CN104074519B - 一种浮动孔深分段回采法 - Google Patents

一种浮动孔深分段回采法 Download PDF

Info

Publication number
CN104074519B
CN104074519B CN201410316275.6A CN201410316275A CN104074519B CN 104074519 B CN104074519 B CN 104074519B CN 201410316275 A CN201410316275 A CN 201410316275A CN 104074519 B CN104074519 B CN 104074519B
Authority
CN
China
Prior art keywords
hole
back production
mine locating
place
medium
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410316275.6A
Other languages
English (en)
Other versions
CN104074519A (zh
Inventor
曹斌
杨坤
毛勇
高进
王洁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Daye Nonferrous Metals Co Ltd
Original Assignee
Daye Nonferrous Metals Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Daye Nonferrous Metals Co Ltd filed Critical Daye Nonferrous Metals Co Ltd
Priority to CN201410316275.6A priority Critical patent/CN104074519B/zh
Publication of CN104074519A publication Critical patent/CN104074519A/zh
Application granted granted Critical
Publication of CN104074519B publication Critical patent/CN104074519B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Drilling And Exploitation, And Mining Machines And Methods (AREA)

Abstract

一种浮动孔深分段回采法,其特征是:包括以下步骤:⑴开挖竖井或斜井以及水平巷道;⑵沿水平巷道,根据坑深揭露情况,每1.5m布置一个探矿孔进行深孔探矿;⑶根据深孔探矿取得的每个探矿孔处的矿体厚度,绘制矿体上向延伸状态图;⑷根据状态图进行采矿分段,以每两个波谷为一回采段;⑸在每一回采段的波峰处开挖一个切割井;⑹从最前一段开始向后依次逐段实施回采在每一段回采中,是以切割井为起点向前后两侧分段进行回采至波谷;⑺在安全确认到位的情况下,组织铲运机或遥控铲运机出矿;本发明克服了传统回采方法采切工程量大,贫矿量大等问题,主要适用于有色金属矿的开采。

