CN103924527A - 一种节约资源、绿色环保、制架一体化的公路梁场布置及其施工方法 - Google Patents

一种节约资源、绿色环保、制架一体化的公路梁场布置及其施工方法 Download PDF

Info

Publication number
CN103924527A
CN103924527A CN201410182289.3A CN201410182289A CN103924527A CN 103924527 A CN103924527 A CN 103924527A CN 201410182289 A CN201410182289 A CN 201410182289A CN 103924527 A CN103924527 A CN 103924527A
Authority
CN
China
Prior art keywords
bridge
girder
fabrication
straddle truck
highway
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410182289.3A
Other languages
English (en)
Other versions
CN103924527B (zh
Inventor
武伟华
朱兴福
扶杰
王珍
丁鹏飞
高正强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Third Construction Co Ltd of CTCE Group
Original Assignee
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Third Construction Co Ltd of CTCE Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Tiesiju Civil Engineering Group Co Ltd CTCE Group, Third Construction Co Ltd of CTCE Group filed Critical China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Priority to CN201410182289.3A priority Critical patent/CN103924527B/zh
Publication of CN103924527A publication Critical patent/CN103924527A/zh
Application granted granted Critical
Publication of CN103924527B publication Critical patent/CN103924527B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本发明涉及一种节约资源、绿色环保、制架一体化的公路梁场布置及其施工方法,包括存梁区、制梁区、龙门吊,所述的存梁区设置在双幅桥梁其中的半幅桥梁上,制梁区设置在紧邻半幅桥梁的外侧,大吨位龙门吊横跨在在建的半幅桥梁与制梁区的上方,将该半幅桥梁和制梁区结合起来。本发明主要是将传统的梁场布置用地与公路永久用地有机的结合起来,达到减少用地的目的;同时利用梁场龙门吊提梁后直接存至桥梁上,减少存梁台座设置;合理组织制梁、架梁进行流水作业,可直接利用龙门吊提梁后放至桥面上的运梁车上,进行运梁,达到减少运梁便道和运梁工序时间的目的。

Description

一种节约资源、绿色环保、制架一体化的公路梁场布置及其施工方法
技术领域
本发明属于公路制梁领域,涉及公路预制梁场布置施工,尤其是一种节约资源、绿色环保型的公路梁场布置及其施工方法。
背景技术
桥梁预制是公路工程的一部分,梁场设置往往占用大面积的土地,且施工完后恢复困难,既对环境破坏较大又造成经济上的浪;施工中通常由梁场龙门吊吊梁,运梁车通过便道将梁运至现场,既造成时间上的浪费,又存在安全隐患。
通过检索,尚未发现与本发明申请相关的公开专利文献。
发明内容
本发明的目的在于克服现有技术的不足之处,提供一种既加快施工速度又节约资源、绿色环保、制架一体化的公路梁场布置,同时提供一种该梁场布置的施工方法。
本发明解决技术问题所采用的技术方案是:
一种节约资源、绿色环保、制架一体化的公路梁场布置,包括存梁区、制梁区及龙门吊,在制梁区内均布间隔在横向安装多个制梁台座,该制梁台座用于预制梁体,在存梁区内存放已经浇筑好的梁体,所述的存梁区设置在双幅桥梁其中的半幅桥梁上,在紧邻该半幅桥梁的外侧设置为制梁区,在制梁区与该半幅桥梁的上方横跨大吨位龙门吊,将该半幅桥梁与制梁区组合成整体。
而且,所述大吨位龙门吊的内侧轨道沿双幅桥梁的中线铺设,大吨位龙门吊的外侧轨道铺设在制梁区的外侧且与桥梁走向平行,将传统的梁场布置用地与公路永久用地有机的结合起来。
一种节约资源、绿色环保、制架一体化的公路梁场的施工方法,步骤如下:
⑴确定双幅桥梁的线路红线与中线的位置,根据制梁数量及工期合理计算制梁台座的数量和制梁区的面积,确定红线外侧需临时增加的征地范围和龙门吊轨道的设置长度;
⑵在双幅桥梁的中线上按中线线型进行龙门吊内侧轨道的基础施工,根据龙门吊跨度设置外侧轨道,外侧轨道线型应与线路中线线型一致;
⑶在半幅桥梁的适当位置预留二或三个墩柱暂不进行施工,在预留不施工的墩跨范围内施工桩基础和承台,施工后进行场地平整,并将承台顶作为临时存梁台座,同时在桥梁外侧设置顺线路方向的制梁台座,满足桥梁预制;
⑷进行大吨位龙门吊和小吨位龙门吊的安装、检测;
⑸对预留不施工墩跨的相邻墩下部进行结构施工,同时进行制梁施工;
⑹在相邻墩跨施工完达到强度后即作为存梁区的一部分,倒换施工预留处墩柱,盖梁;
⑺预制梁达到要求后,直接利用大吨位龙门吊将制梁区梁体提起、架设至龙门吊范围内的存梁区的盖梁上;
⑻存梁区范围内的半幅桥梁架设完成后,直接将梁面作为运梁便道,利用龙门吊将梁提至梁面上的运梁车上,由运梁车通过梁面便道运至架桥机处进行架设。
本发明的优点和积极效果是:
1、本发明利用跨半幅桥梁的梁场龙门吊在预制梁满足质量要求后,直接利用龙门吊进行存梁区范围内半幅桥梁架设,其他范围利用已架设桥梁的桥面作为运梁通道,直接利用龙门吊提梁后将梁放到在桥面上的运梁车上进行运梁,运至架桥机处进行梁体架设,形成流水作业,实现了制梁、架梁一体化,大大提高了空间利用率,节约了材料及设备成本,提高了施工效率。
2、本发明利用部分既有红线用地进行梁场建设,既节约了良田又节约了征地成本,同时减少了征地恢复费用。
3、本发明利用龙门吊跨桥梁半幅,把龙门吊范围内新建桥梁作为存梁区域,减少了存梁区域场地平整和台座设置,节约了成本。
4、本发明利用龙门吊提梁后直接放至桥面的运梁车上,减少了施工便道的设置又缩短了运输距离,且桥面上结构强度高,运输平稳,保证了安全、加快了进度。
5、本发明在保证质量、安全等基本要求的前提下,通过科学管理和技术进步,最大限度地节约了资源与减少对环境负面影响的施工活动,实现了四节一环保。
附图说明
图1为本发明的梁场布置平面图;
图2为图1的A-A向截面剖视图;
图3为图1的B-B向截面剖视图。
具体实施方式
下面结合附图并通过具体实施例对本发明作进一步详述,以下实施例只是描述性的,不是限定性的,不能以此限定本发明的保护范围。
一种节约资源、绿色环保、制架一体化的公路梁场布置,包括存梁区3、制梁区2、及龙门吊,在制梁区内均布间隔布置多个制梁台座5,该制梁台座用于预制梁体10,在存梁区内存放已经浇筑好的梁体。
本发明的创新点在于:
所述的存梁区设置在双幅桥梁其中的半幅桥梁上,在紧邻该半幅桥梁的外侧设置为制梁区,在制梁区与该半幅桥梁的上方横跨大吨位龙门吊1,将在建半幅桥梁与临时制梁区组合成整体。该大吨位龙门吊的内侧轨道8沿双幅桥梁的中线铺设,大吨位龙门吊的外侧轨道4铺设在制梁区的外侧且与桥梁走向平行。当梁体在制梁区浇筑完成后由大吨位龙门吊直接吊至半幅桥梁上的存梁区,无需再另找场地设置存梁台座来盛放已制梁体,实现了制架梁一体化,大大提高了空间利用率,节约了材料及设备成本,提高了施工效率。
一种节约资源、绿色环保、制架一体化的公路梁场的施工方法,步骤如下:
1、确定双幅桥梁的线路红线7与中线的位置,根据制梁数量及工期合理计算制梁台座的数量和制梁区的面积,确定红线外侧需临时增加的征地范围和龙门吊轨道的设置长度。
2、在双幅桥梁的中线上按中线线型进行龙门吊内侧轨道的基础施工,根据龙门吊跨度设置外侧轨道,外侧轨道线型应与线路中线线型一致。
3、在半幅桥梁的适当位置预留二或三个墩柱6暂不进行施工,在预留不施工的墩跨范围内施工桩基础和承台,施工后进行场地平整,并将承台顶作为临时存梁台座,同时在桥梁外侧设置顺线路方向的制梁台座,满足桥梁预制。
4、进行大吨位龙门吊和小吨位龙门吊9(吊装材料和模板用)的安装、检测。
5、对预留不施工墩跨的相邻墩下部进行结构施工,同时进行制梁施工。
6、在相邻墩跨施工完达到强度后即作为存梁区的一部分,倒换施工预留处墩柱,盖梁,此时可将临时存放在预留墩处的梁存放到已施工完的盖梁上。
7、预制梁达到要求后,可直接利用龙门吊将制梁区梁体提起、架设至龙门吊范围内的存梁区的盖梁上。
8、存梁区范围内的半幅桥梁架设完成后,可直接将梁面作为运梁便道,利用龙门吊将梁提至梁面上的运梁车11上,由运梁车通过梁面便道运至架桥机12处进行架设。
本梁场布置的原理是:
将传统的梁场布置用地与公路永久用地有机的结合起来,即将半幅桥梁作为梁场的一部分,达到减少用地的目的;同时利用梁场龙门吊提梁后直接存至桥梁上,减少了存梁台座设置;合理组织制梁、架梁,利用制梁、架梁各工序时间安排,保证制梁速度与架梁速度均衡后,直接利用龙门吊提梁后将梁放到在桥面上的运梁车上进行运梁,利用已架设桥梁的桥面作为运梁通道,将梁直接运至架桥机处进行桥梁架设,形成制架梁一体化。

