CN104074390A - 750kV transformer substation steel pipe concrete framework - Google Patents
750kV transformer substation steel pipe concrete framework Download PDFInfo
- Publication number
- CN104074390A CN104074390A CN201410322251.1A CN201410322251A CN104074390A CN 104074390 A CN104074390 A CN 104074390A CN 201410322251 A CN201410322251 A CN 201410322251A CN 104074390 A CN104074390 A CN 104074390A
- Authority
- CN
- China
- Prior art keywords
- bus
- framework
- column
- posts
- inlet
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Rod-Shaped Construction Members (AREA)
Abstract
The invention belongs to the technical field of ultra-high-voltage transmission and transformation, and particularly relates to a 750kV transformer substation steel pipe concrete framework, which comprises a plurality of inlet-outlet wire framework posts, a ground wire post and a plurality of bus framework posts, wherein the inlet-outlet wire framework posts are in linear arrangement; the tops of the two adjacent inlet-outlet wire framework posts are provided with inlet and outlet wire beams; the number of the bus framework posts is identical to the number of the inlet-outlet wire framework posts; the bus framework posts are in linear arrangement and are parallelly arranged beside the inlet-outlet wire framework posts; bus beams are arranged on the inlet-outlet wire framework posts and the bus framework posts in parallel arrangement; and the tops of the inlet-outlet wire framework posts are connected with the ground wire post through flanges. The inlet-outlet wire framework posts adopt equal-cross-section steel pipe concrete herringbone posts; inlet-outlet wire beams adopt trussed beams; the bus framework posts adopt equal-cross-section steel pipe concrete herringbone posts; and the bus beams adopt trussed beams. The 750kV transformer substation steel pipe concrete framework has the advantages that steel materials can be effectively saved; the occupied area is reduced; the engineering cost is reduced; and obvious economic benefits and social benefits are realized.
Description
Technical field
The invention belongs to ehv power transmission technical field, relate to the frame structures of a kind of 750kV transformer station, be specifically related to a kind of 750kV transformer station concrete filled steel tube framework.
Background technology
Along with the fast development of China's economy, increasing to electricity needs, therefore, country greatly develops extra-high pressure grade project of transmitting and converting electricity.China's T & D Technology development is very fast, and long distance high-voltage grade technology of transmission of electricity is ripe, and the construction of 750kV high voltage substation produces material impact to China's economy.At present, the 750kV transformer station having built up adopts traditional steel pipe inverted Y-shaped column framework or steel pipe lattice type framework mostly, and steel using amount and floor space are all larger, so need to improve 750kV transformer substation framework structure.
Summary of the invention
In order to solve the technical problem that 750kV substation framework steel using amount is large, floor space is large, object of the present invention will provide a kind of saving steel, saving soil, reduce the 750kV transformer station concrete filled steel tube framework of construction costs.
To achieve these goals, the technical solution used in the present invention is: a kind of 750kV transformer station concrete filled steel tube framework, comprise several line truss columns, and ground terminal, is characterized in that: also comprise several bus truss columns; Several line truss columns are arranged in a linear, and the top of adjacent two line truss columns is provided with line beam; Bus truss column is identical with line truss column quantity, several bus truss columns are arranged in a linear and are set up in parallel on several line truss column sides, on the bus truss column being set up in parallel and line truss column, bus girders is installed, the top of line truss column connects ground terminal by flange; Line truss column is uniform section concrete filled steel tube herringbone column; Bus truss column is uniform section concrete filled steel tube herringbone column.
Because line truss column of the present invention and bus truss column are all the truss columns that adopt concrete filled steel tube to make, at pouring concrete within steel pipe, compare with current employing steel pipe inverted Y-shaped column framework or steel pipe lattice type framework, effective saving steel, save floor space, reduce construction costs, there is significant economic benefit and social benefit.
Accompanying drawing explanation
Fig. 1 is perspective view of the present invention;
Fig. 2 is elevation of the present invention;
Fig. 3 is lateral view of the present invention.
In figure: 1-ground terminal, 2-line beam, 3-stull, 4-bus girders, 5-line truss column,, the support of 6-end, 7-bus truss column, 8-steel core concrete column, 9-hound.
The specific embodiment
Below in conjunction with the drawings and specific embodiments, the present invention is described in detail.As shown in Figure 1, Figure 2 with shown in Fig. 3: a kind of 750kV transformer station concrete filled steel tube framework, it comprises several line truss columns 5, ground terminal 1; Also comprise several bus truss columns 7; The line truss column 5 of the present embodiment and bus truss column 7 are seven; Seven line truss columns 5 are arranged in a linear, and the top of adjacent two line truss columns 5 is provided with line beam 2; Bus truss column 7 is identical with line truss column 5 quantity, seven bus truss columns 7 are arranged in a linear and are set up in parallel on seven line truss column 5 sides, on the bus truss column 7 being set up in parallel and line truss column 5, bus girders 4 is installed, the top of line truss column 5 connects ground terminal 1 by flange.
Line truss column 5 comprises two steel core concrete columns 8, and steel core concrete column 8 is at pouring concrete within steel pipe; Two steel core concrete columns 8 form concrete filled steel tube herringbone column, and the plane forming concrete filled steel tube herringbone column is outside equipped with hound 9 to improve the stability of line truss column 5; The cross section that is provided with 3, two steel core concrete columns 8 of stull between two steel core concrete columns 8 equates, guarantees the weight capacity of line truss column 5; The line truss column 5 of the present embodiment head and end, first and the 7th line truss column 5 is provided with end support 6, and end support 6 bottoms are concordant with line truss column 5 bottoms, end support 6 tops are fixedly connected with line beam 2.
Bus truss column 7 adopts the structure identical with line truss column 5, but the specification of bus truss column 7 is slightly less than line truss column 5; Line beam 2 adopts braced beam; Bus girders 4 adopts braced beam; The chord member of line beam 2 and bus girders 4 all adopts common steel tube; Post, beam chord member joints adopt rigid flange, with bolts between soffit of girder bar and chord member; Ground terminal 1 is uniform section steel pipe ground terminal 1.
Constructure scheme of the present invention is after the integral hoisting of steel framework is in place, to carry out the pouring construction of post core concrete.
While adopting this constructure scheme, the segmentation transportation of truss of steel tube, on-site hoisting, stull connection etc. are all identical with original 750kV transformer station pure truss of steel tube, after difference is to adopt steel core concrete column, the specification of steel pipe diminishes, and hauled weight and lifting weight are all less than pure truss of steel tube.
After the whole hoisted in position of steel framework, adopt pumping-up method concreting.Pumping-up method can be disposable by the concrete lift-up in steel core concrete column to desired height, without vibration, can effectively avoid the defects such as steel pipe column inner concrete leakiness, segregation, guarantees concrete quality.Also can reduce process links, easy construction is quick.
While adopting pumping-up method concreting, need to steam vent and spout hole be set in capital appropriate location, in suspension column appropriate location, charging hole be set.
Claims (6)
1.Yi Zhong 750kV transformer station concrete filled steel tube framework, several line truss columns is characterized in that with ground terminal: also comprise several bus truss columns (7); Several line truss columns (5) are arranged in a linear, and the top of adjacent two line truss columns (5) is provided with line beam (2); Bus truss column (7) is identical with line truss column (5) quantity, several bus truss columns (7) are arranged in a linear and are set up in parallel on several line truss columns (5) side, on the bus truss column (7) being set up in parallel and line truss column (5), bus girders 4 is installed, the top of line truss column (5) connects ground terminal (1) by flange.
2. a kind of 750kV as claimed in claim 1 transformer station concrete filled steel tube framework, is characterized in that: line truss column (5) comprises two steel core concrete columns (8), and two steel core concrete columns (8) form concrete filled steel tube herringbone column; Steel core concrete column (8) is in steel pipe, to be perfused with concrete.
3. a kind of 750kV as claimed in claim 2 transformer station concrete filled steel tube framework, is characterized in that: the plane forming concrete filled steel tube herringbone column is outside equipped with hound (9), is provided with stull (3) between two steel core concrete columns (8).
4. a kind of 750kV as claimed in claim 3 transformer station concrete filled steel tube framework, is characterized in that: the cross section of two steel core concrete columns (8) equates; The line truss column (5) of head and end is provided with end support (6), and end support (6) bottom is concordant with line truss column (5) bottom, end support (6) top is fixedly connected with line beam (2).
5. a kind of 750kV transformer station concrete filled steel tube framework as described in claim 1 to 4 any one, is characterized in that: bus truss column (7) is identical with the structure of line truss column (5).
6. a kind of 750kV as claimed in claim 5 transformer station concrete filled steel tube framework, is characterized in that: line beam (2) adopts braced beam; Bus girders (4) adopts braced beam.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410322251.1A CN104074390A (en) | 2014-07-08 | 2014-07-08 | 750kV transformer substation steel pipe concrete framework |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410322251.1A CN104074390A (en) | 2014-07-08 | 2014-07-08 | 750kV transformer substation steel pipe concrete framework |
Publications (1)
Publication Number | Publication Date |
---|---|
CN104074390A true CN104074390A (en) | 2014-10-01 |
Family
ID=51595960
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410322251.1A Pending CN104074390A (en) | 2014-07-08 | 2014-07-08 | 750kV transformer substation steel pipe concrete framework |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104074390A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104563578A (en) * | 2014-12-31 | 2015-04-29 | 中国电力工程顾问集团西南电力设计院有限公司 | Combined framework pillar for 500kV transformer substation and mounting method of combined framework pillar |
CN105332538A (en) * | 2015-11-25 | 2016-02-17 | 中国能源建设集团浙江省电力设计院有限公司 | Light steel connection pipe trussed frame for transformer substation |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3556310A (en) * | 1968-05-27 | 1971-01-19 | Jack Loukotsky | Prefabricated modular power substation |
CN101906896A (en) * | 2010-07-23 | 2010-12-08 | 中国电力工程顾问集团华北电力设计院工程有限公司 | 750KV power-transformation framework structure |
CN202090664U (en) * | 2010-12-30 | 2011-12-28 | 国家电网公司 | Alternating-current ultrahigh voltage steel pipe inverted Y-shaped column framework |
CN202788126U (en) * | 2012-03-31 | 2013-03-13 | 上海市电力公司 | Anchor bolt type column foot herringbone framework |
CN203308159U (en) * | 2013-05-31 | 2013-11-27 | 中国电力工程顾问集团东北电力设计院 | Anticorrosion framework column of transformer substation |
CN203583974U (en) * | 2013-09-30 | 2014-05-07 | 中国电力工程顾问集团西南电力设计院 | 750KV outdoor A-shaped column, lattice type column and power distribution device |
CN204060109U (en) * | 2014-07-08 | 2014-12-31 | 甘肃省电力设计院 | 750kV transformer station concrete filled steel tube framework |
-
2014
- 2014-07-08 CN CN201410322251.1A patent/CN104074390A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3556310A (en) * | 1968-05-27 | 1971-01-19 | Jack Loukotsky | Prefabricated modular power substation |
CN101906896A (en) * | 2010-07-23 | 2010-12-08 | 中国电力工程顾问集团华北电力设计院工程有限公司 | 750KV power-transformation framework structure |
CN202090664U (en) * | 2010-12-30 | 2011-12-28 | 国家电网公司 | Alternating-current ultrahigh voltage steel pipe inverted Y-shaped column framework |
CN202788126U (en) * | 2012-03-31 | 2013-03-13 | 上海市电力公司 | Anchor bolt type column foot herringbone framework |
CN203308159U (en) * | 2013-05-31 | 2013-11-27 | 中国电力工程顾问集团东北电力设计院 | Anticorrosion framework column of transformer substation |
CN203583974U (en) * | 2013-09-30 | 2014-05-07 | 中国电力工程顾问集团西南电力设计院 | 750KV outdoor A-shaped column, lattice type column and power distribution device |
CN204060109U (en) * | 2014-07-08 | 2014-12-31 | 甘肃省电力设计院 | 750kV transformer station concrete filled steel tube framework |
Non-Patent Citations (1)
Title |
---|
高赞: "750kV变电构架结构型式优化研究", 《中国优秀硕士学位论文全文数据库 工程科技Ⅱ辑》 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104563578A (en) * | 2014-12-31 | 2015-04-29 | 中国电力工程顾问集团西南电力设计院有限公司 | Combined framework pillar for 500kV transformer substation and mounting method of combined framework pillar |
CN105332538A (en) * | 2015-11-25 | 2016-02-17 | 中国能源建设集团浙江省电力设计院有限公司 | Light steel connection pipe trussed frame for transformer substation |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104695979B (en) | A kind of method using tall and big chassis whole lateral moving high and big die plate | |
CN206562762U (en) | A kind of Fabricated Beam-Slab aluminum dipping form fast assembling disassembling structure | |
CN206088775U (en) | Gantry crane ultra -large -span track support | |
CN105239514A (en) | Stepless-adjustment ball-hinge type multi-support-leg forward transverse shifting track system of bridge girder erection machine | |
CN102777050B (en) | Assembly type jig frame for longspan pipe truss roof girder | |
CN104074390A (en) | 750kV transformer substation steel pipe concrete framework | |
CN204060109U (en) | 750kV transformer station concrete filled steel tube framework | |
CN202644410U (en) | Protection canopy frame of triangle-shaped trusswork | |
CN203461693U (en) | Ultrahigh steel support leg for combined gantry crane with Bailey truss | |
CN202989781U (en) | Width widened cast-in-place box beam moving support | |
CN204849604U (en) | Section closure was with rear -mounted strength nature skeleton concrete arch rib festival | |
CN202689585U (en) | Ground fitting up assembly mould of large steel truss | |
CN206110793U (en) | Do not take framework of ground area | |
CN207143753U (en) | A kind of auxiliary body of steel box-girder swivel | |
CN202185973U (en) | Device for assisting dismounting and installing T beam formwork | |
CN209975552U (en) | Steel construction tower crane foundation cushion cap of adjustable size | |
CN203499020U (en) | Column foot rigid connection joint between steel column and transfer girders | |
CN208068242U (en) | A kind of detachable precast wall body piling bin | |
CN201952736U (en) | Auxiliary pier movable bracket for assisting invariable-amplitude beam erecting crane in erecting steel box girder | |
CN207295980U (en) | A kind of space grid | |
CN203393721U (en) | Inner support main purlin component | |
CN201883728U (en) | DC filter structural frame for converter station | |
CN201924600U (en) | Cast-in-place crossbeam construction formwork supporting system with beam type switching layer | |
CN203382382U (en) | Universal bar gantry | |
CN102427204B (en) | Installation method for 1000kV alternating-current substation structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20141001 |
|
WD01 | Invention patent application deemed withdrawn after publication |