CN107725054A - 一种倾角多变薄矿脉的开采方法 - Google Patents
一种倾角多变薄矿脉的开采方法 Download PDFInfo
- Publication number
- CN107725054A CN107725054A CN201710714406.XA CN201710714406A CN107725054A CN 107725054 A CN107725054 A CN 107725054A CN 201710714406 A CN201710714406 A CN 201710714406A CN 107725054 A CN107725054 A CN 107725054A
- Authority
- CN
- China
- Prior art keywords
- section
- flat
- ore deposit
- nugget
- grade mine
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 23
- 210000003462 vein Anatomy 0.000 title claims abstract description 16
- 238000005065 mining Methods 0.000 title abstract description 7
- 238000007598 dipping method Methods 0.000 claims description 36
- 238000004519 manufacturing process Methods 0.000 claims description 26
- 238000009412 basement excavation Methods 0.000 claims description 10
- 238000011084 recovery Methods 0.000 claims description 9
- 229910052500 inorganic mineral Inorganic materials 0.000 claims description 6
- 239000011707 mineral Substances 0.000 claims description 6
- 238000005553 drilling Methods 0.000 claims description 3
- 230000001788 irregular Effects 0.000 claims description 3
- 230000007704 transition Effects 0.000 claims description 3
- 239000002699 waste material Substances 0.000 abstract description 2
- 230000032258 transport Effects 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 1
- 230000035772 mutation Effects 0.000 description 1
- 239000013589 supplement Substances 0.000 description 1
- 230000005641 tunneling Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21C—MINING OR QUARRYING
- E21C41/00—Methods of underground or surface mining; Layouts therefor
- E21C41/16—Methods of underground mining; Layouts therefor
- E21C41/22—Methods of underground mining; Layouts therefor for ores, e.g. mining placers
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Mining & Mineral Resources (AREA)
- Environmental & Geological Engineering (AREA)
- Remote Sensing (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
本发明属于地下采矿方法技术领域,公开了一种倾角多变薄矿脉的开采方法,以解决在薄矿块回采中造成地下有限资源的浪费的问题,该倾角多变薄矿脉的开采方法,该方法包括矿块结构参数划分、采准切割、缓倾斜矿段回采出矿、急倾斜矿段回采出矿等步骤,为同一矿块中缓倾斜矿段和急倾斜矿段选择不同的采准工程、回采方法和出矿工艺,并将同一矿块中不同倾角矿段不同的采准工程、回采方法和出矿工艺有机的结合起来,实现了倾角多变薄矿脉的灵活开采。
Description
技术领域
本发明涉及地下采矿方法技术领域,具体涉及一种倾角多变薄矿脉的开采方法。
背景技术
在薄矿脉开采中,现行矿山都是推广应用全面法、房柱法、留矿法等。但是薄矿脉复杂多变,在矿块回采中,有时矿体倾角会发生突变,原设计的采矿方法不再适用,一般都是被迫停产,或者另行补充采准,现有技术在回采下部缓倾斜矿段30°以下,上部急倾斜矿段矿段倾角60°以上的薄矿脉时,往往是用全面法回采下部倾角0-30°矿段或留矿法回采上部倾角60°矿段后,其余部分丢弃不采,造成了极大地资源浪费。现有技术无法解决上述问题。
发明内容
本发明的目的是为了解决在倾角多变薄矿块回采中造成地下有限资源的浪费的问题,提供了一种倾角多变薄矿脉的开采方法。
为了达到上述目的,本发明采用以下技术方案:一种倾角多变薄矿脉的开采方法,包括以下步骤:
1)矿块结构参数划分:阶段高度40-60m,在阶段内,沿走向划分块段,矿块长度50-70m;矿块间柱为5-8m,矿块底柱为5-6m,矿块顶柱为5-6m,在矿块内缓倾斜矿段和急倾斜矿段的过渡地带留设隔离矿柱,隔离矿柱为8-10m,在矿块内缓倾斜矿段内留设不规则矿柱。
2)采准切割:首先掘进阶段运输巷道和阶段通风平巷,在阶段运输巷道每隔8-12m掘进垂直矿体走向的缓倾斜矿段联络上山直到隔离矿柱;在缓倾斜矿段联络上山尽头间柱内掘进天井至阶段通风平巷,通过天井每隔4-6m掘进急倾斜矿段联络道;并在隔离矿柱内掘进急倾斜矿段放矿漏斗;分别在缓倾斜矿段底部和急倾斜矿段底部掘进拉底巷道,形成缓倾斜矿段回采空间和急倾斜矿段回采空间。
3)缓倾斜矿段回采出矿:在缓倾斜矿段联络上山上钻凿炮孔,垂直于拉底巷道向另一侧推进,全厚一次回采,采用铲运机出矿,崩落矿石由缓倾斜矿段联络上山经阶段运输巷道运出。
4)急倾斜矿段回采出矿:回采急倾斜矿段时,从设置在急倾斜矿段内的浅孔落矿,回采自下而上分层进行,每次崩下矿石通过布置在隔离矿柱内的急倾斜矿段放矿漏斗放出三分之一,其余暂存矿房中作为继续上采工作平台,待矿房采完后进行最终放矿,急倾斜矿段矿石先经隔离矿柱内的急倾斜矿段放矿漏斗放到缓倾斜矿段内,再由铲运机或点耙经阶段运输巷道运出。
作为本发明进一步改进,首先回采缓倾斜矿段,缓倾斜矿段回采结束后,再回采急倾斜矿段。
作为本发明进一步改进,缓倾斜矿段的位于矿块下部,倾角小于30°;急倾斜矿段位于矿块上部,倾角大于60°。
本发明现对于现有技术,具有以下有益效果:本发明的一种倾角多变薄矿脉的开采方法针对矿脉倾角的变化情况,为同一矿块中缓倾斜矿段和急倾斜矿段选择不同的采准工程、回采方法和出矿工艺,并将同一矿块中不同倾角矿段不同的采准工程、回采方法和出矿工艺有机的结合起来,实现倾角多变薄矿脉的灵活开采。
附图说明
图1为本发明的主视图。
图2为本发明的侧视图。
附图标记含义如下:1.顶柱;2.间柱;3.底柱;4.隔离矿柱;5.不规则矿柱;6.阶段运输巷道;7.阶段通风平巷;8.缓倾斜矿段联络上山;9.天井;10.急倾斜矿段联络道;11.急倾斜矿段放矿漏斗;12.缓倾斜矿段回采空间;13.急倾斜矿段回采空间;14.浅孔;15.崩落矿石。
具体实施方式
下面结合附图和具体实施方式对本发明做进一步说明。
如图1-2所示,一种倾角多变薄矿脉的开采方法,包括以下步骤:
1)矿块结构参数划分:阶段高度40-60m,在阶段内,沿走向划分块段,矿块长度50-70m;矿块间柱2一般为5-8m,矿块底柱3为5-6m,矿块顶柱1为5-6m,在矿块内缓倾斜矿段和急倾斜矿段的过渡地带留设隔离矿柱4,隔离矿柱4为8-10m;在矿块内缓倾斜矿段内留设不规则矿柱5。
2)采准切割:首先掘进阶段运输巷道6和阶段通风平巷7,在阶段运输巷道6每隔8-12m掘进垂直矿体走向的缓倾斜矿段联络上山8直到隔离矿柱4;在缓倾斜矿段联络上山8尽头间柱2内掘进天井9至阶段通风平巷7,通过天井9每隔4-6m掘进急倾斜矿段联络道10;并在隔离矿柱4内掘进急倾斜矿段放矿漏斗11;并在缓倾斜矿段底部和急倾斜矿段底部掘进拉底巷道,形成缓倾斜矿段回采空间12和急倾斜矿段回采空间13。
3)缓倾斜矿段回采出矿:首先回采倾角为0-30°的缓倾斜矿段。在缓倾斜矿段联络上山8钻凿炮孔,垂直于拉底巷道向另一侧推进,全厚一次回采,采用铲运机出矿,崩落矿石由缓倾斜矿段联络上山8经阶段运输巷道6运出。
4)急倾斜矿段回采出矿:缓倾斜矿段回采结束后,再回采倾角60°以上的急倾斜矿段。回采急倾斜矿段时,从设置在急倾斜矿段内的浅孔14落矿,回采自下而上分层进行,每次崩下矿石15通过布置在隔离矿柱4内的急倾斜矿段放矿漏斗11放出三分之一,其余暂存矿房中作为继续上采工作平台,待矿房采完后进行最终放矿。急倾斜矿段矿石先经隔离矿柱4内的急倾斜矿段放矿漏斗11放到缓倾斜矿段内,再由铲运机或点耙经阶段运输巷道6运出。
Claims (4)
1.一种倾角多变薄矿脉的开采方法,其特征是:包括以下步骤:
1)矿块结构参数划分:阶段高度40-60m,在阶段内,沿走向划分块段,矿块长度50-70m,矿块间柱(2)为5-8m,矿块底柱(3)为5-6m,矿块顶柱(1)为5-6m,在矿块内缓倾斜矿段和急倾斜矿段的过渡地带留设隔离矿柱(4),隔离矿柱(4)为8-10m,在矿块内缓倾斜矿段内留设不规则矿柱(5);
2)采准切割:首先掘进阶段运输巷道(6)和阶段通风平巷(7),在阶段运输巷道(6)每隔8-12m掘进垂直矿体走向的缓倾斜矿段联络上山(8)直到隔离矿柱(4);在缓倾斜矿段联络上山(8)尽头间柱(2)内掘进天井(9)至阶段通风平巷(7),通过天井(9)每隔4-6m掘进急倾斜矿段联络道(10);并在隔离矿柱(4)内掘进急倾斜矿段放矿漏斗(11);分别在缓倾斜矿段底部和急倾斜矿段底部掘进拉底巷道形成缓倾斜矿段回采空间(12)和急倾斜矿段回采空间(13);
3)缓倾斜矿段回采出矿:在缓倾斜矿段联络上山(8)上钻凿炮孔,垂直于拉底巷道向另一侧推进,全厚一次回采,采用铲运机出矿,崩落矿石由缓倾斜矿段联络上山(8)经阶段运输巷道(6)运出;
4)急倾斜矿段回采出矿:回采极倾斜矿段时,采用浅孔(14)落矿方式,回采自下而上分层进行,每次崩下矿石(15)通过布置在隔离矿柱(4)内的急倾斜矿段放矿漏斗(11)放出三分之一,其余暂存矿房中作为继续上采工作平台,待矿房采完后进行最终放矿;极倾斜矿段矿石先经隔离矿柱(4)内的急倾斜矿段放矿漏斗(11)放到缓倾斜矿段内,再由铲运机或点耙经阶段运输巷道(6)运出。
2.根据权利要求1所述的一种倾角多变薄矿脉的开采方法,其特征是:首先回采缓倾斜矿段,缓倾斜矿段回采结束后,再回采急倾斜矿段。
3.根据权利要求1所述的一种倾角多变薄矿脉的开采方法,其特征是:所述缓倾斜矿段位于矿块下部,倾角小于30°。
4.根据权利要求1所述的一种倾角多变薄矿脉的开采方法,其特征是:所述急倾斜矿段位于矿块上部,倾角大于60°。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710714406.XA CN107725054A (zh) | 2017-08-18 | 2017-08-18 | 一种倾角多变薄矿脉的开采方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710714406.XA CN107725054A (zh) | 2017-08-18 | 2017-08-18 | 一种倾角多变薄矿脉的开采方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107725054A true CN107725054A (zh) | 2018-02-23 |
Family
ID=61205260
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710714406.XA Pending CN107725054A (zh) | 2017-08-18 | 2017-08-18 | 一种倾角多变薄矿脉的开采方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107725054A (zh) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109356580A (zh) * | 2018-11-16 | 2019-02-19 | 西北矿冶研究院 | 一种倾角局部变缓的急倾斜薄矿体开采方法 |
CN109630117A (zh) * | 2018-11-16 | 2019-04-16 | 西北矿冶研究院 | 一种适合倾角多变矿体的全面留矿联合法 |
CN110295907A (zh) * | 2019-06-19 | 2019-10-01 | 中国华冶科工集团有限公司 | 破碎薄矿体水平深孔阶段分层崩落采矿方法及采场 |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3789511A (en) * | 1972-02-04 | 1974-02-05 | Columbia Gas Syst Service Corp | Apparatus for sensing a curvature in a conduit |
CN101737047A (zh) * | 2008-11-19 | 2010-06-16 | 孙广义 | 一种急倾斜薄煤层的采煤方法 |
CN103362510A (zh) * | 2013-08-01 | 2013-10-23 | 广西大学 | 分段凿岩并段出矿分段矿房采矿法 |
CN104847356A (zh) * | 2015-05-15 | 2015-08-19 | 西北矿冶研究院 | 一种薄小矿体的开采方法 |
CN104929642A (zh) * | 2015-06-03 | 2015-09-23 | 西安科技大学 | 大倾角煤层变角度综放工作面顶煤放煤量分区域控制方法 |
CN105756679A (zh) * | 2016-04-01 | 2016-07-13 | 江西稀有稀土金属钨业集团有限公司 | 一种极薄复杂石英矿脉由缓变急浅孔综合采矿方法 |
CN106437838A (zh) * | 2016-12-05 | 2017-02-22 | 广西大学 | 底部结构下卡车直接出矿后期放矿充填同步水平深孔留矿法 |
-
2017
- 2017-08-18 CN CN201710714406.XA patent/CN107725054A/zh active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3789511A (en) * | 1972-02-04 | 1974-02-05 | Columbia Gas Syst Service Corp | Apparatus for sensing a curvature in a conduit |
CN101737047A (zh) * | 2008-11-19 | 2010-06-16 | 孙广义 | 一种急倾斜薄煤层的采煤方法 |
CN103362510A (zh) * | 2013-08-01 | 2013-10-23 | 广西大学 | 分段凿岩并段出矿分段矿房采矿法 |
CN103362510B (zh) * | 2013-08-01 | 2015-04-22 | 广西大学 | 分段凿岩并段出矿分段矿房采矿法 |
CN104847356A (zh) * | 2015-05-15 | 2015-08-19 | 西北矿冶研究院 | 一种薄小矿体的开采方法 |
CN104929642A (zh) * | 2015-06-03 | 2015-09-23 | 西安科技大学 | 大倾角煤层变角度综放工作面顶煤放煤量分区域控制方法 |
CN105756679A (zh) * | 2016-04-01 | 2016-07-13 | 江西稀有稀土金属钨业集团有限公司 | 一种极薄复杂石英矿脉由缓变急浅孔综合采矿方法 |
CN106437838A (zh) * | 2016-12-05 | 2017-02-22 | 广西大学 | 底部结构下卡车直接出矿后期放矿充填同步水平深孔留矿法 |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109356580A (zh) * | 2018-11-16 | 2019-02-19 | 西北矿冶研究院 | 一种倾角局部变缓的急倾斜薄矿体开采方法 |
CN109630117A (zh) * | 2018-11-16 | 2019-04-16 | 西北矿冶研究院 | 一种适合倾角多变矿体的全面留矿联合法 |
CN109356580B (zh) * | 2018-11-16 | 2020-08-25 | 西北矿冶研究院 | 一种倾角局部变缓的急倾斜薄矿体开采方法 |
CN110295907A (zh) * | 2019-06-19 | 2019-10-01 | 中国华冶科工集团有限公司 | 破碎薄矿体水平深孔阶段分层崩落采矿方法及采场 |
CN110295907B (zh) * | 2019-06-19 | 2021-03-23 | 中国华冶科工集团有限公司 | 破碎薄矿体水平深孔阶段分层崩落采矿方法及采场 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108612530B (zh) | 一种上盘围岩破碎倾斜中厚矿体的采矿方法 | |
CN108442930B (zh) | 一种倾斜中厚金属矿体采矿方法 | |
CN104806244B (zh) | 一种倾斜中厚矿体充填采矿方法 | |
CN101338674B (zh) | 直接装运矿石的无底柱分段崩落采矿法 | |
CN110952982B (zh) | 一种急倾斜薄脉至极薄脉矿体的中深孔预裂爆破采矿法 | |
CN102953732A (zh) | 房柱式大直径深孔倒台阶状分段侧向崩矿嗣后充填采矿法 | |
CN103590831A (zh) | 一种缓倾斜薄-中厚矿体的新型采矿方法 | |
CN108547618A (zh) | 一种两步骤采矿方法遗留间柱的回收工艺 | |
CN104481543B (zh) | 阶段留矿崩落采矿法 | |
CN104632220B (zh) | 缓倾斜中厚矿体条柱再造采场结构尺寸可调可控采矿方法 | |
CN107829742A (zh) | 一种崩落‑充填‑空场‑崩落采矿方法 | |
CN101285384B (zh) | 大直径深孔不拉底采矿法 | |
CN105927226A (zh) | 一种中深孔落矿连续分段水平充填采矿法 | |
CN108798672B (zh) | 一种大垮塌区矿石高效开采的采矿方法 | |
CN111058847B (zh) | 一种厚大矿体连续大孔径深孔爆破机械化开采方法 | |
CN106640080B (zh) | 一种深部高应力环境下自稳窿形采场布置采矿方法 | |
CN111894584A (zh) | 一种缓倾斜薄矿体全伪布置预留巷道胶结充填采矿法 | |
CN108625855B (zh) | 一种充填体下的采矿方法 | |
CN107725054A (zh) | 一种倾角多变薄矿脉的开采方法 | |
CN109869150A (zh) | 一种矿山资源分段全采局充开采方法 | |
CN107829739A (zh) | 一种急倾斜薄矿脉的开采方法 | |
CN108104816B (zh) | 一种急倾斜薄矿体的上向开采方法 | |
CN109899070B (zh) | 基于椭球体放矿结构的缓倾斜中厚矿体无固废充填采矿法 | |
CN106593447A (zh) | 一种地下采矿缓倾斜中厚矿体采矿方法 | |
CN101737051A (zh) | 一种盲矿体覆盖层形成方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180223 |
|
RJ01 | Rejection of invention patent application after publication |