Claims (3)

1.一种节约资源、绿色环保、制架一体化的公路梁场布置,包括存梁区、制梁区及龙门吊,在制梁区内均布间隔在横向安装多个制梁台座,该制梁台座用于预制梁体,在存梁区内存放已经浇筑好的梁体,其特征在于:所述的存梁区设置在双幅桥梁其中的半幅桥梁上,在紧邻该半幅桥梁的外侧设置为制梁区,在制梁区与该半幅桥梁的上方横跨大吨位龙门吊,将该半幅桥梁与制梁区组合成整体。
2.根据权利要求1所述的节约资源、绿色环保、制架一体化的公路梁场布置,其特征在于:所述大吨位龙门吊的内侧轨道沿双幅桥梁的中线铺设,大吨位龙门吊的外侧轨道铺设在制梁区的外侧且与桥梁走向平行,将传统的梁场布置用地与公路永久用地有机的结合起来。
3.一种如权利要求1所述节约资源、绿色环保、制架一体化的公路梁场的施工方法,其特征在于:步骤如下:
⑴确定双幅桥梁的线路红线与中线的位置,根据制梁数量及工期合理计算制梁台座的数量和制梁区的面积,确定红线外侧需临时增加的征地范围和龙门吊轨道的设置长度;
⑵在双幅桥梁的中线上按中线线型进行龙门吊内侧轨道的基础施工,根据龙门吊跨度设置外侧轨道,外侧轨道线型应与线路中线线型一致;
⑶在半幅桥梁的适当位置预留二或三个墩柱暂不进行施工,在预留不施工的墩跨范围内施工桩基础和承台,施工后进行场地平整,并将承台顶作为临时存梁台座,同时在桥梁外侧设置顺线路方向的制梁台座,满足桥梁预制;
⑷进行大吨位龙门吊和小吨位龙门吊的安装、检测;
⑸对预留不施工墩跨的相邻墩下部进行结构施工,同时进行制梁施工;
⑹在相邻墩跨施工完达到强度后即作为存梁区的一部分,倒换施工预留处墩柱,盖梁;
⑺预制梁达到要求后,直接利用大吨位龙门吊将制梁区梁体提起、架设至龙门吊范围内的存梁区的盖梁上;
⑻存梁区范围内的半幅桥梁架设完成后,直接将梁面作为运梁便道,利用龙门吊将梁提至梁面上的运梁车上,由运梁车通过梁面便道运至架桥机处进行架设。
CN201410182289.3A 2014-04-29 2014-04-29 一种制架一体化的公路梁场布置结构及其施工方法 Active CN103924527B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410182289.3A CN103924527B (zh) 2014-04-29 2014-04-29 一种制架一体化的公路梁场布置结构及其施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410182289.3A CN103924527B (zh) 2014-04-29 2014-04-29 一种制架一体化的公路梁场布置结构及其施工方法

Publications (2)

Publication Number Publication Date
CN103924527A true CN103924527A (zh) 2014-07-16
CN103924527B CN103924527B (zh) 2016-04-20

Family

ID=51142907

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410182289.3A Active CN103924527B (zh) 2014-04-29 2014-04-29 一种制架一体化的公路梁场布置结构及其施工方法

Country Status (1)

Country Link
CN (1) CN103924527B (zh)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107191016A (zh) * 2017-06-16 2017-09-22 中交四航局第二工程有限公司 一种扭王字块生产施工场地布置
CN108442258A (zh) * 2018-05-29 2018-08-24 中交路桥北方工程有限公司 一种预制梁场地
CN108589568A (zh) * 2018-05-04 2018-09-28 中铁四局集团第二工程有限公司 一种狭小空间内上跨营业线棚洞t型梁快速施工方法
CN109403674A (zh) * 2018-12-24 2019-03-01 中交航局第二工程有限公司 用于桥梁施工的装配式预制厂及其施工方法
CN109868747A (zh) * 2019-03-14 2019-06-11 中交一公局海威工程建设有限公司 预制梁施工方法及装置
CN110526121A (zh) * 2019-08-15 2019-12-03 中铁七局集团有限公司 高速公路曲线路基上设置梁场时龙门吊运行监测系统及方法
CN111139743A (zh) * 2019-12-26 2020-05-12 中铁十七局集团第三工程有限公司 提高公路梁架梁速度的方法及龙门吊的安装方法
CN113832863A (zh) * 2021-10-14 2021-12-24 中铁十九局集团广州工程有限公司 一种双幅桥架梁的方法
CN114737482A (zh) * 2022-04-22 2022-07-12 中国二十二冶集团有限公司 狭窄环境下运梁车的出梁运梁方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101028726A (zh) * 2006-09-21 2007-09-05 中铁大桥局股份有限公司 短线法预制pc箱梁工艺
CN101250854A (zh) * 2007-12-05 2008-08-27 中铁大桥局股份有限公司 大跨度双线箱梁串架法施工造桥机
CN201128193Y (zh) * 2007-08-10 2008-10-08 董光辉 可拆装式箱梁存梁台架
KR20120117362A (ko) * 2011-04-15 2012-10-24 브이에스엘코리아 주식회사 이동식 작업차와 이동식 작업차를 이용한 교량의 시공 방법
JP5184248B2 (ja) * 2008-07-31 2013-04-17 鹿島建設株式会社 立体交差の施工方法
CN203200668U (zh) * 2013-04-28 2013-09-18 中国建筑土木建设有限公司路桥分公司 一种公路桥梁预制梁场自动喷淋养护系统

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101028726A (zh) * 2006-09-21 2007-09-05 中铁大桥局股份有限公司 短线法预制pc箱梁工艺
CN201128193Y (zh) * 2007-08-10 2008-10-08 董光辉 可拆装式箱梁存梁台架
CN101250854A (zh) * 2007-12-05 2008-08-27 中铁大桥局股份有限公司 大跨度双线箱梁串架法施工造桥机
JP5184248B2 (ja) * 2008-07-31 2013-04-17 鹿島建設株式会社 立体交差の施工方法
KR20120117362A (ko) * 2011-04-15 2012-10-24 브이에스엘코리아 주식회사 이동식 작업차와 이동식 작업차를 이용한 교량의 시공 방법
CN203200668U (zh) * 2013-04-28 2013-09-18 中国建筑土木建设有限公司路桥分公司 一种公路桥梁预制梁场自动喷淋养护系统

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
高清炎: "浅谈现场预制梁场地建设", 《科学咨询(决策管理)》 *

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107191016A (zh) * 2017-06-16 2017-09-22 中交四航局第二工程有限公司 一种扭王字块生产施工场地布置
CN108589568A (zh) * 2018-05-04 2018-09-28 中铁四局集团第二工程有限公司 一种狭小空间内上跨营业线棚洞t型梁快速施工方法
CN108589568B (zh) * 2018-05-04 2020-03-27 中铁四局集团第二工程有限公司 一种狭小空间内上跨营业线棚洞t型梁快速施工方法
CN108442258A (zh) * 2018-05-29 2018-08-24 中交路桥北方工程有限公司 一种预制梁场地
CN109403674A (zh) * 2018-12-24 2019-03-01 中交航局第二工程有限公司 用于桥梁施工的装配式预制厂及其施工方法
CN109403674B (zh) * 2018-12-24 2023-08-08 中交一航局第二工程有限公司 用于桥梁施工的装配式预制厂及其施工方法
CN109868747A (zh) * 2019-03-14 2019-06-11 中交一公局海威工程建设有限公司 预制梁施工方法及装置
CN110526121A (zh) * 2019-08-15 2019-12-03 中铁七局集团有限公司 高速公路曲线路基上设置梁场时龙门吊运行监测系统及方法
CN111139743A (zh) * 2019-12-26 2020-05-12 中铁十七局集团第三工程有限公司 提高公路梁架梁速度的方法及龙门吊的安装方法
CN113832863A (zh) * 2021-10-14 2021-12-24 中铁十九局集团广州工程有限公司 一种双幅桥架梁的方法
CN114737482A (zh) * 2022-04-22 2022-07-12 中国二十二冶集团有限公司 狭窄环境下运梁车的出梁运梁方法

Also Published As

Publication number Publication date
CN103924527B (zh) 2016-04-20

Similar Documents

Publication Publication Date Title
CN103924527B (zh) 一种制架一体化的公路梁场布置结构及其施工方法
CN205205635U (zh) 一种大跨径贝雷架钢便桥结构
CN104097253B (zh) 跨座式单轨交通环保型活动式预制轨道梁模板系统
CN103215894B (zh) 移动式临时预应力张拉锚块
CN202227360U (zh) 用作楼房车间等地面的大跨度预应力混凝土桩梁板结构
CN206290016U (zh) 一种铁路站房及其站台雨棚结构
CN204986247U (zh) 一种煤改燃工程中燃煤锅炉承台用燃气锅炉底座
CN205874987U (zh) 简易架桥机
CN207260605U (zh) 一种超大平面结构施工物料运输系统
CN103437349B (zh) 钢筋混凝土灌注异形桩的施工方法
CN106988344B (zh) 一种装配式车站现浇段拼装台车的施工方法
CN206092014U (zh) 一种适用于多导洞开挖的临时支撑体系转换台车
CN206513032U (zh) 一种在空间桁架梁上设置双轨道进行顶推累积滑移用节点
CN202899639U (zh) 一种混凝土柱结构
CN212771950U (zh) 用于工字钢-混凝土组合梁横梁安装的移动操作平台
CN102418414A (zh) 大板跨预制梁楼板支模体系
CN109322490A (zh) 一种布料机与爬升钢平台连接结构
CN204001214U (zh) 高精度柱顶预埋板
CN203755092U (zh) Phc桩提梁机轨道基础
CN205188975U (zh) 一种移动式混凝土浇筑平台
CN209369359U (zh) 一种布料机与爬升钢平台连接结构
CN203213022U (zh) 一种移动式临时预应力张拉锚块
CN206428665U (zh) 一种方便转向式半断面渠道衬砌机
CN204803758U (zh) 一种用于组合桁梁较重钢腹杆安装的横移体系
CN206189438U (zh) 一种带隔湿功能的地基

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Fu Xiangcai

Inventor after: Qin Lin

Inventor after: Wu Weihua

Inventor after: Liu Guidong

Inventor after: Fu Jie

Inventor after: Zhu Xingfu

Inventor after: Wang Zhen

Inventor after: Gao Zhengqiang

Inventor after: Ding Pengfei

Inventor before: Wu Weihua

Inventor before: Zhu Xingfu

Inventor before: Fu Jie

Inventor before: Wang Zhen

Inventor before: Ding Pengfei

Inventor before: Gao Zhengqiang

COR Change of bibliographic data
C14 Grant of patent or utility model
GR01 Patent grant