CN107165017A - The permanent composite pavement structure transformed for old asphalt pavement - Google Patents

The permanent composite pavement structure transformed for old asphalt pavement Download PDF

Info

Publication number
CN107165017A
CN107165017A CN201710604957.0A CN201710604957A CN107165017A CN 107165017 A CN107165017 A CN 107165017A CN 201710604957 A CN201710604957 A CN 201710604957A CN 107165017 A CN107165017 A CN 107165017A
Authority
CN
China
Prior art keywords
cement concrete
performance
basic unit
old asphalt
performance cement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710604957.0A
Other languages
Chinese (zh)
Inventor
过震文
何昌轩
孙文州
张绪国
王强
梁亚军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Municipal Planning And Design Institute Co ltd
Original Assignee
Shanghai Municipal Planning & Design Research Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Municipal Planning & Design Research Institute filed Critical Shanghai Municipal Planning & Design Research Institute
Priority to CN201710604957.0A priority Critical patent/CN107165017A/en
Publication of CN107165017A publication Critical patent/CN107165017A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C7/00Coherent pavings made in situ
    • E01C7/08Coherent pavings made in situ made of road-metal and binders
    • E01C7/32Coherent pavings made in situ made of road-metal and binders of courses of different kind made in situ

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention provides a kind of permanent composite pavement structure transformed for old asphalt pavement, include high-performance cement concrete layer successively from top to bottom, asphalt surface course, basic unit, underlayment and roadbed, high-performance cement concrete layer is installed on asphalt surface course, asphalt surface course is installed in basic unit, or, high-performance cement concrete layer is replaced asphalt surface course and is installed in basic unit, basic unit is installed on underlayment, underlayment is installed on roadbed, vertical recess runs through asphalt surface course and basic unit, if there is no asphalt surface course, then only run through basic unit, high-performance cement concrete column is filled in vertical recess and connects high-performance cement concrete layer and underlayment respectively.The present invention's is used for the permanent composite pavement structure Stability Analysis of Structures that old asphalt pavement is transformed, and excellent performance is hardly damaged, and service life is long, ingenious in design, construction environmental protection, and convenient, cost is low, suitable for large-scale promotion application.

