CN103925862A - 一种rh精炼炉升降框架导轨安装调校方法 - Google Patents

一种rh精炼炉升降框架导轨安装调校方法 Download PDF

Info

Publication number
CN103925862A
CN103925862A CN201410190100.5A CN201410190100A CN103925862A CN 103925862 A CN103925862 A CN 103925862A CN 201410190100 A CN201410190100 A CN 201410190100A CN 103925862 A CN103925862 A CN 103925862A
Authority
CN
China
Prior art keywords
guide rail
guide rails
foundation pit
center
distance
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410190100.5A
Other languages
English (en)
Other versions
CN103925862B (zh
Inventor
李焱熠
赵臣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Metallurgical Construction Engineering Group Co Ltd
Original Assignee
China Metallurgical Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Metallurgical Construction Engineering Group Co Ltd filed Critical China Metallurgical Construction Engineering Group Co Ltd
Priority to CN201410190100.5A priority Critical patent/CN103925862B/zh
Publication of CN103925862A publication Critical patent/CN103925862A/zh
Application granted granted Critical
Publication of CN103925862B publication Critical patent/CN103925862B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

本发明公开了一种RH精炼炉升降框架导轨安装调校方法,包括如下步骤:1)确定基础坑的中心;2)在基础坑的顶部设置线架,线架的端部水平伸向基础坑的中心并悬挂线坠,线坠在竖直方向上与基础坑的中心对应,并将线坠作为基准中心;3)通过测量各根导轨与线坠之间的距离,进而调整各导轨相互之间的距离;通过测量各根导轨的底部和顶部分别到线坠的距离,进而调校导轨的垂直度。本发明根据RH精炼炉钢包升降装置四根导轨均布在基础坑的四角的特点,在基准中心进行一次吊线,设置一根基准线,同时调校四根导轨,以达到基准统一,经济可靠,既保证导轨调校精度,也减少仪器和人力使用,降低成本,简化操作,提高施工效率。

Description

一种RH精炼炉升降框架导轨安装调校方法
技术领域
本发明涉及RH精炼炉升降框架导轨安装,尤其是导轨呈四周均布类型的导轨安装调校。
背景技术
传统RH精炼炉升降框架导轨安装采用各个导轨吊线调校或多台经纬仪联合持续检测的方法。各个导轨单独吊线调校,不但措施多,占用线坠多,而且基准易发生不统一;采用多台经纬仪联合检测,过多地占用了经纬仪和人力,经济性较差。
发明内容
针对现有技术中存在基准统一难、过多占用仪器及人力等经济性较差的问题,本发明提供了一种经济可靠,既保证导轨调校精度,也减少仪器和人力使用,降低成本,简化操作,提高效率的RH精炼炉升降框架导轨安装调校方法。
为了解决上述技术问题,本发明采用了如下技术方案:
一种RH精炼炉升降框架导轨安装调校方法,该方法包括如下步骤:
1)根据RH精炼炉钢包升降装置四根导轨均布在基础坑的四角的特点,确定基础坑的中心;
2)在基础坑的顶部设置线架,线架的一端固定在基础坑的顶部,线架的另一端水平伸向基础坑的中心,在线架的另一端上悬挂线坠,线坠在竖直方向上与基础坑的中心对应,并将线坠作为基准中心;
3)用钢尺或千分尺测量检查导轨,调校导轨:
3.1)通过测量各根导轨与线坠之间的距离,进而调整各导轨相互之间的距离;
3.2)通过测量各根导轨的底部和顶部分别到线坠的距离,进而调校导轨的垂直度。
作为本发明的一种优选方案,在步骤3)中,调整各根导轨后,四根导轨到基准中心的距离为等距,导轨安装位置偏差允许±0.5mm,相对两导轨平行度为1mm,导轨直线度为0.5mm。
本发明的有益效果是:本发明根据RH精炼炉钢包升降装置四根导轨均布在基础坑的四角的特点,在基准中心进行一次吊线,设置一根基准线,同时调校四根导轨,以达到基准统一,经济可靠,既保证导轨调校精度,也减少仪器和人力使用,降低成本,简化操作,提高施工效率。 
附图说明
图1为导轨平面布置图;
图2为图1沿A—A方向的导轨断面布置图;
图3为导轨调校的示意图。
具体实施方式
下面结合附图和具体实施方式对本发明作进一步详细地描述。
一种RH精炼炉升降框架导轨安装调校方法,该方法包括如下步骤:
1)根据RH精炼炉钢包升降装置四根导轨1均布在基础坑2的四角的特点,如图1、2所示,确定基础坑的中心3。
2)在基础坑2的顶部设置线架6,如图3所示,线架6的一端固定在基础坑的顶部,线架的另一端水平伸向基础坑2的中心,在线架6的另一端上悬挂线坠4,线坠4在竖直方向上与基础坑的中心对应,并将线坠4作为基准中心。
3)用钢尺5或千分尺测量检查导轨,调校导轨:
3.1)通过测量各根导轨与线坠之间的距离,进而调整各导轨相互之间的距离,以实现四根导轨到基准中心的距离相等;
3.2)通过测量各根导轨的底部和顶部分别到线坠的距离,进而调校导轨的垂直度,即实现各根导轨的底部和顶部到线坠的距离相等。
调整各根导轨后,四根导轨到基准中心的距离为等距,导轨安装位置偏差允许±0.5mm(即相邻最近的两个导轨之间的距离偏差控制在±0.5mm以内),相对两导轨平行度为1mm(即基础坑2对角上的导轨之间的平行度偏差控制在1mm以内),导轨直线度为0.5mm(即导轨的底部和顶部距离线坠的距离之差控制在0.5mm以内,以实现导轨垂直安装)。
最后说明的是,以上实施例仅用以说明本发明的技术方案而非限制,尽管参照较佳实施例对本发明进行了详细说明,本领域的普通技术人员应当理解,可以对本发明的技术方案进行修改或者等同替换,而不脱离本发明技术方案的宗旨和范围,其均应涵盖在本发明的权利要求范围当中。

