthrough 45 degree of angular bit holes, the diameter of head needle until aperture, depth 10-15cm, cross borehole, and keep pitch of holes 8-12cm;Only Head needle is wanted buried and is tightened, and basal plane 1-1.5cm is exposed, with high-pressure grout injector slip casting until having slurry spilling;Equal slurries drying Afterwards, basal plane slurry, and knock-off slip casting end are removed with perching knife;Seal treatment is carried out to slip casting point with waterproofing and leakage-stopping king, it is rear to carry out Basal plane is levelling;
D) pipeline on waterproof matrix, built-in fitting, Equipment Foundations are buried and are installed before construction of waterproof layer, in pipe The node location coating spraying 500mm wide coatings of root, inner corner trim, Equipment Foundations, the corner at negative and positive angle, plane and facade, which is used, prevents Water sand slurry smears into circular arc, arc radius 50mm;Then the floating ash of base and building waste are cleaned out with broom or hair-dryer, It is rinsed well with giant, airing;
Step 2:Uncured water-repellent paint integral spray, on the blinding layer handled well uniform mechanically spraying or Artificial to brush the uncured rubber asphalt waterproof coating of 2mm thickness self-cure types, the thin portions paintbrush auxiliary construction such as inner corner trim, pipe root is wanted Consistency of thickness is sought, there must not be the defects of leakage is scraped, accumulated, being bubbled, and carries out in corresponding pipe root, metope turning over processing, top is high Degree is no less than 250mm, multipass brushing;
Step 3:The thick strengths of 2mm are intersected the two-sided high-polymer self-adhesion waterproof coiled material of film and are laid with;
A) before being laid with large area waterproof roll, in pipe root, the node of Equipment Foundations, negative and positive angle, Shui Luokou, ventilation The position laying additional waterproofing layer of mouth, drainage gutter, deformation joint, laying width is 500mm;
B) by the pre- drawout of coiled material, stress is discharged, tries to spread according to datum line, it is ensured that coiled material lapping position is in 8-10cm, control The direction of installation of membrane processed and straight beauty;It holds fired heater to heat against coiled material to be spread, pushes away rolling coiled material in time and carry out viscous paving, Gas is discharged and is compacted, must not excessively be heated;Coiled material answers smooth overlap joint size correct after paving, must not distort;If twice are rolled up Material overlapping construction, after first of installation of membrane is good, snap the line construction second coiled material, upper layer and lower layer coiled material cannot be the same as seam, Er Qieshang It descends two layers and the short of the adjacent two width coiled material of same layer overlaps fissure of displacement 1500mm, coiled material answers smooth overlap joint size correct after paving, no It must distort;
C) joint treatment:Layer coiled material bottom surface and lower layer coiled material upper surface pitch coating are fully toasted with grilled gun, are compacted It is sealed with Rubber Modified Asphalt Waterproof Coating, it is ensured that ne-leakage point;
Step 4:Coiled material protective layer is constructed, with dilution concrete 50mm protective layers protection bottom plate or plane;
Step 5:It is dry in structure base slab construction to spread 1.5 ㎏/㎡ of penetrant crystalline;
After bottom plate or flat concrete pour, when solidifying, but can also be trampled completely not yet, cement is oozed with sieve Crystallization is equably sprinkling upon on bottom plate thoroughly, then press polish.
Further, the recess width in the step 1 is 30mm, and deep 10mm, shape is V-type.
Further, the basal plane in the step 1 is answered smooth, dry, solid, must not there is peeling dusting phenomenon.
Further, the coating in the step 1 is the uncured rubber asphalt waterproof coating of 2mm thickness self-cure types.
The waterproof method of the present invention combine various waterproof materials construction, using with the characteristic and knot that are showed in repair Fruit ensures waterproof project quality, it is ensured that ne-leakage to greatest extent for different construction sites, it is ensured that long-term ne-leakage, and grind Send out a set of materials'use scheme the most reliable, standard construction method.
It is obvious to a person skilled in the art that invention is not limited to the details of the above exemplary embodiments, Er Qie In the case of without departing substantially from spirit or essential attributes of the invention, the present invention can be realized in other specific forms.Therefore, no matter From the point of view of which point, the present embodiments are to be considered as illustrative and not restrictive, and the scope of the present invention is by appended power Profit requires rather than above description limits, it is intended that all by what is fallen within the meaning and scope of the equivalent requirements of the claims Variation is included within the present invention.

Claims (4)

1. a kind of waterproof technology, which is characterized in that including following steps:
Step 1:Blinding layer is cleared up;
A) by inner corner trim and pipe root recessing, the groove opened is blocked with leak stopping king, groove is rinsed well with clear water, and the high intensity that reconciles is stifled Leakage king fills to groove, and when leak stopping king reaches expansion point, compacting is smoothed out to former height;
B) crack location opens wide 30mm in flooring and ceiling location, deep 10mmV type grooves are rinsed well with clear water, are reconciled high-strength It spends leak stopping king to block, when leak stopping king reaches expansion point, compacting is smoothed out to former height;
C) perforation seam is being formed and the crack dripped carries out slip casting, 45 degree of the places 3-4cm and basal plane holding by crack or breakthrough Angular bit hole, the diameter of head needle until aperture, depth 10-15cm, cross borehole, and keep pitch of holes 8-12cm;Sealing head Needle is wanted buried and is tightened, and basal plane 1-1.5cm is exposed, with high-pressure grout injector slip casting until having slurry spilling;After equal slurries drying, use Perching knife removes basal plane slurry, and knock-off slip casting end;Seal treatment is carried out to slip casting point with waterproofing and leakage-stopping king, the rear basal plane that carries out is looked for It is flat;
D) pipeline on waterproof matrix, built-in fitting, Equipment Foundations are buried and are installed before construction of waterproof layer, in pipe root, the moon Angle, Equipment Foundations node location with coating spray 500mm wide coatings, the corner Waterproof sand at negative and positive angle, plane and facade Slurry smears into circular arc, arc radius 50mm;Then the floating ash of base and building waste are cleaned out with broom or hair-dryer, with height Pressure hydraulic giant is rinsed well, airing;
Step 2:Uncured water-repellent paint integral spray, the uniform mechanically spraying or artificial on the blinding layer handled well Brush the uncured rubber asphalt waterproof coating of 2mm thickness self-cure types, the thin portions paintbrush auxiliary construction such as inner corner trim, pipe root, it is desirable that thick Degree is consistent, must not there is the defects of leakage is scraped, accumulated, being bubbled, and carries out in corresponding pipe root, metope turning over processing, and height is not Less than 250mm, multipass brushing;
Step 3:The thick strengths of 2mm are intersected the two-sided high-polymer self-adhesion waterproof coiled material of film and are laid with;
A) before being laid with large area waterproof roll, in pipe root, the node of Equipment Foundations, negative and positive angle, Shui Luokou, ventilation opening, row The position laying additional waterproofing layer of water gutter, deformation joint, laying width is 500mm;
B) by the pre- drawout of coiled material, stress is discharged, tries to spread according to datum line, it is ensured that coiled material lapping position is in 8-10cm, control volume The direction of material paving and straight beauty;It holds fired heater to heat against coiled material to be spread, pushes away rolling coiled material in time and carry out viscous paving, by gas Body is discharged and is compacted, and must not excessively heat;Coiled material answers smooth overlap joint size correct after paving, must not distort;If twice coiled material is folded Construction is closed, after first of installation of membrane is good, snap the line construction second coiled material, upper layer and lower layer coiled material same cannot stitch, and upper and lower two The short of layer and the adjacent two width coiled material of same layer overlaps fissure of displacement 1500mm, and coiled material answers smooth overlap joint size correct after paving, must not turn round It is bent;
C) joint treatment:Layer coiled material bottom surface and lower layer coiled material upper surface pitch coating are fully toasted with grilled gun, rubber is used in compacting Glue modified waterproof asphalt material seals, it is ensured that ne-leakage point;
Step 4:Coiled material protective layer is constructed, with dilution concrete 50mm protective layers protection bottom plate or plane;
Step 5:It is dry in structure base slab construction to spread 1.5 ㎏/㎡ of penetrant crystalline;
After bottom plate or flat concrete pour, when solidifying, but can also be trampled completely not yet, cement is permeated with sieve and is tied Crystalline substance is equably sprinkling upon on bottom plate, then press polish.
2. a kind of waterproof technology according to claim 1, which is characterized in that the recess width in the step 1 is 30mm, Deep 10mm, shape are V-type.
3. a kind of waterproof technology according to claim 1, which is characterized in that the basal plane in the step 1 is answered smooth, dry It is dry, solid, there must not be peeling dusting phenomenon.
4. a kind of waterproof technology according to claim 1, which is characterized in that the coating in the step 1 is 2mm thickness self-healings The uncured rubber asphalt waterproof coating of type.
CN201810558716.1A 2018-06-01 2018-06-01 Waterproof process Active CN108755983B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810558716.1A CN108755983B (en) 2018-06-01 2018-06-01 Waterproof process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810558716.1A CN108755983B (en) 2018-06-01 2018-06-01 Waterproof process

Publications (2)

Publication Number Publication Date
CN108755983A true CN108755983A (en) 2018-11-06
CN108755983B CN108755983B (en) 2020-09-08

Family

ID=64002208

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810558716.1A Active CN108755983B (en) 2018-06-01 2018-06-01 Waterproof process

Country Status (1)

Country Link
CN (1) CN108755983B (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109356295A (en) * 2018-11-21 2019-02-19 陕西中林建筑装饰工程有限公司 The construction technique of toilet and kitchen antiseep
CN109372026A (en) * 2018-11-09 2019-02-22 江苏兴厦建设工程集团有限公司 A kind of the combination waterproof layer structure and its construction method of greenbelt underground engineering top plate
CN109457716A (en) * 2018-11-15 2019-03-12 李延敏 It is uncured to intersect film waterproof system construction technology with SPC self-adhesion
CN110409632A (en) * 2019-07-03 2019-11-05 广州市艺鸿装饰工程有限公司 A kind of balcony waterproof technology
CN110777951A (en) * 2019-11-13 2020-02-11 北京首钢建设集团有限公司 Waterproof construction method for waterproof interfaces made of different materials
CN111042348A (en) * 2019-12-25 2020-04-21 山东工程职业技术大学 Waterproof construction process for base layer in various complex forms
CN112095816A (en) * 2020-09-25 2020-12-18 天津滨海澳泰防水材料有限公司 Construction method for forming three composite waterproof layers through single construction
CN112196298A (en) * 2020-09-10 2021-01-08 斯科瑞新材料科技(山东)股份有限公司 Novel building waterproof process and material
CN114961125A (en) * 2022-08-01 2022-08-30 江苏凯伦建材股份有限公司 Construction method of roof system
CN116971189A (en) * 2023-08-03 2023-10-31 烟台市洛蒙防水材料有限公司 High-viscosity waterproof coating and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102758486A (en) * 2012-07-12 2012-10-31 振华集团(昆山)建设工程有限公司 Anti-seepage method for building engineering
KR20140109022A (en) * 2013-03-05 2014-09-15 박호규 Functionality special mortar composition use Method of water proofing
CN104213653A (en) * 2013-06-04 2014-12-17 江苏中洋集团股份有限公司 Building heat preservation wall structure
CN105904816A (en) * 2016-04-19 2016-08-31 深圳市蓝盾防水工程有限公司 A waterproof system coating-coiled material composite plane and a constructing process
CN106968451A (en) * 2017-04-21 2017-07-21 上海东方雨虹防水工程有限公司 A kind of prestressing force roof boarding leakage maintaining method and its system and surface waterproofing construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102758486A (en) * 2012-07-12 2012-10-31 振华集团(昆山)建设工程有限公司 Anti-seepage method for building engineering
KR20140109022A (en) * 2013-03-05 2014-09-15 박호규 Functionality special mortar composition use Method of water proofing
CN104213653A (en) * 2013-06-04 2014-12-17 江苏中洋集团股份有限公司 Building heat preservation wall structure
CN105904816A (en) * 2016-04-19 2016-08-31 深圳市蓝盾防水工程有限公司 A waterproof system coating-coiled material composite plane and a constructing process
CN106968451A (en) * 2017-04-21 2017-07-21 上海东方雨虹防水工程有限公司 A kind of prestressing force roof boarding leakage maintaining method and its system and surface waterproofing construction method

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109372026A (en) * 2018-11-09 2019-02-22 江苏兴厦建设工程集团有限公司 A kind of the combination waterproof layer structure and its construction method of greenbelt underground engineering top plate
CN109457716A (en) * 2018-11-15 2019-03-12 李延敏 It is uncured to intersect film waterproof system construction technology with SPC self-adhesion
CN109356295A (en) * 2018-11-21 2019-02-19 陕西中林建筑装饰工程有限公司 The construction technique of toilet and kitchen antiseep
CN110409632A (en) * 2019-07-03 2019-11-05 广州市艺鸿装饰工程有限公司 A kind of balcony waterproof technology
CN110777951A (en) * 2019-11-13 2020-02-11 北京首钢建设集团有限公司 Waterproof construction method for waterproof interfaces made of different materials
CN111042348A (en) * 2019-12-25 2020-04-21 山东工程职业技术大学 Waterproof construction process for base layer in various complex forms
CN112196298A (en) * 2020-09-10 2021-01-08 斯科瑞新材料科技(山东)股份有限公司 Novel building waterproof process and material
CN112095816A (en) * 2020-09-25 2020-12-18 天津滨海澳泰防水材料有限公司 Construction method for forming three composite waterproof layers through single construction
CN114961125A (en) * 2022-08-01 2022-08-30 江苏凯伦建材股份有限公司 Construction method of roof system
CN116971189A (en) * 2023-08-03 2023-10-31 烟台市洛蒙防水材料有限公司 High-viscosity waterproof coating and construction method thereof

Also Published As

Publication number Publication date
CN108755983B (en) 2020-09-08

Similar Documents

Publication Publication Date Title
CN108755983A (en) A kind of waterproof technology
CN104153400B (en) Construction method for preventing soft soil foundation cast-in-place pile head from being waterproof
CN110528789A (en) A kind of roof waterproof engineering construction method
CN110093989A (en) A kind of interior waterproof construction and its construction method
CN111042348A (en) Waterproof construction process for base layer in various complex forms
CN206319910U (en) Infiltration disposal system is reinforced in a kind of tunnel-liner
CN113047459A (en) Construction process for laying HDPE (high-density polyethylene) high-molecular self-adhesive film waterproof coiled material
CN105951893A (en) Uplift pile head node waterproof structure and construction method thereof
CN204492025U (en) The waterproof construction of the contour deformation joint of roofing
CN108086684B (en) Construction method for building waterproofing by using non-cured rubber asphalt and application thereof
CN204492022U (en) The waterproof construction of parapet high-low bay deformation joint
CN114876117A (en) Multi-gradient planting roof structure and construction method thereof
CN109339303B (en) Opening-type curtain wall inner and outer edge closing structure and construction method
CN101545269A (en) Method for rigid waterproof construction of beam and slab type basement
CN113550451A (en) Waterproof construction method for building outer wall
CN111535368A (en) Basement waterproof construction process
CN208329409U (en) A kind of parapet of roofing water leak-proof structure
CN109881794A (en) A kind of swimming pool waterproof construction
CN109826325A (en) A kind of anti-seepage construction method of architectural engineering
CN205976015U (en) Waterproof construction of basement outer wall
CN212671027U (en) Leakage-proof structure for terrace roof
CN211037568U (en) Plant vegetation roof waterproof construction
CN113530124A (en) Construction method for preventing water-blocking wet plaster inside and outside volcanic rocks on wall surface
CN110424641A (en) A kind of waterproof and insulation integrated system wet-laying construction technology of modified-high polymer
CN108193784A (en) A kind of upper and lower conduit slot antiseep technique

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20221111

Address after: 410116 Workshop 109, Floor 1, Building B3, Building B4 and Building B5, Lingzhi Industrial Park, No. 128 Jinhai Road, Yuhua District, Changsha City, Hunan Province

Patentee after: Hunan Jimmy Passive House Technology Co.,Ltd.

Address before: 410007 Room 301, Building 11, Phase II, Wanjing Shui'an, Minmetals, Guitang Road, Yuhua District, Changsha City, Hunan Province

Patentee before: HUNAN JIMI WATERPROOF TECHNOLOGY Co.,Ltd.