Description

一种浮动孔深分段回采法
技术领域
本发明涉及有色金属矿山的开采技术领域,尤其是一种浮动孔深分段回采法。
背景技术
目前在有色金属矿山进行的传统采矿方法主要是以上向分段碎石胶结充填法,即采用“采一留一”分布局,分步骤回采,利用上分段对应充填巷分步骤碎石胶结填充。在传统采矿方法中,回采方法是:首先开挖竖井或斜井及水平巷道,再在水平巷道最前端打出一个切割井,然后按排距1.5m进行中深孔设计(采用标准规范设计),见图1,打爆矿孔,逐排爆破回采,传统设计每排中深孔的向上孔深均为一致的,即每排孔深都为图2所示设计。这就要求矿体较倾斜、连续、上下延伸较为深厚。对于倾角、走向、上下延伸极不规则的残小矿体,如图1矿体布置情况,传统回采方法则不能控制贫损率,而且采切工程量太大,贫矿量大,回采贫损率在25%~40%以上,回采成本高,矿产品质量差。
发明内容
本实用新型的目的就是要解决传统回采方法不能适应倾角、走向、上下延伸不规则的残小矿体开采的问题,提供一种回采成本低,贫损率低的一种浮动孔深分段回采法。
本发明的具体方案是:一种浮动孔深分段回采法,其特征是:包括以下步
骤:⑴开挖竖井或斜井以及水平巷道;⑵沿水平巷道,根据坑深揭露情况,每1.5m布置一个探矿孔进行深孔探矿;⑶根据深孔探矿取得的每个探矿孔处的矿体高度,绘制矿体上向延伸状态图;⑷根据状态图进行采矿分段,以每两个波谷为一回采段;⑸在每一回采段的波峰处开挖一个切割井;⑹从最前一段开始向后依次逐段实施回采在每一段回采中,是以切割井为起点向前后两侧分段进行回采至波谷,所述回采是以切割井边沿为起点按标准规范进行若干中深孔设计,每一排中深孔的顶点高度等于该处矿体上向延伸状态图中的标注高度,然后逐排爆破回采;⑺在安全确认到位的情况下,组织铲运机或遥控铲运机出矿,一个分段回采完毕后,应及时封堵,避免出矿损失。
本发明中在上述步骤⑸中以切割井边沿为起点,其中第一排中深孔距离起点为0.5m,以后每隔1.5m设计一排中深孔。
本发明中采用了中深孔逐排变化设计(根据矿体上向深(厚)度进行浮动),大大减少了采切工程量,降低了回采成本,同时使本矿区的最终单个矿体贫化率,损失率得到明显的改善,回采贫损率可控制在10%以内,大大提高了矿产品位和质量,有效提高了生产收益。
附图说明
图1是某矿体布置状态图;
图2是传统回采其中一排中深孔的布置图;
图3是采用本发明方法设计切割井,纵向布置中深孔的位置示意图;
图4是采用本发明方法第1排中深孔的布置放大示意图;
图5是采用本发明方法第3排中深孔的布置放大示意图;
图6是采用本发明方法第5排中深孔的布置放大示意图;
图7是采用本发明方法第8排中深孔的布置放大示意图;
图8是采用本发明方法第10排中深孔的布置放大示意图;
图9是采用本发明方法第12排中深孔的布置放大图;
图10是采用本发明方法第15排中深孔的布置放大图;
图11是采用本发明方法第16排中深孔的布置放大图;
图12是采用本发明方法第18排中深孔横断面的布置图。
图中:1—水平巷道,2—竖井,3—矿体,4—中深孔,5-矿体边线,6-切割井,7-探矿孔,8-铲运机。
具体实施方式
参见图3,对该矿体3采用本发明进行回采的方法包括以下步骤:⑴开挖竖井2或斜井以及水平巷道1;⑵沿水平巷道1,根据坑深揭露情况,每1.5m布置一个探矿孔7进行深孔探矿(共21个);⑶根据深孔探矿取得的每个探矿孔7处的矿体厚度,绘制矿体上向延伸状态图;⑷根据状态图进行采矿分段,以每两个波谷为一回采段;⑸在每一回采段的波峰处开挖一个切割井6;⑹从最前一段开始向后依次逐段实施回采在每一段回采中,是以切割井6为起点向前后两侧分段进行回采至波谷,所述回采是以切割井6边沿为起点按标准规范进行中深孔4设计(参见图3-12),共设计有21排中深孔,其中第一排中深孔4距离起点为0.5m,以后每隔1.5m设计一排中深孔4,每一排中深孔4的顶点高度等于该处矿体3上向延伸状态图中的标注高度,然后逐排爆破回采;⑺在安全确认到位的情况下,组织铲运机8或遥控铲运机出矿,一个分段回采完毕后,应及时封堵,避免出矿损失。

Claims (2)

1.一种浮动孔深分段回采法,其特征是:包括以下步骤:
⑴开挖竖井或斜井以及水平巷道;
⑵沿水平巷道,根据坑深揭露情况,每1.5m布置一个探矿孔进行深孔探矿;
⑶根据深孔探矿取得的每个探矿孔处的矿体厚度,绘制矿体上向延伸状态图;
⑷根据状态图进行采矿分段,以每两个波谷为一回采段;
⑸在每一回采段的波峰处开挖一个切割井;
⑹从最前一段开始向后依次逐段实施回采,在每一段回采中,是以切割井为起点向前后两侧分段进行回采至波谷,所述回采是以切割井边沿为起点按标准规范进行若干中深孔设计,每一排中深孔的顶点高度等于该处矿体上向延伸状态图中的标注高度,然后逐排爆破回采;
⑺在安全确认到位的情况下,组织铲运机或遥控铲运机出矿,一个分段回采完毕后,应及时封堵,避免出矿损失。
2.根据权利要求1所述的一种浮动孔深分段回采法,其特征是:在上述步骤⑸中以切割井边沿为起点,其中第一排中深孔距离起点为0.5m,以后每隔1.5m设计一排中深孔。
CN201410316275.6A 2014-07-04 2014-07-04 一种浮动孔深分段回采法 Active CN104074519B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410316275.6A CN104074519B (zh) 2014-07-04 2014-07-04 一种浮动孔深分段回采法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410316275.6A CN104074519B (zh) 2014-07-04 2014-07-04 一种浮动孔深分段回采法

Publications (2)

Publication Number Publication Date
CN104074519A CN104074519A (zh) 2014-10-01
CN104074519B true CN104074519B (zh) 2016-03-16

Family

ID=51596085

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410316275.6A Active CN104074519B (zh) 2014-07-04 2014-07-04 一种浮动孔深分段回采法

