CN104047215A - Method for changing cement concrete pavement into pervious concrete pavement - Google Patents

Method for changing cement concrete pavement into pervious concrete pavement Download PDF

Info

Publication number
CN104047215A
CN104047215A CN201410217596.0A CN201410217596A CN104047215A CN 104047215 A CN104047215 A CN 104047215A CN 201410217596 A CN201410217596 A CN 201410217596A CN 104047215 A CN104047215 A CN 104047215A
Authority
CN
China
Prior art keywords
concrete pavement
macropore
pervious concrete
cement concrete
pervious
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410217596.0A
Other languages
Chinese (zh)
Other versions
CN104047215B (en
Inventor
陈代果
姚勇
李谦
苏军
朱榆萍
任耕北
石军
邓勇军
褚云朋
张兆强
高红伟
徐刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Lianggu Ecological Environment Technology Co ltd
Southwest University of Science and Technology
Original Assignee
Mianyang Jing Gu Science And Technology Ltd
Southwest University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mianyang Jing Gu Science And Technology Ltd, Southwest University of Science and Technology filed Critical Mianyang Jing Gu Science And Technology Ltd
Priority to CN201410217596.0A priority Critical patent/CN104047215B/en
Publication of CN104047215A publication Critical patent/CN104047215A/en
Application granted granted Critical
Publication of CN104047215B publication Critical patent/CN104047215B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

The invention provides a method for changing a cement concrete pavement into a pervious concrete pavement. The method is characterized by comprising the following steps: A, determining the porosity P of pervious concrete and preparing corresponding pervious concrete; B, uniformly perforating holes in the cement concrete pavement, wherein it is ensured that each hole penetrates from a cement concrete pavement layer (5) to a roadbed (6), the holes are composed of uniformly distributed large holes (2) and small holes (4) uniformly distributed around the large holes (2), and the aperture ratio phi of the cement concrete pavement should be greater than P; C, laying geotechnic cloth (3) on the perforated cement concrete pavement layer (5), wherein the parts of the geotechnic cloth (3) located above the large holes (2) are cut open and the sizes of openings of the geotechnic cloth (3) are identical to the sizes of the large holes (2) so as to allow the large holes (2) to penetrate the geotechnic cloth (3); D, casting a pervious concrete surface layer (1) on the laid geotechnic cloth (3) and tamping the large holes (2) with the pervious concrete; and E, carrying out maintenance so as to form the pervious concrete pavement.

Description

Cement concrete pavement changes the method for pervious concrete pavement into
Technical field
The present invention relates to Pavement Improvement construction method, the particularly remodeling method of the region such as city trees and shrubs, parking lot cement concrete pavement in a kind of " changing in vain black " process.
Background technology
Along with the continuous progress of science and technology, ecological, environmental protective construction coming into one's own all the more, different kinds of roads retrofit work just carries out ruly, and wherein, the area road transformations such as city trees and shrubs, parking lot occupy certain ratio.Tradition road surface adopts pitch, concrete, stone slab or cement brick to lay mostly, therefore be called as hard surfacing.Its advantage is that road surface is neat, intensity is high, good endurance, and maximum shortcoming is waterproof, and draining relies on underground sewer, during rainfall, rainwater is directly processed as sewage, has blocked rainwater to the supplementing of underground water, and is unfavorable for the water circulation of natural environment.And for the not smooth area of drainage system, rain, sewage is easily in road surface alluvial, have a strong impact on municipal sanitary after dissolving in household garbage.In addition, hard surfacing easily absorbs, stores and reflect solar heat, and ground average temperature is raise, the formation of aggravation urban heat land effect, thus cause environment and ecological negative effect, be unfavorable for the ecological homeostasis and environmental protection.
In order to solve this series of problem, the researchers of various countries are actively thinking deeply the paving material of exploring development of new, and therefore pervious concrete also arises at the historic moment.Compare with traditional ground surface material, that pervious concrete pavement has is permeable, ventilative, regulate urban climate, reduce the advantages such as surface temperature, alleviating urban heat island phenomenon; Simultaneously, can supplement urban groundwater resource, maintain the soil moisture, improve the life condition of urban surface plants and soil biology, be conducive to the ecological homeostasis, and pervious concrete can absorb the noise that vehicle to run produces, be conducive to create quiet comfortable traffic environment, pervious concrete can effectively alleviate the problems such as road drainage system burden that rainwater causes.
Detection shows, when pervious concrete terrace porosity reaches 15%-25%, its permeable speed reaches 31118L/m 2/ h-51196L/m 2/ h, discharge rate is high.Pervious concrete is significant to the sustainable development of urban ecological environment.
Pervious concrete is mainly to utilize this material to be different from the water permeability of ordinary concrete for road reformation engineering, and therefore, how effectively improving its water permeability is the main points that each construction corps considers.Investigation demonstration, in existing road reformation engineering, the constructing structure method of pervious concrete pavement is mainly directly to cover and build pervious concrete on original cement concrete pavement.
Summary of the invention
The object of the invention is to be intended to utilize the water permeability of pervious concrete itself, adopt the construction method of more optimizing to promote cement concrete pavement, to change the water permeability of pervious concrete pavement, reach permeable effect better.
The present invention is achieved in that
Cement concrete pavement changes a method for pervious concrete pavement into, it is characterized in that the method carries out according to the following steps successively:
A, according to local conditions, determine pervious concrete porosity P, and prepare corresponding pervious concrete;
B, evenly boring on cement concrete pavement, and guarantee that each hole runs through cement concrete pavement layer until roadbed, described hole is by equally distributed macropore and be evenly distributed on macropore aperture around and form, and the quantity of macropore is far fewer than the quantity of aperture, orifice area sum and the ratio of cement concrete pavement area are called to cement concrete pavement percent opening Φ, need Φ to be greater than P;
On C, the cement concrete pavement layer after boring, lay geotextiles, and meeting place, macropore aperture by geotextiles opening, openings of sizes and macropore aperture are in the same size, make macropore connect geotextiles;
D, at the geotextiles upper pervious concrete surface layer of laying, and in macropore, tamp pervious concrete;
After E, maintenance, just form pervious concrete pavement.
The 5-20 of the quantity that the quantity that further scheme is aperture is macropore doubly.
In the present invention:
Pervious concrete in macropore and pervious concrete surface layer monobloc cast, rainwater can be penetrated into lower soil by macropore; Meanwhile, " post " that the pervious concrete in macropore forms forms occlusion structure by top pervious concrete surface layer and bottom cement concrete pavement layer, thereby, should " post " play the whole structural effect of strengthening.
Aperture forms water-permeable passage, strengthens water permeable ability.
This structure forms respectively the water-permeable passage of two kinds of diameters of size, makes the whole road surface can both be permeable, has guaranteed the water permeable ability of pervious concrete pavement.
The isolation of geotechnique's layer of cloth, impurity screening, avoid stopping up water-permeable passage.
Water-permeable passage is communicated with roadbed, plays directly permeable effect.
And in the past in road reformation, most of construction methods are directly on Portland Cement Concrete Surface Course, to lay pervious concrete, can not reach so the permeable effect of expection, can not guarantee the globality of structure, easily occur the phenomenon of Local Cracking.
Porosity P and percent opening Φ mainly determine according to situations such as local geology, weather, particularly amount of precipitations.
The quantity of the quantity of aperture and size, macropore and size, pitch of holes etc., except meeting percent opening Φ requirement, also should be determined according to combined factors such as the thickness of Portland Cement Concrete Surface Course, intensity.Experiment shows, the 5-20 of the quantity that the quantity of aperture is macropore doubly.
Advantage of the present invention:
The pervious concrete material of this structure itself is a kind of green material, maximum feature is its pervious function, in addition, the loose structure of material makes it have sound absorption reduction, absorb the effect of solar radiation, can also need to change concrete color according to using, can well merge with environment.The rational topology layout of the method utilization, improved constructing structure in the past can not utilize the present situation of pervious concrete water permeability completely, road structure is optimized more.With regard to structure itself, major diameter pervious concrete post and the tight interlock of old cement concrete pavement, be guaranteed the overall performance of road structure.The setting of geotechnique's layer of cloth not only can prevent aggregate blocking channel in work progress, and can isolate impurity, is convenient to follow-up cleaning.Meanwhile, major diameter, two kinds of water-permeable passage forms of minor diameter are set, both can have strengthened the bulk strength on transformation road surface, can meet again the requirement of water permeability.
Accompanying drawing explanation
Fig. 1 is road structure vertical cut-away schematic view after laying pervious concrete.
Fig. 2 is the schematic top plan view after former cement concrete pavement perforate.
In figure, 1 is pervious concrete surface layer, and 2 is macropore, and 3 is geotextiles, and 4 is aperture, and 5 is cement concrete pavement layer, and 6 is roadbed.
The specific embodiment:
Below in conjunction with specific embodiment, the present invention is further described.But range of application of the present invention is not limited to the following example.
As Fig. 1 and Fig. 2, a kind of cement concrete pavement changes the method for pervious concrete pavement into, it is characterized in that the method carries out according to the following steps successively:
A, according to local conditions, determine pervious concrete porosity P, and prepare corresponding pervious concrete;
B, evenly boring on cement concrete pavement, and guarantee that cement concrete pavement layer 5 is run through in each hole until roadbed 6, described hole is by equally distributed macropore 2 and be evenly distributed on macropore 2 aperture 4 around and form, and the quantity of macropore 2 is far fewer than the quantity of aperture 4, orifice area sum and the ratio of cement concrete pavement area are called to cement concrete pavement percent opening Φ, need Φ to be greater than P;
On C, the cement concrete pavement layer after boring 5, lay geotextiles 3, and meeting macropore 2 places, aperture by geotextiles 3 openings, openings of sizes and macropore 2 apertures are in the same size, make macropore 2 connect geotextiles 3;
D, at the geotextiles 3 upper pervious concrete surface layers 1 of laying, and tamp pervious concrete in macropore 2;
After E, maintenance, just form pervious concrete pavement.
The quantity of aperture 4 is that the 5-20 of the quantity of macropore 2 is doubly advisable.
During construction, can use the instrument punchings such as electric drill, during punching, will guarantee that each water-permeable passage all runs through cement concrete layer, after completing, clean out each passage; The laying of geotechnique's layer of cloth, should note in process of deployment, exposing macropore hole, has covered all apertures and has met geotextiles construction requirement; In pervious concrete surface layer 5 and macropore 2, the work such as the building of pervious concrete, maintenance meets related specifications.

Claims (2)

1. cement concrete pavement changes a method for pervious concrete pavement into, it is characterized in that the method carries out according to the following steps successively:
A, according to local conditions, determine pervious concrete porosity P, and prepare corresponding pervious concrete;
B, evenly boring on cement concrete pavement, and guarantee that cement concrete pavement layer (5) is run through in each hole until roadbed (6), described hole is by equally distributed macropore (2) and be evenly distributed on macropore (2) aperture (4) formation around, and the quantity of macropore (2) is far fewer than the quantity of aperture (4), orifice area sum and the ratio of cement concrete pavement area are called to cement concrete pavement percent opening Φ, need Φ to be greater than P;
C, the upper geotextiles (3) of laying of the cement concrete pavement layer after boring (5), and meeting place, macropore (2) aperture by geotextiles (3) opening, openings of sizes and macropore (2) aperture is in the same size, makes macropore (2) connect geotextiles (3);
D, at geotextiles (3) the upper pervious concrete surface layer (1) of laying, and tamp pervious concrete in macropore (2);
After E, maintenance, just form pervious concrete pavement.
2. cement concrete pavement changes a method for pervious concrete pavement into, the quantity that it is characterized in that aperture (4) be macropore (2) quantity 5-20 doubly.
CN201410217596.0A 2014-05-21 2014-05-21 Cement concrete pavement changes the method for pervious concrete pavement into Active CN104047215B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410217596.0A CN104047215B (en) 2014-05-21 2014-05-21 Cement concrete pavement changes the method for pervious concrete pavement into

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410217596.0A CN104047215B (en) 2014-05-21 2014-05-21 Cement concrete pavement changes the method for pervious concrete pavement into

Publications (2)

Publication Number Publication Date
CN104047215A true CN104047215A (en) 2014-09-17
CN104047215B CN104047215B (en) 2016-04-13

Family

ID=51500588

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410217596.0A Active CN104047215B (en) 2014-05-21 2014-05-21 Cement concrete pavement changes the method for pervious concrete pavement into

Country Status (1)

Country Link
CN (1) CN104047215B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105113362A (en) * 2015-09-21 2015-12-02 常熟市华诚建设工程有限责任公司 Pebble flow guide road
CN105544340A (en) * 2015-12-04 2016-05-04 浙江方远建材科技有限公司 Water permeable pavement
CN105714645A (en) * 2014-12-22 2016-06-29 天津工众生物技术有限公司 Construction method of permeable concrete pavements
CN105839492A (en) * 2016-04-18 2016-08-10 方耀 Application method of novel colored water-permeable concrete
CN107165017A (en) * 2017-07-24 2017-09-15 上海市市政规划设计研究院 The permanent composite pavement structure transformed for old asphalt pavement
CN110804918A (en) * 2019-10-22 2020-02-18 滁州市富邦商品混凝土有限公司 Concrete road surface structure of preventing collapsing of antidetonation
US11939729B2 (en) 2018-11-13 2024-03-26 Imperial College Innovations Limited High strength porous cement-based materials

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6454489B1 (en) * 1996-08-16 2002-09-24 Mitsubishi Materials Corporation NOx removing pavement structure
JP3900404B2 (en) * 2001-10-17 2007-04-04 ケミカルグラウト株式会社 Paved road
CN102031744A (en) * 2010-11-22 2011-04-27 长沙理工大学 Composite pavement structure and construction method thereof
CN202766945U (en) * 2012-08-10 2013-03-06 吉林省中力通信工程有限公司 Water containing road surface capable of solving waterlogging
CN203334156U (en) * 2013-06-05 2013-12-11 北京中景橙石建筑科技有限公司 Drainage floor structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6454489B1 (en) * 1996-08-16 2002-09-24 Mitsubishi Materials Corporation NOx removing pavement structure
JP3900404B2 (en) * 2001-10-17 2007-04-04 ケミカルグラウト株式会社 Paved road
CN102031744A (en) * 2010-11-22 2011-04-27 长沙理工大学 Composite pavement structure and construction method thereof
CN202766945U (en) * 2012-08-10 2013-03-06 吉林省中力通信工程有限公司 Water containing road surface capable of solving waterlogging
CN203334156U (en) * 2013-06-05 2013-12-11 北京中景橙石建筑科技有限公司 Drainage floor structure

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105714645A (en) * 2014-12-22 2016-06-29 天津工众生物技术有限公司 Construction method of permeable concrete pavements
CN105113362A (en) * 2015-09-21 2015-12-02 常熟市华诚建设工程有限责任公司 Pebble flow guide road
CN105113362B (en) * 2015-09-21 2017-12-01 绍兴明煌建材科技有限公司 A kind of cobblestone channelizing road
CN105544340A (en) * 2015-12-04 2016-05-04 浙江方远建材科技有限公司 Water permeable pavement
CN105839492A (en) * 2016-04-18 2016-08-10 方耀 Application method of novel colored water-permeable concrete
CN107165017A (en) * 2017-07-24 2017-09-15 上海市市政规划设计研究院 The permanent composite pavement structure transformed for old asphalt pavement
US11939729B2 (en) 2018-11-13 2024-03-26 Imperial College Innovations Limited High strength porous cement-based materials
CN110804918A (en) * 2019-10-22 2020-02-18 滁州市富邦商品混凝土有限公司 Concrete road surface structure of preventing collapsing of antidetonation

Also Published As

Publication number Publication date
CN104047215B (en) 2016-04-13

Similar Documents

Publication Publication Date Title
CN104047215B (en) Cement concrete pavement changes the method for pervious concrete pavement into
CN106351103A (en) Permeable pavement structure with high strength and high permeability and paving method thereof
CN206352331U (en) The concave herbaceous field structure of sponge the idea of the city
CN204662552U (en) Urban road Rainwater collection system
CN206219935U (en) A kind of permeable pavement structure of high intensity, high osmosis
CN106758638A (en) A kind of city sponge brick and its construction technology
CN106087632A (en) A kind of laying brick having both row's water storage function based on sponge urban construction
CN205420945U (en) Concrete road permeates water
CN207032427U (en) A kind of Rainwater collection system suitable for old cell
CN104831599A (en) Composite water storage-drainage eco-friendly floor
CN207143643U (en) Water drainage template
CN109338839B (en) Urban seepage storage system for recycling construction waste
CN205711605U (en) Permeable pavement structure
CN215210279U (en) Modular permeable pavement system
CN105401499A (en) Ecologic water-permeable terrace provided with siphoning type drained water collection and reutilization system
CN205557244U (en) Can splice high durable environmental ecology of formula brick that permeates water
CN205223783U (en) But hole regenerative permeable ground surface structure
CN204780521U (en) Compound row water environmental protection ground of holding
CN208362838U (en) A kind of porous pavement
CN206545257U (en) A kind of novel greening band water storage structure
CN207469190U (en) A kind of infitration galleries structure of efficient draining
CN105484125A (en) Step capable of collecting and utilizing rainwater
CN206616661U (en) A kind of sponge city concave herbaceous field
CN206090204U (en) Height ecological road surface structure of permeating water
CN214656073U (en) Natural permeable quarrying paving structure for sponge city

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 621010, No. 59, Qinglong Avenue, Qinglong Town, Fucheng District, Sichuan, Mianyang

Co-patentee after: SICHUAN LGLITTER TECHNOLOGY GROUP CO.,LTD.

Patentee after: Southwest University of Science and Technology

Address before: 621010, No. 59, Qinglong Avenue, Qinglong Town, Fucheng District, Sichuan, Mianyang

Co-patentee before: MIANYANG LIANGGU TECHNOLOGY CO.,LTD.

Patentee before: Southwest University of Science and Technology

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20190807

Address after: 621010 Fucheng District, Sichuan, Mianyang

Co-patentee after: Xinjiang Lianggu Science and Technology Co.,Ltd.

Patentee after: Southwest University of Science and Technology

Address before: 621010, No. 59, Qinglong Avenue, Qinglong Town, Fucheng District, Sichuan, Mianyang

Co-patentee before: SICHUAN LGLITTER TECHNOLOGY GROUP CO.,LTD.

Patentee before: Southwest University of Science and Technology

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200109

Address after: 621010 Fucheng District, Sichuan, Mianyang

Co-patentee after: SICHUAN LGLITTER TECHNOLOGY GROUP CO.,LTD.

Patentee after: Southwest University of Science and Technology

Address before: 621010 Fucheng District, Sichuan, Mianyang

Co-patentee before: Xinjiang Lianggu Science and Technology Co.,Ltd.

Patentee before: Southwest University of Science and Technology

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200507

Address after: 621010 Fucheng District, Sichuan, Mianyang

Co-patentee after: Shanghai Lianggu Ecological Environment Technology Co.,Ltd.

Patentee after: Southwest University of Science and Technology

Address before: 621010 Fucheng District, Sichuan, Mianyang

Co-patentee before: SICHUAN LGLITTER TECHNOLOGY GROUP Co.,Ltd.

Patentee before: Southwest University of Science and Technology