Description

The permanent composite pavement structure transformed for old asphalt pavement
Technical field
The present invention relates to road pavement technical field of structures, more particularly, to asphalt pavement technique field, particularly relate to A kind of permanent composite pavement structure transformed for old asphalt pavement.
Background technology
With the development of high-grade highway particularly expressway construction, asphalt concrete pavement one jumps and turns into road surface Principal mode.
But, comed one after another the problem of new, national economy high speed development and the volume of traffic that brings are increased rapidly, vehicle is large-scale Change, overload serious, vehicle channelization etc., bituminous paving is faced with severe tests.Heavy traffic road due to not carrying out in time Preventive maintenance, bituminous paving is serious with the increase performance degradation of active time, occurs in that structural damage.
At present mostly scheme is carried out for there is the bituminous paving of structural damage according to the technical requirements of medium-capital overhauling specification Design, medium-capital overhauling conceptual design generally required to the acute belly breaking of original road, digs that pavement structure is long in time limit and outer freight volume Greatly, site operation pole is not environmentally.
Accordingly, it is desirable to provide a kind of pavement structure transformed the bituminous paving for structural damage occur, its structure Stable, excellent performance is hardly damaged, and service life is long, construction environmental protection, convenient.
The content of the invention
In order to overcome above-mentioned shortcoming of the prior art, it is used for Bituminous concrete surface road it is an object of the present invention to provide one kind The permanent composite pavement structure of face transformation, its Stability Analysis of Structures, excellent performance is hardly damaged, and service life is long, suitable for big rule Mould popularization and application.
Another object of the present invention is to provide a kind of permanent composite pavement structure transformed for old asphalt pavement, Its is ingenious in design, construction environmental protection, and convenient, cost is low, suitable for large-scale promotion application.
To achieve the above objectives, it is used for the permanent of old asphalt pavement transformation there is provided a kind of in the first aspect of the present invention Property composite pavement structure, be characterized in, from top to bottom successively include high-performance cement concrete layer, asphalt surface course, basic unit, bottom Basic unit and roadbed, the high-performance cement concrete layer are installed on the asphalt surface course, and the asphalt surface course is installed in described In basic unit, the basic unit is installed on the underlayment, and the underlayment is installed on the roadbed, and described is used for Bituminous concrete surface The permanent composite pavement structure of Pavement Improvement also includes vertical recess, and the vertical recess runs through the asphalt surface course and institute Basic unit is stated, the high-performance cement concrete column is filled in the vertical recess and connects the high-performance cement coagulation respectively Soil layer and the underlayment.
The high performance concrete of the high-performance cement concrete layer possess splendid impervious, resistance to compression, anti-folding, freeze thawing resistance, Etc. performance, and drying shrinkage is small, slump good, but needs the moisture-keeping maintaining of certain time length, and the key technical indexes is as follows:(1) 4h resistance to compressions Intensity >=40MPa, 28d compression strength >=80MPa;(2) 28d rupture strengths >=15.0MPa;(3) concrete limitation drying shrinkage≤200 μ ε, (4) slump is 10.0 ± 2.0cm;(5) 2h~4h moisture-keeping maintaining need to be carried out;(6) seepage-resistant grade is more than P20, with good Good freeze thawing resistance characteristic.
The high performance concrete can be suitably composed with any, it is preferred that the high performance concrete is by common Portland cement:Silicon ash:Sulphate aluminium cement:Sand:Microlith:Steel fibre:Water:Additive:Retarder is with mass ratio 260:40: 450:650:800:80:187:10:6.8 mix.
The high-performance cement concrete column and the high-performance cement concrete layer can be two separate parts, mutually Link together, or a single part, be integrally formed, it is preferred that the high-performance cement concrete column and described High-performance cement concrete layer is integrally formed.
The vertical recess can be any suitable vertical recess, it is preferred that the vertical recess is selected from vertical shrinkage pool At least one of with vertical groove.
The number of the vertical recess can be determined as needed, it is preferred that the number of the vertical recess is multiple, more Goodly, multiple vertical recesses are evenly distributed in the asphalt surface course and the basic unit.
The center of circle of four adjacent vertical shrinkage pools can be with located at any suitable location, more preferably, and four adjacent described It is on 90 ° of four angles of rhombus that the center of circle of vertical shrinkage pool, which is located at square or each side angle,.
The aperture of the vertical shrinkage pool can determine as needed, more preferably, the aperture of the vertical shrinkage pool for 150mm~ 250mm。
Interval between two vertical shrinkage pools can determine as needed, more preferably, two vertical shrinkage pools it Between at intervals of 1m~2m.
The width of the vertical groove can determine as needed, more preferably, the width of the vertical groove for 100mm~ 200mm。
Spacing between two vertical grooves can determine as needed, more preferably, two vertical grooves it Between spacing be 3m~5m.
The minimum range at the vertical recess to the edge of the high-performance cement concrete layer can determine as needed, It is preferred that minimum range >=3 times the high-performance water of the vertical recess to the edge of the high-performance cement concrete layer The thickness of cement concrete layer and the thickness of≤15 times of high-performance cement concrete layers.In other words, the vertical recess away from From the thickness and≤15 of the minimum range >=3 times high-performance cement concrete layer at the edge of road outer rim such as asphalt surface course The thickness of the high-performance cement concrete layer again.
The thickness of the high-performance cement concrete layer can be determined as needed, it is preferred that the high-performance cement is mixed Solidifying the thickness of the layer is 8cm~15cm.
In order to improve old asphalt pavement structural strength uniformity, it is preferred that described is used for old asphalt pavement transformation forever Long property composite pavement structure also includes high-performance water cement concrete intensive aspect, and the high-performance water cement concrete intensive aspect is plugged In the asphalt surface course and connect the high-performance cement concrete layer.
The high-performance cement concrete column and the high-performance water cement concrete intensive aspect can be two separate parts, Interconnect, or a single part, be integrally formed, more preferably, the high-performance cement concrete column and The high-performance water cement concrete intensive aspect is integrally formed.
Old asphalt pavement generally includes asphalt surface course, basic unit, underlayment and roadbed, the asphalt surface course successively from top to bottom It is installed in the basic unit, the basic unit is installed on the underlayment, the underlayment is installed on the roadbed, above-mentioned The preparation method for the permanent composite pavement structure transformed for old asphalt pavement comprises the following steps:
(1) vertical recess is set on the old asphalt pavement, and the vertical recess runs through the asphalt surface course and described Basic unit;
(2) pave high-performance water cement concrete on the old asphalt pavement, a part of high-performance water cement concrete The vertical recess is poured into, the remaining high-performance cement concrete speading is in the asphalt surface course and a part of high property On energy cement concrete, after moisture-keeping maintaining, a part of high-performance water cement concrete formation high-performance cement concrete column, The remaining high-performance water cement concrete formation high-performance cement concrete layer.
In the step (1), the vertical recess can be vertical shrinkage pool or vertical groove.
, can be to the asphalt surface course especially intensity of the old asphalt pavement prior to, concurrently with, or after the step (1) Not enough place carries out injecting treatment, and the disease such as pit and crack to the asphalt surface course of old asphalt pavement is repaired.It is used Slurry can be high-performance water cement concrete.
In the step (2), the time of moisture-keeping maintaining can extend curing time when being 2h~4h, such as low-temperature construction.
In the second aspect of the present invention, there is provided another permanent composite pavement knot transformed for old asphalt pavement Structure, is characterized in, includes high-performance cement concrete layer, basic unit, underlayment and roadbed, the high-performance water successively from top to bottom Cement concrete layer is installed in the basic unit, and the basic unit is installed on the underlayment, and the underlayment is installed in the road On base, the described permanent composite pavement structure for being used for old asphalt pavement transformation also includes vertical recess, described vertical recessed The basic unit is run through in portion, and the high-performance cement concrete column is filled in the vertical recess and connects the high-performance respectively Cement concrete layer and the underlayment.
Same as above, the high performance concrete of the high-performance cement concrete layer possesses splendid impervious, resistance to compression, anti- The performances such as folding, freeze thawing resistance, and drying shrinkage is small, slump good, but the moisture-keeping maintaining of certain time length is needed, the key technical indexes is as follows: (1) 4h compression strength >=40MPa, 28d compression strength >=80MPa;(2) 28d rupture strengths >=15.0MPa;(3) concrete is limited The μ ε of drying shrinkage≤200, (4) slump is 10.0 ± 2.0cm;(5) 2h~4h moisture-keeping maintaining need to be carried out;(6) seepage-resistant grade exceedes P20, with good freeze thawing resistance characteristic.
The high-performance cement concrete column and the high-performance cement concrete layer can be two separate parts, mutually Link together, or a single part, be integrally formed, it is preferred that the high-performance cement concrete column and described High-performance cement concrete layer is integrally formed.
The vertical recess can be any suitable vertical recess, it is preferred that the vertical recess is selected from vertical shrinkage pool At least one of with vertical groove.
The number of the vertical recess can be determined as needed, it is preferred that the number of the vertical recess is multiple, more Goodly, multiple vertical recesses are evenly distributed in the basic unit.
The center of circle of four adjacent vertical shrinkage pools can be with located at any suitable location, more preferably, and four adjacent described It is on 90 ° of four angles of rhombus that the center of circle of vertical shrinkage pool, which is located at square or each side angle,.
The aperture of the vertical shrinkage pool can determine as needed, more preferably, the aperture of the vertical shrinkage pool for 150mm~ 250mm。
Interval between two vertical shrinkage pools can determine as needed, more preferably, two vertical shrinkage pools it Between at intervals of 1m~2m.
The width of the vertical groove can determine as needed, more preferably, the width of the vertical groove for 100mm~ 200mm。
Spacing between two vertical grooves can determine as needed, more preferably, two vertical grooves it Between spacing be 3m~5m.
The minimum range at the vertical recess to the edge of the high-performance cement concrete layer can determine as needed, It is preferred that minimum range >=3 times the high-performance water of the vertical recess to the edge of the high-performance cement concrete layer The thickness of cement concrete layer and the thickness of≤15 times of high-performance cement concrete layers.In other words, the vertical recess away from Thickness and≤15 times of institutes from the minimum range >=3 times high-performance cement concrete layer at the edge of road outer rim such as basic unit State the thickness of high-performance cement concrete layer.
The thickness of the high-performance cement concrete layer can be determined as needed, it is preferred that the high-performance cement is mixed Solidifying the thickness of the layer is 8cm~15cm.
In order to improve old asphalt pavement structural strength uniformity, it is preferred that described is used for old asphalt pavement transformation forever Long property composite pavement structure also includes high-performance water cement concrete intensive aspect, and the high-performance water cement concrete intensive aspect is plugged In the basic unit and connect the high-performance cement concrete layer..
The high-performance cement concrete column and the high-performance water cement concrete intensive aspect can be two separate parts, Interconnect, or a single part, be integrally formed, more preferably, the high-performance cement concrete column and The high-performance water cement concrete intensive aspect is integrally formed.
Old asphalt pavement generally includes asphalt surface course, basic unit, underlayment and roadbed, the asphalt surface course successively from top to bottom It is installed in the basic unit, the basic unit is installed on the underlayment, the underlayment is installed on the roadbed, above-mentioned The preparation method for the permanent composite pavement structure transformed for old asphalt pavement comprises the following steps:
A. asphalt surface course described in milling;
B., vertical recess is set in the basic unit, and the vertical recess runs through the basic unit;
C. pave high-performance water cement concrete in the basic unit, and a part of high-performance water cement concrete pours into described Vertical recess, the remaining high-performance cement concrete speading is in the basic unit and a part of high-performance water cement concrete On, after moisture-keeping maintaining, a part of high-performance water cement concrete formation high-performance cement concrete column, the remaining height Performance cement concrete formation high-performance cement concrete layer.
In the step B, the vertical recess can be vertical shrinkage pool or vertical groove.
Prior to, concurrently with, or after the step B, the place not enough to the basic unit especially intensity is carried out at slip casting Manage, the disease such as pit and crack to basic unit is repaired.Slurry therewith can be high-performance water cement concrete.
In the step C, the time of moisture-keeping maintaining can extend curing time when being 2h~4h, such as low-temperature construction.
The beneficial effects of the present invention are:
(1) the permanent composite pavement structure for being used for old asphalt pavement transformation of the invention includes height successively from top to bottom Performance cement concrete layer, asphalt surface course, basic unit, underlayment and roadbed, high-performance cement concrete layer are installed in asphalt surface course On, asphalt surface course is installed in basic unit, or, high-performance cement concrete layer is replaced asphalt surface course and is installed in basic unit, base Layer is installed on underlayment, and underlayment is installed on roadbed, in addition to vertical recess, and vertical recess runs through asphalt surface course and base Layer, if there is no asphalt surface course, then vertical recess is only through basic unit, and high-performance cement concrete column is filled in vertical recess And connection high-performance cement concrete layer and underlayment, therefore, its Stability Analysis of Structures, excellent performance are hardly damaged respectively, use the longevity Life length, suitable for large-scale promotion application.
(2) the permanent composite pavement structure for being used for old asphalt pavement transformation of the invention includes height successively from top to bottom Performance cement concrete layer, asphalt surface course, basic unit, underlayment and roadbed, high-performance cement concrete layer are installed in asphalt surface course On, asphalt surface course is installed in basic unit, or, high-performance cement concrete layer is replaced asphalt surface course and is installed in basic unit, base Layer is installed on underlayment, and underlayment is installed on roadbed, in addition to vertical recess, and vertical recess runs through asphalt surface course and base Layer, if there is no asphalt surface course, then vertical recess is only through basic unit, and high-performance cement concrete column is filled in vertical recess And high-performance cement concrete layer and underlayment are connected respectively, therefore, its is ingenious in design, construction environmental protection, and convenient, cost is low, fits In large-scale promotion application.
These and other objects, feature and the advantage of the present invention, is obtained by following detailed descriptions, drawings and claims To fully demonstrate, and it can be achieved by the means specially pointed out in appended claims, device and combinations thereof.
Brief description of the drawings
Fig. 1 is the specific implementation to form the permanent composite pavement structure for being used for old asphalt pavement transformation of the present invention The main view perspective diagram of vertical shrinkage pool is set during example to old asphalt pavement.
Fig. 2 is the specific implementation to form the permanent composite pavement structure for being used for old asphalt pavement transformation of the present invention The schematic top plan view of vertical shrinkage pool is set during example to old asphalt pavement.
Fig. 3 is another specific reality to form the permanent composite pavement structure for being used for old asphalt pavement transformation of the present invention The side view perspective diagram of vertical groove is set when applying to old asphalt pavement.
Fig. 4 is another specific reality to form the permanent composite pavement structure for being used for old asphalt pavement transformation of the present invention The schematic top plan view of vertical groove is set when applying to old asphalt pavement.
(symbol description)
1 asphalt surface course;11 superficial layers;Surface layer in 12;13 cutting optimals;2 basic units;3 underlayments;4 roadbeds;5 vertical shrinkage pools;6 Vertical groove.
Embodiment
In order to be more clearly understood that the technology contents of the present invention, described in detail especially exemplified by following examples.All hundred Point rate is weight percent, unless otherwise specified.
Raw material used in embodiment 1- embodiments 3 has:
(strength grade is 52.5 grades of portland cement, C to cement3A content is 8% weight, purchased from Anhui Conch Cement Limited company);
(Sai Pusen silicon ashes, average grain diameter is 0.1 μm, SiO to silicon ash2Content be 98% weight, activity index is 115%, Purchased from Shandong Bo Ken silicon materials Co., Ltd);
Sulphate aluminium cement (strength grade is 42.5 grades, purchased from Anhui Conch Cement limited company);
Sand, microlith (being purchased from Jiangsu Ya Bang mining industry Co., Ltd);
(copper facing steel fibre, a diameter of 0.22mm, length is 14mm to steel fibre, and tensile strength is 2200MPa, purchased from Hebei Square moral silk screen products factory);
(8525 type water reducers, are a kind of polycarboxylate water-reducer to additive, and water-reducing rate 40% builds work purchased from Shanghai Mace spy High-tech architecture Chemical Co., Ltd.);
Retarder (borax, purchased from Shanghai Hui Guang Fine Chemical Co., Ltd)
Embodiment 1
Old asphalt pavement includes asphalt surface course 1, basic unit 2, underlayment 3 and roadbed 4 successively from top to bottom, and asphalt surface course 1 is pacified It is located in basic unit 2, basic unit 2 is installed on underlayment 3, underlayment 3 is installed on roadbed 4, asphalt surface course 1 is wrapped successively from top to bottom Include superficial layer 11, middle surface layer 12, cutting optimal 13.
The construction method for the permanent composite pavement structure transformed for old asphalt pavement comprises the following steps:A, it will set The position of the vertical shrinkage pool 5 of meter is marked on old asphalt pavement (namely asphalt surface course 1), the position in the center of circle of each vertical shrinkage pool 5 Put the rhombus distribution that line formation angle is 90 °, the length of side is 115cm, the most narrow spacing of each vertical shrinkage pool 5 to the outer rim of asphalt surface course 1 From for 24cm;B, using 15cm diameters core drilling machine each mark position drill old asphalt pavement, depth to basic unit 2 bottom mark Height, is referred to shown in Fig. 1 and Fig. 2;C, processing old asphalt pavement surface, carry out slip casting joint filling, milling and cleaning, and joint filling is used to starch Material can be high-performance water cement concrete;D, according to match ratio (Portland cement:Silicon ash:Sulphate aluminium cement:Sand:Carefully Stone:Steel fibre:Water:Additive:The mass ratio 260 of retarder:40:450:650:800:80:187:10:6.8) mix high-performance Cement concrete;E, 8cm that the uniform high-performance water cement concrete of mix paved on old asphalt pavement using paver are thick High-performance cement concrete layer forms high-performance cement concrete column and on the surface of asphalt surface course 1 in vertical shrinkage pool 5 simultaneously Gap in formed high-performance water cement concrete intensive aspect;F, the moisture-keeping maintaining for carrying out 4h, treat that compression strength reaches 40MPa, curved Tensile strength reaches that 5MPa can open to traffic.
Embodiment 2
Old asphalt pavement includes asphalt surface course 1, basic unit 2, underlayment 3 and roadbed 4 successively from top to bottom, and asphalt surface course 1 is pacified It is located in basic unit 2, basic unit 2 is installed on underlayment 3, underlayment 3 is installed on roadbed 4, asphalt surface course 1 is wrapped successively from top to bottom Include superficial layer 11, middle surface layer 12, cutting optimal 13.
The construction method for the permanent composite pavement structure transformed for old asphalt pavement comprises the following steps:A, it will set The position of the vertical groove 6 of meter is marked in old asphalt pavement (namely asphalt surface course 1), to be subsequently formed along old asphalt pavement Laterally uniform vertical groove 6, groove width 10cm, each groove is at a distance of 300cm, and each vertical groove to the outer rim of asphalt surface course 1 is most Small distance is 50cm;B, slotted in the cutting old asphalt pavement formation of each mark position using cutting machine, and require groove depth to basic unit 2 Bottom absolute altitude, be consequently formed vertical groove 6, refer to shown in Fig. 3 and Fig. 4;C, processing old asphalt pavement surface, carry out slip casting and fill out Seam, milling and cleaning, joint filling slurry therewith can be high-performance water cement concrete;D, according to match ratio (Portland cement: Silicon ash:Sulphate aluminium cement:Sand:Microlith:Steel fibre:Water:Additive:Retarder mass ratio is 260:40:450:650:800: 80:187:10:6.8) mix high-performance water cement concrete;E, the uniform high-performance water cement concrete of mix existed using paver The high-performance cement concrete layer thick 11cm that paved on old asphalt pavement forms high-performance cement coagulation in vertical groove 6 simultaneously Earth pillar and the formation high-performance water cement concrete intensive aspect in the gap on the surface of asphalt surface course 1;F, the moisture-keeping maintaining for carrying out 3h.
Embodiment 3
Old asphalt pavement includes asphalt surface course 1, basic unit 2, underlayment 3 and roadbed 4 successively from top to bottom, and asphalt surface course 1 is pacified It is located in basic unit 2, basic unit 2 is installed on underlayment 3, underlayment 3 is installed on roadbed 4, asphalt surface course 1 is wrapped successively from top to bottom Include superficial layer 11, middle surface layer 12, cutting optimal 13.
The construction method for the permanent composite pavement structure transformed for old asphalt pavement comprises the following steps:A, milling 15cm asphalt surface course 1;B, the position of the vertical shrinkage pool 5 of design marked in basic unit 2, the position in the center of circle of each vertical shrinkage pool 5 The rhombus distribution that line formation angle is 90 °, the length of side is 159cm, each vertical shrinkage pool 5 to the minimum range of the outer rim of basic unit 2 is 225cm;C, using 25cm diameters core drilling machine each mark position drill basic unit 2, the bottom absolute altitude of depth to basic unit 2;D, processing The surface of basic unit 2, carries out slip casting joint filling, milling and cleaning, joint filling slurry therewith can be high-performance water cement concrete,;E, according to Match ratio (Portland cement:Silicon ash:Sulphate aluminium cement:Sand:Microlith:Steel fibre:Water:Additive:Retarder mass ratio For 260:40:450:650:800:80:187:10:6.8) mix high-performance water cement concrete;F, by the uniform high-performance of mix Cement concrete utilizes the high-performance cement concrete layer thick 15cm shape in vertical shrinkage pool 5 simultaneously that paved in paver basic unit 2 High-performance water cement concrete intensive aspect is formed into high-performance cement concrete column and in the gap on the surface of basic unit 2;G, progress 2h moisture-keeping maintaining..
The composite pavement structure of the formation of embodiment 1- embodiments 3 is compared with protobitumen pavement structure:
(1) service life of cement concrete pavement is substantially 2 times of bituminous paving service life, adds the steel fibre way of escape Face globality enhancing is hardly damaged;
(2) reduce disease, and certain basic unit and subgrade defect can be resisted:Flood is difficult to destroy by rush of water, when basic unit or roadbed Reinforced concrete pavement remains to normally use when occurring small-sized empty;
(3) temperature tolerance is strong, in extreme air high/low temperature timeinvariance;
(4) fire resistance is high, and cement concrete pavement is incombustible material, concrete be thermal inertia material i.e. thermal conductivity factor very It is small, surface temperature can be only achieved to its internal temperature after concrete component heating and some time constant temperature, such as length of side 100mm's is vertical About 6 hours its central temperatures of 700 DEG C of heated at constant temperature of cube can be only achieved 680 DEG C;
(5) maintenance is simple with repairing, and disease seldom occurs, conserves simplicity of keeping a public place clean, and jewel hole bar planting after disease occurs and uses fast hard Early strength concrete can fast and high quality reparation.
So as to, the present invention is the overlay high-performance cement concrete layer on old asphalt pavement, or by after asphalt surface course milling Replaced using high-performance cement concrete layer, that is, select high-performance water cement concrete as surface material to meet the structure on road surface Intensity requirement, while vertical recess for example drills or grooving fills part during high-performance cement concrete speading by setting Enter hole or groove, to improve cohering for bituminous paving and high-performance cement concrete layer, it is ensured that high-performance water cement concrete Layer is integrated into a whole with bituminous paving, and high-performance water cement concrete used possesses splendid impervious, freeze thawing resistance, corrosion resistant The performances such as erosion, high temperature resistant, resistant abrasion.
Therefore, the invention provides the permanent combined type road that reinforcement is rebuild in a kind of overlay of old asphalt pavement or asphalt surface course Face structure, the old asphalt pavement that especially a kind of bearing capacity is poor, structural damage is more serious is overlayed or asphalt surface course rebuilds benefit Strong permanent composite pavement structure.It is using overlaying high-performance cement concrete layer as surface layer or by high-performance cement Concrete layer replaces a kind of Maintenanice techngue of bitumin pavement of protobitumen surface layer, by the good stress of high-performance water cement concrete Former pavement damage critical regions can carried out directly spreading out after injecting treatment improves pavement structural strength uniformity by diffusivity High-performance water cement concrete is spread, it is environmentally friendly, convenient to construct, and composite pavement structure also improves the Long-Term Properties of road.
The present invention's is used for the permanent composite pavement structure good integrity that old asphalt pavement is transformed, road surface bearing capacity Height, is adapted to the maintenance and renovation of road Lack of support and the serious old asphalt pavement of road surface breakage, site operation rapid and convenient, Structure durability is lasting.
In summary, the permanent composite pavement structure Stability Analysis of Structures transformed for old asphalt pavement of the invention, property Can be excellent, it is hardly damaged, service life is long, ingenious in design, construction environmental protection, convenient, cost is low, suitable for large-scale promotion application.
In this description, the present invention is described with reference to its specific embodiment.But it is clear that can still make Various modifications and alterations are without departing from the spirit and scope of the present invention.Therefore, specification is considered as illustrative rather than limit Property processed.

Claims (10)

1. a kind of permanent composite pavement structure transformed for old asphalt pavement, it is characterised in that wrap successively from top to bottom High-performance cement concrete layer, asphalt surface course, basic unit, underlayment and roadbed are included, the high-performance cement concrete layer is installed in On the asphalt surface course, the asphalt surface course is installed in the basic unit, and the basic unit is installed on the underlayment, the bottom Basic unit is installed on the roadbed, and the described permanent composite pavement structure for being used for old asphalt pavement transformation also includes vertical Recess, the vertical recess runs through the asphalt surface course and the basic unit, and the high-performance cement concrete column is filled in described Connect in vertical recess and respectively the high-performance cement concrete layer and the underlayment.
2. a kind of permanent composite pavement structure transformed for old asphalt pavement, it is characterised in that wrap successively from top to bottom High-performance cement concrete layer, basic unit, underlayment and roadbed are included, the high-performance cement concrete layer is installed in the basic unit On, the basic unit is installed on the underlayment, and the underlayment is installed on the roadbed, and described is used for old asphalt pavement The permanent composite pavement structure of transformation also includes vertical recess, and the vertical recess runs through the basic unit, the high-performance Cement and concrete is filled in the vertical recess and connects the high-performance cement concrete layer and the underlayment respectively.
3. it is used for the permanent composite pavement structure that old asphalt pavement is transformed according to claim 1 or claim 2, Characterized in that, the high-performance cement concrete column and the high-performance cement concrete layer are integrally formed.
4. it is used for the permanent composite pavement structure that old asphalt pavement is transformed according to claim 1 or claim 2, Characterized in that, the vertical recess is selected from least one of vertical shrinkage pool and vertical groove.
5. the permanent composite pavement structure according to claim 4 transformed for old asphalt pavement, it is characterised in that It is on 90 ° of four angles of rhombus that the center of circle of four adjacent vertical shrinkage pools, which is located at square or each side angle,.
6. the permanent composite pavement structure according to claim 4 transformed for old asphalt pavement, it is characterised in that The aperture of the vertical shrinkage pool is at intervals of 1m~2m between 150mm~250mm, two vertical shrinkage pools;Or, it is described The width of vertical groove is that the spacing between 100mm~200mm, two vertical grooves is 3m~5m.
7. it is used for the permanent composite pavement structure that old asphalt pavement is transformed according to claim 1 or claim 2, Characterized in that, minimum range >=3 times at the vertical recess to the edge of the high-performance cement concrete layer high property The thickness and the thickness of≤15 times of high-performance cement concrete layers of energy cement concrete layer.
8. it is used for the permanent composite pavement structure that old asphalt pavement is transformed according to claim 1 or claim 2, Characterized in that, the thickness of the high-performance cement concrete layer is 8cm~15cm.
9. it is used for the permanent composite pavement structure that old asphalt pavement is transformed according to claim 1 or claim 2, Characterized in that, the described permanent composite pavement structure for being used for old asphalt pavement transformation also includes high-performance cement coagulation Native intensive aspect, the high-performance water cement concrete intensive aspect is plugged in the asphalt surface course and connects the high-performance cement and mixes Solidifying soil layer.
10. the permanent composite pavement structure according to claim 2 transformed for old asphalt pavement, its feature exists In the described permanent composite pavement structure for being used for old asphalt pavement transformation also includes high-performance water cement concrete and strengthened Body, the high-performance water cement concrete intensive aspect is plugged in the basic unit and connects the high-performance cement concrete layer.
CN201710604957.0A 2017-07-24 2017-07-24 The permanent composite pavement structure transformed for old asphalt pavement Pending CN107165017A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710604957.0A CN107165017A (en) 2017-07-24 2017-07-24 The permanent composite pavement structure transformed for old asphalt pavement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710604957.0A CN107165017A (en) 2017-07-24 2017-07-24 The permanent composite pavement structure transformed for old asphalt pavement

Publications (1)

Publication Number Publication Date
CN107165017A true CN107165017A (en) 2017-09-15

Family

ID=59818113

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710604957.0A Pending CN107165017A (en) 2017-07-24 2017-07-24 The permanent composite pavement structure transformed for old asphalt pavement

Country Status (1)

Country Link
CN (1) CN107165017A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109490971A (en) * 2018-11-29 2019-03-19 江苏北极星交通产业集团有限公司 The detection restorative procedure that composite pavement comes to nothing
CN113430890A (en) * 2021-07-01 2021-09-24 驻马店市华中公路设计有限公司 Permanent composite pavement structure for old asphalt pavement reconstruction and construction device

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101016716A (en) * 2007-02-14 2007-08-15 易志坚 Influent polymer cement concrete pavement structure on asphalt surface course and contracture method
CN103526663A (en) * 2013-10-28 2014-01-22 三峡大学 Method for repairing asphalt concrete pavement distresses by utilization of combined-type concrete repaving surfacing
CN104047215A (en) * 2014-05-21 2014-09-17 西南科技大学 Method for changing cement concrete pavement into pervious concrete pavement
CN203960704U (en) * 2014-07-15 2014-11-26 济南市市政工程设计研究院(集团)有限责任公司 A kind of composite base asphalt pavement structure
CN104328730A (en) * 2014-09-26 2015-02-04 杭州江润科技有限公司 Construction method for transforming cement concrete pavement with embedded reinforced asphalt layer
CN205893847U (en) * 2016-08-08 2017-01-18 广东工业大学 Cement concrete pavement's repair structure
CN207003171U (en) * 2017-07-24 2018-02-13 上海市市政规划设计研究院 Permanent composite pavement structure for old asphalt pavement transformation

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101016716A (en) * 2007-02-14 2007-08-15 易志坚 Influent polymer cement concrete pavement structure on asphalt surface course and contracture method
CN103526663A (en) * 2013-10-28 2014-01-22 三峡大学 Method for repairing asphalt concrete pavement distresses by utilization of combined-type concrete repaving surfacing
CN104047215A (en) * 2014-05-21 2014-09-17 西南科技大学 Method for changing cement concrete pavement into pervious concrete pavement
CN203960704U (en) * 2014-07-15 2014-11-26 济南市市政工程设计研究院(集团)有限责任公司 A kind of composite base asphalt pavement structure
CN104328730A (en) * 2014-09-26 2015-02-04 杭州江润科技有限公司 Construction method for transforming cement concrete pavement with embedded reinforced asphalt layer
CN205893847U (en) * 2016-08-08 2017-01-18 广东工业大学 Cement concrete pavement's repair structure
CN207003171U (en) * 2017-07-24 2018-02-13 上海市市政规划设计研究院 Permanent composite pavement structure for old asphalt pavement transformation

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109490971A (en) * 2018-11-29 2019-03-19 江苏北极星交通产业集团有限公司 The detection restorative procedure that composite pavement comes to nothing
CN113430890A (en) * 2021-07-01 2021-09-24 驻马店市华中公路设计有限公司 Permanent composite pavement structure for old asphalt pavement reconstruction and construction device

Similar Documents

Publication Publication Date Title
Shamsaei et al. Experimental investigation of using cross-linked polyethylene waste as aggregate in roller compacted concrete pavement
CN108316089B (en) Method for repairing pavement by adopting plain concrete and reinforced concrete
CN106012743B (en) Semi-rigid type base anti-crack road surface structure and construction method suitable for high temperature difference area
Hu et al. Laboratory evaluation of cement treated aggregate containing crushed clay brick
CN104652212B (en) A kind of Promotion Transformation method of Old cement concrete
Chen et al. Long-lasting waterproofing solution for the subgrade of high-speed railway in cold region
CN104631268B (en) A kind of concrete road pavement structure
CN107165017A (en) The permanent composite pavement structure transformed for old asphalt pavement
Wu et al. The semi-rigid pavement with higher performances for roads and parking aprons
Mezhoud et al. Field investigations on injection method for sealing longitudinal reflective cracks
CN207003171U (en) Permanent composite pavement structure for old asphalt pavement transformation
CN108301276A (en) A kind of long-life tencel concrete road surface structure and construction method
CN204940039U (en) Plant stone Bridge Surface Paving by Cement structure for one kind
CN114182595B (en) Construction method of long-life asphalt road
Davidson et al. Best practices in cold in-place recycling
CN216193743U (en) Low-strength thick plate cement pavement
Wang Analysis the Control techniques of reflection crack on asphalt overlay of old cement concrete pavement
Nasiri et al. Laboratory and Field Study of Construction and Demolition Waste for Roller-Compacted Concrete Pavement
CN111395094A (en) Method for manufacturing resonance disintegration base course of existing asphalt pavement recycled concrete
CN108842550B (en) Asphalt mixture hoop structure and construction method thereof
CN219824779U (en) Cement concrete pavement structure
Mishra A Study On Thin White Topping: An Alternate For Pavement Treatment
CN212025807U (en) Anti-rutting composite pavement structure
CN113174797B (en) Device and method for repairing and improving road surface bearing capacity
CN213389568U (en) Sand-containing fog seal pre-curing anti-crack pavement structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20190212

Address after: Room 201, Building 609, Jianguo West Road, Xuhui District, Shanghai 200030

Applicant after: SHANGHAI MUNICIPAL PLANNING AND DESIGN INSTITUTE Co.,Ltd.

Address before: 200030 No. 609 Jianguo West Road, Xuhui District, Shanghai

Applicant before: SHANGHAI MUNICIPAL PLANNING DESIGN Research Institute

TA01 Transfer of patent application right
RJ01 Rejection of invention patent application after publication

Application publication date: 20170915

RJ01 Rejection of invention patent application after publication