Country Status (1)

Country Link
CN (1) CN104074519B (zh)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3707307A (en) * 1970-12-11 1972-12-26 Harry Kristoffersson Methods in mining by sublevel caving
CN1424488A (zh) * 2003-01-08 2003-06-18 广东高要河台金矿 一种采用两种材料胶结的人工间柱构筑方法
RU2208162C1 (ru) * 2001-12-07 2003-07-10 Институт горного дела СО РАН Способ разработки рудных месторождений подэтажным обрушением
CN101424186A (zh) * 2007-11-01 2009-05-06 宝钢集团上海梅山有限公司 倾斜矿体上盘矿石回收方法
CN101725350A (zh) * 2008-10-21 2010-06-09 招金矿业股份有限公司大尹格庄金矿 下盘沿脉凿岩穿脉进路出矿式崩落采矿法
CN102182461A (zh) * 2011-04-02 2011-09-14 山东黄金矿业(玲珑)有限公司 倾斜中厚金属矿体高效采矿方法

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3707307A (en) * 1970-12-11 1972-12-26 Harry Kristoffersson Methods in mining by sublevel caving
RU2208162C1 (ru) * 2001-12-07 2003-07-10 Институт горного дела СО РАН Способ разработки рудных месторождений подэтажным обрушением
CN1424488A (zh) * 2003-01-08 2003-06-18 广东高要河台金矿 一种采用两种材料胶结的人工间柱构筑方法
CN101424186A (zh) * 2007-11-01 2009-05-06 宝钢集团上海梅山有限公司 倾斜矿体上盘矿石回收方法
CN101725350A (zh) * 2008-10-21 2010-06-09 招金矿业股份有限公司大尹格庄金矿 下盘沿脉凿岩穿脉进路出矿式崩落采矿法
CN102182461A (zh) * 2011-04-02 2011-09-14 山东黄金矿业(玲珑)有限公司 倾斜中厚金属矿体高效采矿方法

Also Published As

Publication number Publication date
CN104074519A (zh) 2014-10-01

Similar Documents

Publication Publication Date Title
CN104806244B (zh) 一种倾斜中厚矿体充填采矿方法
CN102635356B (zh) 急倾斜薄矿脉多爆破自由面中深孔采矿法
CN106121648B (zh) 一种分段空场采矿底盘进路放矿嗣后充填采矿法
CN101967973B (zh) 空场—崩落组合采矿方法
CN105569659B (zh) 一种巷道水力割缝定向爆破切顶卸压方法
CN105626071B (zh) 一种缓倾斜薄矿体采矿方法
CN104314570B (zh) 长厚矿体挂帮矿回收及露天转地下过渡期的开采方法
CN107829742B (zh) 一种崩落-充填-空场-崩落采矿方法
CN102182461A (zh) 倾斜中厚金属矿体高效采矿方法
CN102720500A (zh) 一种急倾斜薄矿体机械化地下开采方法
CN108547618A (zh) 一种两步骤采矿方法遗留间柱的回收工艺
CN104712358A (zh) 基于首采全岩卸压工作面沿空留巷的高瓦斯煤层群卸压共采方法
CN110905512B (zh) 一种缓倾斜中厚矿体空场采矿法
CN105735996A (zh) 一种薄矿脉预裂削壁充填采矿法
CN106640080B (zh) 一种深部高应力环境下自稳窿形采场布置采矿方法
CN102589372A (zh) 采空区的硐室与深孔爆破法
CN109958438A (zh) 一种高分段爆力运矿空场采矿方法
CN111502664B (zh) 一种窄矿体高阶段分段崩矿嗣后充填采矿法
CN108104816B (zh) 一种急倾斜薄矿体的上向开采方法
CN109356581A (zh) 一种高分段双六边形崩落采矿法
CN104153782B (zh) 连续崩落采矿方法
CN101737051A (zh) 一种盲矿体覆盖层形成方法
RU2524716C1 (ru) Способ открытой разработки месторождений полезных ископаемых, включающий отработку рудных тел в зонах контакта руды и вскрыши подуступами
CN107725054A (zh) 一种倾角多变薄矿脉的开采方法
CN105298493A (zh) 地下缓倾斜薄层状玉石矿无损爆破采矿方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant