CN104100026A - Disassembling-free steel-frame three-dimensional screen formwork cast-in-place foaming concrete composite wall and construction method - Google Patents

Disassembling-free steel-frame three-dimensional screen formwork cast-in-place foaming concrete composite wall and construction method Download PDF

Info

Publication number
CN104100026A
CN104100026A CN201410346440.2A CN201410346440A CN104100026A CN 104100026 A CN104100026 A CN 104100026A CN 201410346440 A CN201410346440 A CN 201410346440A CN 104100026 A CN104100026 A CN 104100026A
Authority
CN
China
Prior art keywords
template
concrete
cast
steel frame
foamed concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410346440.2A
Other languages
Chinese (zh)
Other versions
CN104100026B (en
Inventor
闫广达
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGXI SHUANGDE BUILDING ENGINEERING CO., LTD.
Original Assignee
BEIJING ZHONGLIANHUAN HUANGMEI LIGHT STEEL STRUCTURE INSTALLATION Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING ZHONGLIANHUAN HUANGMEI LIGHT STEEL STRUCTURE INSTALLATION Co Ltd filed Critical BEIJING ZHONGLIANHUAN HUANGMEI LIGHT STEEL STRUCTURE INSTALLATION Co Ltd
Priority to CN201410346440.2A priority Critical patent/CN104100026B/en
Publication of CN104100026A publication Critical patent/CN104100026A/en
Application granted granted Critical
Publication of CN104100026B publication Critical patent/CN104100026B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention discloses a non-bearing maintenance structure wall and particularly relates to a disassembling-free steel-frame three-dimensional screen formwork cast-in-place foaming concrete composite wall comprising a wall board composed of a disassembling-free steel-frame three-dimensional screen formwork, a connecting plate fixedly connected to the top of a foaming concrete formwork and physical foaming concrete. The connecting plate is provided with pouring holes used for pouring the physical foaming concrete. The invention further discloses a construction method of the cast-in-place foaming concrete composite wall. The method includes 1, setting and manufacturing the disassembling-free steel-frame three-dimensional screen formwork; 2, paying off; 3, mounting keels; 4, mounting the forming concrete formwork; 5, mounting the cement plate connecting plate; 6, pouring the foaming concrete. The composite wall has the advantages of lightweight, fine heating and sound insulating effects, high entire comprehensive strength, fine fire-resistant and earthquake-resistant performance, low cost and high construction speed.

Description

Exempt to tear open the cast-in-place foaming concrete combined wall of steel frame stereo silk-screen template and construction method
Technical field
The present invention relates to a kind of nonweight-bearing enclosed structure materials for wall using in building construction, be specially one and exempt to tear open the cast-in-place foaming concrete combined wall of steel frame stereo silk-screen template and construction method.
Background technology
Can thermal insulation, can prevent fires again, this is two large function demands of current building.
China's building energy consumption accounts for 1/3 of whole society's total energy consumption at present.Northern China urban heating floor space only accounts for 10% of National urban floor space, and building energy consumption but accounts for 40%.Energy consumption maximum in China building is heating and refrigeration, and compared with the developed country close with weather conditions, every square metre of building heating energy consumption of China is 3 times of left and right of developed country.Will greatly increase energy consumption as the method with traditional solves heat supply in winter problem, worsen atmosphere pollution.
Because of the defective fire incident case causing of external wall heat insulating material for external combustibility too numerous to enumerate." about strengthening and improving firemanic suggestion " (No. [2011] 46, promulgated by the State Council) requirement that State Council prints and distributes, the heat insulating material for external of newly-built, renovating and enlarging engineering must not use combustible material without exception, and strict restriction is used combustible material.Occur in recent years some large-sized fires of various places, all relevant with external wall heat insulating material for external.
The requirement of building energy conservation is proposed among three of China's " energy-saving and emission-reduction " 12 planning " regulations.How to realize building energy conservation imperative, on market, there is now the new material of a lot of energy-conserving and environment-protective, such as prefabricated solid concrete wall is due to too heavy, transport installation cost is higher, polystyrene board wall body due to the not fire-retardant existence of polyphenyl material is flammable and burning after discharge a large amount of toxic gases and have insecurity, for the polyurethane of exterior-wall heat insulation or paste foamed concrete plate secondary heat preservation construction outward and cause cost too high.Also have gas concrete stripe board, cement block, GRC gently porous stripe board processed etc. use function singleness, and have wall crazing, the problem such as speed of application is slow.
Insulation and fire prevention, how cost and environmental protection, get both? also fewer at present high, the energy-conserving and environment-protective again of intensity, also fire prevention and inexpensive compatible material market.
Summary of the invention
For the problems referred to above, the invention discloses and exempt to tear open the cast-in-place foaming concrete combined wall of steel frame stereo silk-screen template, there is intensity high, energy-conserving and environment-protective, also fire prevention and inexpensive advantage.
Concrete solution is: exempt to tear open the cast-in-place foaming concrete combined wall of steel frame stereo silk-screen template, described combined wall comprises that exempting to tear open wallboard, the junction plate that is fixedly connected on foamed concrete template top and the filling that steel frame 3 D stereo screen template forms exempts to tear open the physical blowing concrete composition between steel frame 3 D stereo screen template, and described junction plate is provided with builds the concrete pouring hole of physical blowing.
Further, described in, exempting to tear open steel frame 3 D stereo screen template periphery is arranged with and can, for the galvanized steel plain sheet frame of joggle connection, be provided with three-dimensional steel silk screen as skeleton in the foamed concrete in frame.
Further, described junction plate is cement board, junction plate with exempt to tear steel frame 3 D stereo screen template open and be fixedly connected with by screw.On described junction plate, pouring hole is uniformly distributed, and the number of every junction plate plug hole is 4-5, and diameter is 100mm.Describedly exempt to tear open steel frame 3 D stereo screen template external surface and have the crack resist at mortar with grid cloth that 5mm is thick.
The invention also discloses the construction method of exempting to tear open the cast-in-place foaming concrete combined wall of steel frame stereo silk-screen template, comprise the steps:
The first step, typesetting and the making of exempting to tear open steel frame 3 D stereo screen template: carry out typesetting by design drawing, determine the specification of foamed concrete template, in factory, complete foamed concrete template construct.
Second step, unwrapping wire: in strict accordance with typesetting figure unwrapping wire, foamed concrete template hookup wire on the bullet of body of wall installation position.
The 3rd step, installs keel: according to keel installation baseline, keel installation is put in place.
The 4th step, foamed concrete template is installed: foamed concrete template should carefully check that whether specifications and models, installation direction etc. be correct before installing, and whether foamed concrete template has modification or damage.
The 5th step, cement board junction plate is installed: after both sides foamed concrete template installs, junction plate is fixed on tapping screw in the groove of two templates, make two templates form entirety, on junction plate, bore again plug hole with rig, be used for pouring foaming concrete, in the time that foamed concrete does not tamp in lower floor's foamed concrete template, can supplement with upper strata foamed concrete.
The 6th step, foamed concrete cast: carefully check whether template installation meets the requirements, and after meeting the requirements on inspection, can carry out foamed concrete cast, and one deck template is installed, pouring one step foaming concrete.
Further, in the first step, the principle of typesetting is that foamed concrete template specification should be minimum, reduces factory process workload and on-the-spot installation difficulty.
Further, in second step, equal hookup wire on bullet at the bottom of floor slab bottoms and beam, and corresponding hookup wire should be vertical, to ensure planeness and the verticality etc. of body of wall, simultaneously and identify the position of door and window hole.
Further, in the 3rd step, with screw by keel installation on concrete floor or with welding method keel are fixedly welded on steel work.
Further, in the 4th step, determining errorless in the situation that, when all inspection items meet the requirements, foamed concrete template is being fixed on keel with tapping screw.And check its planeness and verticality etc., use the same method opposite side foamed concrete template is installed.
Further, in the 6th step, before pouring foaming concrete, bottom foamed concrete template and floor contact position should be carried out to joint filling processing by cement mortar, encapsulation process also should be carried out in other apertured places.
Further, in the 6th step, each pouring is highly 600mm, waters to same foamed concrete template height, and when foamed concrete template is vertically installed, cast height must not exceed 1.55m.
The present invention compared with prior art has following advantage:
1, energy conservation: cast-in-place foamed concrete combined wall, by the airtight combination that forms of many small pores, can effectively completely cut off the discrepancy of heat, can play auxiliary adjusting air effect to Indoor environment outdoor environment, improves heat-insulating property.Reduce the loss of heat, not containing any toxic substance, environmental protection, nontoxic, reach low-carbon energy-saving environmental protection.
2, fire-proof shock-proof: the present invention uses A1 noncombustible construction material.Fire endurance >=3h, bending resistance carrying >=1.5.
3, heat preservation and soundproof: it is airtight porous that the present invention uses the foamed concrete that special process is made.240mm thickness of slab wall thermal transmittance≤0.543.240mm thickness of slab wall air borne sound sound transmission loss/dB >=42.
4, bulk strength is high: 3 D stereo silk screen steel frame is combined into an entirety with joggle and horizontal connection, has given full play to the advantage of each material, therefore this combined wall has higher bulk strength.
5, not dewfall of surface: not only compact conformation, firmly but also there is no cold bridge of integral assembled form of the present invention, the inside and outside foamed concrete of body of wall has effectively been avoided the dewfall phenomenon causing greatly due to the inside and outside humidity temperature difference, to affect the normal use of building.
6, labor and material saving: the present invention's insulation can be adjusted thickness of wall body by designing requirement makes it to reach requirement, and exterior wall need not do secondary insulation, the target reducing costs to reach labor and material saving again.
7, speed of application is fast: template of the present invention is that on-the-spot joggle assembling need not be dismantled, and infilled wall is cast in situs foamed concrete, therefore saves a large amount of transports and hanging device, has also saved a large amount of operating expenses.Cast 30m per hour 3 .
Brief description of the drawings
Fig. 1 is for exempting to tear open the cast-in-place foaming concrete composite wall body structure of steel frame stereo silk-screen template schematic diagram;
Fig. 2 is polylith combined wall combination scheme of installation;
Fig. 3 is combined wall joggle connected node enlarged drawing;
In figure, 1-exempts to tear open steel frame 3 D stereo screen template; 11-exempts to tear open steel frame 3 D stereo screen template end opening; It is suitable for reading that 12-exempts to tear open steel frame 3 D stereo screen template; 2-junction plate; 3-physical blowing concrete; 4-three-dimensional steel silk screen; 5-screw; 6-plug hole; 7-galvanized steel plain sheet frame.
Detailed description of the invention
Below in conjunction with accompanying drawing, the specific embodiment of the present invention is described.
Of the present inventionly exempt to tear open the cast-in-place foaming concrete combined wall of steel frame stereo silk-screen template and comprise exempting to tear open wallboard, the junction plate 2 that is fixedly connected on foamed concrete template top that steel frame 3 D stereo screen template 1 forms and filling the physical blowing concrete 3 of exempting to tear open between steel frame 3 D stereo screen template and form, junction plate is provided with builds the concrete pouring hole 6 of physical blowing.Exempt to tear open steel frame 3 D stereo screen template periphery and be arranged with the galvanized steel plain sheet frame 7 that can connect for joggle, in foamed concrete in frame, be provided with three-dimensional steel silk screen 4 as skeleton, exempting to tear open steel frame 3 D stereo screen template 1 external surface has the crack resist at mortar with grid cloth that 5mm is thick.Junction plate is cement board, junction plate with exempt to tear steel frame 3 D stereo screen template open and be fixedly connected with by screw 5.On junction plate, pouring hole is uniformly distributed, and the number of every junction plate plug hole is 4-5, and diameter is 100mm.
The construction method of exempting to tear open the cast-in-place foaming concrete combined wall of steel frame stereo silk-screen template of the present invention is:
The first step, typesetting and the making of exempting to tear open steel frame 3 D stereo screen template: carry out typesetting by design drawing, determine the specification of template, in factory, complete template construct.The principle of typesetting is that template specification should be minimum, reduces factory process workload and on-the-spot installation difficulty.
Second step, unwrapping wire: in strict accordance with typesetting figure unwrapping wire, at body of wall installation position bullet cope match-plate pattern hookup wire.Equal hookup wire on bullet at the bottom of floor slab bottoms and beam, and corresponding hookup wire should be vertical, to ensure planeness and the verticality etc. of body of wall, simultaneously and identify the position of door and window hole.
The 3rd step, installs keel: according to keel installation baseline, keel installation is put in place.With screw by keel installation on concrete floor or with welding method keel are fixedly welded on steel work.
The 4th step, template is installed: foamed concrete template should carefully check that whether specifications and models, installation direction etc. be correct before installing, and whether template has modification or damage.Determining errorless in the situation that, when all inspection items meet the requirements, template is being fixed on keel with tapping screw.And check its planeness and verticality etc., use the same method opposite side template is installed.
The 5th step, cement board junction plate is installed: after two side templates install, junction plate is fixed on tapping screw in the groove of two templates, make two templates form entirety, on junction plate, bore again plug hole with rig, be used for pouring foaming concrete, in the time that foamed concrete in lower template does not tamp, can supplement with upper strata foamed concrete.
The 6th step, foamed concrete cast: carefully check whether template installation meets the requirements, and after meeting the requirements on inspection, can carry out foamed concrete cast, and one deck template is installed, pouring one step foaming concrete.Before pouring foaming concrete, bottom template and floor contact position should be carried out to joint filling processing by cement mortar, encapsulation process also should be carried out in other apertured places, and each pouring is highly 600mm, water to isotype plate height, when template is vertically installed, cast height must not exceed 1.55m.

Claims (10)

1. exempt to tear open the cast-in-place foaming concrete combined wall of steel frame stereo silk-screen template for one kind, it is characterized in that, described combined wall comprises that exempting to tear open the wallboard of steel frame 3 D stereo screen template (1) formation, the junction plate (2) that is fixedly connected on foamed concrete template top and filling exempts to tear open physical blowing concrete (3) composition between steel frame 3 D stereo screen template, and described junction plate is provided with builds the concrete pouring hole of physical blowing (6).
2. exempting from described in 1 torn the cast-in-place foaming concrete combined wall of steel frame stereo silk-screen template open as requested, it is characterized in that, describedly exempt to tear open steel frame 3 D stereo screen template periphery and be arranged with the galvanized steel plain sheet frame (7) that can connect for joggle, in the foamed concrete in described frame, be provided with three-dimensional steel silk screen (4) as skeleton.
3. exempting from described in 1 torn the cast-in-place foaming concrete combined wall of steel frame stereo silk-screen template open as requested, it is characterized in that, described junction plate is cement board, junction plate with exempt to tear steel frame 3 D stereo screen template open and be fixedly connected with by screw (5); On described junction plate, pouring hole is uniformly distributed, and the number of every junction plate plug hole (6) is 4-5, and diameter is 100mm; Describedly exempt to tear open steel frame 3 D stereo screen template (1) external surface and have the crack resist at mortar with grid cloth that 5mm is thick.
4. a construction method of exempting to tear open the cast-in-place foaming concrete combined wall of steel frame stereo silk-screen template, is characterized in that, comprises the steps:
The first step, typesetting and the making of exempting to tear open steel frame 3 D stereo screen template: carry out typesetting by design drawing, determine the specification of foamed concrete template, in factory, complete foamed concrete template construct;
Second step, unwrapping wire: in strict accordance with typesetting figure unwrapping wire, foamed concrete template hookup wire on the bullet of body of wall installation position;
The 3rd step, installs keel: according to keel installation baseline, keel installation is put in place;
The 4th step, foamed concrete template is installed: foamed concrete template should carefully check that whether specifications and models, installation direction etc. be correct before installing, and whether foamed concrete template has modification or damage;
The 5th step, cement board junction plate is installed: after two side templates install, junction plate is fixed on tapping screw in the groove of two templates, make two templates form entirety, on junction plate, bore again plug hole with rig, be used for pouring foaming concrete, in the time that foamed concrete in lower template does not tamp, can supplement with upper strata foamed concrete;
The 6th step, foamed concrete cast: carefully check whether template installation meets the requirements, and after meeting the requirements on inspection, can carry out foamed concrete cast, and one deck foamed concrete template is installed, pouring one step foaming concrete.
5. construction method of exempting to tear open the cast-in-place foaming concrete combined wall of steel frame stereo silk-screen template according to claim 4, it is characterized in that, in the first step, the principle of typesetting is that foamed concrete template specification should be minimum, reduces factory process workload and on-the-spot installation difficulty.
6. construction method of exempting to tear open the cast-in-place foaming concrete combined wall of steel frame stereo silk-screen template according to claim 4, it is characterized in that, in second step, equal hookup wire on bullet at the bottom of floor slab bottoms and beam, and corresponding hookup wire should be vertical, to ensure planeness and the verticality etc. of body of wall, the while also identifies the position of door and window hole.
7. construction method of exempting to tear open the cast-in-place foaming concrete combined wall of steel frame stereo silk-screen template according to claim 4, it is characterized in that, in the 3rd step, with screw by keel installation on concrete floor or with welding method keel are fixedly welded on steel work.
8. construction method of exempting to tear open the cast-in-place foaming concrete combined wall of steel frame stereo silk-screen template according to claim 4, it is characterized in that, in the 4th step, determining errorless in the situation that, when all inspection items meet the requirements, foamed concrete template is fixed on keel with tapping screw, and checks its planeness and verticality etc., use the same method opposite side foamed concrete template is installed.
9. construction method of exempting to tear open the cast-in-place foaming concrete combined wall of steel frame stereo silk-screen template according to claim 4, it is characterized in that, in the 6th step, before pouring foaming concrete, bottom foamed concrete template and floor contact position should be carried out to joint filling processing by cement mortar, encapsulation process also should be carried out in other apertured places.
10. construction method of exempting to tear open the cast-in-place foaming concrete combined wall of steel frame stereo silk-screen template according to claim 4, it is characterized in that, in the 6th step, each pouring is highly 600mm, water to same foamed concrete template height, when foamed concrete template is vertically installed, cast height must not exceed 1.55m.
CN201410346440.2A 2014-07-18 2014-07-18 Construction method for disassembling-free steel-frame three-dimensional screen formwork cast-in-place foaming concrete composite wall Active CN104100026B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410346440.2A CN104100026B (en) 2014-07-18 2014-07-18 Construction method for disassembling-free steel-frame three-dimensional screen formwork cast-in-place foaming concrete composite wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410346440.2A CN104100026B (en) 2014-07-18 2014-07-18 Construction method for disassembling-free steel-frame three-dimensional screen formwork cast-in-place foaming concrete composite wall

Publications (2)

Publication Number Publication Date
CN104100026A true CN104100026A (en) 2014-10-15
CN104100026B CN104100026B (en) 2017-05-24

Family

ID=51668539

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410346440.2A Active CN104100026B (en) 2014-07-18 2014-07-18 Construction method for disassembling-free steel-frame three-dimensional screen formwork cast-in-place foaming concrete composite wall

Country Status (1)

Country Link
CN (1) CN104100026B (en)

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104775621A (en) * 2015-04-23 2015-07-15 奥克森(北京)新材料科技有限公司 Building formwork constructing method
CN105113709A (en) * 2015-09-10 2015-12-02 河南万道捷建股份有限公司 Novel wallboard convenient to install
CN105756233A (en) * 2015-04-02 2016-07-13 张波 Beam-wall composite exterior wall component
CN105926813A (en) * 2016-07-31 2016-09-07 王春明 Building partition board
CN106088578A (en) * 2016-08-02 2016-11-09 驻马店市永泰建筑节能材料设备有限公司 Non-dismantling formwork, foam concrete self-heat conserving composite wall body structure and construction method
CN106193292A (en) * 2016-07-16 2016-12-07 江南大学 A kind of steel frame assembled integral reinforced concrete shear wall structure system
CN106193436A (en) * 2015-05-04 2016-12-07 北新集团建材股份有限公司 A kind of assembled cementitious core heat-preserving wall and production method thereof
CN106193427A (en) * 2015-05-04 2016-12-07 北新集团建材股份有限公司 The corner unit of a kind of assembled body of wall and production method thereof
CN106193443A (en) * 2015-05-04 2016-12-07 北新集团建材股份有限公司 The door-window opening wall element of a kind of assembled body of wall and production method thereof
CN106193426A (en) * 2015-05-04 2016-12-07 北新集团建材股份有限公司 The decussation unit of a kind of assembled body of wall and production method thereof
CN106193382A (en) * 2015-05-04 2016-12-07 北新集团建材股份有限公司 The T-shaped corner unit of a kind of assembled body of wall and production method thereof
CN106592814A (en) * 2016-12-22 2017-04-26 辽宁金帝建筑设计有限公司 Integrally cast demolding-free self-thermal insulation wall and construction method thereof
CN108086584A (en) * 2018-01-23 2018-05-29 南京国电南自电网自动化有限公司 A kind of prefabricated GRC assembled wall boards
CN108374488A (en) * 2018-04-27 2018-08-07 浙江正合建筑网模有限公司 A kind of light steel gently mixes cavity net mould building and its construction method soon
CN108756052A (en) * 2018-06-15 2018-11-06 湖南省异格建筑节能工程有限公司 A kind of cast-in-place foamed concrete PVC skeletons combined wall and its construction method
CN110984463A (en) * 2019-11-08 2020-04-10 中科住创成都科技有限公司 Net mould component of industrial low-rise assembled house
CN112282147A (en) * 2020-09-02 2021-01-29 众合天成(大连)科技发展有限公司 Method for manufacturing disassembly-free template by scraping and smearing reinforced cement on steel plate mesh
CN115419213A (en) * 2022-08-15 2022-12-02 中建(天津)工业化建筑工程有限公司 Prefabricated mold-dismantling-free heat-preservation light-transmission integrated concrete slab and manufacturing method thereof
CN117403804A (en) * 2023-12-14 2024-01-16 国建绿色智慧工程设计研究院(天津)有限公司 Novel assembled external wall panel and assembling method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007032159A (en) * 2005-07-28 2007-02-08 Kansai Electric Power Co Inc:The Connecting structure of steel plate concrete structural body
CN201679111U (en) * 2009-09-11 2010-12-22 闫振甲 Cast-in-situ foam concrete structure for external wall heat insulation
CN201835520U (en) * 2010-11-06 2011-05-18 吴和生 End panel used for concrete pouring wall body on template
CN202689255U (en) * 2012-07-12 2013-01-23 泰安市当代建筑设计咨询有限公司 Demoulding-free cast-in-place foam concrete internal partition wall
CN202706266U (en) * 2012-07-31 2013-01-30 长沙远大住宅工业有限公司 Dismounting-free die system of steel wire net rack
CN202767293U (en) * 2012-07-12 2013-03-06 泰安市当代建筑设计咨询有限公司 Cast-in-place foam concrete external wall free of form removal
CN203947631U (en) * 2014-07-18 2014-11-19 北京中联环环美轻钢结构安装有限公司 Exempt to tear open the cast-in-place foaming concrete combined wall of steel frame stereo silk-screen template

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007032159A (en) * 2005-07-28 2007-02-08 Kansai Electric Power Co Inc:The Connecting structure of steel plate concrete structural body
CN201679111U (en) * 2009-09-11 2010-12-22 闫振甲 Cast-in-situ foam concrete structure for external wall heat insulation
CN201835520U (en) * 2010-11-06 2011-05-18 吴和生 End panel used for concrete pouring wall body on template
CN202689255U (en) * 2012-07-12 2013-01-23 泰安市当代建筑设计咨询有限公司 Demoulding-free cast-in-place foam concrete internal partition wall
CN202767293U (en) * 2012-07-12 2013-03-06 泰安市当代建筑设计咨询有限公司 Cast-in-place foam concrete external wall free of form removal
CN202706266U (en) * 2012-07-31 2013-01-30 长沙远大住宅工业有限公司 Dismounting-free die system of steel wire net rack
CN203947631U (en) * 2014-07-18 2014-11-19 北京中联环环美轻钢结构安装有限公司 Exempt to tear open the cast-in-place foaming concrete combined wall of steel frame stereo silk-screen template

Cited By (26)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105756233B (en) * 2015-04-02 2018-01-12 张波 A kind of beam wall composite exterior wall component
CN105756233A (en) * 2015-04-02 2016-07-13 张波 Beam-wall composite exterior wall component
CN104775621A (en) * 2015-04-23 2015-07-15 奥克森(北京)新材料科技有限公司 Building formwork constructing method
CN106193436A (en) * 2015-05-04 2016-12-07 北新集团建材股份有限公司 A kind of assembled cementitious core heat-preserving wall and production method thereof
CN106193382B (en) * 2015-05-04 2019-05-31 北新集团建材股份有限公司 A kind of the T-type corner unit and its production method of assembled wall
CN106193426B (en) * 2015-05-04 2019-05-31 北新集团建材股份有限公司 A kind of the right-angled intersection unit and its production method of assembled wall
CN106193443B (en) * 2015-05-04 2019-05-31 北新集团建材股份有限公司 A kind of the door-window opening wall element and its production method of assembled wall
CN106193427A (en) * 2015-05-04 2016-12-07 北新集团建材股份有限公司 The corner unit of a kind of assembled body of wall and production method thereof
CN106193443A (en) * 2015-05-04 2016-12-07 北新集团建材股份有限公司 The door-window opening wall element of a kind of assembled body of wall and production method thereof
CN106193426A (en) * 2015-05-04 2016-12-07 北新集团建材股份有限公司 The decussation unit of a kind of assembled body of wall and production method thereof
CN106193382A (en) * 2015-05-04 2016-12-07 北新集团建材股份有限公司 The T-shaped corner unit of a kind of assembled body of wall and production method thereof
CN106193427B (en) * 2015-05-04 2019-05-31 北新集团建材股份有限公司 A kind of corner unit and its production method of assembled wall
CN106193436B (en) * 2015-05-04 2019-05-28 北新集团建材股份有限公司 A kind of assembled cementitious core heat-preserving wall and its production method
CN105113709A (en) * 2015-09-10 2015-12-02 河南万道捷建股份有限公司 Novel wallboard convenient to install
CN106193292A (en) * 2016-07-16 2016-12-07 江南大学 A kind of steel frame assembled integral reinforced concrete shear wall structure system
CN105926813A (en) * 2016-07-31 2016-09-07 王春明 Building partition board
CN106088578A (en) * 2016-08-02 2016-11-09 驻马店市永泰建筑节能材料设备有限公司 Non-dismantling formwork, foam concrete self-heat conserving composite wall body structure and construction method
CN106592814A (en) * 2016-12-22 2017-04-26 辽宁金帝建筑设计有限公司 Integrally cast demolding-free self-thermal insulation wall and construction method thereof
CN108086584A (en) * 2018-01-23 2018-05-29 南京国电南自电网自动化有限公司 A kind of prefabricated GRC assembled wall boards
CN108374488A (en) * 2018-04-27 2018-08-07 浙江正合建筑网模有限公司 A kind of light steel gently mixes cavity net mould building and its construction method soon
CN108756052A (en) * 2018-06-15 2018-11-06 湖南省异格建筑节能工程有限公司 A kind of cast-in-place foamed concrete PVC skeletons combined wall and its construction method
CN110984463A (en) * 2019-11-08 2020-04-10 中科住创成都科技有限公司 Net mould component of industrial low-rise assembled house
CN112282147A (en) * 2020-09-02 2021-01-29 众合天成(大连)科技发展有限公司 Method for manufacturing disassembly-free template by scraping and smearing reinforced cement on steel plate mesh
CN115419213A (en) * 2022-08-15 2022-12-02 中建(天津)工业化建筑工程有限公司 Prefabricated mold-dismantling-free heat-preservation light-transmission integrated concrete slab and manufacturing method thereof
CN117403804A (en) * 2023-12-14 2024-01-16 国建绿色智慧工程设计研究院(天津)有限公司 Novel assembled external wall panel and assembling method thereof
CN117403804B (en) * 2023-12-14 2024-03-22 国建绿色智慧工程设计研究院(天津)有限公司 Assembled external wall panel and assembling method thereof

Also Published As

Publication number Publication date
CN104100026B (en) 2017-05-24

Similar Documents

Publication Publication Date Title
CN104100026A (en) Disassembling-free steel-frame three-dimensional screen formwork cast-in-place foaming concrete composite wall and construction method
CN203947631U (en) Exempt to tear open the cast-in-place foaming concrete combined wall of steel frame stereo silk-screen template
CN202073197U (en) Composite board and assembly thereof, template, concrete slab and mould section bar comprising same
CN204112532U (en) Integral light grouting heat-preserving wall
CN211774751U (en) Steel construction prefabricated wall panel mounting structure
CN203821627U (en) Wall structure system with light steel keels, and wall
CN211286074U (en) Self-heat-insulation system for prefabricated light high-strength foam concrete filled wallboard outer wall
CN107100296A (en) A kind of integrated inner partition plate of framework spinning bolt-type and its installation method
CN110331778B (en) Construction method of green energy-saving fabricated building
CN104805928A (en) Pump watering core material fibreboard wrapping sandwich insulation outer wall
CN104047457A (en) Light steel structure anti-seismic house
CN203145232U (en) Novel energy-saving insulation wall
CN203684522U (en) Lightweight composite prefabricated wall plate for house
CN115977258A (en) ALC wallboard and girder steel and concrete floor joint construction
CN116044106A (en) Integrated construction method for assembled phase-change heat-preservation decorative plate
CN110029759B (en) Environment-friendly, energy-saving and safe simple passive house
CN113944274A (en) Construction method of overhead flat roof capable of being loaded with people
CN210067146U (en) Simple passive house with environmental protection, energy saving and safety
CN203821669U (en) Floor slab structure system with light steel keels, and floor slab
CN203821925U (en) Earthquake-proofing house of light steel structure
CN207296480U (en) A kind of assembled villa
CN108252434B (en) Wall body and building house that T shaped steel is connected
CN202850287U (en) Architectural curtain wall
CN111379375A (en) Folding type heat-insulation wallboard
CN206616752U (en) The prefabricated superimposed sheet surface structure of assembled architecture

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Xu Junyi

Inventor after: Xu Shen

Inventor after: Huang Zanxu

Inventor after: Ding Jie

Inventor after: Tu Wenjun

Inventor after: Ren Guiquan

Inventor before: Yan Guangda

TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20170420

Address after: 330030 Jiangxi province Qingyunpu District of Nanchang City Shi Yao Road No. 999 building B building room 1301-1324 garden flora (thirteenth layer)

Applicant after: JIANGXI SHUANGDE BUILDING ENGINEERING CO., LTD.

Address before: Room 1, building Hua Huiyuan, No. 1, Warwick South Road, Beijing, Chaoyang District, China, No. 100021, building No. 1408

Applicant before: BEIJING ZHONGLIANHUAN HUANGMEI LIGHT STEEL STRUCTURE INSTALLATION CO., LTD.

GR01 Patent grant
GR01 Patent grant