Claims (2)

1.一种RH精炼炉升降框架导轨安装调校方法,其特征在于,该方法包括如下步骤:
1)根据RH精炼炉钢包升降装置四根导轨均布在基础坑的四角的特点,确定基础坑的中心;
2)在基础坑的顶部设置线架,线架的一端固定在基础坑的顶部,线架的另一端水平伸向基础坑的中心,在线架的另一端上悬挂线坠,线坠在竖直方向上与基础坑的中心对应,并将线坠作为基准中心;
3)用钢尺或千分尺测量检查导轨,调校导轨:
3.1)通过测量各根导轨与线坠之间的距离,进而调整各导轨相互之间的距离;
3.2)通过测量各根导轨的底部和顶部分别到线坠的距离,进而调校导轨的垂直度。
2.根据权利要求1所述的一种RH精炼炉升降框架导轨安装调校方法,其特征在于:在步骤3)中,调整各根导轨后,四根导轨到基准中心的距离为等距,导轨安装位置偏差允许±0.5mm,相对两导轨平行度为1mm,导轨直线度为0.5mm。
CN201410190100.5A 2014-05-07 2014-05-07 一种rh精炼炉升降框架导轨安装调校方法 Active CN103925862B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410190100.5A CN103925862B (zh) 2014-05-07 2014-05-07 一种rh精炼炉升降框架导轨安装调校方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410190100.5A CN103925862B (zh) 2014-05-07 2014-05-07 一种rh精炼炉升降框架导轨安装调校方法

Publications (2)

Publication Number Publication Date
CN103925862A true CN103925862A (zh) 2014-07-16
CN103925862B CN103925862B (zh) 2016-06-01

Family

ID=51144163

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410190100.5A Active CN103925862B (zh) 2014-05-07 2014-05-07 一种rh精炼炉升降框架导轨安装调校方法

Country Status (1)

Country Link
CN (1) CN103925862B (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106403750A (zh) * 2016-08-30 2017-02-15 中国冶集团有限公司 双工位精炼炉导电臂升降导轮的安装找正方法
CN107285230A (zh) * 2017-08-10 2017-10-24 中国十七冶集团有限公司 Rh精炼炉液压顶升导轨的安装方法
CN107401964A (zh) * 2016-05-20 2017-11-28 株式会社日立大厦系统 电梯曳引机的定心装置及定心方法
CN114000532A (zh) * 2021-11-17 2022-02-01 中国二十冶集团有限公司 一种杯口基础方形钢柱的安装定位方法

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110615340B (zh) * 2019-09-17 2021-02-12 浙江尼邦电梯有限公司 一种减小曳引轮位移偏差的曳引轮

