CN103969065A - 防爆设备吊车负荷试验方法 - Google Patents

防爆设备吊车负荷试验方法 Download PDF

Info

Publication number
CN103969065A
CN103969065A CN201310053878.7A CN201310053878A CN103969065A CN 103969065 A CN103969065 A CN 103969065A CN 201310053878 A CN201310053878 A CN 201310053878A CN 103969065 A CN103969065 A CN 103969065A
Authority
CN
China
Prior art keywords
crane
load
water tank
tons
carrying
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201310053878.7A
Other languages
English (en)
Inventor
不公告发明人
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201310053878.7A priority Critical patent/CN103969065A/zh
Publication of CN103969065A publication Critical patent/CN103969065A/zh
Pending legal-status Critical Current

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

本发明公开了一种深水钻井船上大型防爆设备吊车负荷试验的方法,包括以下步骤:1、防爆设备吊车安装到预定轨道上;2、将一个载重350吨水的钢制方形水箱吊到防爆设备吊车下;3、用防爆设备的吊车与水箱的第一个连杆臂有效连接;4、用防爆设备的吊车将水箱进行前后、左右、上下六个方位的等速负荷试验;5、用防爆设备的吊车将水箱进行前后、左右、上下六个方位的不同速度的负荷试验;6、用防爆设备的吊车与水箱的第二个连杆臂有效连接,按照步骤4和步骤5做同样的负荷试验。其有益效果是在船台或船坞内部解决了防爆设备吊车的负荷试验难题,节省了租借小船的费用和时间,增加了试验效果,使试验更加方便和快捷。

Description

防爆设备吊车负荷试验方法
技术领域
本发明涉及深水钻井船上大型防爆设备吊车负荷试验方法的技术领域。
背景技术
深水钻井船上大型防爆设备重达两百多吨,且设备机器昂贵,所以吊车负荷试验要求试验物体达到三百多吨,现有技术是用租借来的自重约三百多吨的小船做试验,也必须等到钻井船在海上时才能做此试验,由于小船板材单薄,起吊的吊耳很难找到适合安装的位置,试验时给小船带来很大的损伤,小船的尺寸特殊,吊试验时有很多盲点,给试验带来的效果不佳,且租借费用和维修费用大,小船一般用在大型防爆设备下有悬臂梁结构的试验上,深水钻井船上大型防爆设备在船的钻井架旁,空间很小,负荷试验难度更大。
发明内容
为了克服上述现有技术的不足,本发明提供了一种深水钻井船上大型防爆设备吊车负荷试验方法,减少了租借小船的费用,增加了试验效果,灵便且快速的解决了负荷试验的难题。
为了达到上述目的,本发明的技术方案如下:
防爆设备吊车负荷试验方法,包括以下步骤:
1)、防爆设备的吊车安装到预定轨道上,能保证正常运作;
2)、用重型吊车将一个载重350吨水的钢制大水箱从地面吊到防爆设备吊车下;
3)、用防爆设备的吊车与载重350吨水的钢制大水箱的第一个连杆臂有效连接;
4)、用防爆设备的吊车将载重350吨水的钢制大水箱进行前后、左右、上下六个方位的等速负荷试验;
5)、用防爆设备的吊车将载重350吨水的钢制大水箱进行前后、左右、上下六个方位的等不同速度的负荷试验;
6)、用防爆设备的吊车与载重350吨水的钢制大水箱的第二个连杆臂有效连接,按照步骤4)和步骤5)做同样的负荷试验。
所述的载重350吨水的钢制大水箱是方形的,用船厂的废旧材料制作而成,闲置时可用于船上临时的淡水供应。
本发明的有益效果是:在船台或船坞内就部解决了海工石油装备钻井船上大型防爆器吊车的负荷试验问题,节省了租借小船的费用,增加了试验效果,使试验更加方便和快捷,节约了试验时间,试验用的水箱还可多次重复利用。
具体实施方式
防爆设备吊车负荷试验方法,是一种深水钻井船和海工石油装备上大型防爆设备吊车负荷试验的方法,包括以下步骤:
1)、防爆设备的吊车安装到预定轨道上,能保证正常运作;
2)、用重型吊车将一个载重350吨水的钢制大水箱从地面吊到防爆设备吊车下;
3)、用防爆设备的吊车与载重350吨水的钢制大水箱的第一个连杆臂有效连接;
4)、用防爆设备的吊车将载重350吨水的钢制大水箱进行前后、左右、上下六个方位的等速负荷试验;
5)、用防爆设备的吊车将载重350吨水的钢制大水箱进行前后、左右、上下六个方位的等不同速度的负荷试验;
6)、用防爆设备的吊车与载重350吨水的钢制大水箱的第二个连杆臂有效连接,按照步骤4)和步骤5)做同样的负荷试验。
所述的载重350吨水的钢制大水箱是方形的,方形的水箱尺寸应根据试验空间做优化,用船厂的废旧材料制作而成,闲置时可用于船上临时的淡水供应。

Claims (2)

1.防暴设备吊车负荷试验方法,是一种深水钻井船和海工石油装备上大型防暴设备吊车负荷试验的方法,其特征包括以下步骤:
1)、防爆设备的吊车安装到预定轨道上,能保证正常运作;
2)、用重型吊车将一个载重350吨水的钢制大水箱从地面吊到防爆设备吊车下;
3)、用防爆设备的吊车与载重350吨水的钢制大水箱的第一个连杆臂有效连接;
4)、用防爆设备的吊车将载重350吨水的钢制大水箱进行前后、左右、上下六个方位的等速负荷试验;
5)、用防爆设备的吊车将载重350吨水的钢制大水箱进行前后、左右、上下六个方位的等不同速度的负荷试验;
6)、用防爆设备的吊车与载重350吨水的钢制大水箱的第二个连杆臂有效连接,按照步骤4)和步骤5)做同样的负荷试验。
2.如权利1所述的防暴设备吊车负荷试验方法,其特征在于,载重350吨水的钢制大水箱是方形的,用船厂的废旧材料制作而成,闲置时可用于船上临时的淡水供应。
CN201310053878.7A 2013-02-03 2013-02-03 防爆设备吊车负荷试验方法 Pending CN103969065A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310053878.7A CN103969065A (zh) 2013-02-03 2013-02-03 防爆设备吊车负荷试验方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310053878.7A CN103969065A (zh) 2013-02-03 2013-02-03 防爆设备吊车负荷试验方法

Publications (1)

Publication Number Publication Date
CN103969065A true CN103969065A (zh) 2014-08-06

Family

ID=51238835

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310053878.7A Pending CN103969065A (zh) 2013-02-03 2013-02-03 防爆设备吊车负荷试验方法

Country Status (1)

Country Link
CN (1) CN103969065A (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104483149A (zh) * 2014-12-03 2015-04-01 大连船舶重工集团有限公司 一种浮式海洋平台吊机负荷试验的配载获取方法

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104483149A (zh) * 2014-12-03 2015-04-01 大连船舶重工集团有限公司 一种浮式海洋平台吊机负荷试验的配载获取方法
CN104483149B (zh) * 2014-12-03 2017-02-22 大连船舶重工集团有限公司 一种浮式海洋平台吊机负荷试验的配载获取方法

Similar Documents

Publication Publication Date Title
CN102030076B (zh) 5万吨半潜船主柴油发电机组进舱工艺
CN104443260B (zh) 一种全回转推进器水下部分安装装置及方法
CN203853999U (zh) 水下控制模块下入回收工具
CN102588675B (zh) 深水柔性软管保护性回收的方法
CN109292040A (zh) 一种多方位全回转舵桨总段安装方法
CN204916044U (zh) 一种船用可拆式木甲板固定装置
CN105752861B (zh) 利用浮力块和吊导两用索安装深海水下重型设施的方法
CN101870435B (zh) 直升机平台的翻转式吊装方法
CN106185699B (zh) 一种简易托架
CN103969065A (zh) 防爆设备吊车负荷试验方法
CN203638042U (zh) 一种集装箱船导轨安装的挂锥工装
CN203715209U (zh) 船体分段升降焊接装置
CN103448067A (zh) 一种用于电机定子装配的机械手夹具装置
CN103171911B (zh) 装船机安装工艺
CN106364537B (zh) 一种科考船用可调式水下机器人托架
CN106564819B (zh) 一种船用重型吊机及水下安装工艺
CN102674138A (zh) 一种船用艉轴吊装工装
CN201761629U (zh) 船舶舵叶舵销纵向拂配吊装装置
CN209127937U (zh) 一种起重机回转支承更换装置
CN203558801U (zh) 便携式起重机
CN202894711U (zh) 大型销轴的安装工具
CN102114897B (zh) 大型导缆器结构水上安装方法
CN202192457U (zh) 液压缸缸底钻孔夹具
CN104895503B (zh) 一种固定于水下管道外表面的工作平台
CN204265244U (zh) 一种燃油管吊的基座

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
DD01 Delivery of document by public notice

Addressee: Jiang Qifeng

Document name: Notification of Passing Examination on Formalities

C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20140806