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
BR9605522A (pt) * 1996-11-01 1998-08-11 Gonvalves Itamar Bipé para demarcação de curva de nível no terreno determinação de porcentagem de rampas para fins de terraplenagem
CN101456039A (zh) * 2007-12-12 2009-06-17 中国二十冶建设有限公司 轧机底座安装测量方法
CN201387325Y (zh) * 2009-02-26 2010-01-20 中国二十冶建设有限公司 声控法冶金设备垂直度、平行度测量装置
CN202915872U (zh) * 2012-11-20 2013-05-01 中国十七冶集团有限公司 垂直导轨垂直度的简易测量装置
CN103575191A (zh) * 2013-11-19 2014-02-12 中国电力科学研究院 基础模型试验破坏面的测试装置

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
BR9605522A (pt) * 1996-11-01 1998-08-11 Gonvalves Itamar Bipé para demarcação de curva de nível no terreno determinação de porcentagem de rampas para fins de terraplenagem
CN101456039A (zh) * 2007-12-12 2009-06-17 中国二十冶建设有限公司 轧机底座安装测量方法
CN201387325Y (zh) * 2009-02-26 2010-01-20 中国二十冶建设有限公司 声控法冶金设备垂直度、平行度测量装置
CN202915872U (zh) * 2012-11-20 2013-05-01 中国十七冶集团有限公司 垂直导轨垂直度的简易测量装置
CN103575191A (zh) * 2013-11-19 2014-02-12 中国电力科学研究院 基础模型试验破坏面的测试装置

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107401964A (zh) * 2016-05-20 2017-11-28 株式会社日立大厦系统 电梯曳引机的定心装置及定心方法
CN107401964B (zh) * 2016-05-20 2020-06-05 株式会社日立大厦系统 电梯曳引机的定心装置及定心方法
CN106403750A (zh) * 2016-08-30 2017-02-15 中国冶集团有限公司 双工位精炼炉导电臂升降导轮的安装找正方法
CN106403750B (zh) * 2016-08-30 2018-10-23 中国一冶集团有限公司 双工位精炼炉导电臂升降导轮的安装找正方法
CN107285230A (zh) * 2017-08-10 2017-10-24 中国十七冶集团有限公司 Rh精炼炉液压顶升导轨的安装方法
CN107285230B (zh) * 2017-08-10 2019-10-25 中国十七冶集团有限公司 Rh精炼炉液压顶升导轨的安装方法
CN114000532A (zh) * 2021-11-17 2022-02-01 中国二十冶集团有限公司 一种杯口基础方形钢柱的安装定位方法
CN114000532B (zh) * 2021-11-17 2023-02-21 中国二十冶集团有限公司 一种杯口基础方形钢柱的安装定位方法

Also Published As

Publication number Publication date
CN103925862B (zh) 2016-06-01

Similar Documents

Publication Publication Date Title
CN103925862A (zh) 一种rh精炼炉升降框架导轨安装调校方法
CN102628680B (zh) 回转窑同心度测量方法及该方法中的基准线的确定方法
CN104924016A (zh) 一种铸件校正装置
CN204421906U (zh) 远距离配合全站仪使用的精确棱镜杆
CN203785613U (zh) 一种变压器油箱变形量测量工装
CN103451338A (zh) 高炉煤气系统上升管及五通球安装方法
CN203877793U (zh) 一种塔吊基座调平结构
CN102641895A (zh) 热连轧精轧机组侧导开度快速标定方法
CN104006798A (zh) 墩柱垂直度测量仪
CN202928539U (zh) 一种检测大直径圆柱面同轴度的正弦定心架
CN210268495U (zh) 辊道辊子的平行度校准装置及系统
CN104340847B (zh) 轧机压下装置的螺母安装装置及方法
CN203893846U (zh) 墩柱垂直度测量仪
CN204265868U (zh) 电解槽安装定位成套工具
CN204358390U (zh) 一种双挂槽显示器挂件
CN107860376B (zh) 一种大型间冷塔锥体段的三角架的测量定位方法
CN202452945U (zh) 一种新型钢化玻璃绝缘体形变测量装置
CN205400124U (zh) 建筑模板支撑杆
CN106555401B (zh) 用于导向管上部定位的台架
CN202522234U (zh) 一种路基边坡坡度测量仪
CN204265869U (zh) 电解槽定位安装放线架
CN202547662U (zh) 一种水平尺校准台
CN104482376A (zh) 一种双挂槽显示器挂件
CN211824405U (zh) 一种高效快速多功能复合测量装置
CN204924112U (zh) 新型建筑用尺

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant